Friday, February 22

UPCOMING CONSTRUCTION-RELATED CLOSURES

Loop 1604 – North Central San Antonio
  • Monday, February 25 until Friday, March 1. Nightly 9 p.m. until 5 a.m. Nightly left lane closure of the eastbound frontage road from the Stone Oak Parkway entrance ramp to the US 281 southbound frontage road for bridge work. 
  • Monday, February 25 until Friday, March 1. Nightly 9 p.m. until 5 a.m. Full closure of the westbound frontage road from the US 281 southbound frontage road to the Stone Oak Parkway exit ramp. DETOUR: Take the turnaround at US 281, continue east and take the Redland Road turnaround, use the Redland Road entrance ramp and take the ramp to Stone Oak Parkway to remove overhangs. 
  • Monday, February 25 until Friday, March 1. Nightly 9 p.m. until 5 a.m. Full closure of the westbound frontage road from Gold Canyon Road to US 281, including the US 281 northbound exit ramp to erect overhangs. DETOUR: Take the double left at Gold Canyon Drive, take the double left at Redland Road, use the Redland Road entrance ramp, take the Stone Oak Parkway exit ramp and use the turnaround at Stone Oak Parkway. 
Loop 1604 – Northeast San Antonio
  • Sunday, February 24 until Wednesday, February 27. Nightly 9 p.m. until 5 a.m. Northbound exit ramp to I-35 for paving work. 
  • Sunday, February 24 until Friday, March 1. Nightly 9 p.m. until 5 a.m. Northbound left mainlane from FM 1976 to Kitty Hawk for barrier work. 
  • Sunday, February 24 until Friday, March 1. Nightly 9 p.m. until 5 a.m. Northbound right mainlane from FM 218 (Pat Booker Road) to I-35 for paving work. 
  • Sunday, February 24 until Friday, March 1. Nightly 9 p.m. until 5 a.m. Southbound left mainlane from Kitty Hawk to FM 1976 for barrier work. 
  • Friday, March 1 until Monday, March 4. Nightly 9 p.m. until 5 a.m. Full mainlane closure in both directions from FM 218 (Pat Booker Road) to I-35 northbound and from Lookout Road to Kitty Hawk southbound as well as Pat Booker Road turnaround for bridge demolition work. 
  • Friday, March 1 until Friday, March 8. Daily 9 a.m. until 3 p.m. Northbound turnaround at FM 218 (Pat Booker Road) for bridge demolition work. 
  • Friday, March 8. 9 a.m. until 5 p.m. Southbound turnaround at FM 218 (Pat Booker Road) for bridge demolition work. 
Loop 1604 – Northwest San Antonio
  • Sunday, February 24 until Friday, March 1. Nightly 9 p.m. until 5 a.m. One eastbound and one westbound frontage road lane from SH 16 (Bandera Road) to I-10 for milling and paving work. 
  • Thursday, February 28 until Friday, March 1. 9 p.m. until 5 a.m. Full mainlane closure in both directions at Bitters Road/Rogers Ranch Road (including overpass) for turnaround bridge work. 
  • Sunday, February 24 until Friday, March 1. Nightly 9 p.m. until 5 a.m. One westbound and one eastbound mainlane from SH 16 (Bandera Road) to Kyle Seale Parkway for mow strip work. 
  • Sunday, February 24 until Friday, March 1. Nightly 9 p.m. until 5 a.m. Frontage roads in both directions at SH 16 (Bandera Road) intersection for traffic signal work. 
  • Saturday, March 2. 7 a.m. until 5 p.m. Frontage roads in both directions at Bulverde Road (including the intersection) for traffic signal work. 
Loop 1604 – West San Antonio
  • Current until 3 p.m. Saturday, February 23. Northbound right mainlane from Marbach to Falcon Wolff for traffic signal work. 
  • Monday, February 25 until Friday, March 1. Daily 9 a.m. until 3 p.m. Southbound left frontage road lane from SH 151 to Misty Wood Street for drainage work. 
  • Thursday, February 28 until Friday, March 1. 9 p.m. until 5 a.m. Northbound left frontage road lane from Caracol Creek to Potranco Road for barrier work. 
  • Friday, March 1 until Saturday, March 2. 9 p.m. until 5 a.m. Northbound right frontage road lane from North Ellison Drive to SH 151 for traffic switch from current entrance ramp to new entrance ramp. 
US 281 – North Central San Antonio
  • Sunday, February 24 until Friday, March 1. Nightly 9 p.m. until 5 a.m. Full southbound closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp to install steel girders. 
  • Monday, February 25 until Friday, March 1. Nightly 9 p.m. until 5 a.m. Full northbound closure from the Frontage Road exit ramp to the Sonterra Boulevard entrance ramp to install steel girders. DETOUR: take the turnaround at US 281, continue east and take the Redland Road turnaround, used the Redland Road entrance ramp and take the Stone Oak Parkway exit ramp. 
  • Monday, February 25 until Friday, March 1. Nightly 9 p.m. until 5 a.m. One northbound turn lane at Evans Road. 
  • Monday, February 25 until Friday, March 1. Nightly 9 p.m. until 5 a.m. Northbound Sonterra Boulevard exit ramp for bridge work. DETOUR: take the Frontage Road exit ramp and proceed through the Loop 1604 intersection. 
  • Monday, February 25 until Friday, March 1. Nightly 9 p.m. until 5 a.m. Full northbound frontage road closure from Loop 1604 to the Sonterra Boulevard exit ramp for beam work and restriping. DETOUR: Use the Donella Drive turnaround, take the Donella Drive entrance ramp and use the Sonterra Boulevard exit ramp. 
  • Monday, February 25 until Friday, March 1. Nightly 9 p.m. until 5 a.m. Full southbound frontage road closure from the Sonterra Boulevard exit ramp to the Loop 1604 westbound frontage road. DETOUR: Sonterra Boulevard traffic will go north on US 281, take the turnaround south of Encino Rio and stay on southbound US 281. All southbound US 281 mainlane traffic will take the Donella Drive exit ramp, use the turnaround at Donella Drive and stay on the northbound frontage road. 
  • Saturday, March 2 until Monday, March 4. Full weekend closure 2 p.m. until 5 a.m. Northbound Sonterra Boulevard exit ramp for bridge work. DETOUR: take the Frontage Road exit ramp and proceed through the Loop 1604 intersection. 
I-10 – Northwest San Antonio/Bexar County/Kendall County
  • Saturday, February 23. 3 a.m. until 10 p.m. Full mainlane closure in both directions from one mile west and one mile east of Fair Oaks Parkway for turnaround bridge work. DETOUR: Traffic will be diverted to the frontage road, continue through the intersection and re-enter I-10 at the next entrance ramp. 
  • Sunday, February 24 until Friday, March 1. Nightly 9 p.m. until 5 a.m. Alternating eastbound mainlanes from Frederick Creek to US 87 for striping work. 
  • Sunday, February 24 until Friday, March 1. Nightly 9 p.m. until 5 a.m. Alternating westbound mainlanes from US 87 to Frederick Creek for striping and barrier work. 
  • Sunday, February 24 until Monday, February 25. 9 p.m. until 5 a.m. Eastbound left mainlane from Camp Bullis Road to Dominion Drive for barrier removal work. 
  • Monday, February 25 until Saturday, March 2. Daily 9 a.m. until 4 p.m. Right mainlane in both directions from Fair Oaks Parkway to FM 3351 (Ralph Fair Road) for ramp work. 
  • Monday, February 25 until Tuesday, February 26. 9 p.m. until 5 a.m. Right westbound mainlane from Old Fredericksburg Road to FM 3351 (Ralph Fair Road) for barrier removal work. 
  • Tuesday, February 26 until Wednesday, February 27. 9 p.m. until 5 a.m. Left westbound mainlane from Dominion Drive to Camp Bullis Road for barrier removal work. 
  • Wednesday, February 27 until Thursday, February 28. 9 p.m. until 5 a.m. Left eastbound mainlane from Dominion Drive to Camp Buills Road for barrier removal work. 
I-10 – Far East San Antonio
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604. 
  • Sunday, February 24 until Friday, March 1. Nightly 9 p.m. until 5 a.m. Left mainlane in both directions from just west of I-410 to Foster Road and from FM 1516 to Loop 1604 for construction truck access. 
  • Monday, February 25 until Friday, March 1. Daily 9 p.m. until 3:30 p.m. Eastbound-to-westbound turnaround at FM 1516 for overpass construction. 
I-35 – Northeast San Antonio
  • Monday, February 25 until Wednesday, February 27. Nightly 8 p.m. until 5 a.m. Alternating northbound & southbound frontage road lanes at North New Braunfels Avenue (including the bridge/overpass) for striping work. 
  • Thursday, February 28 until Friday, March 1. 9 p.m. until 5 a.m. Full mainlane closure in both directions at FM 1103 (Exit 178) for bridge work.
 I-35 – Southern Region 
  • Current until Friday, March 8. Nightly 8 p.m. until 6 a.m. Alternating mainlanes in both directions from Loop 13 (Military Drive) to the Atascosa County line for crack-sealing work. 
I-410 – West San Antonio
  • Current until Friday, March 8. 8 p.m. until 5 a.m. Two frontage road lanes in both directions at Marbach Road (including the intersection) for various tasks including installing panels, installing overhangs and pouring concrete. 
  • Friday, February 22 until Monday, February 25. Nightly 8 p.m. until 5 a.m. Full southbound mainlane closure at US 90 for Overhead Sign Bridge (OSB) work. 
  • Friday, February 22 until Monday, February 25. Nightly 8 p.m. until 5 a.m. Left northbound mainlane from US 90 to Marbach Road for Overhead Sign Bridge (OSB) work. 
  • Sunday, February 24 until Friday, March 8. Nightly 8 p.m. until 5 a.m. Full southbound and northbound mainlane closure and left frontage road lane from US 90 to Valley Hi/Marbach Road (mainlanes) & from US 90 to Bertetti Drive (frontage road) for Overhead Sign Bridge (OSB) and frontage road widening work. 
  • Monday, February 25 until Thursday, March 7. Daily 9 a.m. until 3 p.m. Right northbound frontage road lane from Meadow Bend Drive to Meadow Glade Drive for debris removal work. 
  • Monday, February 25 until Thursday, March 7. Daily 9 a.m. until 3 p.m. Left northbound frontage road lane from Landing Avenue to Airlift Avenue for direct connector work. 
US 90 – West San Antonio
  • Current until Friday, February 22. 8 p.m. until 5 a.m. Alternating eastbound mainlanes from Ray Ellison Drive to I-410 for barrier removal and asphalt work. 
  • Current until Saturday, February 23. Daily 9 a.m. until 3 p.m. Westbound turnaround at Loop 1604. 
  • Sunday, February 24 until Friday, March 8. Nightly 8 p.m. until 5 a.m. Full eastbound mainlane and frontage road closure from Ray Ellison Drive to I-410 (mainlanes) & from Loop 1604 to I-410 (frontage road) for barrier, asphalt and road widening work. 
SH 151 – Far West San Antonio
  • Current until 5 a.m. Saturday, February 16. Alternating westbound frontage road lanes from Marbach Road to West Military Drive for milling and asphalt work. 
  • Sunday, February 24 until Friday, March 1. 8 p.m. until 5 a.m. Alternating eastbound frontage road lanes from Military Drive to Callaghan Road for milling and inlay work. 
FM 1560 – Hausman Road
  • Monday, February 25 until Monday, March 25. Daylong closure of the right-turn lane from FM 1560 (Hausman Road) to SH 16 (Bandera Road) for utility work/road excavation. 
PA 1502 – Wurzbach Parkway
  • City of San Antonio closure for Hardberger Park Landbridge project. Saturday, March 23 & Monday, February 25 until Friday, March 1. Daily 9 a.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access. 
FM 1976 – Walzem Road
  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes from Woodlake Parkway until Gibbs Sprawl Road for barrier work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle). 
US 87 – Rigsby Avenue
  • Monday, February 25 until Friday, March 1. Daily 9 a.m. until 4 p.m. Westbound right lane from Willenbrook Avenue to Bonair Road for sidewalk and driveway work. 
Other Roads – Bexar County
  • Monday, February 25 until Friday, March 1. 9 a.m. until 3 p.m. Alternating lanes of Potranco Road, Military Drive and Wiseman Boulevard in both directions at Loop 1604 for demolition and reconstruction of curb islands and medians. 
  • Monday, February 25 until Friday, March 1. Nightly 9 p.m. until 5 a.m. Nightly 9 p.m. until 5 a.m. Alternating lanes of eastbound and westbound Evans Road, west of US 281 for intersection work. 
  • Tuesday, February 26 until Thursday, February 28. All lanes of West Byrd Lane at Loop 1604 northbound for drainage work.