Tuesday, February 18
Wurzbach Parkway progress
›
Wetmore to Jones-Maltsbergrer More of the work to get the Mud Creek bridge has been finished - the support columns are all formed and buil...
Tuesday, February 11
Wurzbach Parkway: lots of work along U.S. 281 (and some at West Ave., too)
›
The northbound entrance ramp from Nakoma Drive has been replaced with a temporary ramp nearer to Bitters Road, allowing Williams Brothers Co...
Wednesday, January 22
Major closures, major openings and more progress on Wurzbach Parkway
›
Beginning this week— Wednesday , actually—alternating lane closures will be used on West Avenue to allow bridge crews to begin constructin...
Wednesday, December 18
TxDOT lead inspector recognized
›
Lloyd Mair, the lead inspector for the center segment of Wurzbach Parkway and a 28-year veteran at the Texas Department of Transportation, w...
Thursday, December 12
Temperatures cooling work (and other Wurzbach Parkway stuff)
›
Near-freezing temperatures are delaying pavement scheduled for Jones-Maltsberger and for the western segment of the parkway, causing projec...
Wednesday, November 20
West Avenue closure scheduled, other Wurzbach updates
›
Williams Brothers Construction will close West Avenue the nights of Wednesday and Thursday, December 4 and 5 , to set support beams to bui...
›