I-10 – Boerne
  • Friday-Monday, March 18-21. 9 p.m. until 5 a.m. continuous. Main lanes, both directions, at Scenic Loop Road. The left lane will close while crews remove bridge rail.
I-10 – Downtown San Antonio
  • Current thru Thursday, March 31. 9 p.m. until 6 a.m. nightly. Main lanes, both directions, between North Colorado and Fredericksburg Road (lower level). The right lane will close while crews do overhead bridge work.
I-35 – East San Antonio
  • Current thru March 2016. Exit ramps, both directions, to Eisenhauer Road. The ramps will close while crews build a new exit ramp. Traffic will use the next available ramp and turn around to reach Eisenhauer Road.
  • Current thru March 2016. Northbound entrance ramp from Eisenhauer Road. The ramp will close while crews build a new entrance ramp. Traffic will use the next available ramp.
  • Friday-Saturday, March 11-12. 9 p.m. until 5 a.m. Main lanes, both directions, between AT&T Center Parkway and Binz Engleman. Alternating lanes will close while crews do work on overhead highway sign support columns.
  • Friday-Saturday, March 11-12. 9 p.m. until 5 a.m. Southbound frontage road between AT&T Center Parkway and Binz Engleman. Alternating lanes will close while crews do concrete work.
  • Friday-Saturday, March 11-12. 9 p.m. until 5 a.m. Southbound exit to AT&T Center Parkway. The ramp will close while crews do concrete work. Traffic will exit George Beach and turn around to reach its destination. This closure will not impact traffic headed to Spurs games
  • Sunday-Monday, March 13-14. Midnight until 5 a.m. (five hours). Main lanes, both directions, between Binz Engleman and AT&T Center Parkway. Alternating lanes will close while crews do work on overhead highway sign support columns.
  • Sunday-Friday, March 13-18. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between Rittiman and Walzem roads. Alternating lanes will close while crews do road work.
  • Sunday-Saturday, March 13-19. 9 a.m. until 3 p.m. daily. Southbound frontage road between AT&T Center Parkway and Binz-Engleman. Alternating lanes will close while crews do road work.
  • Sunday-Saturday, March 13-19. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between AT&T Center Parkway and Binz-Engleman. Alternating lanes will close while crews do road work.
  • Sunday-Saturday, March 13-19. 9 p.m. until 5 a.m. nightly. Southbound exit to AT&T Center Parkway. The ramp will close while crews do concrete work. Traffic will exit George Beach and turn around to reach its destination. This closure will not impact traffic headed to Spurs games.
  • Sunday-Saturday, March 13-19. 9 p.m. until 5 a.m. daily. Frontage road, both directions, between AT&T Center Parkway and Binz-Engleman. Alternating lanes will close while crews do road work.
  • Monday-Tuesday, March 14-15. 9 p.m. until 5 a.m. Northbound main lanes at westbound I-410. Alternating lanes will close while crews do bridge work.
  • Monday-Friday, March 14-18. 9 a.m. until 3:30 p.m. daily. Frontage road, both directions, between Rittiman and Walzem roads. Alternating lanes will close while crews do utility work.
I-410 – South Bexar County
  • Tuesday-Friday, March 15-18. 9 p.m. until 5 a.m. nightly. Eastbound main lanes between Somerset and Roosevelt. The right lane will close while crews set barrier.
I-410 – Northwest San Antonio
  • Tuesday-Thursday, March 15-17. 9 p.m. until 5 a.m. nightly. Southbound exit ramp to Hwy 151. The ramp will close while crews set bridge support beams on the frontage road. Traffic will exit Military Road and use Military to reach Hwy 151 or traffic will exit Marbach, turn around and reach Hwy 151 from northbound I-410.
  • Tuesday-Thursday, March 15-17. 9 p.m. until midnight nightly. Southbound frontage road between Military Road and Hwy 151. The right lane will close while crews prepare to set bridge beams.
  • Tuesday-Thursday, March 15-17. Midnight to 5 a.m. nightly. Southbound frontage road between Military Road and Hwy 151. All lanes will close while crews set bridge beams. Traffic will use Military Road to reach Hwy 151.
U.S. Hwy 90 – West San Antonio
  • Current until May 2016. Westbound frontage road between Hunt Lane and East Kriewald. The frontage road will close while crews reconstruct the Medio Creek Bridge.
  • Thursday-Friday, March 17-18. 8 p.m. until 5 a.m. Main lanes, both directions, at Loop 1604. All lanes will close while crews hang overhead bridge support beams. Traffic will exit Loop 1604, pass through the intersection and re-enter the highway. Off-duty police officers will control traffic at the intersections.
Loop 1604 – Northwest San Antonio
  • Current through Monday, March 21. 9 a.m. until 4 p.m. daily. Southbound frontage road between Braun and Bandera roads. The right lane will close while crews construct sidewalk.
  • Current through Monday, March 21. 9 a.m. until 4 p.m. daily. Southbound frontage road between Braun and Shaenfield roads. The right lane will close while crews do concrete work.
  • Current through Monday, March 21. 4 a.m. until 4 p.m. daily. South-to-north turnaround at Shaenfield. The turnaround will close while crews do concrete work.
  • Monday-Friday, March 14-18. 9 a.m. until 4 p.m. daily. North-to-south turnaround at Shaenfield. The turnaround will close while crews work on retaining walls.
  • Tuesday-Friday, March 15-18. 9 p.m. until 6 a.m. nightly. Southbound main lanes at Hwy 151. All lanes will close while crews do overhead bridge work. Traffic will exit Hwy 151, follow the frontage road and re-enter the highway.
  • Wednesday-Friday, March 16-18. 9 a.m. until 4 p.m. daily. Northbound frontage road between Shaenfield and Braun roads. The right lane will close while crews do concrete work.
  • Friday-Monday, March 18-21. 9 a.m. until 4 a.m. daily. Northbound frontage road between Braun and Bandera roads. The right lane will close while crews do curb and sidewalk work.
Hwy 151 – Northwest San Antonio
  • Current until December 2016. Westbound exit ramp to Ingram and Potranco roads. The ramp will remain closed while crews install bridge support structures for the direct connector ramps being constructed.
  • Current until December 2016. Eastbound entrance ramp from Ingram and Potranco roads. The ramp will remain closed while crews install bridge support structures for the direct connector ramps being constructed.
Other roads – East San Antonio
  • Monday-Wednesday, March 14-16. 9 a.m. until 4 p.m. Rigsby Avenue, both directions, at I-410. Alternating lanes will close while crews install lighting under the I-410 overpass.
  • Monday-Wednesday, March 14-16. 9 a.m. until 4 p.m. Sinclair Road, both directions, at I-410. Alternating lanes will close while crews install lighting under the I-410 overpass.
  • Tuesday-Wednesday, March 15-16. 10 p.m. until 5 a.m. Eisenhauer Road, both directions, at I-35. All lanes will close while crews do overhead bridge work. Traffic will turn right and use the next available turnaround to reach its destination.
Other roads – Boerne
  • Friday-Monday, March 18-21. 9 p.m. until 5 a.m. continuous. Scenic Loop Road, both directions, at I-10. All lanes will close while crews do overhead bridge work. Traffic will go to Business 87 or Balcones Creek, as appropriate, to turn around and reach its destination.
Other roads – Pleasanton
  • Current through Friday, March 18. State Highway 97, both directions, one mile east of Charlotte city limits. One-way traffic control will be employed for one mile with temporary traffic signals while crews rebuild the roadway. Expect delays.
Other roads – Comal County
  • Sunday-Tuesday, March 13-15. 9 p.m. until 6 a.m. nightly. Hwy 46, both directions, between Old Boerne Road and U.S. Hwy 281. Alternating lanes will close while crews mill pavement.