I-10 – East San Antonio
  • Current until Friday, June 9. 7:30 a.m. until 5 p.m. daily. Westbound frontage road between Woodlake Parkway and FM 1516. Alternating lanes will close while crews install storm drains. Traffic will be one-way, controlled by flaggers.
I-35 – New Braunfels
  • Sunday-Friday, June 4-9. 9 p.m. until 6 a.m. nightly. Main lanes, both directions, between Schmidt and Solms roads. Alternating lanes will close as crews resurface the road.
  • Sunday-Friday, June 4-9. 9 p.m. until 6 a.m. Southbound main lanes between the Comal-Hayes county line and FM 306. Alternating lanes, two at a time, will close while crews resurface the road.
  • Wednesday, June 7. 10 a.m. until 3 p.m. Southbound main lanes at York Creek. The right lane will close while crews work on the guardrail.
I-35 – Northeast San Antonio
  • Current until Tuesday, August 1 at 5 a.m. Turnarounds, both directions, at Walzem Road. The turnarounds will remain closed while crews do overhead bridge work.
  • Sunday-Tuesday, June 4-6. 9 p.m. until 5 a.m. Main lanes, both directions, between Walzem Road and Crestway Drive. The left lane will close while crews work on overhead highway signs.
  • Tuesday-Friday, June 6-9. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between Eisenhauer Road and Crestway Drive. The left lane will close while crews work on the center median.
I-35 – East San Antonio
  • Friday-Saturday, June 2-3. 8 p.m. until 5 a.m. Southbound main lanes at New Braunfels Avenue. All lanes will close while crews do overhead bridge work. Traffic will exit New Braunfels Avenue, continue along the frontage road and re-enter the highway at the next available ramp.
I-35 – Downtown
  • Sunday, June 4. 6 a.m. until 5 p.m. Northbound main lanes at U.S. Hwy 90. The two right lanes will close while crews do bridge work. This includes the on ramp from Theo Avenue. Traffic will head south to Division Avenue, turn around and use the available ramp.
I-410 – Northwest San Antonio
  • Current until August 31. Northbound exit to Culebra Road. The exit will close while crews widen the main lanes and frontage road. Traffic will exit Ingram Road, turn around and get to Culebra on the southbound frontage road.
  • Monday-Wednesday, June 5-7. 9 p.m. until 5 a.m. nightly. Southbound frontage road at Hwy 151. All lanes will close while crews do overhead concrete work. Traffic will turn right onto the westbound frontage road of Hwy 151 and turn around at Ingram Road to reach its destination.
  • Monday-Wednesday, June 5-7. 9 p.m. until 5 a.m. nightly. Northbound frontage road between Military Drive and Culebra Road. All lanes will close while crews install drain structures. Traffic will enter the main lanes of I-410 and exit Ingram Road then turn around to reach Culebra Road.
  • Tuesday-Friday, June 6-9. 9 p.m. until 5 a.m. nightly. Northbound main lanes between US 90 and Marbach. The right lane will close while crews set barrier.
U.S. Hwy 90 – West San Antonio
  • Sunday-Friday, June 4-9. 9 p.m. until 5:30 a.m. nightly. Westbound frontage road between Tomar and Hunt Lane. All lanes will close while crews install storm drains. Traffic will enter the main lanes of US 90 and exit Hunt Lane as needed.
U.S. Hwy 281 – Near North San Antonio
  • Sunday-Monday, June 4-5. 9 p.m. until 6 a.m. Southbound main lanes between Jones Maltsberger and Basse Road. The right two lanes will close while crews resurface the roadway.
  • Monday-Tuesday, June 5-6. 9 p.m. until 6 a.m. Northbound main lanes between Stadium Drive and Jones-Maltsberger. The two right lanes will close while crews do concrete work. This closure will include ramps as needed. Traffic will use the next available ramp to reach its destination.
  • Monday-Tuesday, June 5-6. 9 p.m. until 6 a.m. Southbound main lanes between Hildebrand and Stadium Drive. The two right lanes will close while crews resurface the road. This closure includes ramps as needed. Traffic will use the next available ramp to reach its destination.
  • Tuesday-Wednesday, June 6-7. 9 p.m. until 6 a.m. Southbound exit ramp to Josephine. The ramp will close while crews resurface the road. Traffic will use the next available ramp and turn around to reach its destination.
  • Tuesday-Wednesday, June 6-7. 9 p.m. until 6 a.m. Northbound main lanes between I-410 and Josephine. The three left lanes will close while crews resurface the roadway.
  • Wednesday-Thursday, June 7-8. 9 p.m. until 6 a.m. Northbound main lanes between I-410 and St. Mary’s. The two right lanes will close while crews resurface the roadway.
  • Thursday-Friday, June 8-9. 9 p.m. until 6 a.m. Northbound exit ramps to Basse Road. The ramps will close while crews resurface the road. Traffic will use the next available ramp and turn around to reach its destination.
Hwy 151 – Northwest San Antonio
  • Current until August 31. Westbound exit ramp to Hunt Lane. The exit will close while crews work on retaining walls. Traffic will exit Ingram Road and follow the frontage road to reach its destination.
  • Monday-Wednesday, June 5-7. 9 p.m. until 5 a.m. nightly. Eastbound main lanes between I-410 and Ingram Road. All lanes will close while crews do overhead concrete work. Traffic will exit I-410, travel through the I-410 intersection and re-enter the highway at the next available ramp.
  • Tuesday, June 6. 10 a.m. until noon. Westbound frontage road at Ingram Road. The left lane will close while crews set bridge support beams.
Other roads – Seguin
  • Current until August 31. Austin Street between Martindale and Seidman. The road will be converted to one-way only, moving southbound only, while crews do road work. Northbound traffic will use Guadalupe Street to reach its destination.
Other roads – East San Antonio
  • Friday-Saturday, June 2-3. 8 p.m. until 5 a.m. New Braunfels Avenue, both directions, at I-35. All lanes will close while crews do bridge work on the New Braunfels Avenue overpass. Traffic will turn right onto the frontage road and turn around to reach its destination.
Other roads – Northwest San Antonio
  • Monday-Friday, June 5-9. 9 a.m. until 4 p.m. daily. Potranco Road, both directions, between Dugas Drive and Hunt Lane. The left lane will close while crews work on the median.
  • Tuesday, June 6. 10 a.m. until noon. Ingram Road, both directions, at Hwy 151. All lanes will close while crews set overhead bridge support beams. Traffic will turn right onto the Hwy 151 frontage road and turn around at the next cross street to reach its destination.
  • Tuesday, June 6. 9 a.m. until 3 p.m. Westbound Wiseman Boulevard at Loop 1604. The right lane will close while crews set bridge beams overhead.
  • Tuesday-Wednesday, June 6-7. 9 p.m. until 5 a.m. Wiseman Boulevard, both directions, at Loop 1604. All lanes will close while crews set bridge beams overhead. Traffic will turn right onto Loop 1604 and turn around at the next cross street to reach its destination.