UPCOMING SCHEDULED CONSTRUCTION CLOSURES

 


Loop 1604 – North East San Antonio/Bexar County

  • Monday, August 30 until Tuesday, August 31. 1:00 a.m. to 8 a.m. Northbound exit ramp to southbound I-35 closed, including the collector road for barrier movement.
  • Wednesday, September 1 until Thursday, September 3. 1:00 a.m. to 8:00 a.m. Southbound exit ramp and collect to I-35 southbound closed for barrier movement. 

Loop 1604 – Far East San Antonio/Bexar County

  • Sunday, August 29 until Monday, August 30. 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 at the I-10 intersection for bridge repairs. 

Loop 1604 – North Central San Antonio/Bexar County

  • Saturday, August 28 until Sunday, August 29. Continuous 9 a.m. until 3 p.m. Alternating eastbound mainlane closure from Stone Oak Parkway to US 281 for signage installation.
  • Saturday, August 28 until Sunday, August 29. Continuous 9 a.m. until 3 p.m. Alternating westbound mainlane closure from US 281 to Stone Oak Parkway for signage installation.
  • Saturday, August 28 until Sunday, August 29. Continuous 9 a.m. until 3 p.m. Alternating eastbound mainlane closure from Stone Oak Parkway to US 281 for signage installation.
  • Saturday, August 28 until Sunday, August 29. Continuous 9 a.m. until 3 p.m. Alternating westbound mainlane closure from US 281 to Stone Oak Parkway for signage installation.
  • Monday, August 30 until Friday, September 3. Nightly 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Stone Oak Parkway to US 281 for signage installation.
  • Monday, August 30 until Friday, September 3. Nightly 9 p.m. until 5 a.m. Alternating westbound mainlane closure from US 281 to Stone Oak Parkway for signage installation. 

Loop 1604 – North West San Antonio/Bexar County

  • Current until Saturday, August 28. Weeknights 9 p.m. to 5 a.m. Alternating closures on the frontage roads in both directions, from SH 16 (Bandera Rd.) to I-10 for barrier installation.
  • Current until Saturday, August 28. Weeknights 9 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from SH 16 (Bandera Rd.) to I-10 for barrier installation.
  • Current until Thursday, September 2. Weeknights 9 p.m. to 5 a.m. Eastbound exit ramp to I-10 closed for barrier setting. DETOUR: Traffic will be directed to use the Vance Jackson Rd. exit ramp and continue the eastbound frontage road to I-10.
  • Sunday, August 29 until Friday, September 10. 9 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from SH 16 (Bandera Rd.) to I-10 for barrier setting. One mainlane to remain open at all times.
  • Sunday, August 29 until Friday, September 10. 9 p.m. to 5 p.m. Alternating lane closures on the frontage roads, in both directions, from SH 16 (Bandera Rd.) to I-10 for barrier setting.
  • Sunday, September 12 until Saturday, September 25. 9 p.m. to 5 a.m. Alternating mainlane closures from SH 16 (Bandera Rd.) to I-10 for barrier installation. One lane to remain open at all times.
  • Sunday, September 12 until Saturday, September 25. 9 p.m. to 5 a.m. Alternating lane closures on frontage roads, in both directions, from SH 16 (Bandera Rd.) to I-10 for barrier installations. One lane to remain open at all times.

US 281 – North Central San Antonio/Bexar County

  • Current until Tuesday, August 31. Right lane closure on northbound frontage road from Northern Blvd. to S. Terminal Dr. for roadway repairs.
  • Saturday, August 28 until Sunday, August 29. 11:30 p.m. to 6 a.m. Single southbound lane closure at Borgfeld Rd. for utility work.
  • Saturday, August 28. 4 a.m. to 6 p.m. Northbound lane closure from Borgfeld Rd. to Cibolo Creek for sidewalk improvements.
  • Saturday, August 28. 4 a.m. to 6 p.m. Southbound lane closure from Cibolo Creek to Borfeld Rd. for sidewalk improvements.
  • Sunday, August 29 until Thursday, September 2. 9 p.m. to 5 a.m. Single southbound lane closure from Cibolo Creek to Borgfeld Rd. for sidewalk improvements.
  • Sunday, August 29 until Friday, September 3. 9 p.m. to 5 a.m. Single northbound lane closure from Borgfeld Rd. to Cibolo Creek for sidewalk improvements.
  • Saturday, August 28 until Sunday, August 29. Continuous 9 a.m. until 3 p.m. Alternating northbound mainlane closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for concrete paving.
  • Saturday, August 28 until Sunday, August 29. Continuous 9 a.m. until 3 p.m. Alternating southbound mainlane closure from Stone Oak Parkway to Loop 1604 for concrete paving.
  • Saturday, August 28 until Sunday, August 29. Continuous 9 a.m. until 3 p.m. Alternating northbound frontage road closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for concrete paving.
  • Saturday, August 28 until Sunday, August 29. Continuous 9 a.m. until 3 p.m. Alternating southbound frontage road closure from Stone Oak Parkway to Loop 1604 for concrete paving.
  • Monday, August 30 until Friday, September 3. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for signage installation.
  • Monday, August 30 until Friday, September 3. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Stone Oak Parkway to Loop 1604 for signage installation. 

I-10 –East San Antonio/Bexar County/Seguin/Guadalupe County 

  • Saturday, August 28. 5 a.m. to 7 p.m. Single eastbound mainlane closure at FM 1518 for bridge work.
  • Sunday, August 29 until Wednesday, September 1. 8:30 p.m. to 5:30 a.m. Alternating westbound mainlanes closed from Zuehl Rd. to Pfeil Rd. for striping operations.
  • Tuesday, August 31 until Wednesday, September 1. 9 p.m. to 5 a.m. Full closure of westbound mainlanes from FM 1516 to Weichold Rd. for bridge work. Single eastbound mainlane closure from FM 1516 and Weichold Rd. for bridge work.
  • Wednesday, September 1 until Thursday, September 2. 9 p.m. to 5 a.m. Full closure of the westbound mainlanes from FM 1516 to Weichold Rd. for retaining wall work.
  • Thursday, September 2 until Friday, September 3. 9 p.m. to 5 a.m. Full closure of the eastbound mainlanes from FM 1516 to Weichold Rd. for retaining wall work.
  • Current until further notice. Graytown Road closed at I-10. DETOURS: Graytown Road traffic may use the frontage road and the Pfeil Road underpass or Loop 1604 turnaround to cross I-10. 

I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

  • Friday, August 27 until Saturday, August 28. 9 p.m. to 9 a.m. Full closure of the southbound mainlanes from Watson Ln. to Conrads Ln. for bridge demolition.
  • Saturday, August 28 until Sunday, August 29. 9 p.m. to 9 a.m. Double southbound mainlane closure from Watson Ln. to Conrad Ln. for bridge demolition.
  • Sunday, August 29 until Monday, August 30. 9 p.m. to 5 a.m. Double northbound mainlane closure from Watson Ln. to Conrads Ln. for bridge demolition.
  • Current until Saturday, August 28. Single lane closures on the frontage roads, in both directions, from FM 2252 to FM 1103 for material haul-off.
  • Current until Saturday, August 28. 9 a.m. to 5:30 p.m. Right lane closure on the northbound frontage road from FM 1103 to Schwab Rd. for curb demolition and material haul-off.
  • Monday, August 30 until Thursday, September 2. 9 p.m. to 5 a.m. Single northbound lane closure at the exit ramp to Loop 410 south for bridge repairs.
  • Current until Saturday, August 28. 8 p.m. to 5 a.m. Double mainlane closures, in both directions, from Watson to Conrads Ln. for setting barrier and striping work. The Watson and Conrads Ln. ramps will also be closed. Traffic will need to use the Parkway bridge.
  • Current until Saturday, September 4. 9 a.m. to 5:30 p.m. Single lane closures on the frontage roads, in both directions, from FM 2252 to FM 1103 for material haul-off.
  • Current until Saturday September 4. 9 a.m. to 5:30 p.m. Right lane closure on the northbound frontage road from FM 1103 to Schwab Rd. for curb demolition and material haul-off.

I-410 – East San Antonio

  • Sunday, August 29 until Friday, September 3. 9 p.m. to 5 a.m. Various mainlane closures, in both directions, from I-35 to I-10 for overhead sign replacements. 

I-410 – West San Antonio

  • Current until Sunday, August 29. 8 p.m. to 5 a.m. Full closure of the northbound frontage road from Meadow Breeze Dr. to SH 151 for bridge work.
  • Current until Sunday, August 29. 8 p.m. to 5 a.m. Full closure of the mainlanes, in both directions, from W. Military Dr. to Marbach Rd. for bridge work.
  • Current until Sunday, August 29. 9 a.m. to 3 p.m. Alternating lane closures, in both directions, on the frontage roads from Marbach Rd. to Bandera Rd. for bridge work.
  • Current until Sunday, August 29. 8 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from Marbach Rd. to Ingram Rd. for bridge work.
  • Current until Sunday, August 29. 8 a.m. to 4 p.m. Southbound bypass lane at W. Military Dr. closed for concrete work.
  • Sunday, August 29 until Monday, September 13. 8 p.m. to 5 a.m. Full closure of mainlanes, in both directions, from W. Military Dr. to Marbach Rd. for bridge work.
  • Sunday, August 29 until Monday, September 13. 9 a.m. to 3 p.m. Alternating lane closure on frontage roads, in both directions, from Marbach Rd. to Bandera Rd. for bridge work.
  • Sunday, August 29 until Monday, September 13. 8 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from Marbach Rd. to Ingram Rd. for bridge work.
  • Sunday, August 29 until Monday, September 13. 8 p.m. to 5 a.m. Full closure of the northbound frontage road from Meadow Breeze Dr. to SH 151 for bridge work.  

I-410 – Southwest San Antonio

  • Current until December 2021. Left lane closed on the southbound frontage road at Valley Hi. 

SH 151 – West San Antonio

  • Current until Sunday, August 29. 8 p.mm. to 5 a.m. Full closure of the eastbound frontage road from Cable Ranch Rd. to Loop 410 for bridge work.
  • Sunday, August 29 until Monday, September 13. 8 p.m. to 5 a.m. Full closure of the eastbound frontage road from Cable Ranch Rd. to Loop 410 for bridge work.
  • Sunday, August 29 until Monday, September 13. 8 p.m. to 5 a.m. Full closure of the westbound frontage road at the Loop 410 intersection for bridge work.  

SL 13 – Military Dr.

  • Current until Tuesday, August 31. 8 a.m. to 4 p.m. Single westbound lane closure from Bardwell Dr. to Alsbrook Dr. for sidewalk improvements.
  • Current until Tuesday, August 31. 8 a.m. to 4 p.m. Single westbound lane closure from New Laredo Hwy. to Somerset Rd. for sidewalk improvements. 

Alamo Ranch Parkway

  • Tuesday, September 7 until Wednesday, September 8. 9 p.m. to 5 a.m. Full closure of the Westwood Loop intersection for bridge work.
  • Wednesday, September 8 until Thursday, September 9. 9 p.m. to 5 a.m. Full closure of the Westwood Loop intersection for bridge work. 

SH 16 – Bandera Road

  • Current until Friday, September 3. Eastbound right lane closed from Braun Rd. to Loop 410 for sidewalk and driveway improvements. 

PA 1502 – Wurzbach Parkway

  • Monday, August 30 until Thursday, September 2. 9 a.m. to 4 p.m. Single westbound lane closure at the N.W. Military Highway intersection for demolition and paving. 

FM 1976 – Walzem Road/Gibbs Sprawl Road

  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes between Woodlake Parkway and Gibbs Sprawl Road for barrier/pavement work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
  • Current until further notice. Full-day closure. Southbound lane between Toepperwein Road and Walzem Road for barrier setting work and road rehab work.  

FM 345 – Fredericksburg Rd.

  • Current until Tuesday, August 31. 8 a.m. to 4 p.m. Single eastbound lane closure from Loop 410 to Hillcrest Dr. for sidewalk improvements.  

US 87 – Rigsby Road

  • Current until Tuesday, August 31. 8 a.m. to 4 p.m. Single eastbound lane closure from Pecan Valley Rd. to Ancel Rd. for sidewalk improvements.
  • Current until Saturday, September 4. 7 a.m. to 7 p.m. Double lane closures, in both directions, from Roland Ave. to Loop 410 for roadway repairs. 

SH 46 – Kendall County

  • Current until September 2021. Roadway at I-10 intersection reduced to two-lanes, with the closure of the inbound right turn lane and Whataburger driveway. Traffic will be shifted onto temporary pavement as new roadway is constructed.


Friday, August 20

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

 


Loop 1604 – North East San Antonio/Bexar County

  • Sunday, August 22 until Monday, August 23. 9 p.m. to 6 a.m. Single southbound mainlane closure from Pat Booker Rd. to Palisades Dr. for traffic switch.
  • Monday, August 30 until Tuesday, August 31. 1:00 a.m. to 8 a.m. Northbound exit ramp to southbound I-35 closed, including the collector road for barrier movement.
  • Wednesday, September 1 until Thursday, September 3. 1:00 a.m. to 8:00 a.m. Southbound exit ramp and collect to I-35 southbound closed for barrier movement.

Loop 1604 – North Central San Antonio/Bexar County

  • Saturday, August 21 until Sunday, August 22. Continuous 9 a.m. until 3 p.m. Alternating eastbound mainlane closure from Stone Oak Parkway to US 281 for signage installation.
  • Saturday, August 21 until Sunday, August 22. Continuous 9 a.m. until 3 p.m. Alternating westbound mainlane closure from US 281 to Stone Oak Parkway for signage installation.
  • Monday, August 23 until Friday, August 27. Nightly 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Stone Oak Parkway to US 281 for signage installation.
  • Monday, August 23 until Friday, August 27. Nightly 9 p.m. until 5 a.m. Alternating westbound mainlane closure from US 281 to Stone Oak Parkway for signage installation.
  • Saturday, August 28 until Sunday, August 29. Continuous 9 a.m. until 3 p.m. Alternating eastbound mainlane closure from Stone Oak Parkway to US 281 for signage installation.
  • Saturday, August 28 until Sunday, August 29. Continuous 9 a.m. until 3 p.m. Alternating westbound mainlane closure from US 281 to Stone Oak Parkway for signage installation. 

Loop 1604 – North West San Antonio/Bexar County

  • Current until Saturday, August 28. Weeknights 9 p.m. to 5 a.m. Alternating closures on the frontage roads in both directions, from SH 16 (Bandera Rd.) to I-10 for barrier installation.
  • Current until Saturday, August 28. Weeknights 9 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from SH 16 (Bandera Rd.) to I-10 for barrier installation.
  • Thursday, August 26 until Thursday, September 2. Weeknights 9 p.m. to 5 a.m. Eastbound exit ramp to I-10 closed for barrier setting. DETOUR: Traffic will be directed to use the Vance Jackson Rd. exit ramp and continue the eastbound frontage road to I-10.
  • Sunday, August 29 until Friday, September 10. 9 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from SH 16 (Bandera Rd.) to I-10 for barrier setting. One mainlane to remain open at all times.
  • Sunday, August 29 until Friday, September 10. 9 p.m. to 5 p.m. Alternating lane closures on the frontage roads, in both directions, from SH 16 (Bandera Rd.) to I-10 for barrier setting. 

US 281 – North Central San Antonio/Bexar County

  • Current until Saturday, August 21. 7 a.m. to 6 p.m. Right lane closed, in both directions, from Borgfeld Rd. to Cibolo Creek for sidewalk improvements.
  • Current until Tuesday, August 31. Right lane closure on northbound frontage road from Northern Blvd. to S. Terminal Dr. for roadway repairs.
  • Current until Saturday, August 21. 9 p.m. to 5 a.m. Alternating southbound lane closures from Overlook Parkway to Marshall Rd. for signal work.
  • Saturday, August 21 until Sunday, August 22. Continuous 9 a.m. until 3 p.m. Alternating northbound mainlane closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for concrete paving.
  • Saturday, August 21 until Sunday, August 22. Continuous 9 a.m. until 3 p.m. Alternating southbound mainlane closure from Stone Oak Parkway to Loop 1604 for concrete paving.
  • Saturday, August 21 until Sunday, August 22. Continuous 9 a.m. until 3 p.m. Alternating northbound frontage road closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for concrete paving.
  • Saturday, August 21 until Sunday, August 22. Continuous 9 a.m. until 3 p.m. Alternating southbound frontage road closure from Stone Oak Parkway to Loop 1604 for concrete paving.
  • Monday, August 23 until Friday, August 27. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for signage installation.
  • Monday, August 23 until Friday, August 27. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Stone Oak Parkway to Loop 1604 for signage installation.
  • Saturday, August 28 until Sunday, August 29. Continuous 9 a.m. until 3 p.m. Alternating northbound mainlane closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for concrete paving.
  • Saturday, August 28 until Sunday, August 29. Continuous 9 a.m. until 3 p.m. Alternating southbound mainlane closure from Stone Oak Parkway to Loop 1604 for concrete paving.
  • Saturday, August 28 until Sunday, August 29. Continuous 9 a.m. until 3 p.m. Alternating northbound frontage road closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for concrete paving.
  • Saturday, August 28 until Sunday, August 29. Continuous 9 a.m. until 3 p.m. Alternating southbound frontage road closure from Stone Oak Parkway to Loop 1604 for concrete paving. 

I-10 – Northwest San Antonio/Bexar County/Kendall County 

  • Friday, August 20 9 p.m. to Monday, August 23 5 a.m. Full closure of mainlanes, in both directions, from SH 46 to Scenic Loop Rd. for demolition of the US 87 bridge. 

I-10 –East San Antonio/Bexar County/Seguin/Guadalupe County 

  • Sunday, August 22 thru Friday, August 27. NIGHTWORK. Eastbound and westbound alternating lane closures between East I-410 interchange and Loop 1604 from 9 p.m. to 5 a.m. for pavement work.
  • Thursday, August 26 until Friday, August 27. 8:30 p.m. to 5:30 a.m. Alternating mainlanes closures, in both directions, from Zuehl Rd. to Graytown Rd. for shoulder cleanup.
  • Sunday, August 29 until Wednesday, September 1. 8:30 p.m. to 5:30 a.m. Alternating westbound mainlanes closed from Zuehl Rd. to Pfeil Rd. for striping operations.
  • Current until further notice. Graytown Road closed at I-10. DETOURS: Graytown Road traffic may use the frontage road and the Pfeil Road underpass or Loop 1604 turnaround to cross I-10. 

I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

  • Current until Saturday, August 21. Single lane closures on the frontage roads, in both directions, from FM 2252 to FM 1103 for material haul-off.
  • Current until Saturday, August 21. 9 a.m. to 5:30 p.m. Right lane closure on the northbound frontage road from FM 1103 to Schwab Rd. for curb demolition and material haul-off.
  • Friday, August 20 until Saturday, August 21. 9 p.m. to 8 a.m. Double mainlane closures, in both directions, from FM 306 to Conrads Ln. for setting barrier and striping work. The Watson and Conrads Ln. ramps will also be closed.
  • Sunday, August 22 until Monday, August 23. 9 p.m. to 5 a.m. Double mainlane closures, in both directions, from FM 306 to Conrads Ln. for setting barrier and striping work. The Watson and Conrads Ln. ramps will also be closed.
  • Wednesday, August 25 until Thursday, August 26. 8 p.m. to 5 a.m. Double mainlane closures, in both directions, from Watson Ln. to Conrads Ln. for bridge demolition.
  • Thursday, August 26 until Friday, August 27. 9 p.m. to 5 a.m. Full closure of the northbound mainlanes from Watson Ln. to Conrads Ln. for bridge demolition.
  • Friday, August 27 until Saturday, August 28. 9 p.m. to 9 a.m. Full closure of the southbound mainlanes from Watson Ln. to Conrads Ln. for bridge demolition.
  • Saturday, August 28 until Sunday, August 29. 9 p.m. to 9 a.m. Double southbound mainlane closure from Watson Ln. to Conrad Ln. for bridge demolition.
  • Sunday, August 29 until Monday, August 30. 9 p.m. to 5 a.m. Double northbound mainlane closure from Watson Ln. to Conrads Ln. for bridge demolition.
  • Current until Tuesday, August 24. 9 p.m. to 5 a.m. Double mainlane closures, in both directions, from Watson Ln. to Parkway for access work under Parkway bridge and drainage operations.
  • Current until Saturday, August 28. Single lane closures on the frontage roads, in both directions, from FM 2252 to FM 1103 for material haul-off.
  • Current until Saturday, August 28. 9 a.m. to 5:30 p.m. Right lane closure on the northbound frontage road from FM 1103 to Schwab Rd. for curb demolition and material haul-off.
  • Friday, August 20 until Saturday, August 21. 9 p.m. to 5 a.m. Double mainlane closures, in both directions, from FM 306 to Conrads Ln. for setting barrier and striping work. The Watson and Conrads Ln. ramps will also be closed.
  • Sunday, August 22 until Monday, August 23. 9 p.m. to 5 a.m. Full northbound mainlane and southbound left shoulder closure, from Exit 178 to Schwab Rd. for overhead sign bridge work.
  • Wednesday, August 25 until Saturday, August 28. 8 p.m. to 5 a.m. Double mainlane closures, in both directions, from Watson to Conrads Ln. for setting barrier and striping work. The Watson and Conrads Ln. ramps will also be closed. Traffic will need to use the Parkway bridge. 

I-410 – North San Antonio

  • Sunday, August 22 until Monday, August 23. 9 p.m. to 5 a.m. Eastbound and westbound flyover ramps to southbound US 281 closed for bridge repairs. DETOUR: Traffic will be diverted to the frontage roads. 

I-410 – East San Antonio

  • Sunday, August 22 until Friday, August 27. 9 p.m. to 5 a.m. Various mainlane closures, in both directions from I-35 to I-10 for overhead sign replacements. 

I-410 – West San Antonio

  • Current until Sunday, August 29. 8 p.m. to 5 a.m. Full closure of the northbound frontage road from Meadow Breeze Dr. to SH 151 for bridge work.
  • Current until Sunday, August 29. 8 p.m. to 5 a.m. Full closure of the mainlanes, in both directions, from W. Military Dr. to Marbach Rd. for bridge work.
  • Current until Sunday, August 29. 9 a.m. to 3 p.m. Alternating lane closures, in both directions, on the frontage roads from Marbach Rd. to Bandera Rd. for bridge work.
  • Current until Sunday, August 29. 8 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from Marbach Rd. to Ingram Rd. for bridge work.
  • Current until Sunday, August 29. 8 a.m. to 4 p.m. Southbound bypass lane at W. Military Dr. closed for concrete work.

I-410 – Southwest San Antonio

  • Sunday, August 22 until Friday, August 27. 9 p.m. to 5 a.m. Left lane on southbound frontage road closed from Medina Base Rd. to Ray Ellison Blvd. for striping and barrier installation.
  • Current until December 2021. Left lane closed on the southbound frontage road at Valley Hi. 

SH 151 – West San Antonio

  • Current until Sunday, August 29. 8 p.mm. to 5 a.m. Full closure of the eastbound frontage road from Cable Ranch Rd. to Loop 410 for bridge work.
  • Current until Monday, August 23. 8 p.m. to 5 a.m. Eastbound flyover ramp to northbound Loop 410 closed for rail work. DETOUR: Traffic will exit SH 151 at Cable Ranch Rd., turn left at Loop 410 intersection and enter Loop 410 at W. Military Dr. entrance ramp. 

SL 13 – Military Dr.

  • Current until Tuesday, August 31. 8 a.m. to 4 p.m. Single westbound lane closure from Bardwell Dr. to Alsbrook Dr. for sidewalk improvements.
  • Current until Tuesday, August 31. 8 a.m. to 4 p.m. Single westbound lane closure from New Laredo Hwy. to Somerset Rd. for sidewalk improvements. 

SH 16 – Bandera Road

  • Monday, August 23 until Friday, September 3. Eastbound right lane closed from Braun Rd. to Loop 410 for sidewalk and driveway improvements. 

FM 1976 – Walzem Road/Gibbs Sprawl Road

  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes between Woodlake Parkway and Gibbs Sprawl Road for barrier/pavement work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
  • Current until further notice. Full-day closure. Southbound lane between Toepperwein Road and Walzem Road for barrier setting work and road rehab work. 

FM 345 – Fredericksburg Rd.

  • Current until Tuesday, August 31. 8 a.m. to 4 p.m. Single eastbound lane closure from Loop 410 to Hillcrest Dr. for sidewalk improvements. 

US 87 – Rigsby Road

  • Current until Tuesday, August 31. 8 a.m. to 4 p.m. Single eastbound lane closure from Pecan Valley Rd. to Ancel Rd. for sidewalk improvements. 

SH 46 – Kendall County

  • Current until September 2021. Roadway at I-10 intersection reduced to two-lanes, with the closure of the inbound right turn lane and Whataburger driveway. Traffic will be shifted onto temporary pavement as new roadway is constructed. 

SH 123 – Guadalupe County

  • Current until Friday, August 27. 8 a.m. to 7 p.m. Full closure in both directions from 3 miles north of FM 1681 to Zion Hill Rd. for roadway repairs.