Pages

Friday, October 14

Next week's construction-related closures

I-10 – Fair Oaks Parkway
  • Monday-Wednesday, October 17-19. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, at Fair Oaks Parkway. The right lane will close while crews set barrier. 
I-10 – East San Antonio
  • Saturday, October 15. 7 a.m. until 7 p.m. Westbound main lanes between I-410 and WW White. Alternating lanes will close while crews repair the road. 
I-35 – New Braunfels
  • Monday, October 17. 9 a.m. until 3 p.m. Northbound main lanes at York Creek. The right lane will close while crews do concrete work. 
  • Monday-Tuesday, October 17-18. 9 a.m. until 3 p.m. daily. Northbound main lanes at Alligator Creek. Alternating lanes will close while crews do bridge work. 
  • Tuesday-Wednesday, October 18-19. 9 a.m. until 3 p.m. daily. Northbound main lanes at York Creek. Alternating lanes will close while crews do bridge work. 
  • Tuesday-Friday, October 18-21. 8 p.m. until 5 a.m. nightly. Southbound main lanes between the Comal-Hays county line and FM 306. Alternating lanes will close while crews lay asphalt. 
I-35 – Northeast San Antonio
  • Sunday-Monday, October 16-17. 8 p.m. until 5 a.m. Southbound exit to southbound I-410. The connector will close while crews install concrete rail. Traffic will exit George Beach, turn around and reach southbound I-410 from the northbound I-35 frontage road. 
  • Sunday-Friday, October 16-21. 9 p.m. until 5 a.m. nightly. Northbound exit to westbound I-410. Alternating lanes will close while crews do overhead bridge work. Traffic will exit Walzem and continue along the frontage road to reach I-410. 
  • Sunday-Friday, October 16-21. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between Rittiman and Walzem roads. Alternating lanes will close while crews do road work. 
  • Sunday-Friday, October 16-21. 9 p.m. until 5 a.m. nightly. Frontage roads, both directions, between Rittiman and Walzem. Alternating lanes will close while crews do road work. 
  • Monday-Friday, October 17-21. 9 a.m. until 3:30 p.m. daily. Frontage roads, both directions, between Rittiman and Walzem roads. Alternating lanes will close while crews do road work. 
I-35 – East San Antonio
  • Sunday-Thursday, October 16-20. 9 p.m. until 5 a.m. nightly. Southbound main lanes between I-410 and Broadway. The right lane will close while crews lay asphalt. 
I-410 – Northeast San Antonio
  • Sunday-Friday, October 16-21. 9 p.m. until 5 a.m. nightly. Eastbound exit ramp to Randolph Boulevard and the city of Windcrest. The ramp will close while crews do bridge work. Traffic will exit Thousand Oaks, turn around and return to Randolph Boulevard to reach its destination. 
I-410 – East San Antonio
  • Current through Friday, December 2. Southbound main lanes over North WW White. The right lane will close while crews repair damaged bridge rail. 
  • Sunday-Monday, October 16-17. 8 p.m. until 5 a.m. Northbound connector to northbound I-35. The ramp will close while crews install barrier. Traffic will exit Space Center Drive, pass through Rittiman Road and use the next available ramp to get to northbound I-35. 
I-410 – Northwest San Antonio
  • Sunday-Monday, October 16-17. 9 p.m. until 5 a.m. Northbound main lanes between Marbach and Military. All lanes will close while crews move construction equipment. Traffic will exit Hwy 151, follow the frontage road and re-enter at the next available ramp. 
  • Sunday-Tuesday, October 16-18. 9 p.m. until 5 a.m. nightly. Southbound main lanes between Culebra Road and Military Drive. Alternating lanes will close while crews restripe the road. 
  • Monday-Friday, October 17-21. 9 p.m. until 5 a.m. nightly. Main lanes, both lanes, between Marbach and Military. The left two lanes will close while crews do overhead bridge work. 
US Hwy 281 – Central San Antonio
  • Sunday-Friday, October 16-21. 11 a.m. until 3 p.m. daily. Main lanes, both directions, between Airport and Josephine. The right lane will close while crews work on guardrail. This closure includes ramps as needed. Traffic will follow the posted detour route. 
  • Sunday-Friday, October 16-21. 9 p.m. until 6 a.m. nightly. Main lanes, both directions, between Airport and Josephine. Alternating lanes will close while crews do bridge work. This closure includes ramps as needed. Traffic will follow the posted detour route. 
Loop 1604 – North San Antonio
  • Monday, October 24. 9 a.m. until 3 p.m. Eastbound main lanes between Huebner Road and Stone Oak Parkway. The right lane and shoulder will close while crews repair signs. 
Loop 1604 – Northwest San Antonio
  • Current through Wednesday, October 19. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, at Hwy 151. Alternating lanes will close while crews do overhead bridge work. Traffic will use the frontage roads to reach its destination. 
  • Current through Wednesday, October 19. 9 p.m. until 5 a.m. nightly. Southbound frontage road at Alamo Ranch Parkway. Alternating lanes will close as needed while crews do overhead bridge work. 
  • Current through Sunday, October 16. 9 p.m. until 5 a.m. nightly. Northbound main lanes at Hwy 151. All lanes will close while crews resurface the road. Traffic will exit Hwy 151, turn around at Wiseman Road and re-enter Loop 1604 from westbound Hwy 151. 
  • Saturday, October 15. 9 a.m. until 4 p.m. Southbound entrance ramp from Shaenfield. The ramp will close while crews repair guardrail. Traffic will continue through Culebra Road to enter southbound Loop 1604. Traffic to Hwy 151 should go to New Guilbeau and turn around to reach the direct connector. 
  • Tuesday, October 18. 9 a.m. until 3 p.m. Frontage roads, both directions, between Hausman and Babcock roads. The right lane will close while crews survey the road. 
Hwy 151 – Northwest San Antonio
  • Current through Friday, October 21. 9 p.m. until 5 a.m. nightly, weeknights only. Westbound frontage road between I-410 and Potranco Road. All lanes will close while crews pour concrete overhead. Traffic will use West Military Road to reach its destination. 
  • Current until December 2016. Westbound exit ramp to Ingram and Potranco roads. The ramp will remain closed while crews install bridge support structures for the direct connector ramps being constructed. 
Other roads – New Braunfels
  • Monday-Friday, October 17-21. 8 a.m. until 4 p.m. daily. FM 306, both directions, between River Chase Drive and Western Oaks Drive. Traffic will be reduced to one-way traffic, controlled by flaggers, while crews install drain pipes under the road. 
Other roads – Seguin
  • Current until Saturday, December 31. 9 a.m. until 4 p.m. daily. King Street, both directions, between Cedar Street and US 90. All lanes will close while crews install storm drains and rebuild the road. Traffic will use Hwy 123 as a detour. 
Other roads – Northeast San Antonio
  • Sunday-Friday, October 16-21, 9 p.m. until 5 a.m. nightly. Randolph Boulevard, both directions, between Crestway and I-35. Traffic will be reduced to a single lane, controlled by off-duty police, while crews do overhead bridge deck work. 
Other roads – South San Antonio
  • Sunday, October 18-Sunday, October 25. 7 a.m. until 5 p.m. daily. Northbound Palo Alto Road (state Highway 16) between South Zarzamora and I-410. The right lane will close while crews resurface the road. 
Other roads – Southeast Bexar County
  • Sunday-Friday, October 16-21. 7 p.m. until 6 a.m. nightly. Northbound WW White between Sinclair and I-10. The right lane will close while crews resurface the road. 
Other roads – Northwest San Antonio
  • Tuesday, October 18. 9 a.m. until 3 p.m. Bandera Road, both directions, between Quincy Lee and Cedar Trail. The right lane will close while crews survey the road. 
All closures are pending weather.