I-410/US 90 Interchange Project: Traffic Switch & Ramp Work

New exit for SH 151 on I-410 northbound
For our peeps on San Antonio's West Side, listen up, this one's for you!

There will be quite a bit of construction activity taking place this weekend on the I-410/US 90 interchange project.

Friday night
Starting tonight (Friday 8/23) at 8 p.m., all northbound mainlanes between the US 90 exit ramp to SH 151 will be closed to restripe the northbound mainlanes and open up the new exit ramps for Marbach Road and SH 151.

A third frontage road lane will also open up for the exit and entrance ramps. Traffic will be detoured to the frontage road. The new configuration will be open to traffic tomorrow (Saturday 8/24) at 5 a.m.

Saturday night
Later that same day (Saturday) starting at 8 p.m. and running through Monday (8/26) morning at 5 a.m. all southbound mainlanes between the Lakeside exit ramp to the US 90 bridge will be closed to prepare for a traffic switch and to open up the new Marbach Road entrance ramp.
Crews working on the new southbound entrance ramp near Marbach Road


A look ahead
We are gradually approaching the last phase of this project (yay!) that is expected to be completed in 2020. We know, we know, that should prompt a round of applause for everyone!

But we're not quite there yet. We still have work at Marbach Road that includes demolishing the middle section of the current bridge.

Weather permitting, we are planning for the bridge to be demolished the weekend after Labor Day. Stay tuned here and on our social media channel for further updates on this project!