Friday, March 5

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

 


US 281 – North Central San Antonio/Bexar County

  • Saturday, March 6. 7 a.m. to 6 p.m. Single southbound lane closure from Bulverde Rd. to Estate Gate for sidewalk pouring.
  • Saturday, March 6. 7 a.m. to 6 p.m. Single southbound lane closure from Cibolo Creek to Borgfeld Rd. for sidewalk pouring.
  • Sunday, March 7 until Friday, March 12. Nightly 9 p.m. until 5 a.m. Full northbound mainlane closure of the Sonterra Boulevard exit ramp for concrete paving. DETOUR: Continue north on US 281 mainlanes, use the Evans Road exit ramp, and take the turnaround to access the southbound US 281 frontage road.
  • Sunday, March 7 until Friday, March 12. Nightly 9 p.m. until 5 a.m. Full northbound frontage road closure from Loop 1604 to Sonterra Boulevard for concrete paving. DETOUR: Take the southbound US 281 frontage road, use the turnaround at Donella Drive to return to the northbound US 281 frontage road and take the US 281 Donella Drive entrance ramp.
  • Sunday, March 7 until Friday, March 12. Nightly 9 p.m. until 5 a.m. Full northbound frontage road closure north of Evans Road to Stone Oak/Tournament Players Club (TPC) Parkway for concrete paving. DETOUR: Take the southbound US 281 frontage road, take the turnaround at Loop 1604 to return to the northbound US 281 frontage road and use the US 281 Sonterra Boulevard entrance ramp.
  • Sunday, March 7 until Friday, March 12. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for concrete paving.
  • Sunday, March 7 until Friday, March 12. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Stone Oak Parkway to Loop 1604 for concrete paving.
  • Sunday, March 7 until Friday, March 12. Nightly 9 p.m. until 5 a.m. Alternating northbound frontage road closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for concrete paving.
  • Sunday, March 7 until Friday, March 12. Nightly 9 p.m. until 5 a.m. Alternating southbound frontage road closure from Stone Oak Parkway to Loop 1604 for concrete paving.
  • Saturday, March 13 until Monday, March 15. Weekend continuous 3 p.m. until 5 a.m. Alternating southbound frontage road closure from Redland Road to Loop 1604 for concrete paving.

Stone Oak Parkway – North Central San Antonio

  • Saturday, March 6. Weekend continuous 2 a.m. until 5 p.m. Alternating eastbound crossing closure at US 281 for striping.

 I-10 – North West San Antonio/Bexar County/Kendall County/Kerr County 

  • Saturday, March 6. 6 a.m. to 5 p.m. Single westbound mainlane closure from Scenic Loop Rd. to US 87 to allow crews to pick up barriers.
  • Saturday, March 6. 8 a.m. to 5 p.m. Single eastbound mainlane closure from US 87 to Scenic Loop Rd. for barrier installations.
  • Current until further notice. Eastbound entrance ramp from US 87 closed for continued construction improvements.
  • Monday, March 8 until Wednesday, March 10. 9 a.m. to 3 p.m. Eastbound exit ramp to Dominion Dr. closed for sign installation.
  • Monday, March 8 until Wednesday, March 10. 9 a.m. to 3 p.m. Alternating lane closures through Boerne Stage Rd. intersection for sign installation. 

I-10 – Far East San Antonio/Bexar County/Seguin/Guadalupe County 

  • Saturday, March 6 from midnight to 5 p.m. Westbound right lane closed between Ackerman Road and I-410 interchange for barrier work.
  • Saturday, March 6 from midnight to 5 p.m. Westbound collector road between Ackerman Road and I-410 closed for barrier work. DETOUR: Motorists may exit W.W. White Road, use turnaround and access I-410 interchange.
  • Sunday, March 7 thru Tuesday, March 9 from 9 p.m. to 5 a.m. each night. Eastbound alternating lane closures from W.W. White to I-410 for paving work.
  • Tuesday, March 9 thru Thursday, March 11 from 9 p.m. to 5 a.m. each night. Westbound alternating lane closures from I-410 to W.W. White for paving work.
  • Current until further notice. East and westbound I-10 frontage road traffic has the right-of-way at Woodlake Parkway intersection. Woodlake traffic must stop before proceeding.
  • Current until further notice. Westbound I-10 entrance ramp from Ackerman Road closed. DETOURS: Southbound Ackerman traffic may travel south under the I-10 overpass, use the eastbound frontage road to Foster Road, turn left on Foster, and take the westbound frontage road to the westbound entrance ramp, just west of Foster. Northbound Ackerman traffic may use the eastbound frontage road to Foster Road, turn left on Foster, and take the westbound frontage road to the westbound entrance ramp, just west of Foster.
  • Current until further notice. Graytown Road closed at I-10. DETOURS: Graytown Road traffic may use the frontage road and the Pfeil Road underpass or Loop 1604 turnaround to cross I-10.
  • Current until further notice. Eastbound entrance ramp from Foster Road closed. DETOUR: Take the next entrance ramp east of Woodlake Parkway. 

I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

  • Current until Saturday, March 6. 9 a.m. to 5:30 p.m. Single lane closure on southbound frontage road from Hubertus Rd. to Schwab Rd. for milling and overlay improvements.
  • Current until Saturday, March 6. 9 a.m. to 5:30 p.m. Single lane closure on northbound frontage road from FM 2252 to FM 1103 for barrier placement.
  • Current until Saturday, March 6. 9 a.m. to 5:30 p.m. Single lane closure on southbound frontage road from Hubertus Rd. to FM 2252 for storm drain installation.
  • Current until Saturday, March 6. 9 a.m. to 5:30 p.m. Single lane closure on northbound frontage road from Hubertus Rd. to Schwab Rd. for barrier removal.
  • Current until Saturday, March 6. 9 a.m. to 5:30 p.m. Single lane closure on southbound frontage road from Hubertus Rd. to FM 2252 for material excavation.
  • Current until Saturday, March 6. 9 a.m. to 5:30 p.m. Single lane closure on northbound frontage road from Hubertus Rd. to Schwab Rd. for site work.
  • Sunday, March 7 until Monday, March 8. 9 p.m. to 5 a.m. Single northbound mainlane closure from Business 35 bridge to FM 306 bridge for traffic switch.
  • Current until Friday, March 12. 8 a.m. to 5 p.m. Single lane closure on northbound frontage road from FM 1103 to Schwab Rd. for mill and overlay improvements.
  • Sunday, March 7 until Friday, March 12. 9 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from US 90 to Olympia Parkway for overhead sign replacements.
  • Monday, March 8 until Tuesday, March 9. 9 a.m. to 5 p.m. Full closure of Schwab Rd. underpass for mill and overlay improvements.
  • Monday, March 8 until Friday, March 12. 8 a.m. to 5 p.m. Single lane closure on southbound frontage road from FM 1103 to FM 2252 for material haul-off.
  • Monday, March 8 until Saturday, March 13. 8 a.m. to 5 p.m. Single lane closure on southbound frontage road from Schwab Rd. to FM 1103 for guard rail improvements.
  • Tuesday, March 9 until Wednesday, March 10. 9 p.m. to 5 a.m. Double southbound mainlane closure from FM 1103 until FM 2252 for barrier placement.
  • Wednesday, March 10 until Thursday, March 11. 9 p.m. to 5 a.m. Double southbound mainlane closure from FM 1103 to FM 2252 for barrier placement.
  • Thursday, March 11 until Friday, March 12. 9 p.m. to 5 a.m. Double northbound mainlane cloure from FM 2252 to FM 1103 for barrier placement.
  • Friday, March 5 until Saturday, March 6. 9 p.m. to 7 a.m. Single mainlane closure, I both directions, from Parkway bridge to Conrad’s bridge for bridge deck pour. 

US 90 – Central/West San Antonio

  • Current until Saturday, March 6. 7 a.m. to 7 p.m. Alternating lane closures on frontage roads, in both directions, from W. Military Dr. to S.W. 36th St. for milling and paving improvements. 

I-410 – West San Antonio

  • Current until Monday, March 8. 8 p.m. to 5 a.m. Full closure of southbound frontage roads at SH 151 interchange for bridge work.
  • Current until Monday, March 8. 8 p.m. to 5 a.m. Full closure of mainlanes, in both directions, from W. Military Dr. to SH 151 for bridge work. DETOUR: Traffic will be directed to frontage roads.
  • Current until Saturday, March 6. 8 p.m. to 5 a.m. Full closure of Culebra Rd. intersection, including two mainlanes from Culebra Rd. to Ingram Rd., for bridge widening and underground work.
  • Saturday, March 6. 6 a.m. to 6 p.m. Full closure of southbound mainlanes from N.W. Crossroads to W. Military Dr. for overhead sign removal.
  • Current until Monday, March 8. 9 a.m. to 3 p.m. Alternating lane closures, in both directions, from Marbach Rd. to Culebra Rd. for bridge work.
  • Current until Monday, March 8. 8 a.m. to 5 p.m. Single lane closure on southbound frontage road from N.W. Crossroads to W. Military Dr. for rail pouring.
  • Monday, March 8 until Monday, March 15. 8 p.m. to 5 a.m. Full closure of mainlanes, in both directions, from W. Military Dr. to SH 151 for bridge work. DETOUR: Traffic will be directed to frontage roads.
  • Monday, March 8 until Monday, March 15. 8 p.m. to 5 a.m. Full closure of intersection at Culebra Rd. for bridge widening.
  • Monday, March 8 until Monday, March 15. 8 p.m. to 5 a.m. Full closure of southbound frontage road from SH 151 to Lakeside Parkway for bridge work.
  • Monday, March 8 until Monday, March 15. 9 a.m. to 3 p.m. Single mainlane closure, in both directions, from Marbach Rd. to Culebra Rd. for bridge work.
  • Monday, March 8 until Monday, March 15. 8 a.m. to 5 p.m. Single lane closure on southbound frontage road from N.W. Crossroads to W. Military Dr. for rail repair.
  • Thursday, March 11 until Friday, March 12. 8 p.m. to 5 a.m. Full closure of southbound mainlanes from N.W. Crossroads to W. Military Dr. for overhead sign removal. 

SH 151 – West San Antonio

  • Current until Saturday, March 6. 8 p.m. to 5 a.m. Full closure of eastbound frontage road from Cable Ranch Rd. to Loop 410 for bridge work.
  • Current until Monday, March 8. 9 a.m. to 3 p.m. Alternating lane closures on eastbound frontage road from Loop 410 to Ingram Rd for bridge work.
  • Monday, March 8 until Monday March 15. 8 p.m. to 5 a.m. Full closure of eastbound frontage road from Cable Ranch Rd. to Loop 410 for bridge work.
  • Monday, March 8 until Monday, March 15. 9 a.m. to 3 p.m. Alternating lane closures on eastbound frontage road from Loop 410 to Ingram Rd. for bridge work. 

FM 1957 – Potranco Road

  • Current until Friday, March 26. 9 a.m. to 4 p.m. Single eastbound lane closure from SH 211 to Talley Rd. for placement of communication lines. 

FM 1535 – N.W. Military Highway

  • Saturday, March 6. 7 a.m. to 4 p.m. Single northbound lane closure at Wurzbach Parkway intersection for potholing utilities.
  • Saturday, March 6. 7 a.m. to 4 p.m. Southbound right turn lane closed at Wurzbach Parkway intersection for potholing utilities. 

PA 1502 – Wurzbach Parkway

  • Saturday, March 6. 7 a.m. to 4 p.m. Westbound right turn lane closed at N.W. Military Highway intersection for potholing utilities. 

Alamo Ranch Parkway – Bexar County

  • Sunday, March 7 until Monday, March 8. 9 p.m. to 5 a.m. Single westbound lane closure from Loop 1604 to Lone Star Parkway for barrier setting.
  • Wednesday, March 10. 9 a.m. to 3 p.m. Single westbound mainlane closure from Loop 1604 to Lone Star Parkway for barrier setting. 

FM 1976 – Walzem Road/Gibbs Sprawl Road

  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes between Woodlake Parkway and Gibbs Sprawl Road for barrier/pavement work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
  • Current until further notice. Full-day closure. Southbound lane between Toepperwein Road and Walzem Road for barrier setting work and road rehab work. 

SH 46 – Comal County

  • Sunday, March 7 until Friday, March 12. Double mainlane closure, in both directions, from Independence Dr. to Kerlick Lane for roadway resurfacing. 

RM 337 – Bandera County

  • Current until March 2021. Full closure of bridge at Mill Creek for bridge replacement.