Pages

Friday, November 2

NEXT WEEK'S CONSTRUCTION-RELATED CLOSURES

I-10 – West San Antonio
  • Current until Friday, November 16. 8 a.m. until 4 p.m. Westbound Exit 551 (Boerne Stage Road/Leon Springs) for retaining wall construction. 
  • Current until 9 p.m. Saturday, November 3. Westbound frontage road and Boerne Stage Road for bridge work. DETOUR: Use Ralph Fair Road and Dominion Drive as alternate exits. 
  • Friday, November 2 until Monday, November 5. 9 p.m. until 5 a.m. Eastbound right mainlane from Frederick Creek to SH 46 for shoulder reconstruction work. DETOUR: Traffic will be diverted to Scenic Loop. 
  • Monday, November 5 until Friday, November 9. 9 p.m until 5 a.m. Alternating mainlanes from Frederick Creek to US 87 for barrier work and striping. 
  • Friday, November 9 until Monday, November 12. 9 p.m. until 5 a.m. Westbound right mainlane from US 87 to SH 46 for shoulder reconstruction work. DETOUR: Traffic on SH 46 will be diverted to the eastbound frontage road to Scenic Loop to the highway westbound entrance ramp. 
I-10 – East San Antonio
  • Saturday, November 3. 5 a.m. until 9 p.m. Alternating lanes in both directions from I-410 to Loop 1604 for striping, milling, paving and barrier installation work. 
  • Sunday, November 4 until Friday, November 9. 9 p.m. until 5 a.m. Alternating mainlanes in both directions between I-410 and Loop 1604 for striping, mill/paving and traffic barrier installation work. 
I-35 – East San Antonio
  • Monday, November 5. 9 a.m. to 3 p.m. Northbound left mainlane at AT&T Parkway (railroad bridge) for guardrail repair work. 
I-410 – West San Antonio
  • Sunday, November 4 until Friday, November 16. 8 p.m. until 5 a.m. Full northbound mainlane closure from US 90 bridge to Marbach Road for barrier removal on the mainlanes and frontage road. DETOUR: Traffic will use the frontage road and use next ramp. 
  • Sunday, November 4 until Friday, November 16. 8 p.m. until 5 a.m. Full southbound mainlane and frontage road closure from Lakeside to Valley Hi for mainlanes and before US 90 to the eastbound cloverleaf for the frontage road for barrier and overhang removal. 
  • Monday, November 5 until Thursday, November 8. 9 a.m. to 3 p.m. Northbound left frontage road lane from Landing Avenue to Bronco Lane for curb installation work. 
Loop 1604 – East San Antonio 
  • Monday, November 5 until Friday, November 9. 9 p.m. until 5 a.m. Pat Booker Road exit to I-35 for barrier placement work. DETOUR: Traffic will take Loop 1604 westbound to the Lookout Road exit and then take turnaround to Loop 1604 eastbound and then take the exit to I-35. 
  • Wednesday, November 7 until Friday, November 9. 9 p.m. until 5 a.m. Right northbound mainlane from Pat Booker Road to I-35 for barrier placement work. DETOUR: Traffic will take Loop 1604 westbound to the Lookout Road exit and then take turnaround to Loop 1604 eastbound and then take the exit to I-35. 
  • Monday, November 5 until Friday, November 9. 9 p.m. until 5 a.m. Westbound entrance ramp from Pat Booker Road to I-35 for barrier placement work. DETOUR: Traffic takes I-35 northbound frontage road up to North Evans Road and take the turnaround to I-35 southbound back to Loop 1604 westbound. 
Loop 1604 – West San Antonio
  • Friday, November 2 until Saturday, November 3. 9 p.m. until 5 a.m. Alternating northbound mainlanes from Military Drive to Wiseman Boulevard for concrete traffic barrier work. 
  • Sunday, November 4 until Friday, November 9. 9 p.m. until 5 a.m. One westbound mainlane and ramps to I-10 from Lockhill Selma Road to Chase Hill Boulevard for guardrail and mow strip work. 
  • Monday, November 5 until Friday, November 9. 9 a.m. until 3 p.m. One westbound frontage road lane from Lockhill Selma Road to Chase Hill Boulevard for guardrail and mow strip work. 
  • Monday, November 5 until Friday, November 9. 9 a.m. until 3 p.m. One westbound frontage road lane from Vance Jackson to I-10 for guardrail and electrical repairs. 
  • Sunday, November 4 until Saturday, December 1. 9 p.m. until 5 a.m. Alternating southbound mainlanes from Potranco Road to US 90 for paving, striping and barrier work. 
  • Tuesday, November 6 until Thursday, November 8. 9 a.m until 3 p.m. Northbound left mainlane from Marbach to US 90 for guard fence work. 
Loop 1604 – North San Antonio
  • Monday, November 5 until Friday, November 9. 9 p.m. until 8 p.m. Alternating westbound frontage road between Gold Canyon Road and US 281 for restripe work. 
  • Monday, November 5 until Friday, November 9. 9 p.m. until 5 a.m. Westbound right mainlane from US 281 North exit to US 281 northbound frontage road for restripe work. DETOUR: Traffic will be diverted to Stone Oak Parkway, take the turnaround and back to Loop 1604. 
US 281 – North San Antonio
  • Sunday, November 4 until Friday, November 9. 9 p.m. until 5 a.m. Alternating northbound mainlanes from Redland Road to Encino Rio for barrier work. 
  • Sunday, November 4 until Friday, November 9. 9 p.m. until 5 a.m. Full closure of northbound mainlanes from Sonterra Boulevard exit ramp to Sonterra Boulevard entrance ramp for barrier work. 
  • Sunday, November 4 until Friday, November 9. 9 p.m. until 5 a.m. Alternating southbound frontage road lanes from Sonterra Boulevard to Loop 1604 westbound frontage road for direct connector work. 
  • Monday, November 5 until Friday, November 9. 9 p.m. until 5 a.m. Full closure of northbound mainlanes from Frontage Road exit to Sonterra Boulevard entrance for direct connector work. 
  • Monday, November 5 until Friday, November 9. 9 p.m. until 5 a.m. Alternating northbound mainlanes from Donellla Drive to Sonterra Boulevard entrance for direct connector work. 
  • Monday, November 5 until Friday, November 9. 9 p.m. until 5 a.m. Full closure of southbound mainlanes from Frontage Road exit to Sonterra Boulevard entrance for direct connector work. DETOUR: Take Sonterra exit and continue south on frontage road, getting back on the highway at the Donella Drive entrance. 
  • Tuesday, November 6 until Friday, November 9. 9 p.m. until 5 a.m. Alternating northbound mainlanes from Redland Road to Encino Rio for barrier work. 
US 90 – West San Antonio
  • Current until Saturday, November 10. 9 p.m. until 5 a.m. Eastbound center mainlane from ½-mile west of Loop 1064 southbound to ½-mile east of Loop 1604 northbound for direct connector work. DETOUR: Traffic rerouted to eastbound frontage road past I-410 interchange and back on to US 90. 
  • Sunday, November 4 until Friday, November 9. 8 p.m. until 5 a.m. Full closure of westbound mainlanes and frontage road from I-410 to Horal Street for bridge panel work. 
  • Sunday, November 4 until Friday, November 16. 8 p.m. until 5 a.m. Full closure of westbound mainlanes from I-410 to Horal Street to set bridge panels. DETOUR: Traffic will take the cloverleaves to I-410 northbound frontage road to the mainlanes; turnaround to southbound frontage road to mainlanes; exit at US 90 to access the westbound frontage road. 
  • Sunday, November 4 until Friday, November 16. 8 p.m. until 5 a.m. Full closure of eastbound mainlanes and frontage road from Ray Ellison Drive to I-410 for eastbound-northbound direct connector work. 
  • Monday, November 5 until Thursday, November 8. 9 a.m. until 3 p.m. Right eastbound mainlane from Hunt Lane to I-410 for traffic rail installation work. 
  • Wednesday, November 7. 9 a.m. until 3 p.m. Eastbound mainlane shoulder from I-410 to Military Drive for concrete barrier pour work. 
US 87 (Rigsby Road) – Southeast San Antonio
  • Monday, November 5. 9 a.m. until 4 p.m. Eastbound right lane from Bonair Road to WW White Road & from WW White Road to Diane Road for sidewalk and driveway work. 
I-37 – South Region
  • Current until November 30. 7 a.m. until 8 p.m. Northbound main lanes from Atascosa/Live Oak county line to approximately one mile north of US 281A for guard rail work. 
FM 1346 (E. Houston St.) – Southeast San Antonio
  • Monday, November 5 until Sunday, November 11. 9 a.m. until 4 p.m. Eastbound right lane from Whispering Creek to Estates Road for sidewalk and driveway work. 
  • Monday, November 5 until Sunday, November 11. 9 a.m. until 4 p.m. Westbound left lane from Flora Road to WW White Road for sidewalk and driveway work. 
Other roads – Bexar County
  • Saturday, November 3. 6 a.m. until 3 p.m. Full closure of Military Drive in both directions at Loop 1604 for traffic signal installation work. 
  • Monday, November 5 until Friday, November 9. 9 p.m. until 5 a.m. Full closure of eastbound Redland Road at US 281 and westbound from Sonterra Boulevard exit to Sonterra Boulevard exit for ramp overhang work. 
  • Current until Friday, December 21. 9 p.m. until 5 a.m. Both directions of Kilmarnoch Lane from Bonny Brae Lane to Loop 1604 for construction work. 
Other roads – Atascosa County
  • Current until November 30. 7 a.m. until 8 p.m. Two lanes of northbound I-37 between Atascosa/Live Oak county line to one mile north of US 281A for pouring concrete, paving and guardrail installation. DETOUR: Northbound traffic on I-37 will be diverted at Exit 98 (FM 541); westbound traffic on FM 1099 will be diverted to US 281A.