I-10 – Northwest San Antonio
  • Monday-Wednesday, September 11-13. 9 p.m. until 5 a.m. nightly. Eastbound main lanes between Ralph Fair Road and La Cantera Parkway. The left lane will close while crews set barrier.
  • Tuesday-Thursday, September 12-14. 9 a.m. until 4 p.m. daily. Eastbound frontage road between Balcones Road and West Avenue. Alternating lanes will close while crews repair the road.
  • Thursday-Monday, September 14-18. 9 p.m. until 5 a.m. nightly. Westbound main lanes between La Cantera Parkway and Ralph Fair Road. The left lane will close while crews set barrier.
I-10 – East San Antonio
  • Current until Friday, September 22. 7 p.m. until 6 a.m. nightly. Main lanes, both directions, between Foster and Graytown roads. The right lane will close while crews resurface the shoulder areas for new ramps. Work will go through the westbound side first, then the eastbound side.
I-35 – Schertz
  • Sunday, September 17 at 9 p.m. until Monday, September 18 at 6 a.m. Northbound main lanes at FM 1103. All lanes will close while crews set up a work zone. Traffic will exit FM 1103, continue through the intersection and re-enter the highway.
  • Monday, September 18 at 9 p.m. until Tuesday, September 19 at 6 a.m. Southbound main lanes at FM 1103. All lanes will close while crews set up a work zone. Traffic will exit FM 1103, continue through the intersection and re-enter the highway.
  • Tuesday, September 19 at 9 p.m. until Wednesday, September 20 at 6 a.m. Northbound main lanes at FM 1103. The two right lanes will close while crews set barrier.
  • Wednesday, September 20 at 9 p.m. until Thursday, September 21 at 6 a.m. Main lanes, both directions, at FM 1103. Alternating lanes will close, two at a time, while crews set barrier.
  • Sunday, September 24 at 9 p.m. until Monday, September 25 at 6 a.m. Southbound main lanes at FM 1103. The left lanes will close while crews set barrier.
I-35 – East San Antonio
  • Current until Monday, September 25. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between George Beach and Thousand Oaks Drive. Alternating lanes will close while crews work on the center median.
  • Monday-Friday, September 11-15. 9 a.m. until 4 p.m. daily. Southbound frontage road between Walters and New Braunfels avenues. The right lane will close while crews build sidewalks.
  • Monday-Friday, September 11-15. 9 a.m. until 4 p.m. daily. Northbound frontage road between Locke Avenue and AT&T Parkway. The right lane will close while crews build sidewalks.
  • Monday-Friday, September 11-15. 8 p.m. until 5 a.m. nightly. Northbound main lanes between Broadway and I-410. The left lanes will close while crews resurface the road.
  • Wednesday, September 13. 9 a.m. until 3 p.m. Main lanes, both directions, between George Beach and Randolph Boulevard. Alternating lanes will close as needed to repair crash cushions.
I-410 – East San Antonio
  • Thursday, September 14. 9 a.m. until 3 p.m. Northbound I-410 ramp to northbound I-35. The left lane will close while crews repair guardrail.
I-410 – Northwest San Antonio
  • Current until Saturday, September 30. 9 a.m. until 4 p.m. daily. Frontage roads, both directions, between US 90 and Hwy 151. Alternating lanes will close while crews do road work.
  • Current until Tuesday, October 31. Northbound exit to Culebra Road. The exit will close while crews widen the main lanes and frontage road. Traffic will exit Ingram Road, turn around and get to Culebra on the southbound frontage road.
U.S. Hwy 281 – North San Antonio
  • Tuesday, September 12 at 9 p.m. until Wednesday, September 13 at 5 a.m. Southbound main lanes between Sonterra Road and Loop 1604. The right lane will close while crews set barrier. The ramp will not be impacted by this closure.
  • Wednesday, September 13 at 9 p.m. until Thursday, September 14 at 5 a.m. Southbound main lanes at Sonterra Road. The left lanes will close while crews do road work. This closure includes the Sonterra exit ramp. Traffic will exit Donella Drive and turn around to reach its destination.
  • Wednesday, September 13 at 9 p.m. until Thursday, September 14 at 5 a.m. Northbound frontage road at Sonterra Road. The left lane will close while crews set barrier.
  • Thursday, September 14 at 9 p.m. until Friday, September 15 at 5 a.m. Southbound main lanes between Redland Road and Sonterra Boulevard. The right lanes will close while crews set barrier.
U.S. Hwy 281 – Near North San Antonio
  • Monday-Wednesday, September 11-13. 9 p.m. until 6 a.m. nightly. Northbound main lanes at Olmos Basin. The left lanes will close while crews do bridge work.
  • Monday-Friday, September 11-15. 9 a.m. until 4 p.m. daily. Northbound frontage road between Heimer and Bitters roads. The right lane will close while crews build sidewalks.
Hwy 151 – Northwest San Antonio
  • Current until Friday, September 29. Westbound exit ramp to Hunt Lane. The exit will close while crews work on retaining walls. Traffic will exit Ingram Road and follow the frontage road to reach its destination.
Loop 1604 – North San Antonio
  • Monday, September 11 at 9 p.m. until Tuesday, September 12 at 5 a.m. Eastbound main lanes between US 281 and Gold Canyon. The right lane will close while crews set barrier. This closure will not impact any ramps.
  • Tuesday, September 12 at 9 p.m. until Wednesday, September 13 at 5 a.m. Westbound frontage road at US Hwy 281. Alternating lanes will close while crews restripe the road and set barrier.
  • Tuesday, September 12 at 9 p.m. until Wednesday, September 13 at 5 a.m. Westbound main lanes between Gold Canyon Road and US Hwy 281. The right lane will close while crews restripe the road and set barrier.
Loop 1604 – Far west San Antonio
  • Current until Friday, September 15. 9 p.m. until 5 a.m. nightly. Westbound frontage road between Arby’s and Applebee’s. Alternating lanes will close while crews restripe the road and set barrier.
Loop 1604 – Northwest San Antonio
  • Monday, September 11 at 9 p.m. until Tuesday, September 12 at 5 a.m. Southbound main lanes between Dodge City Trail and Marbach Road. The right lane will close while crews set barrier.
  • Tuesday, September 12 at 9 p.m. until Wednesday, September 13 at 5 a.m. Southbound main lanes between Medio Creek and Emory Peak. The left lane will close while crews set barrier.
Other roads – Uvalde
  • Tuesday, September 12. 6 a.m. until 7 p.m. U.S. Hwy 83, both directions, between FM 1051 and the Uvalde-Real county line. Alternating lanes will close while crews seal coat the road.
  • Wednesday, September 13. 6 a.m. until 5 p.m. FM 2369, both directions, between U.S. Hwy 90 and U.S. Hwy 83. Alternating lanes will close while crews seal coat the road.
  • Wednesday-Thursday, September 12-13. 6 a.m. until 7 p.m. daily. U.S. Hwy 90, both directions, between FM 2369 and FM 1049. Alternating lanes will close while crews seal coat the road.
Other roads – Castroville
  • Friday-Saturday, September 15-16. 6 a.m. until 7 p.m. daily. U.S. Hwy 90, both directions, between Dunlay and FM 1343, FM 471 and the Medina-Bexar county line. Alternating lanes will close while crews seal coat the road.
Other roads – Boerne
  • Monday, September 11 at 8 p.m. until Tuesday, September 12 at 5 a.m. Hwy 46, both directions, between Ammann Road and Rust Lane. Alternating lanes will close while crews resurface the road.
Other roads – East San Antonio
  • Monday-Friday, September 11-15. 9 p.m. until 5 a.m. nightly. Westbound FM 78 between Gulf Shore Boulevard and Rittiman Road. The right lane will close while crews do concrete work.
Other roads – Far west San Antonio
  • Monday, September 11 at 9 p.m. until Tuesday, September 12 at 5 a.m. Eastbound Potranco Road immediately west of Loop 1604. The right lane will close while crews install drain structures.
  • Current until Thursday, September 14 at 5 p.m. Dodge City Trail, both directions, at Loop 1604. All lanes will close while crews rebuild the intersection of Dodge City Trail and the southbound frontage road of Loop 1604. Traffic will use Emory Peak to reach its destination.
  • Tuesday, September 12 at 9 p.m. until Wednesday, September 13 at 5 a.m. Military Drive, both directions, west of Loop 1604. All lanes will close while crews do overhead bridge work. Traffic will use Westcreek Oaks Drive to reach its destination.
Other roads – Northwest San Antonio
  • Current until Friday, September 29. 9 p.m. until 5 a.m. nightly. Hunt Lane, both directions, at Hwy 151. All lanes will close as needed while crews do overhead bridge work. Traffic will turn right onto the frontage road and turn around at the next intersection to reach its destination. This closure will not be in place if Potranco Road is closed.
  • Current until Friday, September 29. 9 p.m. until 5 a.m. nightly. Potranco Road, both directions, at Hwy 151. All lanes will close as needed while crews do overhead bridge work. Traffic will turn right onto the frontage road and turn around at the next intersection to reach its destination. This closure will not be in place if Hunt Lane is closed.
All closures are pending weather.