Pages

Friday, May 29

Next week's construction-related closures



Previously scheduled closures at the intersection of Fredericksburg Road and Medical Drive, as well as the westbound exit ramp to DeZavala Road, have been postponed (again) due to weather.

I-10
  • Tuesday, May 26-Friday, June 5. 9 a.m. until 3 p.m. daily. Eastbound frontage road between Cincinnati Road and Culebra Road (downtown). The left lane will close while crews do bridge work.
  • Monday-Friday, June 1-5. 9 a.m. until 4 p.m. daily. Frontage road, both directions, between Loop 1604 and Huebner Road (northwest San Antonio). Alternating lanes will close for road work.
  • Sunday-Friday, May 31-June 5. 8:30 p.m. until 5:30 a.m. nightly. Frontage road, both directions between Loop 1604 and Huebner Road (northwest San Antonio). Alternating lanes will close for road work.
  • Sunday-Friday, May 31-June 5. 8:30 p.m. until 5:30 a.m. nightly. Main lanes, both directions, between Huebner Road and Loop 1604 (northwest San Antonio). Alternating lanes will close while crews repave the roadway and work on overhead highway signs.
  • Wednesday-Friday, June 3-5. 9 p.m. until 5:30 a.m. Eastbound main lanes between I-37 and New Braunfels Ave (east San Antonio). Alternating lanes will close while crews work on overhead highway signs.
I-35
  • Sunday-Friday, May 31-June 5. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between Walzem and George Beach (east San Antonio). Alternating lanes will close while crews do road work.
  • Sunday-Friday, May 31-June 5. 9 p.m. until 5 a.m. nightly. Southbound frontage road between Walzem and George Beach (east San Antonio). Alternating lanes will close for road work.
  • Sunday-Friday, May 31-June 5. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between Binz-Engleman and AT&T Parkway (east San Antonio). Two right lanes will close while crews set barrier.
  • Monday-Friday, June 1-5. 9 a.m. until 3:30 p.m. daily. Northbound connector to westbound I-410 (Windcrest). The right lane will close while crews work on the guardrail.
  • Monday-Friday, June 1-5. 9 a.m. until 3:30 p.m. daily. Northbound frontage road between Greatfare and Rittiman Road (east San Antonio). The left lane will close to allow access for work trucks.
  • Monday-Friday, June 1-5. 9 a.m. until 3:30 p.m. daily. Southbound frontage road at Fratt Road (east San Antonio). The left lane will close while crews do concrete work.
  • Monday-Friday, June 1-5. 9 a.m. until 3:30 p.m. daily. Frontage road, both directions, between Walzem and George Beach (east San Antonio). Alternating lanes will close for road work.
  • Monday-Friday, June 1-5. 9 p.m. until 5 a.m. nightly. Frontage road, both directions, between Binz-Engleman and AT&T Parkway (east San Antonio). Alternating lanes will close while crews work on temporary light fixtures.
  • Monday-Friday, June 1-5. 9 p.m. until 5:30 a.m. nightly. Main lanes, both directions, between FM 3009 and Solms Road (Schertz-New Braunfels). Alternating lanes will close, including alternating closures of exit or entrance ramps, while crews repave the roadway.
  • Wednesday-Friday, June 3-5. 9 a.m. until 3 p.m. daily. Turnarounds on both sides of Salado Creek (east San Antonio). Traffic will be cut to one lane, using one-way traffic control, while crews do bridge work.
I-410
  • Sunday-Friday, May 31-June 5. 9 p.m. until 5 a.m. nightly. Northbound connector to northbound I-35 (east San Antonio). All lanes will close while crews move barrier. Traffic will exit Space Center and continue through Rittiman Road, then enter northbound I-35.
  • Sunday-Friday, May 31-June 5. 9 p.m. until 5 a.m. nightly. Eastbound connector to northbound I-35 (Windcrest). The right lane will close while crews repair crash cushions.
U.S. Hwy 281
  • Monday-Sunday, June 1-6. 9 p.m. until 5 a.m. nightly. Northbound main lanes at Nakoma Drive (north-central San Antonio). All lanes will close while crews work on the Nakoma turnaround bridges. Traffic will exit Nakoma Drive, pass through the intersection, and re-enter the main lanes.
Loop 1604
  • Monday-Wednesday, June 1-3. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between Culebra Road and Wiseman Boulevard (northwest San Antonio). Alternating lanes will close while crews place barrier.
  • Monday-Friday, June 1-5. 9 a.m. until 4 p.m. daily. Turnarounds, both directions, at Braun Road (northwest San Antonio). The turnarounds will close while crews do bridge work. Traffic will move through the intersection to turn around.
Other roads
  • Saturday-Sunday, May 30-31. 7 a.m. until 7 p.m. daily. Braun Road, both directions, at Loop 1604. All lanes will close while crews hang bridge support beams. Eastbound traffic will travel south on Loop 1604 and turn around after Shaenfield Road to reach northbound Loop 1604. Westbound traffic will travel north on Loop 1604 and turn around at Bandera Road to reach southbound Loop 1604.
  • Monday-Friday, June 1-5. 9 p.m. until 5 a.m. nightly. Braun Road, both directions, at Loop 1604. All lanes will close while crews hang bridge deck panels. Eastbound traffic will travel south on Loop 1604 and turn around after Shaenfield Road to reach northbound Loop 1604. Westbound traffic will travel north on Loop 1604 and turn around at Bandera Road to reach southbound Loop 1604.
  • Sunday-Friday, May 31-June 5. 9 p.m. until 5 a.m. nightly. Westbound Eisenhauer Road at I-35 (east San Antonio). All lanes will close while crews move barrier and do bridge work. Traffic will use the I-35 frontage road to the next intersection and turn around to reach its destination.
  • Sunday-Friday, May 31-June 5. 9 p.m. until 5 a.m. nightly. Eastbound Eisenhauer Road at I-35 (east San Antonio). The left lane will close while crews move barrier and do bridge work.
  • Sunday-Friday, May 31-June 5. 9 p.m. until 5 a.m. nightly. Westbound Rittiman Road at I-35 (east San Antonio). All lanes will close while crews move barrier and do bridge work. Traffic will use the I-35 frontage road to the next intersection and turn around to reach its destination.
  • Sunday-Friday, May 31-June 5. 9 p.m. until 5 a.m. nightly. Eastbound Rittiman Road at I-35 (east San Antonio). The left lane will close while crews move barrier and do bridge work.
  • Tuesday-Friday, June 2-5. 9 p.m. until 5 a.m. nightly. Hwy 46, both directions, between City Park Road and Ammann Road (Boerne). Alternating lanes will close while crews repair the pavement base.
  • Friday-Monday, June 5-8. 7 p.m. until 5 a.m. continuous. Fredericksburg Road, both directions, between Louis Pasteur and Data Point (Medical Center). All lanes will close while crews reconstruct the road. Traffic will use Wurzbach Road, Ewing Hallsell and Louis Pasteur to reach its destination. Traffic on Medical Drive will use the new through lanes. This closure was initially planned for May 8-11 but rescheduled due to weather.