Interstate 10

Friday-Saturday, July 11-12

8:30 p.m. until 6 a.m.

Eastbound main lanes between UTSA Boulevard and Fredericksburg Road (northwest San Antonio)

The two right lanes will close while crews restripe the road and move barrier. Only one lane will be open. Expect long delays.

 

Monday-FridayJuly 14-18

9 a.m. until 3:30 p.m. daily

Westbound frontage road between Huebner Road and Loop 1604 (northwest San Antonio)

Alternating lanes will close while crews move barrier and lay pipe. Expect delays.

 

Monday-FridayJuly 14-18

9 a.m. until 3:30 p.m. daily

Eastbound frontage road between Huebner Road and Loop 1604 (northwest San Antonio)

Alternating lanes will close while crews move barrier and build storm drain. Expect delays.

 

Monday-FridayJuly 14-18

9 p.m. until 5:30 a.m. nightly

Westbound frontage road between Huebner Road and Loop 1604 (northwest San Antonio)

Alternating lanes will close while crews move barrier and build storm drain. Expect delays.

 

Monday-FridayJuly 14-18

8:30 p.m. until 5:30 a.m. nightly

Eastbound frontage road between Huebner Road and Loop 1604 (northwest San Antonio)

Alternating lanes will close while crews move barrier and build storm drain. Expect delays.

 

Monday-FridayJuly 14-18

8:30 p.m. until 5:30 a.m. nightly

Eastbound main lanes between Loop 1604 and Fredericksburg Road (northwest San Antonio)

Alternating lanes will close while crews move barrier and place asphalt. Expect delays.

 

Monday-FridayJuly 14-18

8:30 p.m. until 5:30 a.m. nightly

Westbound main lanes between UTSA Boulevard and Huebner Road (northwest San Antonio)

The right lane will close while crews widen the roadway. Expect delays.

 

Interstate 35

Sunday-FridayJuly 13-18

9 p.m. until 5:30 a.m. nightly

Main lanes, both directions, between Pat Booker and Evans roads (Live Oak-Selma)

Alternating lanes will close while crews lay asphalt and paint the roadway. Expect delays.

 

Sunday-TuesdayJuly 13-15

9 p.m. until 5 a.m. nightly

Southbound main lanes between Eisenhauer and George Beach (northeast San Antonio)

The two left lanes will close while crews place lane markers. Expect delays.

 

Sunday-Saturday, July 13-August 16

9 p.m. until 5 a.m. nightly

Northbound main lanes at New Braunfels Ave (east San Antonio)

All lanes will close while crews repair the bridge beams. Traffic will exit New Braunfels and reenter the main lanes before Walters Street. Eastbound New Braunfels Ave will also be closed for this work. Traffic on New Braunfels Ave will follow the posted detour. This closure includes the northbound exit to AT&T Parkway. Traffic will use the next available exit and turn around. Expect long delays.

 

Interstate 37

No closures scheduled.

 

Interstate 410

Monday-TuesdayJuly 14-15

9 p.m. until 5 a.m.

Eastbound exit to northbound I-35 (northeast San Antonio)

The right lane will close while crews repair a crash cushion. Expect delays.

 

Loop 1604

Sunday-SaturdayJuly 13-19

9 a.m. until 4 p.m. daily

Main lanes, both directions, between Culebra and Bandera roads (northwest San Antonio)

Various shoulder areas will close while survey crews locate utilities along the project.

 

Sunday-SaturdayJuly 13-19

9 a.m. until 4 p.m. daily

Main lanes, both directions, between Culebra and Bandera roads (northwest San Antonio)

Alternating lanes, including the shoulder area, will close while crews clean up and maintain the work area. Most of these closures will be brief (less than two hours).

 

Sunday-TuesdayJuly 13-15

9 p.m. until 5 a.m. nightly

Northbound main lanes at Culebra Road (northwest San Antonio)

The right lane will close while crews drill foundations for digital message sign supports. Expect delays.

 

Monday-TuesdayJuly 14-15

11 a.m. until 2 p.m. daily

Northbound main lanes at Culebra Road (northwest San Antonio)

The right lane will close while crews pour concrete. Expect delays.

 

U.S. Highway 90

No closures scheduled.

 

U.S. Highway 281

No closures scheduled.

 

Other roads

Friday-MondayJuly 11-14

8:30 p.m. until 5:30 a.m. continuous

DeZavala Road, both directions, at I-10 (northwest San Antonio)

All lanes will close while crews demolish the eastbound overpass bridge deck. Traffic will turn right onto the frontage road and use turnarounds at UTSA Boulevard or at Fredericksburg Road to reach its destination. Expect long delays.

 

Sunday-SaturdayJuly 13-19

8 p.m. until 5 a.m. nightly

Fredericksburg Road, both directions, between Louis Pasteur and Data Point (Medical Center)

Alternating lanes will close while crews build bridge support structures. Expect delays.

 

Sunday-SaturdayJuly 13-19

8 p.m. until 5 a.m. nightly

Medical Drive, both directions, between Fredericksburg Road and Ewing Halsell (Medical Center)

Alternating lanes will close while crews work on the roadway base. Expect delays.

 

Friday-MondayJuly 18-21

8 p.m. until 5 a.m. continuous

Medical Drive, both directions, between Ewing Halsell and Fredericksburg (Medical Center)

Two lanes will close while crews construct the eastbound lanes of Medical Drive. Traffic will have just one lane open in each direction. Expect delays.

 

All planned lane closures are pending weather.