Monday, May 10

OPENING OF THE LOOP 1604 FLYOVER RAMPS TO NORTHBOUND US 281

*OPENING WAS POSTPONED DUE TO WEATHER. RAMPS ARE EXPECTED TO OPEN LATER IN THE WEEK*



Exciting news, we are now ready to open both the east- and westbound Loop 1604 flyover ramps to northbound US 281 mainlanes. 

Opening overnight on Monday, May 10, the new flyover ramps will provide drivers with direct access to northbound US 281 mainlanes without needing to exit or use frontage roads. 

Please note that construction is weather permitting and subject to change.

Want to stay informed of lane closures by receiving alerts directly to your e-mail? Click here to subscribe. You can also see closures across the San Antonio region by following us on Facebook or Twitter.

CONSTRUCTION IS RAMPING UP ON LOOP 1604 EXPANSION PROJECT

 


The Texas Department of Transportation (TxDOT) is ramping up construction on Segment 1 of the Loop 1604 Expansion Project from SH 16 (Bandera Rd.) to I-10 in northwest Bexar County. This week, crews will begin preparation work for the start of major construction activities in early June 2021.

Over the next few weeks, drivers will experience minimal impact to traffic flow as lane shifts are implemented. Currently scheduled lane closures for Segment 1 are listed below.

Monday, May 10 to Friday, May 21
Weekday Nights 9PM to 5AM

  • Eastbound Loop 1604 entrance ramp to La Cantera Parkway
    • DETOUR: La Cantera Parkway traffic will continue on eastbound frontage road and enter Loop 1604 at next entrance ramp. 
  • Eastbound Loop 1604 exit ramp to Vance Jackson
    • DETOUR: Traffic will be directed to exit at La Cantera Parkway, merge to the frontage road, and travel through the La Cantera Parkway intersection.

*Note: Closures are scheduled from 9PM Sunday to 5AM Friday, with no weekend closures. Construction is subject to change, due to weather and other variables.

These closures will allow crews to arrange construction work zones with barrier placements and lane re-striping operations in preparation for major construction activities planned for the expansion project.

The Loop 1604 Expansion Project involves several non-toll transportation improvements, from SH 16 to I-35,  that are designed to increase mobility, reduce congestion and enhance safety along the highly-traveled corridor. Segment 1 of the Loop 1604 Expansion Project has a total estimated cost of $148 million. Williams Brothers Construction Company, Inc. was awarded the project in April 2021.

We want you to stay connected! Subscribe for project updates here


Friday, May 7

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

 


Loop 1604 – North Central San Antonio

  • Friday, May 7 until Sunday, May 9. Weekend continuous 9 p.m. until 5 p.m. Full eastbound mainlane closure of the eastbound direct connector ramp to southbound US 281 for asphalt paving. DETOUR: Use the northbound US 281 exit ramp and take a right on the southbound US 281 frontage road.
  • Friday, May 7 until Sunday, May 9. Weekend continuous 9 p.m. until 5 p.m. Full westbound mainlane closure of the westbound direct connector ramp to southbound US 281 for asphalt paving. DETOUR: Use the northbound US 281 exit ramp and take a left on the southbound US 281 frontage road.
  • Monday, May 10 until Friday, May 14. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure of the eastbound direct connector ramp to southbound US 281 for striping. DETOUR: Use the northbound US 281 exit ramp and take a right on the southbound US 281 frontage road.
  • Monday, May 10 until Friday, May 14. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure of the westbound direct connector ramp to southbound US 281 for asphalt paving. DETOUR: Use the northbound US 281 exit ramp and take a left on the southbound US 281 frontage road.
  • Saturday, May 15 until Sunday, May 16. Weekend continuous 9 a.m. until 3 p.m. Alternating eastbound mainlane closure from Stone Oak Parkway to US 281 for asphalt paving.
  • Saturday, May 15 until Sunday, May 16. Weekend continuous 9 a.m. until 3 p.m. Alternating westbound mainlane closure from US 281 to Stone Oak Parkway for asphalt paving. 

Loop 1604 – Far East San Antonio/Bexar County

  • Saturday, May 8. 5 a.m. to 3 p.m. Full closure of mainlanes at I-10 intersection for bridge work. DETOUR: Northbound traffic will take I-10 eastbound frontage road and turnaround at Pfeil Rd. Southbound traffic will take I-10 westbound frontage road and turnaround at FM 1516. 

Loop 1604 – North East San Antonio/Bexar County

  • Sunday, May 9 until Monday, May 10. 9 p.m. to 5 a.m. Single lane closure on northbound frontage road from Palisades Dr. to Pat Booker Rd. for traffic switch.
  • Tuesday, May 11 until Wednesday, May 12. 9 p.m. to 5 a.m. Single lane closure on northbound frontage road from Palisades Dr. to Pat Booker Rd. for traffic switch. 

Loop 1604 – North West San Antonio/Bexar County

  • Monday, May 10 until Friday, May 21. Weekday Nights 9 p.m. to 5 a.m. Eastbound entrance ramp from La Cantera Parkway closed for barrier setting and re-striping. DETOUR: Traffic will continue on eastbound Loop 1604 frontage road and enter mainlanes after the I-10 intersection.
  • Monday, May 10 until Friday, May 21. Weekday Nights. 9 p.m. to 5 a.m. Eastbound exit ramp to Vance Jackson Rd. closed for barrier setting and re-striping. DETOUR: Traffic will exit at La Cantera Parkway and continue through the La Cantera Parkway intersection. 

Loop 1604 – South San Antonio/Bexar County

  • Monday, May 10 until Thursday, May 13. 8 a.m. to 5 p.m. Single lane closure, in both directions, from Senior Rd. to Morin Rd. for road improvements. 

US 281 – North Central San Antonio/Bexar County

  • Monday, May 10 until Friday, May 14. 9 p.m. to 5 a.m. Various mainlane closures, in both directions, from I-35 to Basse Rd. for overhead sign replacements.
  • Monday, May 10 until Friday, May 14. 9 a.m. to 3 p.m. Single eastbound lane of Overlook Parkway at US 281 closed for sidewalk improvements
  • Friday, May 14 until Friday, May 21. 9 p.m. to 5 a.m. Full closure of Borgfeld Rd. at US 281 intersection for drainage installation.
  • Saturday, May 8 until Sunday, May 9. Weekend continuous 9 a.m. until 3 p.m. Alternating northbound mainlane closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for concrete paving.
  • Saturday, May 8 until Sunday, May 9. Weekend continuous 9 a.m. until 3 p.m. Alternating southbound mainlane closure from Stone Oak Parkway to Loop 1604 for concrete paving.
  • Monday, May 10 until Friday, May 14. Continuous 9 a.m. until 3 p.m. Northbound frontage road closure of the north- to southbound turnaround at Evans Road for concrete paving. DETOUR: Use the turnaround at Stone Oak/Tournament Players Club (TPC) Parkway.
  • Monday, May 10 until Friday, May 14. Continuous 9 a.m. until 3 p.m. Southbound frontage road closure of the south- to northbound turnaround at Evans Road for concrete paving. DETOUR: Use the turnaround at Encino Rio.
  • Monday, May 10 until Friday, May 14. Continuous 9 a.m. until 3 p.m. Northbound frontage road closure of the north- to southbound turnaround at Stone Oak/Tournament Players Club (TPC) Parkway for concrete paving. DETOUR: Use the turnaround at Marshall Road.
  • Monday, May 10 until Friday, May 14. Continuous 9 a.m. until 3 p.m. Alternating northbound frontage road closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for painting, landscaping, and asphalt paving.
  • Monday, May 10 until Friday, May 14. Continuous 9 a.m. until 3 p.m. Alternating southbound frontage road closure from Stone Oak Parkway to Loop 1604 for painting, landscaping, and asphalt paving.
  • Monday, May 10 until Friday, May 14. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for sign installation.
  • Monday, May 10 until Friday, May 14. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Stone Oak Parkway to Loop 1604 for sign installation.
  • Saturday, May 15 until Sunday, May 16. Weekend continuous 9 a.m. until 3 p.m. Alternating northbound mainlane closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for concrete paving.
  • Saturday, May 15 until Sunday, May 16. Weekend continuous 9 a.m. until 3 p.m. Alternating southbound mainlane closure from Stone Oak Parkway to Loop 1604 for concrete paving.
  • Saturday, May 15. 7 a.m. to 5 p.m. Single southbound lane closure from Borgfeld Rd. to Bulverde Rd. for demolition. 

Stone Oak Parkway – North Central San Antonio

  • Friday, May 7 until Saturday, May 8. Weekend overnight 9 p.m. until 5 p.m. Alternating eastbound crossing closure at the US 281 intersection for a traffic switch.
  • Friday, May 7 until Saturday, May 8. Weekend overnight 9 p.m. until 5 p.m. Alternating westbound crossing closure at the US 281 intersection for a traffic switch. 

I-10 – North West San Antonio/Bexar County/Kendall County/Kerr County 

  • Friday, May 14 – 9 p.m. to Monday, May 17 – 5 a.m. Full closure of mainlanes from SH 46 to Scenic Loop Rd. for demolition of US 87 bridge. Lanes under Scenic Loop Rd. bridge will also be closed. DETOUR: Traffic will be directed to frontage roads. 

I-10 – Far East San Antonio/Bexar County/Seguin/Guadalupe County 

  • Saturday, May 8. 7 a.m. to 5 p.m. Single westbound mainlane closure from Martinez Creek to Woodlake Parkway for pipe installation.
  • Monday, May 10 until Tuesday, May 11. 8:30 p.m. to 5:30 p.m. Single westbound mainlane closure from FM 2538 to Pfeil Rd. for barrier movement.
  • Monday, May 10 until Friday, May 14. 7 p.m. to 5 a.m. Double left mainlane closures, in both directions, from Loop 1604 to Saltrillo Creek for material hauling.
  • Wednesday, May 12 until Thursday, May 13. 8:30 p.m. to 5:30 a.m. Alternating westbound mainlane closures from Zuehl Rd. to Pfeil Rd. for barrier movement.
  • Thursday, May 13 until Friday, May 14. 8:30 p.m. to 5:30 a.m. Alternating westbound mainlane closures from Zuehl Rd. to Pfeil Rd. for barrier movement.
  • Saturday, May 15. 5 a.m. to 9 p.m. Single westbound mainlane closure from Zuehl Rd. to Pfeil Rd. for barrier movement asphalt operations.
  • Current until Thursday, July 1. Westbound frontage road left lane closed between Foster Road and Rosillo Creek from noon to 5 p.m. for embankment work. Westbound Ackerman Road exit also closed from noon to 5 p.m. DETOUR: Westbound traffic wanting to exit to Ackerman may use Foster Road exit.
  • Current until further notice. Graytown Road closed at I-10. DETOURS: Graytown Road traffic may use the frontage road and the Pfeil Road underpass or Loop 1604 turnaround to cross I-10.
  • Current until further notice. Eastbound entrance ramp from Foster Road closed. DETOUR: Take the next entrance ramp east of Woodlake Parkway. 

I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

  • Monday, May 10 until Friday, May 1. 9 p.m. to 5 am. Double southbound mainlane closure from Schwab Rd. to FM 1103 for milling and overlay work.
  • Tuesday, May 11 until Saturday, May 22. 9 p.m. to 5 a.m. Double mainlane closures, in both directions, from Watson Lane to Parkway intersection for work on retaining wall. 

I-410 – West San Antonio

  • Current until Monday, May 10. 8 p.m. to 5 a.m. Full closure of Culebra Rd. intersection for bridge work.
  • Current until Monday, May 10. 8 p.m. to 5 a.m. Full closure of mainlane, in both directions, from W. Military Dr. to Marbach Rd. for bridge work.
  • Current until Monday, May 10. 8 a.m. to 5 p.m. Single lane closure on southbound frontage road from N.W. Crossroads to W. Military Dr. for underground work.
  • Current until Monday, May 10. 9 a.m. to 4 p.m. Single lane closure on southbound frontage road from Loop 410 to Ingram Rd. for wall improvements.
  • Current until Monday, May 10. 8 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from Marbach Rd. to Culebra Rd. for bridge work.
  • Current until Monday, May 10. 9 a.m. to 3 p.m. Single lane closure on eastbound frontage road from Loop 410 to Ingram Rd. for bridge work.
  • Current until Monday, May 10. 8 p.m. to 5 a.m. Double lane closure on southbound frontage roads from SH 151 to Lakeside Parkway for bridge work.
  • Current until Monday, May 10. 9 a.m. to 3 p.m. Single lane closures on frontage roads, in both directions, from Marbach Rd. to Bandera Rd. for bridge work.
  • Monday, May 10 until Monday, May 17. 8 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from Marbach Rd. to Culebra Rd. for bridge work.
  • Monday, May 10 until Monday, May 17. 8 p.m. to 5 a.m. Full closure of northbound frontage road from Meadow Breeze Dr. to SH 151 for bridge work.
  • Monday, May 10 until Monday, May 17. 9 a.m. to 3 p.m. Alternating lane closures on frontage roads, in both directions, from Marbach Rd. to Bandera Rd. for bridge work.   

SH 151 – West San Antonio

  • Current until Monday, May 10. 8 p.m. to 5 a.m. Full closure of eastbound frontage road from Cable Ranch Rd. to Loop 410 for bridge work.
  • Monday, May 10 until Monday, May 17. Nightly 8 p.m. to 5 a.m. Full closure of westbound frontage road until Loop 410 to bridge rail demolition.
  • Monday, May 10 until Monday, May 17. 9 a.m. to 3 p.m. Single lane closure on eastbound frontage road from Loop 410 to Ingram Rd. for bridge work. 

FM 471 – Culebra Road

  • Monday, May 10 until Friday, May 28. 8:30 a.m. to 3:30 p.m. Single eastbound lane closure from Mountain View to Les Harrison Dr. for sidewalk improvements.

Loop 13 – Military Drive

  • Monday, May 10 until Friday, May 28. 8:30 a.m. to 3:30 p.m. Single eastbound lane closure from Quintana Rd. to Bynum Ave. for sidewalk improvements. 

SH 218 – Pat Booker Road

  • Sunday, May until Wednesday, May 12. 9 p.m. to 5 a.m. Full closure of eastbound lanes from Village Oak Dr. to Athenian Dr. for traffic switch. 

FM 1976 – Walzem Road/Gibbs Sprawl Road

  • Tuesday, May 11 until Friday, May 21. 8 a.m. to 5 p.m. Alternating northbound lane closures from Toepperwein Rd. to Hilltop Rd. for paving operations.
  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes between Woodlake Parkway and Gibbs Sprawl Road for barrier/pavement work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
  • Current until further notice. Full-day closure. Southbound lane between Toepperwein Road and Walzem Road for barrier setting work and road rehab work.


Thursday, May 6

FULL CLOSURE OF I-10 IN BOERNE STARTING FRIDAY, MAY 14

*DUE TO WEATHER, THIS CLOSURE HAS BEEN POSTPONED TO THE WEEKEND OF JUNE 11.*




As part of the ongoing IH-10 frontage road construction, work is progressing into the next stage of construction which will require the demolition of the existing US-87 (Main Street) bridge. 

In order to safely remove the bridge, crews will need approximately 56 hours of continuous full mainlane closure of the IH-10 eastbound and westbound travel lanes between SH-46 (Bandera Rd) and Scenic Loop. The removal of this bridge will allow crews to start working on the new US-87 bridge.  

The work is scheduled to start on Friday May 14, 2021 at 9:00 pm and is expected to be completed by 5:00 am on Monday May 17, 2021, weather permitting.

The westbound mainlanes will be removed at Exit 542 Business US-87 and will be directed along the Westbound Frontage Road to the next available entrance ramp prior to SH-46, and

The eastbound mainlanes will be removed near SH-46 and will be detoured along the Eastbound Frontage Road and will be allowed to enter back onto the mainlanes east of Scenic Loop.  

During this closure, there will be no through traffic at Scenic Loop under IH-10. All traffic will be required to turn right onto the frontage roads.

  • Northbound Scenic Loop traffic will be detoured to Balcones Creek intersection and
  • Southbound Scenic Loop traffic will be detoured to the SH-46 intersection.
As a reminder, all construction work is subject to change. 

    Need Additional Information?

    Construction Update “Go Ahead!” Bloghttp://txdotsanantonio.blogspot.com/

    Twitter: @TxDOTSanAntonio 

    OPENING OF STONE OAK PARKWAY INTERSECTION AT US 281

    Now that the US 281 mainlanes north of Stone Oak Parkway have opened, we are thrilled to announce that the Stone Oak/Tournament Players Club (TPC) Parkway underpass intersection at US 281 will follow this weekend, the evening of Saturday, May 8. 

    Opening the Stone Oak Parkway intersection under US 281 will allow drivers to cross from one side of Stone Oak Parkway to the other with both east- and westbound lanes of Stone Oak/Tournament Players Club (TPC) Parkway along with both the north- to southbound and south- to northbound turnarounds moving onto the frontage roads. The conversion of this intersection will include pedestrian access.

    Please note that construction is weather permitting and subject to change.

    You can stay informed of lane closures by receiving alerts to your e-mail by registering here or by following us on our Twitter feed .