Loop 1604 – North Central San Antonio

  • Saturday, June 6 until Monday, June 8. Full weekend closure 2 a.m. until 5 a.m.  Full eastbound mainlane closure of the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Saturday, June 6 until Monday, June 8. Full weekend closure 2 a.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Sunday, June 7 until Thursday, June 11. 7 p.m. to 6 a.m. Single mainlane closure, in both directions, from Redland Rd. to Green Mountain Rd. for metal beam guard fence work.
  • Sunday, June 7 until Thursday, June 11. 7 p.m. to 6 a.m. Single lane closure on westbound frontage road from Redland Rd. to Bulverde Rd for metal beam guard fence work.
  • Sunday, June 7 until Friday, June 12. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure of the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Sunday, June 7 until Friday, June 12. Nightly 9 p.m. until 5 a.m. Left lane westbound frontage road closure from the US 281 north exit ramp to the northbound US 281 frontage road.
  • Saturday, June 13 until Monday, June 15. Full weekend closure 2 a.m. until 5 a.m.  Full eastbound mainlane closure of the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Saturday, June 13 until Monday, June 15. Full weekend closure 2 a.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
 Loop 1604 – Northeast San Antonio
  • Sunday, June 7 until Friday, June 12. 8 p.m. to 5 a.m. Single mainlane closures, in both directions, from Green Mountain Rd. to I-35 Cloverleaf ramp for miling and paving work.
  • Sunday, June 7 until Friday, June 12. 8 p.m. to 5 a.m. Single mainlane closures, in both directions, from Green Mountain Rd. to I-35 Cloverleaf famp for guardrail and concrete improvements.

 Loop 1604 – Northwest San Antonio

  • Monday, June 8 until Wednesday, June 10. Nightly 9 p.m. to 5 a.m. Eastbound mainlane and outside shoulder closure from Bandera Rd. and Hausman Rd. to reset a single slope concrete barrier.
  • Monday, June 8. Eastbound Bandera Rd. entrance ramp will be opened to traffic, with the existing Bandera Rd. entrance ramp closing.
  • Monday, June 8 until Wednesday, June 10. Daily 8:30 a.m. to 5:30 p.m. Single eastbound mainlane closure from Bandera Rd. to Hausman Rd. to place work zone pavement markings.
Loop 1604 – West San Antonio

  • None scheduled.
Loop 1604 – Far East San Antonio

  • Friday, June 5 until Monday, June 8. 7 p.m. to 6 a.m. Northbound mainlane closure from FM 1976 to Kitty Hawk Rd. for barrier work.
  • Friday, June 5 until Monday, June 8. 7 p.m. to 6 a.m. Northbound frontage road ramp closures from FM 1976 to Kitty Hawk Rd for barrier work.
  • Friday, June 5 until Monday, June 8. 7 p.m. to 6 a.m. Closure of entrance and exit of Byrd Rd. from northbound frontage road for barrier work.
 Loop 1604 – South San Antonio

  • None scheduled.
 US 281 – North Central San Antonio/Bexar County

  • Friday, June 5 until Monday, June 8. Full weekend closure 9 p.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for a traffic switch. DETOUR: Take the Sonterra Boulevard exit ramp and use the Donella Drive entrance ramp.
  • Saturday, June 6 until Monday, June 8. Full weekend closure 2 a.m. until 5 a.m. Full northbound mainlane closure from the frontage road exit ramp to the Sonterra Boulevard entrance ramp. DETOUR: Take the frontage road exit ramp and use the Sonterra Boulevard entrance ramp.
  • Saturday, June 6 until Monday, June 8. Weekend closure 2 a.m. until 5 p.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for bridge work and safety enhancements.
  • Friday, June 5 until Monday, June 8. Full weekend closure 9 p.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for a traffic switch. DETOUR: Take the Sonterra Boulevard exit ramp and use the Donella Drive entrance ramp.
  • Friday, June 5 until Monday, June 8. Weekend closure 9 p.m. until 5 a.m. Left lane southbound mainlane closure from Evans Road to Redland Road.
  • Sunday, June 7 until Friday, June 12. Nightly 9 p.m. until 5 a.m. Full southbound frontage road closure at Loop 1604 for direct connector work. DETOUR: Turn right on the westbound frontage road, take the turnaround at Stone Oak Parkway and turn right on the southbound frontage road.
  • Sunday, June 7 until Friday, June 12. Nightly 9 p.m. until 5 a.m. Northbound mainlane closure from the north- to southbound turnaround at Encino Rio for bridge work. DETOUR: Use the turnaround at Evans Road. Closure will not happen concurrently with other turnaround closures in the same direction.
  • Sunday, June 7 until Friday, June 12. Nightly 9 p.m. until 5 a.m. Northbound mainlane closure from the north- to southbound turnaround at Evans Road for bridge work. DETOUR: Use the turnaround at Stone Oak/Tournament Players Club (TPC) Parkway. Closure will not happen concurrently with other turnaround closures in the same direction.
  • Sunday, June 7 until Friday, June 12. Nightly 9 p.m. until 5 a.m. Northbound mainlane closure from the north- to southbound turnaround at Stone Oak/Tournament Players Club (TPC) Parkway for bridge work. DETOUR: Use the turnaround north of Stone Oak/Tournament Players Club (TPC) Parkway. Closure will not happen concurrently with other turnaround closures in the same direction.
  • Sunday, June 7 until Friday, June 12. Nightly 9 p.m. until 5 a.m. Southbound mainlane closure from the south- to northbound turnaround at Stone Oak/Tournament Players Club (TPC) Parkway for bridge work. DETOUR: Use the turnaround at Evans Road. Closure will not happen concurrently with other turnaround closures in the same direction.
  • Sunday, June 7 until Friday, June 12. Nightly 9 p.m. until 5 a.m. Southbound mainlane closure from the south- to northbound turnaround at Evans Road for bridge work. DETOUR: Use the turnaround at Encino Rio. Closure will not happen concurrently with other turnaround closures in the same direction.
  • Sunday, June 7 until Friday, June 12. Nightly 9 p.m. until 5 a.m. Southbound mainlane closure from the south- to northbound turnaround at Encino Rio for bridge work. DETOUR: Use the turnaround at Redland Road. Closure will not happen concurrently with other turnaround closures in the same direction.
  • Sunday, June 7 until Friday, June 12. Nightly 9 p.m. until 5 a.m. Left turn lane northbound mainlane closure at Evans Road both north- to westbound turn lanes for bridge work. DETOUR: Use the turnaround at Stone Oak/Tournament Players Club (TPC) Parkway. Closure will not happen concurrently with other turnaround closures in the same direction.
  • Sunday, June 7 until Friday, June 12. Nightly 9 p.m. until 5 a.m. Left turn lane southbound mainlane closure at Evans Road both south- to eastbound turn lanes for bridge work. DETOUR: Use the turnaround at Encino Rio. Closure will not happen concurrently with other turnaround closures in the same direction.
  • Sunday, June 7 until Friday, June 12. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Marshall Road for bridge work and safety enhancements.
  • Sunday, June 7 until Friday, June 12. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for bridge work and safety enhancements.
  • Sunday, June 7 until Friday, June 12. Nightly 9 p.m. until 5 a.m. Alternating southbound frontage road closure from Sonterra Boulevard to Loop 1604 for concrete paving.
  • Saturday, June 13 until Monday, June 15. Full weekend closure 2 a.m. until 5 a.m. Full northbound mainlane closure from the frontage road exit ramp to the Sonterra Boulevard entrance ramp. DETOUR: Take the frontage road exit ramp and use the Sonterra Boulevard entrance ramp.
  • Saturday, June 13 until Monday, June 15. Weekend closure 2 a.m. until 5 a.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for bridge work and safety enhancements.
 Encino Rio – North Central San Antonio
  •  Friday, June 5 until Monday June 8. Full weekend closure 9 p.m. until 5 a.m. Full westbound crossing closure at US 281 for bridge work. DETOUR: Head right on northbound US 281 and take the north- to southbound turnaround at Evans Road.
  •  Sunday, June 7 until Friday, June 12. Nightly 9 p.m. until 5 a.m. Full westbound crossing closure at US 281 for bridge work. DETOUR: Head right on northbound US 281 and take the turnaround at Evans Road.

 Agora Palms Drive – North Central San Antonio
  • Friday, June 5 until Monday, June 8. Full weekend closure 9 p.m. until 5 a.m. Full eastbound crossing closure at the US 281 southbound frontage road for a traffic switch. DETOUR: Take Hardy Oak Boulevard to Loop 1604, take the westbound Loop 1604 frontage road, use the turnaround at Stone Oak Parkway then take Loop 1604 to US 281.

 Sonterra Boulevard Access Road – North Central San Antonio
  • Friday, June 5 until Monday, June 8. Full weekend closure 9 p.m. until 5 a.m. Full eastbound crossing closure at the US 281 southbound frontage road for a traffic switch. DETOUR: Head north on US 281, take the north- to southbound turnaround at Encino Rio and head south on US 281.
  • Friday, June 5 until Monday, June 8. Full weekend closure 9 p.m. until 5 a.m. Full westbound crossing closure at the US 281 southbound frontage road for a traffic switch. DETOUR: Stay on the southbound US 281 frontage road, use the south- to northbound turnaround at Loop 1604, head north on the northbound US 281 frontage road and turn right on Sonterra Boulevard.

 US 281 – South San Antonio

  • None scheduled.
I-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County

  • Sunday, June 7 until Thursday, June 11. Nightly, 9 p.m. to 5 a.m. Full northbound mainlane closure from Dominion Dr. to Ralph Fair Rd. for shoulder repair. DETOUR: All traffic take Exit 552 Dominion Dr. and proceed on I-10W frontage road through Leon Springs, pass the Boerne Stage Road intersection through Ralph Fair Road intersection and re-enter westbound mainlanes ¾ of a mile past Ralph Fair Road.
  • Current until Friday, June 26. Nightly 9 p.m. to 5 a.m. Full southbound mainlane closure from Ralph Fair Rd. to La Cantera Parkway for outside shoulder repair. DETOUR: Traffic take Exit 550 Ralph Fair Rd./Boerne Stage Rd. onto the eastbound frontage road through Ralph Fair Rd. intersection, pass Boerne Stage Rd. intersection, and re-enter the eastbound mainlanes one mile east of Camp Bullis Rd.
 I-10 – Far East San Antonio/Bexar County/Seguin/Guadalupe County 
  • Friday, June 5 until Monday, June 8. Weekend closure from 9 p.m. Friday to 6 a.m. Monday. Single eastbound I-10 mainlane between Ackerman and Foster for eastbound traffic switch. (This switch was originally scheduled for earlier May but has been continually postponed due to weather).
  • Current until further notice. Graytown Road bridge at I-10. DETOURS: Graytown Road traffic will use the frontage roads and the Pfeil Road underpass or Loop 1604 turnaround to cross I-10.
  • Current until further nFotice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Current until further notice. Eastbound entrance ramp from Foster Road. DETOUR: Take next entrance ramp east of Woodlake Parkway.
  • Saturday, June 6. Daytime closure from 5 a.m. to 9 p.m. East and westbound right lane closed between Graytown and Pfeil for shoulder resurfacing and to move barrier and crash cushions.
  • Thursday, June 11. FM 1516 intersection closed from 9 p.m. to 5 a.m. for bridge concrete pour. DETOUR: Northbound FM 1516 traffic can use Loop 1604 turnaround. Southbound FM 1516 traffic can use Woodlake Parkway turnaround.
  • Friday, June 12 until Monday, June 14. Weekend closure from 9 p.m. Friday to 6 a.m. Monday. Single eastbound I-10 mainlane between Ackerman and Foster for eastbound traffic switch. (This switch was originally scheduled for earlier May but has been continually postponed due to weather).
  • Saturday, June 13. Daytime closure from 5 a.m. to 9 p.m. East and westbound alternating lane closures between Loop 1604 and Pfeil Road for striping and traffic switch.
  • Current until further notice. Graytown Road bridge at I-10. DETOURS: Graytown Road traffic will use the frontage roads and the Pfeil Road underpass or Loop 1604 turnaround to cross I-10.
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Current until further notice. Eastbound entrance ramp from Foster Road. DETOUR: Take next entrance ramp east of Woodlake Parkway.
 I-10 – Central San Antonio

  • None scheduled.  
I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

  • Current until Saturday, June 6. 9 a.m. to 5 p.m. Single northbound frontage road lane closure from Schwab Rd. to FM 2252 (Hubertus Rd.) for barrier work.
  • Tuesday, June 9 until Saturday, June 27. 9 a.m. to 5 p.m. Single lane closure of northbound frontage road from Schwab Rd. to FM 2252 (Hubertus Rd.) for barrier work.
I-37 – Central/South San Antonio
  • None scheduled.
I-410 – West San Antonio
  • Current until Sunday, June 7. Daily, 9 a.m. to 3 p.m. Alternating northbound and southbound frontage road lane closures from Marbach Road to Ingram Road, including the Military Rd. turnarounds, for storm drain work.
  • Current until Sunday, June 7. Nightly 8 p.m. to 5 a.m. Alternating northbound and southbound mainlane closures from Marbach Road to Culebra Road for barrier work.
  • Friday, June 5 until Friday, June 26. Nightly, 8 p.m. to 5 a.m. Multiple closures from US-90 to SH 151 to stage equipment: southbound frontage road from US-90 to Marbach Rd.; southbound mainlane off-ramp to Marbach Rd.; and southbound frontage road on-ramp from US-90. DETOUR: Traffic heading to SH 151 coming from Loop 410 northbound mainlanes will detour to exit 7 (Marbach Rd.) and continue on Loop 410 northbound frontage road to SH 151.
  • Friday, June 5 until Friday, June 26. Nightly 8 p.m. to 5 a.m. Multiple closures from US-90 to Marbach Rd. for equipment staging: southbound frontage road from Marbach Rd. to US-90; southbound mainlane off-ramp to east US-90; and southbound frontage road on-ramp from Marbach Rd. DETOUR: Traffic coming from Loop 410 southbound mainlanes will detour to Valley-Hi off-ramp and continue on Loop 410 southbount frontage road to take the turnaround to Loop 410 northbound frontage road and continue on Loop 410 frontage road to US-90 or Marbach Rd.
  • Friday, June 5 until Friday, June 26. Nightly 8 p.m. to 5 a.m. Multiple closures from SH 151 to Marbach Rd. for equipment staging: southbound frontage road from SH 151 to Marbach Rd.; southbound mainlane off-ramp to Marbach Rd.; and southbound frontage road on-ramp from SH 151. DETOUR: Traffic coming from Loop 410 southbound mainlanes will detour to US-90 off-ramp, continue to Loop 410 southbound frontage roads and take the SB/EB cloverleaf and continue on Loop 410 northbound frontage road to Marbach Rd.
  • Friday, June 5 until Friday, June 26. Nightly 8 p.m. to 5 a.m. Multiple lane closures from SH 151 to Marbach Rd. for equipment staging: southbound frontage road from US-90 to Marbach Rd.; southbound mainlane off-ramp to Marbach Rd.; southbound frontage road on-ramp from US-90. DETOUR: Traffic traveling to SH 151 coming from Loop 410 northbound mainlanes will detour to exit 7 (Marbach Rd.) and continue to Loop 410 northbound frontage road to SH 151.
  • Saturday, June 6. 9 .am. to 2 p.m. Multiple soutbound mainlane closures from US-90E off-ramp to Pilar St. for crash cushion installation: two southbound mainlanes from US-90E off-ramp to Pilar St.; and full closure of the Loop 410/US-90 southbound/westbound connector. DETOUR: Traffic traveling to US-90W will detour taking US-90E off-ramp and continue to Loop 410 southbound frontage road and take US-90W frontage road.
  • Monday, June 8 until Monday, June 15. Nightly 8 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from Marbach Rd. to Culebra Rd. for barrier installation.
  • Monday, June 8 until Monday, June 15. Daily 9 a.m. to 3 p.m. Alternating frontage road closures, in both directions, from Marbach Rd. to Ingram Rd., including the Military Dr. turnarounds, for wall and pipe work.
  • Monday, June 8 until Monday, June 15. Daily 9 a.m. to 3 p.m. Single lane closure on southbound frontage road from NW Crossroads to Military Dr. to remove concrete riprap.
US 90 – West San Antonio
  • Monday, June 8 until Friday, June 12. Daily 9 a.m. to 3 p.m. Single frontage road closures, in both directions, from W. Military Dr. to SW 36th St. for guardrail improvements.
 SH 151 – West San Antonio
  • Current until Monday, June 8. 24-hour closure for entire week. Alternating eastbound and westbound frontage road closures from Ingram Road to the Loop 410 intersection, including the eastbound and westbound turnaround, for bent work. DETOUR: Eastbound and westbound turnaround traffic will detour to the 410/151 intersection to take two left turns.
  • Monday, June 8 until Monday, June 15. Nightly, 8 p.m. to 5 a.m. Full westbound mainlane closure from Loop 410 exit to Ingram Rd for bent work. DETOUR: Traffic will be detoured to the frontage road through the 410/151 intersection to take the next entrance ramp to SH 151 westbound.
  • Monday, June 8 until Monday, June 15. Daily, 9 a.m. to 3 p.m. Alternating mainlane closures, in both directions, from Loop 410 to Ingram Rd for bent work.
  • Monday, June 8 until Monday, June 15. Daily 9 a.m. to 3 p.m. Alternating frontage road closures, in both directions, from Loop 410 to Ingram Rd. Eastbound and westbound turnarounds will be closed 24-hours. DETOUR: Eastbound and westbound turnaround will detour to the 410/151 intersection to take two left turns.
  • Monday, June 8 until Monday, June 15. Nightly 8 p.m. to 5 a.m. Alternating lane closures on frontage road, in both directions, from Loop 410 to Ingram Rd. for bent work. Eastbound and westbound turnarounds will be closed 24-hours. DETOUR: Eastbound and westbound traffic will detour to the 410/151 intersection to take two left turns.
SH 16 – Bandera Road

  • None scheduled.
FM 3351 – Ralph Fair Road

  • None scheduled.
PA 1502 – Wurzbach Parkway

  • City of San Antonio/PWD closure for Hardberger Park Land Bridge project. Saturday, June 13 until Sunday, June 14. Daily 9 a.m. to 4 p.m. Single mainlane closure, in both directions, from 0.5 miles from NW Military Dr. (FM 1535) to 0.25 miles from Blanco Rd. (FM 2696) to allow for construction haul trucks to enter roadway.
  • City of San Antonio/PWD closure for Hardberger Park Land Bridge project. Monday, June 15 until Friday, June 19. Nightly 9 p.m. to 5 a.m. Full mainlane closure, in both directions, from NW Military Dr. (FM 1535) to Blanco Rd. (FM 2696) for bridge decking. DETOUR: Traffic will utilize West Ave. and Lockhill Selma Rd.
  • City of San Antonio/PWD closure for Hardberger Park Land Bridge project. Monday, June 15 until Friday, June 19. Daily 9 a.m. to 4 p.m. Single mainlane closure, in both directions, from 0.5 miles from NW Military Dr. (FM 1535) to 0.25 miles from Blanco Rd. (FM 2696) to allow for construction haul trucks to enter roadway.
  • City of San Antonio/PWD closure for Hardberger Park Land Bridge project. Friday, June 19 until Sunday, June 21. Nightly 9 p.m. to 5 a.m. Full mainlane closure, in both directions, from NW Military Dr. (FM 1535) to Blanco Rd. (FM 2696) for bridge decking. DETOUR: Traffic will utilize West Ave. and Lockhill Selma Rd.
 Loop 13 – SW Military Drive

  • Sunday, June 7 until Friday, June 12. 7 p.m. to 5 a.m. Single lane closures, in both directions, from Old Pearsall Rd. to Rockgate Dr. for asphalt work.
  • Monday, June 8 until Friday, June 12. 9 a.m. to 5 p.m. Single lane closures, in both directions, from Old Pearsall Rd. to Rockgate Dr. for concrete and sidewalk work.
FM 2252 – Nacogdoches Road

  • None scheduled.
 FM 1560 – Hausman Road

  • Exit ramp from Loop 1604 eastbound closed for approximately two months starting Monday, March 16.
 SH 218 – Pat Booker Road

  • None scheduled.
 Spur 371 – General Hudnell Drive

  • None scheduled.
 FM 78 – Bexar County

  • Monday, June 8 until Friday, June 12. 9:30 a.m. to 3:30 p.m. Single mainlane closure, in both directions, from Woodlake Parkway to Firestone Parkway for pole installation and utility work.
 US 87 – Roland Avenue

  • None scheduled.
Spur 421 – Bandera Road

  • None scheduled.
 FM 1976 – Walzem Road/Gibbs Sprawl Road

  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes between Woodlake Parkway and Gibbs Sprawl Road for barrier/pavement work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
  • Current until further notice. Full-day closure. Southbound lane between Toepperwein Road and Walzem Road for barrier setting work and road rehab work.
 Loop 353 – New Laredo Highway

  • None scheduled.
 Other Roads – Bexar County

  • Current until Monday, June 7. Green Road closed to thru traffic from Loop 1604 eastbound frontage road for road work. DETOUR: Traffic will be redirected to Loop 1604.
FM 306 – New Braunfels/Comal County

  • None scheduled.
 Loop 337 – New Braunfels/Comal County

  • None scheduled.
 TX 46/FM 311 – Comal County

  • None scheduled.
 FM 1863 – Comal County

  • None scheduled.
FM 2673 – Canyon Lake/Comal County

  • None scheduled.
 FM 1516 – South Seguin Road/Converse

  • None scheduled.
 FM 2252 – Comal County

  • None scheduled.
 SH 46 – Guadalupe County

  • None scheduled.
 FM 78 – Guadalupe County

  • None scheduled.
 FM 1518 – Schertz/Cibolo Guadalupe County

  • None scheduled.
 US 90A – Seguin/Guadalupe County

  • None scheduled.
 SH 123 – Seguin/Guadalupe County

  • Monday, June 8 until Friday, June 12. 7 a.m. to 6 p.m. Single mainlane closure, in both directions, from Wilson-Guadalupe County Line to 4 miles north of the Wilson-Guadalupe County Line for traffic switch.
 Business 123 – South Austin Street/Seguin/Guadalupe County

  • None scheduled.
I-35 – Atascosa County/Frio County

  • None scheduled.
 US 181 – Floresville/Wilson County

  • None scheduled.
 US 87 – Wilson County

  • None scheduled.
 SH 46 – Boerne/Kendall County

  • Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
 RM/FM 1376 – Kendall County

  • None scheduled.
 FM 1333 – Atascosa County

  • None scheduled.
 FM 140 – Atascosa County

  • None scheduled.
 SH 16 – McMullen County

  • None scheduled.
 FM 3009 – Comal County

  • Monday, June 8 until Friday, June 12. Daily 8 a.m. to 5 p.m. Single eastbound lane closure from FM-78 to Elbel Dr. for pavement repairs.
 I-10 – Kerr County

  • Current until Tuesday, June 16. Daylight work. Alternating mainlane and shoulder closures, in both directions, from 1.2 miles east of Kerr/Kimble County Line to 0.5 miles east of Kerr/Kimble County Line for metal beam guard fence work.
 FM 1044 – Comal County

  • Monday, June 8 until Friday, June 12. Southbound shoulder closure from northbound frontage road/FM 1044 intersection to the County Line/FM 1044 intersection. Law enforcement will be on site to assist with traffic control.