Pages

Friday, January 17

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North Central San Antonio
  • Sunday, January 19 until Friday, January 24. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure from the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Sunday, January 19 until Friday, January 24. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Sunday, January 19 until Friday, January 24. Nightly 9 p.m. until 5 a.m. Full westbound frontage road closure from the US 281 southbound frontage road to the Stone Oak Parkway exit ramp. DETOUR: Take the turnaround at US 281, continue east using the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Sunday, January 19 until Friday, January 24. Nightly 9 p.m. until 5 a.m. Eastbound frontage road closure of the east- to westbound turnaround at US 281 for direct connector work. DETOUR: Turn left at the US 281 intersection then turn left again onto the westbound Loop 1604 frontage road.
  • Saturday, January 25 until Monday, January 27. Full weekend closure 3 a.m. until 5 a.m. Full eastbound mainlane closure of the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Saturday, January 25 until Monday, January 27. Full weekend closure 3 a.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Saturday, January 25 until Monday, January 27. Full weekend closure 3 a.m. until 5 a.m. Full eastbound frontage road closure of the east- to westbound turnaround for direct connector work.
Loop 1604 – Northeast San Antonio
  • Sunday, January 19 until Friday, January 24. Nightly 9 p.m. until 5 a.m. Right mainlane in both directions between Green Mountain Road and I-35 (as well as entrance/exit ramps in between) for pavement repair and guard rail work.
  • Sunday, January 19 until Saturday, January 25. Nightly 8 p.m. until 5 a.m. Westbound left frontage road lane between Bulverde Road and Redland Road for truck/equipment access.
  • Monday, January 20 until Friday, January 24. Nightly 9 p.m. until 5 a.m. Eastbound left frontage road lane between Bulverde Road and Redland Road for barrier work.
  • Monday, January 20 until Wednesday, January 22. Nightly 9 p.m. until 5 a.m. Two frontage road lanes in both directions at Bulverde Road (including the intersection) for pavement repair work.
  • Monday, January 20 until Friday, January 24. Daily 9 a.m. until 3 p.m. One mainlane in both directions between Green Mountain Road and I-35 for mow strip work.
Loop 1604 – Northwest San Antonio
  • None scheduled.
US 281 – North Central San Antonio
  • Saturday, January 18. 2 a.m. until 7 a.m. Left turn lane northbound mainlane closure at Stone Oak/Tournament Players Club (TPC) Parkway both north- to westbound turn lanes for bridge work. DETOUR: Use the turnaround north of Stone Oak/Tournament Players Club (TPC) Parkway.
  • Saturday, January 18. 2 a.m. until 7 a.m. Left turn lane southbound mainlane closure at Tournament Players Club (TPC) Parkway both south- to eastbound turn lanes for bridge work. DETOUR: Use the turnaround south of Stone Oak/Tournament Players Club (TPC) Parkway.
  • Sunday, January 19 until Friday, January 24. Nightly 8 p.m. until 5 a.m. Left turn lane northbound mainlane closure at Stone Oak/Tournament Players Club (TPC) Parkway both north- to westbound turn lanes for bridge work. DETOUR: Use the turnaround north of Stone Oak/Tournament Players Club (TPC) Parkway.
  • Sunday, January 19 until Friday, January 24. Nightly 8 p.m. until 5 a.m. Left turn lane southbound mainlane closure at Tournament Players Club (TPC) Parkway both south- to eastbound turn lanes for bridge work. DETOUR: Use the turnaround south of Stone Oak/Tournament Players Club (TPC) Parkway.
  • Sunday, January 19 until Friday, January 24. Nightly 8 p.m. until 5 a.m. Left northbound mainlane closure from Encino Commons to Stone Oak/Tournament Players Club (TPC) Parkway for bridge work.
  • Sunday, January 19 until Friday, January 24. Nightly 9 p.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound frontage road, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Sunday, January 19 until Friday, January 24. Nightly 9 p.m. until 5 a.m. Full southbound frontage road closure at Loop 1604 for direct connector work. DETOUR: Turn right on the westbound frontage road, take the turnaround at Stone Oak Parkway and turn right on the southbound frontage road.
  • Sunday, January 19 until Friday, January 24. Nightly 9 p.m. until 5 a.m. Full northbound frontage road closure from Loop 1604 to Sonterra Boulevard for direct connector work. DETOUR: Turn left on the southbound frontage road, use the turnaround at Donella Drive and use the Donella Drive entrance ramp.
  • Sunday, January 19 until Friday, January 24. Nightly 9 p.m. until 5 a.m. Full southbound frontage road closure from the south- to northbound turnaround at Loop 1604 for direct connector work. DETOUR: Turn left at the intersection then turn left again.
  • Sunday, January 19 until Friday, January 24. Nightly 9 p.m. until 5 a.m. Northbound mainlane ramp closure of the north- to eastbound direct connector ramp for bridge work. DETOUR: Use the frontage road exit ramp, turn right on the Loop 1604 eastbound frontage road, if heading north, take the turnaround at Gold Canyon Road and turn right on the northbound frontage road. If heading west, continue on the eastbound frontage road through the Gold Canyon Road intersection, use the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Sunday, January 19 until Friday, January 24. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for paving and bridge work.
  • Sunday, January 19 until Friday, January 24. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Marshall Road for paving and bridge work.
  • Saturday, January 25 until Monday, January 27. Full weekend closure 3 a.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound frontage road, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Saturday, January 25 until Monday, January 27. Full weekend closure 3 a.m. until 5 a.m. Full southbound frontage road closure at Loop 1604 for direct connector work. DETOUR: Turn right on the westbound frontage road, take the turnaround at Stone Oak Parkway and turn right on the southbound frontage road.
  • Saturday, January 25 until Monday, January 27. Full weekend closure 3 a.m. until 5 a.m. Northbound Redland Road bypass ramp mainlane closure from Sonterra Boulevard to Encino Rio for ramp work.
US 281 – Southeast San Antonio
  • Monday, January 20. 9 a.m. to 4 p.m. The right northbound lane at FM 1937 for barrier work.
I-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County
  • Current until Friday, January 24. Daily 9 a.m. until 3 p.m. Westbound left frontage road lane ½-mile east of Boerne Stage Road for retaining wall work.
  • Sunday, January 19 until Wednesday, January 22. 9 p.m. until 5 a.m. Alternating westbound mainlanes between Balcones Creek bridge and Fair Oaks Parkway for moving barrier and traffic switch.
  • Sunday, January 19 until Friday, January 24. Nightly 9 p.m. until 5 a.m. Alternating mainlanes in both directions between Scenic Loop Road and SH 46 for barrier and pavement marking work.
  • Saturday, February 1. 4 a.m. until 9 p.m. Full eastbound mainlane closure between FM 3351 and Boerne Stage Road for girder installation work on the expanded Boerne Stage Drive bridge. DETOUR: Traffic diverted to FM 3351 (Ralph Fair Road), stay on eastbound frontage road past Ralph Fair intersection (Ralph Fair closed in both directions) and reenter highway through entrance ramp east of Boerne Stage Road.
  • I-10 – Far East San Antonio/Bexar County/Seguin/Guadalupe County
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Current until further notice. Eastbound Ackerman Road exit ramp will be closed through the end of January 2020. DETOUR: Eastbound I-10 and southbound I-410 traffic needing to access Ackerman Road must take southbound I-410, exit at FM 1346/E. Houston St., turn around, and take the northbound frontage road to Ackerman Road.
  • Tuesday, January 21, until Thursday, January 23. 2 a.m. to 6 p.m. The turnaround at I-10 and FM 1516 will be closed to install Continuously Reinforced Concrete Pavement. DETOUR: Traffic needing to access the turnarounds must turn at the signalized intersection at FM 1516.
  • Thursday, January 23 until Friday, January 24. 9 p.m. to 5 a.m. Woodlake Parkway in both directions under I-10 for bridge work. DETOUR: Northbound Woodlake Parkway traffic will take the eastbound I-10 frontage road and turn around at FM 1516. Southbound Woodlake Parkway traffic will take the westbound I-10 frontage road and turn around at Foster Road.
  • Saturday, January 25. 5 a.m. to 9 p.m. Eastbound I-10 frontage road at Foster Road for drainage work. Only local traffic requiring direct access to properties along the eastbound I-10 frontage road between Foster Road and Woodlake Parkway will be allowed to continue through the Foster intersection. DETOUR: All other northbound/southbound Foster Road traffic and eastbound I-10 frontage road traffic needing to access eastbound I-10 must take the I-10 westbound frontage road to WW White, turn around, and enter the eastbound I-10 mainlanes just east of WW White.
I-10 – Central San Antonio
  • Sunday, January 19 until Thursday, January 23. Nightly 8:30 p.m. until 5 a.m. Eastbound ramps to I-37 for guard rail installation work.
  • Thursday, January 23 until Friday, January 24. Daily 9 a.m. until 3 p.m. Eastbound right mainlane and shoulder between Nogalitos Street and I-35 for mow trip and rip rap installation work.
I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County
  • Monday, January 20 until Tuesday, January 21. Nightly 9 p.m. until 5 a.m. Alternating northbound frontage road lanes between Business 35 and New Braunfels Storage (including FM 306 exit ramp) for pavement marking work.
  • Monday, January 20. 7:30 a.m. until 5 p.m. Southbound left frontage road lane between Schwab Road and Hubertus Road for truck access/barrier placement work.
  • Wednesday, January 22. 9 a.m. until 4 p.m. Northbound left frontage road lane at Eisenhauer Road for bridge inspection work.
  • Thursday, January 23 until Friday, January 24. 8:30 p.m. until 5 a.m. Northbound exit ramp to I-10 for guardrail repair work.
I-410 – West San Antonio
  • Current until Friday, January 24. Daily 9 a.m. to 3 p.m. The right northbound frontage road lane between SH 151 to Culebra Road for service pole work.
  • Sunday, January 19 until Friday, January 24. Nightly 7 p.m. to 5 a.m. All mainlanes in both directions between US 90 exit ramp to Marbach Road to stage equipment for east and northbound connector work.
  • Sunday, January 19 until Friday, January 24. Nightly 8 p.m. to 5 a.m. The northbound mainlane between SH 151 to the east and northbound connector ramp at SH 151 for pavement marking on the new temporary exit ramp to W. Military Drive.
  • Monday, January 20 until Friday, January 24. Nightly 8 p.m. to 5 a.m. The right northbound mainlane between W. Military Drive to Culebra Road exit ramp for staging trucks and equipment. The Culebra Road exit ramp will also be closed. DETOUR: Traffic will use the Ingram Road exit and turnaround.
  • Current until Saturday, January 25. Nightly 8 p.m. to 5 a.m. All southbound mainlanes at Marbach Road for bridge deck work. DETOUR: Traffic will be detoured to the frontage road and re-enter at the next entrance ramp.
  • Thursday, January 23 until Friday, January 24. Nightly 8 p.m. to 5 a.m. The right southbound mainlane between W. Military Drive to SH 151 and south and westbound connector for conduit and traffic camera work. DETOUR: Traffic will exit W. Military Drive; stay on frontage road until to access next entrance.
  • Current until Friday, January 31. Daily 9 a.m. to 3 p.m. Alternating frontage road lanes in both directions between US 90 and Ingram Road for staging trucks and equipment.
US 90 – West San Antonio
  • Current until Friday, January 31. Daily 9 a.m. to 3 p.m. Alternating frontage road lanes in both directions between I-410 to Hunt Lane for staging trucks and equipment.
  • Sunday, January 19 until Friday, January 24. Nightly 7 p.m. to 5 a.m. All eastbound mainlanes between Ray Ellison Drive to I-410 for staging equipment for east and northbound connector work.
  • Thursday, January 23 until Friday, January 24. 8 p.m. until 5 a.m. All westbound mainlanes at I-410 for overhang removal work.
SH 16 – Bandera Road
  • None scheduled.
FM 3351 – Ralph Fair Road
  • Saturday, February 1. 4 a.m. until 9 p.m. Full closure in both directions (including turnarounds) at I-10 for bridge work. DETOUR: Westbound traffic diverted to I-10 westbound frontage road to Old Fredericksburg turnaround to I-10 eastbound mainlanes; eastbound traffic diverted to I-10 eastbound frontage road, continue through Boerne Stage Road intersection (Boerne Stage Road closed in both directions under I-10) to Dominion Drive turnaround.
PA 1502 – Wurzbach Parkway
  • City of San Antonio/TCI closure for Hardberger Park Landbridge project. Monday, January 20 until Friday, January 24. 9 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
  • City of San Antonio/TCI closure for Hardberger Park Landbridge project. Saturday, January 25. 7 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
FM 1560 – Hausman Road
  • Monday, January 20 until Friday, January 24. Daily 9 a.m. until 3 p.m. Eastbound lane between Sonoma Parkway and Windy Creek for utility work.
FM 1516 – South Seguin Road/Converse
  • None scheduled.
SH 218 – Pat Booker Road
  • None scheduled.
Spur 371 – General Hudnell Drive
  • Sunday, January 19 until Friday, January 24. Nightly 8 p.m. to 5 a.m. One southbound lane between Billy Mitchell Boulevard to US 90 for milling and paving work.
Spur 421 – Bandera Road
  • Sunday, January 19 until Friday, January 24. Daily 9 a.m. to 3 p.m. One lane in both directions between I-410 to E. Cheryl Drive for signal work
FM 1976 – Walzem Road/Gibbs Sprawl Road
  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes between Woodlake Parkway and Gibbs Sprawl Road for barrier/pavement work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
Loop 353 – New Laredo Highway
  • None scheduled.
Other Roads – Bexar County
  • Sunday, January 19 until Friday, January 24. Nightly 9 p.m. until 5 a.m. Full westbound closure of Encino Rio approaching the US 281 intersection for bridge work. DETOUR: Turn right on the US 281 northbound frontage road and use the north- to southbound turnaround after Evans Road.
  • Sunday, January 19 until Friday, January 24. Nightly 7 p.m. to 5 a.m. All lanes in both directions on Marbach Road for bridge deck work. DETOUR: Traffic traveling west on Marbach Road will be detoured to the northbound frontage road and turnaround at SH 151 to access southbound I-410 frontage road. Traffic traveling east on Marbach Road will be detoured to the southbound frontage road and utilize the east and northbound cloverleafs to access the I-410 northbound frontage road.
  • Monday, January 20. Daily 9 a.m. to 12 noon. All southbound lanes of San Pedro Avenue between Lockhill- Selma Road and West Rector for traffic signal work. DETOUR: Traffic will need to use the I-410 eastbound frontage road.
  • Monday, January 20. Daily 12 noon to 3 p.m. One southbound lane of San Pedro Avenue between Lockhill- Selma Road and West Rector for pavement marking work.
  • Wednesday, January 22 until Friday, January 24. Daily 9 p.m. until 3 p.m. Alternating lanes of Camp Bullis Road at I-10 for electrical work.
  • Thursday, January 30. 4 a.m. until 3 p.m. Full closure of Boerne Stage Road in both directions at I-10 for bridge deck pour work. DETOUR: Westbound traffic diverted to turnaround at FM 3351 (Ralph Fair Road); eastbound traffic diverted to turnaround at Dominion Drive.
  • Saturday, February 1. 4 a.m. until 9 p.m. Full closure of Boerne Stage Road in both directions at I-10 for bridge girder installation work. DETOUR: Westbound traffic diverted to the Old Fredericksburg Road turnaround; eastbound traffic diverted to the Dominion Drive turnaround.
  • Monday, February 10 until Thursday, February 13. Full closure of Boerne Stage Road in both directions at I-10 for bridge concrete panel installation work. DETOUR: Westbound traffic diverted to the Old Fredericksburg Road turnaround; eastbound traffic diverted to the Dominion Drive turnaround.
  • Monday, February 17 until Thursday, February 20. Full closure of Boerne Stage Road in both directions at I-10 for bridge concrete panel installation work. DETOUR: Westbound traffic diverted to the Old Fredericksburg Road turnaround; eastbound traffic diverted to the Dominion Drive turnaround.
FM 2673 – Canyon Lake/Comal County
  • Monday, January 20 until Friday, January 24. Daily 9 a.m. until 5 p.m. One lane in both directions (with flagger and pilot car for traffic control) between FM 306 and River Road for overlay work.
FM 1518 – Schertz/Cibolo Guadalupe County
  • Current until Monday, February 24. Daily 8 a.m. until 5:30 p.m. Right lane in both directions between Main Street and Oak Street for driveway, curb and sidewalk work.
US 90A – Seguin/Guadalupe County
  • Current until Monday, February 24. Daily 8 a.m. until 5:30 p.m. Right lane in both directions between SH 123 and FM 466 for driveway, curb and sidewalk work.
SH 123 – Seguin/Guadalupe County
  • Current until Monday, February 24. Daily 8 a.m. until 5:30 p.m. Southbound right lane at FM 466 for driveway, curb and sidewalk work.
Business 123 – South Austin Street/Seguin/Guadalupe County
  • Current until Monday, February 24. Daily 8 a.m. until 5:30 p.m. Alternating lanes in both directions between Tor Drive and FM 725 for driveway, curb and sidewalk work.
US 181 – Floresville/Wilson County
  • Current until Monday, February 24. Daily 8 a.m. until 5:30 p.m. Right lane in both directions at SH 97 for driveway, curb and sidewalk work.
US 87 – Wilson County
  • Monday, January 20 until Monday, February 10. Daily 7 a.m. until 6 p.m. Northbound left lane from mile marker 726 to mile marker 728 for culvert replacement work.
FM 1518 – Schertz/Cibolo Guadalupe County
  • Current until Monday, February 24. Daily 8 a.m. until 5:30 p.m. Right lane in both directions between Main Street and Oak Street for driveway, curb and sidewalk work.
SH 46 – Boerne/Kendall County
  • Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
FM 1376 – Kendall County
  • Monday, January 20 until Saturday, January 25. Daily 7 a.m. until 7 p.m. Various culvert locations between Indian Knoll Road and Walnut Grove Road for culvert work.
FM 1333 – Atascosa County
  • Current until Friday, May 1. Full closure (all day) in both directions at Atascosa River (between FM 476 and SH 173) for culvert removal and replacement work.
SH 16 – McMullen County
  • Monday, January 20 until Friday, January 24. Daily 7 a.m. until 6 p.m. Alternating southbound lanes between FM 1962 to McMullen-Duval County line (mile markers 686-700) for paving work.