I-10 – Fair Oaks Ranch
  • Current until Friday, February 23. Westbound frontage road at Old Fredericksburg Road. All lanes will close while crews replace drain structures. Traffic will follow the signed detour route, including a temporary route under the new overpass at Old Fredericksburg, to reach its destination.
I-35 – Schertz
  • Current until October 2018. Frontage roads, both directions, at FM 1103. The right lane will close while crews replace the FM 1103 overpass bridge.
  • Friday, January 19. 9 a.m. until 3 p.m. Northbound main lanes at FM 1103. The left lane will close while crews repair a crash cushion.
I-35 – Northeast San Antonio
  • Current until Monday, January 22. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between Thousand Oaks and George Beach. Alternating lanes will close while crews do road work.
  • Saturday, January 13. 5 a.m. until 9 p.m. Main lanes, both directions, between Thousand Oaks and George Beach. Alternating lanes will close while crews work on overhead highway signs and lights.
I-35 – East San Antonio
  • Monday-Friday, January 15-19. 9 a.m. until 4 p.m. daily. Main lanes, both directions, at AT&T Center Pkwy. The right lane will close while crews do concrete work.
  • Thursday, January 18 at 9 p.m. until Friday, January 19 at 5 a.m. Main lanes, both directions, at New Braunfels Avenue. All lanes will close while crews do power line work overhead. This closure includes the southbound on ramp from Walters. All lanes will exit New Braunfels Avenue, continue through the intersection and re-enter the highway at the next available ramp.
  • Friday, January 19 at 9 p.m. until Monday, January 22 at 5 a.m. Main lanes, both directions, at New Braunfels Avenue. All lanes will close while crews set bridge support beams overhead. Traffic will exit New Braunfels Avenue, move through the intersection and re-enter the main lanes. Traffic at New Braunfels Avenue will be right-turn only in all directions (no traffic will be on the New Braunfels Avenue bridge itself).
I-37 – Downtown San Antonio
  • Current and continuous until March 2018 at 9 a.m. Northbound exit ramp to Florida and Carolina avenues (exit 140A). The ramp will close while crews rebuild the slope near the exit. Traffic will exit Cesar Chavez (exit 140B) and turn around to reach its destination.
I-410 – West San Antonio
  • Current until Wednesday, January 31. 8 p.m. until 5 a.m. nightly. Main lanes, both directions between US 90 and Marbach. All lanes will close as needed while crews do overhead bridge work. Traffic will be detoured onto the frontage road and use the next available entrance ramp to reach its destination. This closure will not take place at the same time as the closure on US Hwy 90.
  • Current until December 2018. Turnarounds, both directions, at Marbach Road. The turnarounds will remain closed while crews construct the new Marbach overpass bridge. Traffic will use the signalized intersection.
I-410 – Northwest San Antonio
  • Friday, January 19 at 9 p.m. until Monday, January 22 at 5 a.m. Southbound frontage road at Hwy 151. All lanes will close while crews hang steel bridge support beams overhead. Traffic will go west on the westbound frontage road of Hwy 151, turn around at Ingram Road and return to I-410 to continue on to their destination. Please be aware of the simultaneous closure of the Hwy 151 westbound frontage road at I-410 using a similar path as a detour route.
U.S. Hwy 90 – West San Antonio
  • Current until Wednesday, January 31. 8 p.m. until 5 a.m. nightly. Main lanes, both directions, at I-410. All lanes will close as needed while crews do overhead bridge work. Traffic will be detoured onto the frontage road and use the next available entrance ramp to reach its destination. This closure will not take place at the same time as the closure on I-410.
U.S. Hwy 281 – North San Antonio
  • Saturday, January 13. 6 a.m. until noon. Southbound main lanes between Marshall Road and Stone Oak Parkway. The right lane will close while crews set barrier.
  • Monday-Friday, January 15-19. 9 p.m. until 5 a.m. nightly. Northbound main lanes at Evans Road. The two left turn lanes will close while crews work across Evans Road.
  • Monday-Friday, January 15-19. 9 p.m. until 5 a.m. nightly. Northbound main lanes between Loop 1604 and Sonterra Road. Alternating lanes will close while crews set barrier. This closure includes the Sonterra exit ramp. Traffic will use the frontage road exit ramp to reach Sonterra Road.
Loop 1604 – Northwest San Antonio
  • Sunday-Wednesday, January 14-17. 9 p.m. until 5 a.m. nightly. Frontage roads, both directions, at Bandera Road. The two left lanes will close while crews remove barrier.
  • Current until Friday, January 26. North-to-south turnaround at Bandera Road. The turnaround will remain closed while crews do road work. Traffic will use the signalized intersection to turn around.
Hwy 151
  • Friday, January 19 at 9 p.m. until Monday, January 22 at 5 a.m. Westbound frontage road at I-410. All lanes will close while crews hang steel bridge support beams overhead. Traffic will go north on the northbound frontage road of I-410, turn around at Military Drive and return to Hwy 151 to continue on to their destination. Please be aware of the simultaneous closure of the I-410 southbound frontage road at Hwy 151 using a similar path as a detour route.
Other roads – Converse
  • Tuesday-Friday, January 15-19. 9 a.m. until 4 p.m. daily. FM 1516, both directions, between Avenues F and D. All lanes will close while crews install a water line. Traffic will use Station Street to reach its destination.
Other roads – Helotes
  • Current until Wednesday, January 31. 9 a.m. until 3 p.m. daily. FM 1560, both directions, between Alta Loma and Saltillo Flat. Alternating lanes will close while crews do road work. Traffic will be controlled by a flagger during this closure.
  • Current until Wednesday, January 31. 9 a.m. until 3 p.m. daily. Bandera Road, both directions, at Circle A Trail. Alternating lanes will close while crews do road work.
  • Sunday-Wednesday, January 14-17. 9 p.m. until 5 a.m. nightly. Southbound Bandera Road at Loop 1604. The right two lanes will close while crews move barrier.
Other roads – Castle Hills
  • Tuesday-Friday, January 16-19. 9 a.m. until 3 p.m. daily. Northbound Northwest Military Highway between Northcrest and Briarcliff drives. The right lane will close while crews work on sidewalks.
  • Tuesday-Friday, January 16-19. 9 a.m. until 3 p.m. daily. Southbound Northwest Military Highway between Lemonwood Drive and Ivywood Circle. The right lane will close while crews work on sidewalks.
All closures are pending weather.