Pages

Friday, January 29

UPCOMING SCHEDULED CONSTRUCTION CLOSURES


Loop 1604 – North Central San Antonio

  • Saturday, January 30 until Monday, February 1. Weekend closure 2 a.m. until 5 a.m. Full eastbound mainlane closure of the east- to southbound direct connector ramp to US 281 for illumination work. DETOUR: Take the northbound US 281 exit ramp and turn right on the southbound US 281 frontage road. 
  • Monday, February 1 until Friday, February 5. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure of the east- to southbound direct connector ramp to US 281 for concrete paving. DETOUR: Take the northbound US 281 exit ramp and turn right on the southbound US 281 frontage road.
  • Saturday, February 6 until Monday, February 8. Weekend continuous closure 2 a.m. until 5 a.m. Full eastbound mainlane closure of the east- to southbound direct connector ramp to US 281 for illumination work. DETOUR: Take the northbound US 281 exit ramp and turn right on the southbound US 281 frontage road. 
  • Saturday, February 6 until Monday, February 8. Weekend continuous closure 2 a.m. until 5 a.m. Full westbound mainlane closure of the west- to southbound direct connector ramp to US 281 for overhead concrete paving. DETOUR: Take the northbound US 281 exit ramp and turn left on the southbound US 281 frontage road.  

US 281 – North Central San Antonio/Bexar County

  • Saturday, January 30. 7 a.m. to 5 p.m. Single southbound lane closure from Cibolo Creek to Borgfeld Rd. for riprap pouring.
  • Saturday, February 6. 7 a.m. to 5 p.m. Single southbound lane closure from Cibolo Creek to Borgfeld Rd. for riprap pouring.
  • Saturday, January 30 until Monday, February 1. Weekend continuous closure 2 a.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for concrete paving.
  • Saturday, January 30 until Monday, February 1. Weekend continuous closure 2 a.m. until 5 a.m. Alternating southbound mainlane closure from Stone Oak Parkway to Loop 1604 for concrete paving.
  • Saturday, January 30 until Monday, February 1. Weekend continuous closure 2 a.m. until 5 a.m. Alternating northbound frontage road closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for concrete paving.
  • Saturday, January 30 until Monday, February 1. Weekend continuous closure 2 a.m. until 5 a.m. Alternating southbound frontage road closure from Stone Oak Parkway to Loop 1604 for concrete paving and striping.
  • Sunday, January 31 until Friday, February 5. Nightly 9 p.m. until 5 a.m. Full northbound frontage road closure from Loop 1604 to Sonterra Boulevard for concrete paving.
  • Monday, February 1 until Friday, February 5. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for concrete paving. DETOUR: Take the northbound US 281 frontage road exit ramp, go through the intersection at Loop 1604 and use the northbound US 281 frontage road.
  • Monday, February 1 until Friday, February 5. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Stone Oak Parkway to Loop 1604 for concrete paving. DETOUR: Take the southbound US 281 entrance ramp at Donella Drive.
  • Monday, February 1 until Friday, February 5. Nightly 9 p.m. until 5 a.m. Alternating northbound frontage road closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for concrete paving.
  • Monday, February 1 until Friday, February 5. Nightly 9 p.m. until 5 a.m. Alternating southbound frontage road closure from Stone Oak Parkway to Loop 1604 for concrete paving.
  • Saturday, February 6 until Monday, February 8. Weekend continuous closure 2 a.m. until 5 a.m. Full southbound frontage road closure of the south- to northbound turnaround at Loop 1604 for electrical work.
  • Saturday, February 6 until Monday, February 8. Weekend continuous closure 2 a.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for striping work. DETOUR: Take the northbound US 281 frontage road exit ramp and go through the Loop 1604 intersection.
  • Saturday, February 6 until Monday, February 8. Weekend continuous closure 2 a.m. until 5 a.m. Alternating southbound mainlane closure from Stone Oak Parkway to Loop 1604 for concrete paving. DETOUR: Take the southbound US 281 entrance ramp at Donella Drive.
  • Saturday, February 6 until Monday, February 8. Weekend continuous closure 2 a.m. until 5 a.m. Alternating northbound frontage road closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for concrete paving.
  • Saturday, February 6 until Monday, February 8. Weekend continuous closure 2 a.m. until 5 a.m. Alternating southbound frontage road closure from Stone Oak Parkway to Loop 1604 for concrete paving.

I-10 – North West San Antonio/Bexar County/Kendall County/Kerr County 

  • Current until Sunday, February 14. Full closure of eastbound frontage road from Scenic Loop Rd. to Balcones Creek for road improvements.
  • Monday, February 1 until Friday, February 12. Daily 9 a.m. to 3 p.m. Westbound HOV lane closed at various locations from Old Fredericksburg Rd. to La Cantera Parkway for barrier work. 
  • Monday, February 1 until Friday, February 5. 7 a.m. to 7 p.m. Alternating lane closures, in both directions, at the La Cantera Parkway intersection for laying of hot mix. 
  • Friday, February 5. 7 a.m. to 7 p.m. Alternating lane closures, in both directions, at Camp Bullis Rd. intersection for laying of hot mix. 

I-10 – Far East San Antonio/Bexar County/Seguin/Guadalupe County 

  • Friday, January 29 through Monday, February 1. Westbound alternating closures between Foster Road and WW White Road from 8 p.m. Friday until 5 a.m. Monday for striping work.
  • Saturday, January 30. Full eastbound mainlane closure between Loop 1604 and Graytown Road from 6 a.m. until 6 p.m. for barrier work and pothole repair. Eastbound Loop 1604 exit ramp will also be closed.
  • Current until further notice. East and westbound I-10 frontage road traffic has the right-of-way at Woodlake Parkway intersection. Woodlake traffic must stop before proceeding.
  • Current until further notice. Westbound I-10 entrance ramp from Ackerman Road closed. DETOURS: Southbound Ackerman traffic may travel south under the I-10 overpass, use the eastbound frontage road to Foster Road, turn left on Foster, and take the westbound frontage road to the westbound entrance ramp, just west of Foster. Northbound Ackerman traffic may use the eastbound frontage road to Foster Road, turn left on Foster, and take the westbound frontage road to the westbound entrance ramp, just west of Foster.
  • Current until further notice. Graytown Road closed at I-10. DETOURS: Graytown Road traffic may use the frontage road and the Pfeil Road underpass or Loop 1604 turnaround to cross I-10.
  • Current until further notice. Eastbound entrance ramp from Foster Road closed. DETOUR: Take the next entrance ramp east of Woodlake Parkway.
  • Saturday, January 30. 7 a.m. to 7 p.m. Single lane closure on eastbound frontage road from Camp Bullis Rd. to La Cantera Parkway for laying hot mix.
  • Saturday, January 30. 7 a.m. to 7 p.m. Eastbound entrance and exit ramps at La Cantera Parkway closed for laying hot mix.
  • Monday, February 1 until Thursday, February 4. Daily 7:30 a.m. to 6:30 p.m. Single mainlane closures, in both directions, from US 183 to FM 2438 for foundation drilling.

I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

  • Current until Saturday, January 30. 9 a.m. to 5:30 p.m. Single lane closure on southbound frontage road from Hubertus Rd. to FM 2252 for storm drain installation.
  • Current until Saturday, January 30. 9 a.m. to 5:30 p.m. Single lane closure on northbound frontage road from Hubertus Rd. to Schwab Rd. for curb demolition.
  • Friday, January 29 until Saturday, January 30. 9 p.m. to 5 a.m. Single southbound lane closure from Parkway to Conrad bridge for roadwork.
  • Sunday, January 31 until Friday, February 5. Nightly 9 p.m. to 5 a.m. Various lane closures, in both directions, from US 90 to Olympia Parkway for replacement of overhead signs.
  • Monday, February 1 until Saturday, February 6. 9 a.m.to 5:30 p.m. Single northbound frontage road closure from Hubertus Rd. to Schwab Rd. for backfill work.
  • Monday, February 1 until Saturday, February 6. 9 a.m. to 5:30 p.m. Single northbound frontage road closure from Hubertus Rd. to Schwab Rd. for demolition work.
  • Monday, February 1 until Saturday, February 6. 9 a.m. to 5:30 p.m. Single southbound frontage road closure from Hubertus Rd. to FM 2252 for storm drain installation.
  • Monday, February 1 until Saturday, February 6. 9 a.m. to 5:30 p.m. Single southbound frontage road closure from Hubertus Rd. to FM 2252 for material excavation. 

PA 1502 – Wurzbach Parkway

  • Saturday, January 30. 9 a.m. to 4 p.m. Westbound left turn lane closure at Lockhill Selma Rd. for asphalt placement.
  • Monday, February 1 until Friday, February 5. Single lane closures, in both directions, from Starcrest to Weidner for pavement marking operations. 

US 90 – Central/West San Antonio

  • Current until Saturday, February 6. 7 a.m. to 7 p.m. Alternating lane closure on frontage roads, in both directions, from W. Military Dr. to S.W. 36th St. for milling and paving improvements.
  • Current until Saturday, February 6. 7 a.m. to 7 p.m. Alternating lane closures on frontage roads, in both directions, from W. Military Dr. to S.W. 36th St. for guardrail and concrete improvements. 

I-410 – West San Antonio

  • Current until Monday, February 1. 8 p.m. to 5 a.m. Full closure of southbound frontage road at SH 151 interchange for bridge work.
  • Current until Monday, February 1. 6 a.m. to 5 a.m. Double southbound mainlane closure, including alternating frontage road closures, from Culebra Rd. to Ingram Rd. for restriping and barrier setting.
  • Current until Monday, February 1. 8 p.m. to 5 a.m. Full closure of W. Military Dr. intersection for continued bridge work and beam setting.
  • Current until Monday, February 1. 9 a.m. to 3 p.m. Alternating mainlane closures, in both directions, from Marbach Rd. to Culebra Rd. for continued bridge work.
  • Current until Monday, February 1. 9 a.m. to 3 p.m. Alternating frontage road closures, in both directions, from Marbach Rd. to Roxburry Rd. for retaining wall work.
  • Current until Monday, February 1. 8 a.m. to 5 p.m. Single southbound frontage road lane closure from N.W. Crossroad to W. Military Dr. for concrete pouring.
  • Current until Monday, February 8. 9 a.m. to 3 p.m. Alternating lane closures, in both directions, from Marbach Rd. to Culebra Rd. for bridge work.
  • Monday, February 1 until Monday, February 8. 8 a.m. to 5 p.m. Alternating southbound lane closures, from N.W. Crossroads to Military Dr. for work on traffic rail.
  • Monday, February 1 until Monday, February 8. 8 p.m. to 5 a.m. Full closure of southbound frontage road from SH 151 westbound frontage road to SH 151 eastbound frontage road intersection.
  • Monday, February 1 until Monday, February 8. 8 p.m. to 5 a.m. Full closure of southbound mainlanes from Military Dr. to SH 151 for bridge work.
  • Tuesday, February 2 until Friday, February 5. 8 p.m. to 5 a.m. Full closure of Culebra Rd. intersection, in both directions, for work on traffic signal switch. 

SH 151 – West San Antonio

  • Monday, February 1 until Monday, February 8. 8 p.m. to 5 a.m. Full closure of mainlanes, in both directions, from Ingram Rd. to Loop 410 for continued construction of flyover ramps.
  • Monday, February 1 until Monday, February 8. 9 a.m. to 3 p.m. Alternating lane closures on frontage roads, in both directions, from Loop 410 to Ingram Rd. for continued construction of flyover ramps. 

FM 1535 – Northwest Military Highway

  • Current until Wednesday, February 3. Southbound right turn lane at Loop 1604 closed for sidewalk improvements. 

CR 8480 – Alamo Ranch Parkway

  • Current until Monday, February 1. 9 a.m. to 3 p.m. Alternating frontage road closures, in both directions, from Loop 410 to Ingram for continued work on flyover ramps.
  • Monday, February 1 until Friday, February 5. Nightly 9 p.m. to 5 a.m. Single westbound mainlane closure, including right lane on frontage road, from Loop 1604 to Lone Star Parkway for pavement markings. 

FM 1976 – Walzem Road/Gibbs Sprawl Road

  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes between Woodlake Parkway and Gibbs Sprawl Road for barrier/pavement work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
  • Current until further notice. Full-day closure. Southbound lane between Toepperwein Road and Walzem Road for barrier setting work and road rehab work. 

FM 2252 – North Bexar County

  • Current until Monday, February 1. 7 a.m. to 6 p.m. Single lane closures, in both directions, from one mile south of Evans Rd. to one mile north of Evans Rd. for installation of concrete barriers and striping. 

RM 1376 – Kendall County

  • Current until Saturday, February 6. 8:30 a.m. to 8:30 p.m. Single lane closures at various culvert locations, in both directions, from N. School St. to 0.5 miles past Wasp Creek Rd. for culvert work and roadway construction.  

RM 337 – Bandera County

  • Current until March 2021. Full closure of bridge at Mill Creek for bridge replacement. 

SH 123 – Guadalupe County

  • Monday, February 1 until Friday, February 5. 7 a.m. to 5 p.m. Alternating lane closures, in both directions, from Wilson/Guadalupe County Line to 4 miles north of county line for traffic switch.