Loop 1604 work

Loop 1604 northwest

The design-build project on Loop 1604, which expands the loop to an expressway with overpasses at Braun, Shaenfield and New Guilbeau roads, is moving ahead at full steam. That's even despite the rain storms over the last couple of weeks.

Last month Leslie Road was converted to a one-way road between Shaenfield and Culebra, and local residents are getting accustomed to the new traffic configuration. Crews with Williams Brothers Construction have been adding a temporary widening on Leslie - now effectively the southbound frontage road - to provide some added space for work to be done. The road needs to be rebuilt to meet TxDOT specifications - until now it's been a city road - and match the improvements planned to the area.

Tree trimmers have cut back mesquite trees and other brush that would have been in the way of work, particularly where the southbound frontage road near New Guilbeau will go and along the future northbound frontage road throughout. Those trees that have been removed have been mulched. A few large oak trees - known on the project as 'legacy oaks' have been preserved and sprayed to protect against oak rot.

With trees out of the way, dirt is being moved to form the footprint of the northbound frontage road.

Meanwhile, dirt crews are working - and will be working for the foreseeable future - on the embankment (big dirt mounds) at Braun Road. Because of the room in the center median there, Williams Brothers is moving forward with what will be the overpass structure there. Adjustments to the ramps will need to happen as well.

For now, the everyday driver won't be impacted by the work happening. Planned lane closures are typically at night only, and only a single lane here or there (to set barriers, for instance) at that.

Marbach overpass

Well, there's not a whole lot to say about this project besides we're almost done. We expect to have the overpass open and in use - one lane in each direction - and our project completed in July. We have some minor concrete work to do and some asphalt to lay, and that's about it.

A huge credit to Capital Excavation for working hard at this project for the duration of this project.