Pages

Monday, August 24

THIS week's construction-related closures



Note: Thanks for your patience with us this month! Contributors to the blog have been out most of August and have spent most of their time catching up on emails and phone calls. We'll get caught up and answer some questions through this week and next. As for closures, this week's closures are below.
I-10 – Downtown San Antonio
  • Monday, August 24-Friday, September 4. 9 a.m. until 3 p.m. daily, weekdays only. Eastbound frontage road between Martin and Houston streets. The left lane will close while crews do overhead bridge work.
I-10 – Northwest San Antonio
  • Sunday-Friday, August 23-28. 8:30 p.m. until 5:30 a.m. nightly. Frontage road, both directions between Loop 1604 and Huebner Road. Alternating lanes will close for road work.
  • Sunday-Friday, August 23-28. 8:30 p.m. until 5:30 a.m. nightly. Main lanes, both directions, between Huebner Road and Loop 1604. Alternating lanes will close for road work.
  • Monday-Friday, August 22-28. 9 a.m. until 4 p.m. daily. Frontage road, both directions, between Loop 1604 and Huebner Road. Alternating lanes will close for road work.
I-35 – East San Antonio
  • Sunday-Thursday, August 23-27. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between Eisenhauer and Rittiman. Alternating lanes will close, two at a time, while crews move barrier.
  • Sunday-Thursday, August 23-27. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between Binz-Engleman and AT&T Parkway. Alternating lanes will close, two at a time, while crews do road work.
I-410 – East San Antonio
  • Sunday-Thursday, August 23-27. 9 p.m. until 5 a.m. nightly. Northbound ramp to northbound I-35. The ramp will close while crews move barrier. Traffic will exit Space Center, pass through the Rittiman Road intersection, then enter the main lanes of northbound I-35.
I-410 – Southeast San Antonio
  • Sunday-Tuesday, August 23-25. 8 p.m. until 5 a.m. nightly. Northbound main lanes between Rigsby Avenue and East Houston Street. All lanes will close while crews do asphalt work. Traffic will exit Rigsby, continue along the frontage road, and use the next available ramp to re-enter the highway.
I-410 – Southwest San Antonio
  • Tuesday-Thursday, August 25-27. 9 p.m. until 6 a.m. nightly. Main lanes, both directions, between Freeport Road and I-35. The right lane will close while crews move barrier.
U.S. Hwy 90 – Downtown San Antonio
  • Sunday-Friday, August 23-28. 9 p.m. until 5 a.m. nightly. Westbound exit ramps to I-35. The ramps will close, as will the right lane of U.S. Hwy 90, while crews do repair work. Traffic headed to northbound I-35 will exit Cupples, turn around, exit Nogalitos, turn left onto Powell Street and enter the northbound I-35 ramp. Traffic to Southbound I-35 will exit Cupples, turn around and exit southbound I-35.
  • Sunday-Friday, August 23-28. 9 p.m. until 5 a.m. nightly. Eastbound exit ramp to northbound I-35. The ramp will close while crews do repair work. Traffic headed to northbound I-35 will exit I-35 south and turn around at W. Theo Avenue.
U.S. Hwy 281 – North-central San Antonio
  • Monday-Friday, August 24-28. 9 p.m. until 5 a.m. nightly. Northbound Entrance ramp from Nakoma Drive. The ramp will close while crews do concrete work. Traffic will continue north through Bitters Road to enter the Hwy 281 main lanes.
  • Tuesday-Thursday, August 25-27. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between Bitters Road and Nakoma Drive. The two left lanes will close while crews build median barrier.
Loop 1604 – Northwest San Antonio
  • Monday-Sunday, August 24-30. 10 p.m. until 5:30 a.m. nightly. Southbound frontage road between Braun Road and Shaenfield. The right lane will close while crews work on curb and sidewalk.
Other roads – Northwest San Antonio
  • Monday-Friday, August 24-28. 10 p.m. until 5 a.m. nightly. Braun Road, both directions, at Loop 1604. All lanes will close while crews do overhead bridge work. Traffic will turn right onto Loop 1604, use the next available turnaround and return to the intersection to reach its destination.
  • Friday-Saturday, August 28-29. 10 p.m. until 7 a.m. Braun Road, both directions, at Loop 1604. All lanes will close while crews do overhead bridge work. Traffic will turn right onto Loop 1604, use the next available turnaround and return to the intersection to reach its destination.
Other roads – East San Antonio
  • Sunday-Thursday, August 23-27. 9 p.m. until 5 a.m. nightly. Westbound Rittiman Road at I-35. All lanes will close while crews move barrier. Traffic will turn right onto the frontage road and turn around at the next intersection.
  • Sunday-Thursday, August 23-27. 9 p.m. until 5 a.m. nightly. Eastbound Rittiman Road at I-35. The left lane will close while crews move barrier.
  • Sunday-Thursday, August 23-27. 9 p.m. until 5 a.m. nightly. Westbound Eisenhauer Road at I-35. All lanes will close while crews move barrier. Traffic will turn right onto the frontage road and turn around at the next intersection.
  • Sunday-Thursday, August 23-27. 9 p.m. until 5 a.m. nightly. Eastbound Eisenhauer Road at I-35. The left lane will close while crews move barrier.
All closures are pending weather.