Interstate 10

Monday-FridayJuly 21-25

9 a.m. until 3:30 p.m. daily

Westbound frontage road between Huebner Road and Loop 1604 (northwest San Antonio)

Alternating lanes will close while crews move barrier and lay pipe. Expect delays.

 

Monday-FridayJuly 21-25

9 a.m. until 3:30 p.m. daily

Eastbound frontage road between Huebner Road and Loop 1604 (northwest San Antonio)

Alternating lanes will close while crews move barrier and build storm drain. Expect delays.

 

Monday-FridayJuly 21-25

9 p.m. until 5:30 a.m. nightly

Westbound frontage road between Huebner Road and Loop 1604 (northwest San Antonio)

Alternating lanes will close while crews move barrier and build storm drain. Expect delays.

 

Monday-FridayJuly 21-25

8:30 p.m. until 5:30 a.m. nightly

Eastbound frontage road between Huebner Road and Loop 1604 (northwest San Antonio)

Alternating lanes will close while crews move barrier and build storm drain. Expect delays.

 

Monday-FridayJuly 21-25

8:30 p.m. until 5:30 a.m. nightly

Eastbound main lanes between Loop 1604 and Fredericksburg Road (northwest San Antonio)

Alternating lanes will close while crews move barrier and place asphalt. Expect delays.

 

Monday-FridayJuly 21-25

8:30 p.m. until 5:30 a.m. nightly

Westbound main lanes between UTSA Boulevard and Huebner Road (northwest San Antonio)

The right lane will close while crews widen the roadway. Expect delays.

 

Interstate 35

Sunday-FridayJuly 20-25

9 p.m. until 5 a.m. nightly

Southbound main lanes between Eisenhauer and George Beach (northeast San Antonio)

Alternating lanes will close while crews lay asphalt, stripe the roadway and set barrier. Expect delays.

 

Sunday-FridayJuly 20-25

9 p.m. until 5 a.m. nightly

Northbound main lanes between George Beach and Rittiman Road (northeast San Antonio)

Alternating lanes will close while bridge crews set bridge deck panels. Expect delays.

 

Sunday-Saturday, July 20-August 16

9 p.m. until 5 a.m. nightly

Northbound main lanes at New Braunfels Ave (east San Antonio)

All lanes will close while crews repair the bridge beams. Traffic will exit New Braunfels and reenter the main lanes before Walters Street. Eastbound New Braunfels Ave will also be closed for this work. Traffic on New Braunfels Ave will follow the posted detour. This closure includes the northbound exit to AT&T Parkway. Traffic will use the next available exit and turn around. Expect long delays.

 

Interstate 37

No closures scheduled.

 

Interstate 410

No closures scheduled.

 

Loop 1604

Saturday-MondayJuly 19-21

9 p.m. until 5 a.m. nightly

Intersection at Shaenfield Drive and at New Guilbeau Road (northwest San Antonio)

Alternating lanes will close while surveyors test the roadway. Expect minor delays.

 

U.S. Highway 90

No closures scheduled.

 

U.S. Highway 281

No closures scheduled.

 

Other roads

Sunday-SaturdayJuly 20-26

8 p.m. until 5 a.m. nightly

Fredericksburg Road, both directions, between Louis Pasteur and Data Point (Medical Center)

Alternating lanes will close while crews build bridge support structures. Expect delays.

 

Sunday-SaturdayJuly 20-26

8 p.m. until 5 a.m. nightly

Medical Drive, both directions, between Fredericksburg Road and Ewing Halsell (Medical Center)

Alternating lanes will close while crews work on the roadway base. Expect delays.

 

Friday-MondayJuly 18-21

8 p.m. until 5 a.m. continuous

Medical Drive, both directions, between Ewing Halsell and Fredericksburg (Medical Center)

Two lanes will close while crews construct the eastbound lanes of Medical Drive. Traffic will have just one lane open in each direction. Expect delays.

 

All planned lane closures are pending weather.