Pages

Friday, December 20

Traffic Switch in Boerne: SH 46 (River Road) Will See Minimal Impact

Heads-up to all our folks who live in or usually drive through the heart of beautiful Boerne!

Traffic switch time on the ongoing project in town.

Starting this Monday (December 23), traffic on SH 46 (River Road) will be switched to the north side of the road onto newly constructed pavement east of the Esperanza Boulevard intersection. 

The traffic switch will continue through the Ammann Road intersection and end roughly a quarter mile east of that intersection. 

Important! The lane configurations at both the Esperanza Boulevard and Ammann Raod intersections are not changing -- meaning you'll have the same capacity as you have now.

Also, we would like to emphasize that the designated left turn lanes at Esperanza Boulevard are remaining in place. 

We appreciate your continued patience and, as always, we cannot stress enough the importance of safety for everyone (the traveling public as well as work crews) within the construction zone. Please remember to either move over and/or slow down when approaching crews -- it's the law. 

Happy Holidays and be safe out there!


Thursday, December 19

Switching Things Up: Next Milestone On Loop 337 Project in New Braunfels

Following rush hour tomorrow (Saturday, Dec. 21) morning, the newly constructed southbound Loop 337 lanes between New Braunfels High School (north of the SH 46 overpass) and just south of Oak Run Parkway will open to drivers as the latest in a series of scheduled traffic switches on the Loop 337 Expansion Project.

All southbound traffic will be permanently shifted to the new lanes. Once this section has opened, crews will begin work on existing lanes, with one northbound lane remaining open to traffic.

Following the traffic switch, drivers turning from Oak Run Parkway will only be able to head southbound on Loop 337. Drivers wishing to head north on Loop 337 will need to take southbound Loop 337 and turn around at Stone Crossing.

This section of southbound Loop 337 is the last to open as part of this project. Crews will continue working on sections of northbound Loop 337 and making additional improvements in future phases of this project.

Message signs are in place to inform drivers of this change and additional signage will be placed to help guide drivers safely along the roadway.

We ask the traveling public to follow construction signage and remain alert when traveling through the work zone. We appreciate your patience and understanding as crews work to improve safety and mobility in the area.

Construction for the Loop 337 Expansion project began in November 2017 and is estimated to be completed in late 2021. The construction project is about six miles long, from I-35 to Hillcrest Drive, and includes an upgrade to a 4-lane divided roadway with pedestrian accommodations and new bridges in various locations.


For our latest real-time updates, follow us on Twitter. For district-wide scheduled road closures, check out our blog.

Friday, December 13

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North Central San Antonio
  • None scheduled.
Loop 1604 – Northeast San Antonio
  • Sunday, December 29 until Saturday, January 4. Daily 9 a.m. until 5 p.m. Westbound frontage road left lane between Bulverde Road and Redland Road for embankment work.
  • Thursday, January 2 until Sunday, January 12. Nightly 9 p.m. until 5 a.m. Alternating eastbound mainlanes between Redland Road and Green Mountain Road (including Redland and Green Mountain exit ramps) for pavement repair work.
Loop 1604 – Northwest San Antonio
  • None scheduled.
US 281 – North Central San Antonio
  • None scheduled.
I-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County
  • Sunday, January 5 until Friday, January 10. Nightly 9 p.m. until 5 a.m. Alternating mainlanes in both directions between Scenic Loop Road and SH 46 for moving barrier and pavement marking work.
  • Sunday, January 12 until Friday, January 17. Alternating mainlanes in both directions between Scenic Loop Road and SH 46 for moving barrier and pavement marking work.
I-10 – Far East San Antonio/Bexar County/Seguin/Guadalupe County
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Current until further notice. Eastbound Ackerman Road exit ramp will be closed through January 2020. DETOUR: Eastbound I-10 and southbound I-410 traffic needing to access Ackerman Road must take southbound I-410, exit at FM 1346/E. Houston St., turn around, and take the northbound frontage road to Ackerman Road.
I-10 – Central/South San Antonio
  • None scheduled.
I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County
  • City of San Antonio/CPS Energy closure. Monday, January 6. 9 a.m. until 12 p.m. Northbound right mainlane at Somerset Road for pole work.
I-410 – West San Antonio
  • Monday, December 30 until Friday, January 3. Daily 9 a.m. to 3 p.m. The right northbound frontage road lane between Marbach Road to Meadow Leaf Drive for installing an electric service pole.
  • Monday, December 30 until Friday, January 10. Daily 9 a.m. to 3 p.m. Alternating frontage road lanes in both directions between SH 151 to Ingram Road for illumination work.
  • Friday, January 3 until Monday, January 6. Nightly 8 p.m. to 5 a.m. All lanes in both directions at Marbach Road for setting beams. DETOUR: Traffic traveling west on Marbach Road will be detoured to the northbound frontage road and turnaround at SH 151 to access southbound I-410 frontage road. Traffic traveling east on Marbach Road will be detoured to the southbound frontage road and utilize the east and northbound cloverleafs to access the I-410 northbound frontage road.
  • Friday, January 3 until Friday, January 10. Nightly 8 p.m. to 5 a.m. All southbound mainlanes between the exit and entrance ramp at Marbach Road for setting beams. The south/westbound connector will also be closed. DETOUR: Traffic will be detoured to the frontage road,
  • Friday, January 10 until Monday, January 13. Nightly 9 p.m. to 5 a.m. All northbound mainlanes between SH 151 exit ramp to entrance ramp after Culebra Road for restripe work for traffic switch. DETOUR: Traffic will exit at SH 151 and reenter after Culebra Road.
US 90 – West San Antonio
  • None scheduled.
SH 16 – Bandera Road
  • Monday, January 6 until Friday, January 10. Daily 9 a.m. until 4 p.m. Southbound right lane between Legend Trail and Loop 1604 for guard rail work.
FM 3351 – Ralph Fair Road
  • None scheduled.
PA 1502 – Wurzbach Parkway
  • City of San Antonio closure for Hardberger Park landbridge. Thursday, January 2 until Friday, January 3. 9 a.m. until 4 p.m.. Right lane in both directions between NW Military Highway and FM 2696 (Blanco Road) for truck/equipment access.
FM 1516 – South Seguin Road/Converse
  • Monday, January 6 until Tuesday, January 7. 9 p.m. to 5 a.m. Full closure in both directions under I-10 for bridge work. DETOUR: Southbound FM 1516 traffic will take the westbound I-10 frontage road and turn around at Foster Road. Northbound FM 1516 traffic will take the eastbound I-10 frontage road and turn around at Loop 1604.
SH 218 – Pat Booker Road
  • None scheduled.
FM 1976 – Walzem Road/Gibbs Sprawl Road
  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes between Woodlake Parkway and Gibbs Sprawl Road for barrier/pavement work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
Loop 353 – New Laredo Highway
  • None scheduled.
Other Roads – Bexar County
  • Tuesday, January 5 until Thursday, January 9. Daily 9 a.m. until 2 p.m. All lanes of Boerne Stage Road in both directions at I-10 for concrete panel placement work on the expanded Boerne Stage Road bridge.
SH 46 – Boerne/Kendall County
  • Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
FM 1376 -- Sisterdale Road/Kendall County
  • Monday, December 30 until Friday, January 3. Alternating lanes in both directions between Indian Knoll Road and US 87 for culvert work.
FM 537 -- Wilson County
  • Wednesday, January 8 until September 25. Long-term full closure in both directions between FM 1922 and SH 123 for reconstruction of Cibolo Creek bridge.
SH 16 – McMullen County
  • Monday, January 6 until Friday, January 10. Daily 8 a.m. until 5 p.m. Alternating southbound lanes between FM 1962 and McMullen/Duval county line (mile markers 686-700) for barrier and excavation work.

Monday, December 9

Hitting I-10 Toward Houston At Night? Watch Out For Closures This Week

Heads-up highway night owls, particularly those of you who frequent I-10 toward Seguin and Houston.

Continued work on the I-10 expansion project in Far East San Antonio will require ramp and mainlane closures at the I-410 and I-10 interchange this week. 

Our contractor on this project will be closing both the northbound and southbound I-410 ramps connecting to eastbound I-10, as well as the right eastbound mainlane of 1-10 at the connecting ramp from northbound I-410, to provide access for concrete paving trucks.

The closures will be in effect nightly from 9 p.m. to 5 a.m. tonight (Monday, December 9) through this Friday, December 13. 

Please see the map above and details below on detour routes during this closure.

DETOURS:
  • Southbound I-410 drivers wishing to access eastbound I-10 will exit at FM 1346/E. Houston Street, turn around, travel on the northbound I-410/eastbound I-10 frontage road through the Ackerman Road intersection and enter the eastbound I-10 mainlanes east of Ackerman.
  • Northbound I-410 drivers wishing to access eastbound I-10 will exit at FM 1346/E. Houston Street, travel on the northbound I-410/eastbound I-10 frontage road through the Ackerman Road intersection and enter the eastbound I-10 mainlanes east of Ackerman.

Friday, December 6

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North Central San Antonio
  • Saturday, December 7. Full weekend closure 2 a.m. until 2 p.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Saturday, December 7. Full weekend closure 2 a.m. until 2 p.m. Full eastbound frontage road closure at the east- to westbound turnaround for direct connector work.
  • Saturday, December 7. Full weekend closure 8 a.m. until 2 p.m. Full eastbound mainlane closure from the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Sunday, December 8 until Friday, December 13. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure from the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Sunday, December 8 until Friday, December 13. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Sunday, December 8 until Friday, December 13. Nightly 9 p.m. until 5 a.m. Full westbound frontage road closure from the US 281 southbound frontage road to the Stone Oak Parkway exit ramp. DETOUR: Take the turnaround at US 281, continue east using the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Sunday, December 8 until Friday, December 13. Nightly 9 p.m. until 5 a.m. Eastbound frontage road turnaround closure at US 281 for direct connector work. DETOUR: Turn left at the US 281 intersection then turn left again onto the westbound Loop 1604 frontage road.
  • Saturday, December 14 until Monday, December 16. Full weekend closure 2 a.m. until 5 a.m. Full eastbound mainlane closure from the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Saturday, December 14 until Monday, December 16. Full weekend closure 2 a.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
Loop 1604 – Northeast San Antonio
  • Sunday, December 8 until Friday, December 13. Nightly 9 p.m. until 5 a.m. One mainlane in both directions between Green Mountain Road and I-35 for new guard rail installation work.
  • Sunday, December 8 until Thursday, December 12. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure between Redland Road and Green Mountain Road (including exit ramps) for pavement repair work.
  • Monday, December 9 until Thursday, December 12. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure between Redland Road and Green Mountain Road (including exit ramps) for pavement repair work.
  • Tuesday, December 10 until Saturday, December 14. Nightly 9 p.m. until 5 a.m. Westbound left frontage road lane between Bulverde Road and Redland Road for embankment work.
Loop 1604 – Northwest San Antonio
  • Monday, December 9 until Friday, December 13. Daily 9 a.m. until 3 p.m. Eastbound left frontage road lane between Bandera Road and FM 1560 (Hausman Road) for truck and equipment access.
Loop 1604 – West San Antonio
  • Monday, December 9 until Tuesday, December 10. Daily 9 a.m. to 3 p.m. The right southbound mainlane between FM 1957 (Potranco Road) and Medio Creek for electrical work.
US 281 – North Central San Antonio
  • Saturday, December 7. 7 a.m. until 5 p.m. Northbound right mainlane at Overlook Parkway for setting barrier work.
  • Saturday, December 7. Full weekend closure 2 a.m. until 2 p.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound frontage road, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Saturday, December 7. Full weekend closure 4 a.m. until 2 p.m. Full southbound frontage road closure at Loop 1604 for direct connector work. DETOUR: Turn right on the westbound frontage road, take the turnaround at Stone Oak Parkway and turn right on the southbound frontage road.
  • Saturday, December 7. 6 a.m. until 2 p.m. Northbound Redland Road bypass ramp mainlane closure from Sonterra Boulevard to Encino Rio for ramp work.
  • Saturday, December 7. 6 a.m. until 12 p.m. Southbound right mainlane closure at Stone Oak Parkway for retaining wall work.
  • Sunday, December 8 until Friday, December 13. Nightly 9 p.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound frontage road, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Sunday, December 8 until Friday, December 13. Nightly 9 p.m. until 5 a.m. Full southbound frontage road closure at Loop 1604 for direct connector work. DETOUR: Turn right on the westbound frontage road, take the turnaround at Stone Oak Parkway and turn right on the southbound frontage road.
  • Sunday, December 8 until Friday, December 13. Nightly 9 p.m. until 5 a.m. Northbound mainlane ramp closure of the north- to eastbound direct connector ramp for bridge work. DETOUR: Use the frontage road exit ramp, turn right on the Loop 1604 eastbound frontage road, if heading north, take the turnaround at Gold Canyon Road and turn right on the northbound frontage road. If heading west, continue on the eastbound frontage road through the Gold Canyon Road intersection, use the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Sunday, December 8 until Friday, December 13. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for paving and bridge work.
  • Sunday, December 8 until Friday, December 13. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Marshall Road for paving and bridge work.
  • Saturday, December 14 until Monday, December 16. Full weekend closure 2 a.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound frontage road, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Saturday, December 14 until Monday, December 16. Full weekend closure 2 a.m. until 5 a.m. Full southbound frontage road closure at Loop 1604 for direct connector work. DETOUR: Turn right on the westbound frontage road, take the turnaround at Stone Oak Parkway and turn right on the southbound frontage road.
I-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County
  • Monday, December 9 until Wednesday, December 11. Nightly 9 p.m. until 5 a.m. Alternating mainlanes in both directions between Balcones Creek Bexar/Kendall county line and Fair Oaks Parkway for guard rail repair/upgrade work.
  • CPS Energy closure. Tuesday, December 10 until Friday, December 13. Daily 8:30 a.m. until 5 p.m. Eastbound frontage road between Fair Oaks Parkway and Balcones Creek (Bexar/Kendall county line) for overhead line removal work.
  • Tuesday, December 10 until Friday, December 13. Daily 9 a.m. until 3 p.m. Turnarounds in both directions at Boerne Stage Road for bridge work.
  • Saturday, December 14 until Sunday, December 15. 6 p.m. until 12 p.m. Full eastbound mainlane closure at Boerne Stage Road for bridge work. DETOUR: Traffic diverted to Ralph Fair Road exit onto frontage road, through Ralph Fair Road intersection (Ralph Fair Road closed in both directions over I-10) then through Boerne Stage Road intersection (Boerne Stage Road closed in both directions under I-10) and reenter mainlanes through entrance ramp east of Boerne Stage Road.
  • Saturday, December 14 until Sunday, December 15. 9 p.m. until 12 p.m. Full westbound frontage road closure at Boerne Stage Road (including turnaround) for bridge work.
I-10 – Central San Antonio
  • Friday, December 13. 9 a.m. until 3 p.m. Eastbound right mainlane between Nogalitos Street and I-35 (including I-35 southbound entrance ramp) for guard fence installation work.
I-10 – Far East San Antonio/Bexar County/Seguin/Guadalupe County
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Current until further notice. Eastbound Ackerman Road exit ramp will be closed through the fall. DETOUR: Eastbound I-10 and southbound I-410 traffic needing to access Ackerman Road must take southbound I-410, exit at FM 1346/E. Houston St., turn around, and take the northbound frontage road to Ackerman Road.
  • Sunday, December 8 until Monday, December 9. 8 p.m. until 5 a.m. FM 1516 in both directions under I-10 for bridge panel placement. DETOUR: Southbound FM 1516 traffic will take the westbound I-10 frontage road and turn around at Foster Road. Northbound FM 1516 traffic will take the eastbound I-10 frontage road and turn around at Loop 1604. Police officers will provide traffic control at the FM 1516 and Loop 1604 intersections.
  • Monday, December 9. 9 a.m. until 12 p.m. Eastbound entrance ramp east of Foster Road will be closed. DETOUR: Eastbound frontage road traffic needing to access I-10 will continue along the frontage road until the next entrance ramp after Loop 1604.
  • Monday, December 9 until Friday, December 13. Nightly 9 p.m. to 5 a.m. The right eastbound mainlane of I-10 at the connecting ramp from northbound I-410 for concrete paving truck access. The connecting ramps from northbound and southbound I-410 to eastbound I-10 will also be closed. DETOUR: Southbound I-410 drivers wishing to access eastbound I-10 will exit at FM 1346/E. Houston Street, turn around, travel on the northbound I-410/eastbound I-10 frontage road through the Ackerman Road intersection, and enter the eastbound I-10 mainlanes east of Ackerman. Northbound I-410 drivers wishing to access eastbound I-10 will exit at FM 1346/E. Houston Street, travel on the northbound I-410/eastbound I-10 frontage road through the Ackerman Road intersection, and enter the eastbound I-10 mainlanes east of Ackerman.
I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County
  • Current until Friday, December 20. Full-time closure. Southbound frontage road intersection at North Kowald Lane (including North Koward Lane closure) for culvert work.
  • Tuesday, December 10 & Thursday, December 12. 9 a.m. until 3 p.m. Right mainlane and shoulder in both directions at I-10 interchange for guard fence installation work.
I-37 – Central San Antonio
  • Sunday, December 8 until Monday, December 9. 8:30 p.m. until 5 a.m. Northbound right mainlane between Fair Road and I-10 (including I-10 exit ramp) for guard fence repair work.
  • Monday, December 9 until Friday, December 13. Nightly 8:30 p.m. until 5 a.m. Southbound left mainlane and shoulder between Boyer Street and I-10 interchange (including I-10 eastbound exit ramp) for guard fence installation work.
I-410 – West San Antonio
  • Friday, December 6 until Monday, December 9. Full weekend closure 8 p.m. to 5 a.m. All southbound mainlanes between Culebra Road exit to the Marbach Road entrance ramp for striping and concrete barrier work. The SH 151 connector ramp will also be closed. DETOUR: Traffic on I-410 will be detoured to the frontage road and follow the posted detour.
  • Monday, December 9 until Friday, December 20. Daily 9 a.m. to 3 p.m. Alternating frontage road lanes in both directions between SH 151 to US 90 for staging equipment and trucks.
  • Wednesday, December 11 until Thursday, December 12. 8 p.m. until 1 a.m. Southbound right mainlane between the US 90 entrance ramp to entrance of southbound-to-westbound flyover  for illumination work.
  • Thursday, December 12. 1 a.m. until 5 a.m. Southbound right mainlane between SH 151 to Marbach Road entrance ramp for sign installation work.
  • Thursday, December 12 until Friday, December 13. All southbound mainlanes at US 90 interchange for illumination work.
  • Friday, December 13. 8 p.m. until 5 a.m. Alternating southbound frontage road lanes between SH 151 and Marbach Road exit ramp for striping and barrier work.
US 90 – West San Antonio
  • Monday, December 9 until Friday, December 20. Daily 9 a.m. to 3 p.m. Alternating frontage road lanes in both directions between I-410 to Hunt Lane for staging equipment and trucks.
SH 16 – Bandera Road
  • Monday, December 9 until Friday, December 13. Southbound right lane between Legend Trail and Cooter Brown’s for rail work.
FM 3351 – Ralph Fair Road
  • Saturday, December 14 until Sunday, December 15. 9 p.m. until 12 p.m. Full closure in both directions (including turnarounds) at I-10 for bridge work. DETOUR: Westbound traffic diverted to I-10 westbound frontage road to Old Fredericksburg turnaround to I-10 eastbound mainlanes; eastbound traffic diverted to I-10 eastbound frontage road, continue through Boerne Stage Road intersection (Boerne Stage Road closed in both directions under I-10) to Dominion Drive turnaround.
PA 1502 – Wurzbach Parkway
  • City of San Antonio closure for Hardberger Park Landbridge project. Sunday, December 8. 9 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
  • City of San Antonio closure for Hardberger Park Landbridge project. Monday, December 9 until Friday, December 13. Daily 9 p.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
  • City of San Antonio closure for Hardberger Park Landbridge project. Saturday, December 14. 7 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
Spur 371 – General Hudnell Drive
  • Sunday, December 8 until Friday, December 13. Nightly 9 p.m. to 5 a.m. Alternating lanes in both directions between Frio City Road and Quintana Road for asphalt patching work.
  • Monday, December 9 until Friday, December 13. Daily 7 a.m. to 7 p.m. Alternating lanes in both directions between Frio City Road and Quintana Road for asphalt patching work.
FM 1976 – Walzem Road/Gibbs Sprawl Road
  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes between Woodlake Parkway and Gibbs Sprawl Road for barrier/pavement work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
Other Roads – Bexar County
  • Sunday, December 8 until Friday, December 13. Nightly 9 p.m. until 5 a.m. Full westbound closure of Encino Rio approaching the US 281 intersection for bridge work. DETOUR: Turn right on the US 281 northbound frontage road and use the north- to southbound turnaround after Evans Road.
  • Tuesday, December 10 until Friday, December 13. Daily 9 a.m. until 3 p.m. Alternating lanes of Boerne Stage Road in both directions at I-10 for bridge work.
  • Saturday, December 14 until Sunday, December 15. 9 p.m. until 12 p.m. Full closure of Boerne Stage Road in both directions at I-10 for bridge work. DETOUR: Westbound traffic diverted to Ralph Fair Road turnaround; eastbound traffic diverted to Dominion Drive turnaround.
SH 46 – Boerne/Kendall County
  • Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
FM 1376 – Sisterdale Road (Kendall County)
  • Monday, December 9 until Friday, December 13. Daily 7 a.m. until 7 p.m. Alternating lanes in both directions between Indian Knoll Road and US 87 for culvert work.
SH 16 – McMullen County
  • Monday, December 9 until Friday, December 13. Daily 8 a.m. until 5 p.m. Alternating southbound lanes between FM 1962 to McMullen-Duval County line (mile markers 686-700) for widening and excavation work.

Monday, December 2

THIS WEEK'S SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North Central San Antonio
  • Monday, December 2 until Friday, December 6. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure from the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Monday, December 2 until Friday, December 6. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Monday, December 2 until Friday, December 6. Nightly 9 p.m. until 5 a.m. Full westbound frontage road closure from the US 281 southbound frontage road to the Stone Oak Parkway exit ramp. DETOUR: Take the turnaround at US 281, continue east using the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Monday, December 2 until Friday, December 6. Nightly 9 p.m. until 5 a.m. Eastbound frontage road turnaround closure at US 281 for direct connector work. DETOUR: Turn left at the US 281 intersection then turn left again onto the westbound Loop 1604 frontage road.
  • Saturday, December 7 until Monday, December 9. Full weekend closure 2 a.m. until 5 a.m. Full eastbound mainlane closure from the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Saturday, December 7 until Monday, December 9. Full weekend closure 2 a.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
Loop 1604 – Northeast San Antonio
  • Monday, December 2 until Tuesday, December 3. Daily 9 a.m. until 3 p.m. Right frontage road lane in both directions at FM 2252 (Nacagdoches Road) for traffic island work at the intersection.
  • Monday, December 2 until Friday, December 6. Nightly 9 p.m. until 5 a.m. One mainlane in both directions between Green Mountain Road and I-35 for new guard rail installation work.
  • Tuesday, December 3 until Thursday, December 5. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure between Redland Road and Green Mountain Road (including exit ramps) for pavement repair work.
  • Sunday, December 8 until Thursday, December 12. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure between Redland Road and Green Mountain Road (including exit ramps) for pavement repair work.
  • Monday, December 9 until Thursday, December 12. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure between Redland Road and Green Mountain Road (including exit ramps) for pavement repair work.
Loop 1604 – Northwest San Antonio
  • Monday, December 2 until Friday, December 6. Daily 9 a.m. until 4 p.m. Westbound right frontage road lane at SH 16 for utility work.
US 281 – North Central San Antonio
  • Monday, December 2 until Friday, December 6. Nightly 9 p.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound frontage road, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Monday, December 2 until Friday, December 6. Nightly 9 p.m. until 5 a.m. Full southbound frontage road closure at Loop 1604 for direct connector work. DETOUR: Turn right on the westbound frontage road, take the turnaround at Stone Oak Parkway and turn right on the southbound frontage road.
  • Monday, December 2 until Friday, December 6. Nightly 9 p.m. until 5 a.m. Northbound mainlane ramp closure of the north- to eastbound direct connector ramp for bridge work. DETOUR: Use the frontage road exit ramp, turn right on the Loop 1604 eastbound frontage road, if heading north, take the turnaround at Gold Canyon Road and turn right on the northbound frontage road. If heading west, continue on the eastbound frontage road through the Gold Canyon Road intersection, use the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Monday, December 2 until Friday, December 6. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Marshall Road for paving and bridge work.
  • Monday, December 2 until Friday, December 6. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for paving and bridge work.
  • Saturday, December 7 until Monday, December 9. Full weekend closure 2 a.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound frontage road, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Saturday, December 7 until Monday, December 9. Full weekend closure 2 a.m. until 5 a.m. Full southbound frontage road closure at Loop 1604 for direct connector work. DETOUR: Turn right on the westbound frontage road, take the turnaround at Stone Oak Parkway and turn right on the southbound frontage road.
I-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County
  • Monday, December 2 until Saturday, December 7. Daily 9 a.m. until 4 p.m. Turnarounds at Balcones Creek in both directions for bridge work.
  • Saturday, December 14 until Sunday, December 15. 9 p.m. until 12 p.m. Full eastbound mainlane closure at Boerne Stage Road for bridge work. DETOUR: Traffic diverted to Ralph Fair Road exit onto frontage road, through Ralph Fair Road intersection (Ralph Fair Road closed in both directions over I-10) then through Boerne Stage Road intersection (Boerne Stage Road closed in both directions under I-10) and reenter mainlanes through entrance ramp east of Boerne Stage Road.
I-10 – Central San Antonio
  • Tuesday, December 3 & Thursday, December 5. 9 a.m. until 3 p.m. Westbound right mainlane and shoulder between Probandt and I-35 (including I-35 northbound exit ramp) for guard fence installation work.
I-10 – Far East San Antonio/Bexar County/Seguin/Guadalupe County
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Current until further notice. Eastbound Ackerman Road exit ramp will be closed through the fall. DETOUR: Eastbound I-10 and southbound I-410 traffic needing to access Ackerman Road must take southbound I-410, exit at FM 1346/E. Houston St., turn around, and take the northbound frontage road to Ackerman Road.
I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County
  • Monday, December 2 until Tuesday, December 3. 7:30 a.m. until 5 p.m. Southbound left frontage road lane at Post Road for utility work (Post Road closed until 5:30 p.m.
  • Wednesday, December 4 until Friday, December 20. Full-time closure. Southbound frontage road intersection at North Kowald Lane (including North Koward Lane closure) for culvert work.
I-37 – Central San Antonio
  • Monday, December 2 until Friday, December 6. Nighty 8:30 p.m. until 5 a.m. Northbound right mainlane and shoulder between Boyer Street and I-10 (including I-10 westbound exit ramp) for guard fence installation work.
I-410 – West San Antonio
  • Monday, December 2 until Friday, December 6. Daily 9 a.m. to 3 p.m. The right northbound frontage road lane between Military Drive to Ingram Road for removing high mast poles.
  • Monday, December 2 until Friday, December 6. Daily 9 a.m. to 3 p.m. Alternating frontage road lanes in both directions between SH 151 to US 90 for staging equipment and trucks.
  • Tuesday, December 3 until Thursday, December 5. Nightly 8 p.m. to 5 a.m. All northbound mainlanes between SH 151 to Military Drive striping work. DETOUR: Traffic on I-410 will be detoured to the frontage road and enter at the next available entrance ramp. Traffic on SH 151 eastbound will exit to Cable Ranch Road and continue on the frontage road to access I-410 northbound.
  • Friday, December 6 until Monday, December 9. Full weekend closure 8 p.m. to 5 a.m. All southbound mainlanes between Culebra Road exit to the Marbach Road entrance ramp for striping and concrete barrier work. The SH 151 flyover will also be closed. DETOUR: Traffic on I-410 will be detoured to the frontage road and follow the posted detour.
US 90 – West San Antonio
  • Monday, December 2 until Friday, December 6. Daily 9 a.m. to 3 p.m. Alternating frontage road lanes in both directions between I-410 to Hunt Lane for staging equipment and trucks.
  • Monday, December 2 until Friday, December 6. Nightly 8 p.m. to 5 a.m. All eastbound mainlanes between Ray Ellison Drive to I-410 for mill and overlay work. The east and northbound connector will also be closed. DETOUR: Traffic will be detoured to the frontage road and enter at the next ramp.
  • Monday, December 2 until Friday, December 6. Nightly 8 p.m. to 5 a.m. All westbound mainlanes between I-410 exit to Hunt Lane for mill and overlay work. DETOUR: Traffic will be detoured to the frontage road and enter at the next ramp.
SH 16 – Bandera Road
  • Sunday, November 24 until Wednesday, November 27. Nightly 9 p.m. until 5 a.m. Alternating lanes in both directions between Quincy Lee and Legend Trail for pavement marking work.
  • Monday, December 2 until Friday, December 6. Southbound right lane between Legend Trail and Cooter Brown’s for rail work.
FM 1516 – Far East San Antonio/Bexar County
  • Wednesday, December 4 until Friday, December 6. Nightly 7 p.m. until 5 a.m. Full closure in both directions under I-10 for bridge panel placement. DETOUR: Southbound FM 1516 traffic will take the westbound I-10 frontage road and turn around at Foster Road. Northbound FM 1516 traffic will take the eastbound I-10 frontage road and turn around at Loop 1604. Police officers will provide traffic control at the FM 1516 and Loop 1604 intersections.
FM 3351 – Ralph Fair Road
  • Saturday, December 14 until Sunday, December 15. 9 p.m. until 12 p.m. Full closure in both directions (except turnarounds) at I-10 for bridge work. DETOUR: Westbound traffic diverted to I-10 westbound frontage road to Old Fredericksburg turnaround to I-10 eastbound mainlanes; eastbound traffic diverted to I-10 eastbound frontage road, continue through Boerne Stage Road intersection (Boerne Stage Road closed in both directions under I-10) to Dominion Drive turnaround.
PA 1502 – Wurzbach Parkway
  • City of San Antonio closure for Hardberger Park Landbridge project. Monday, December 2 until Friday, December 6. Daily 9 p.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
  • City of San Antonio closure for Hardberger Park Landbridge project. Saturday, December 7. 7 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
  • City of San Antonio closure for Hardberger Park Landbridge project. Sunday, December 8. 9 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
Spur 371 – General Hudnell Drive
  • Monday, December 2 until Friday, December 6. Nightly 9 p.m. to 5 a.m. Alternating lanes in both directions between Frio City Road and Quintana Road for asphalt patching work..
FM 1976 – Walzem Road/Gibbs Sprawl Road
  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes between Woodlake Parkway and Gibbs Sprawl Road for barrier/pavement work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
Other Roads – Bexar County
  • Monday, December 2 until Friday, December 6. Nightly 9 p.m. until 5 a.m. Full westbound closure of Encino Rio approaching the US 281 intersection for bridge work. DETOUR: Turn right on the US 281 northbound frontage road and use the north- to southbound turnaround after Evans Road.
  • Saturday, December 14 until Sunday, December 15. 9 p.m. until 12 p.m. Full closure of Boerne Stage Road in both directions at I-10 for bridge work. DETOUR: Westbound traffic diverted to Ralph Fair Road turnaround; eastbound traffic diverted to Dominion Drive turnaround.
SH 46 – Boerne/Kendall County
  • Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
FM 1376 – Sisterdale Road (Kendall County)
  • Monday, December 2 until Friday, December 6. Daily 7 a.m. until 7 p.m. Alternating lanes in both directions at various culvert locations between Wasp Creek and US 87 for temporary pavement work.
SH 16 – McMullen County
  • Monday, December 2 until Friday, December 6. Daily 8 a.m. until 5 p.m. Alternating southbound lanes between FM 1962 to McMullen-Duval County line (mile markers 686-700) for widening and excavation work.
  • Monday, December 9 until Friday, December 13. Daily 8 a.m. until 5 p.m. Alternating southbound lanes between FM 1962 to McMullen-Duval County line (mile markers 686-700) for widening and excavation work.