Pages

Monday, February 4

Project updates....

Across the San Antonio area, we have about a dozen major projects to keep you up-to-date on.

Without any ado, we'll just get right into it (for more info on the project itself - what we're doing, the scope and, in some cases, a graphic of what we're doing, hit the link attached to each project title):

Main Street Boerne

Last month our crews laid out the project area at the Cibolo Creek bridge. Expect action to pick up this month, as work on the traffic signal upgrades should start by mid-month. Crews will begin setting up structures to help build support structures for the bridge expansion.

Highway 39 Ingram

Crews set up environmental protection measures in January and, over the next month, will begin work almost exclusively at the Johnson Creek bridge. Most of this work will remain outside the traveling lanes, meaning you shouldn't see much in the way of actual disruption to your drive.

FM 306

Most of the work, at this point, has been setting up a work zone and beginning to widen the roadway at Purgatory Road. Non-TxDOT crews have been relocating utilities between I-35 and Hunter Road. In February, expect the turn-lane work around Purgatory Road to intensify; drivers may see occasional slow-downs as trucks enter and exit the roadway. Meanwhile, we expect work nearer to I-35 to remain about the way it is most of this month.

Business 46

This project will pause for the summer, so crews are working to get as much prep work done as they can. They've already cleared the work zone and have laid out the retaining walls to be built. Next month crews will focus on support structures for the retaining walls, moving the excess material to help build a railroad detour to be used later in the project. Most of this work is outside the traveling lanes, so drivers shouldn't be hindered by the work.

Wurzbach Parkway

Progress continues between West Avenue and Jones-Maltsberger, with most of the work done near U.S. Highway 281. Beams were set on the future east-bound entrance ramp from Hwy 281 to the Parkway, and dirt work is progressing quickly. In February, expect work to ramp up (no pun intended) as we begin our efforts to fit the entrance and exit ramps between Nakoma and Bitters to the new Wurzbach parkway. This will mean some weekend closures of the north-bound frontage road between Arion Parkway and Bitters, scheduled for the weekend of Feb. 16-17 (more on that tomorrow).

We're still working with the responsible bonding company to get new contractors for the "book-end" sections, covering Blanco-to-West and JM-to-Wetmore.

1604-281 Interchange

Work continues - heck, they're nearing completion - on the interchange project. The good folks with the Alamo Regional Mobility Authority will be able to give you a better idea of what the most up-to-date information on that project is, so check them out (by hitting the link attached to the project name).

Fred-Med

If you've been paying attention to the media over the last few months, you may have heard we had a contractor declare bankruptcy. Fortunately, this project hadn't started yet - so we are in the process now of finding a new contractor to build this project. As soon as we have a new contractor, we'll be sure to let you know!

I-10 Huebner

Like the Fred-Med project (and two of the three segments of Wurzbach Parkway), this project has been caught in the tangle with the contractor that has declared bankruptcy. While it's frustrating to consistently drive through the area without seeing much change, we're inching closer to having a new contractor on board so we can get going again. We'll be sure to fill you in when that happens.

I-35 Selma

Wow, so much has happened ... I'm not sure just where to start. In January, we:
  • Built the bridge abutment structures for the FM 3009 turnaround bridges
  • Began laying out the support column structures for the FM 3009 bridges
  • Removed pavement from old exit/entrance ramps to be converted between FM 1518 and Schertz Parkway
  • Closed and began work on the upgrated exit ramp to Forum Parkway
Over February, the contractor will be prioritizing work at the Forum Parkway exit. Work will continue steadily at the entrance and exit ramps between FM 1518 and Schertz Parkway. We should see the support columns at FM 3009 formed and, if weather holds, built.

Vance Jackson Bridge

Not to be confused with the work the city of San Antonio is doing on Vance Jackson near Wurzbach in the city's northwest side, the work we are doing is a simple bridge overpass over Loop 1604 near The Rim (as if a bridge is all that simple...).

Anyway, the project continues smoothly - we've got abutment shelves built and work on the support columns is progressing smoothly. Look for crews to start working on column caps - large shelves on top of the support colmns. These caps will hold the support beams, which should be set in the next several weeks.

U.S. 281 Comal

This project is just getting underway, with crews just starting to lay out work areas. Expect excavation and clearing over the month of February, with most of the work happening outside the traveling lanes.

Loop 1604 Marbach

I almost forgot! We're still working on getting the Web page updated, but we're now at work and this project has moved beyond planning stages. Crews have just started working on clearing the construction zone, and have started laying the project out. Don't expect much to interfere with traffic for the month of February, but before summer things will get a little more hectic.