Pages

Friday, February 18

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

 


Loop 1604 – North East San Antonio/Bexar County

  • Friday, February 18 until Saturday, March 5. Right lane closure on westbound exit ramp to southbound I-35 for rail and panel repairs.
  • Tuesday, February 22 until Wednesday, February 23. 9 a.m. to 3 p.m. Alternating southbound mainlane closure from I-35 to Palisades Dr. for bridge work.
  • Tuesday, February 22 until Friday, February 25. 9 a.m. to 3 p.m. Alternating lane closures, in both directions, on Pat Booker Rd. under the Loop 1604 bridge.
  • Friday, February 25. 9 a.m. to 3 p.m. Single northbound mainlane closure from Kitty Hawk Rd. to Coronado Blvd. for barrier shifting. 

Loop 1604 – North West San Antonio/Bexar County

  • Sunday, February 13 until Saturday, February 26. Weeknights 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Bandera Road (SH 16) to IH-10 for barrier setting.
  • Sunday, February 13 until Saturday, February 26. Weeknights 9 p.m. until 5 a.m. Alternating westbound mainlane closure from IH-10 to Bandera Road (SH 16) for barrier setting.
  • Sunday, February 13 until Saturday, February 26. Weeknights 9 p.m. until 5 a.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for barrier setting.
  • Sunday, February 13 until Saturday, February 26. Weeknights 9 p.m. until 5 a.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for barrier setting.
  • Sunday, February 13 until Saturday, February 26. Weeknights 9 p.m. until 5 a.m. Eastbound mainlane full closure from Bandera Road (SH 16) to Kyle Seale Parkway for bridge construction: caps, beams and rail demo.
  • Sunday, February 13 until Saturday, February 26. Weeknights 9 p.m. until 5 a.m. Westbound mainlane full closure from Kyle Seale Parkway to Bandera Road (SH 16) for bridge construction: caps, beams and rail demo.
  • Sunday, February 13 until Saturday, February 26. Weeknights 9 p.m. until 5 a.m. Northbound Hausman Road full closure at the Loop 1604 intersection for bridge construction: caps, beams and rail demo.
  • Sunday, February 13 until Saturday, February 26. Weeknights 9 p.m. until 5 a.m. Southbound Hausman Road full closure at the Loop 1604 intersection for bridge construction: caps & beams.
  • Sunday, February 13 until Saturday, February 26. Weeknights 9 p.m. until 5 a.m. Eastbound to westbound turnaround full closure at Loop 1604 and Hausman Road for bridge construction: caps & beams.
  • Sunday, February 13 until Saturday, February 26. Weeknights 9 p.m. until 5 a.m. Westbound to eastbound turnaround full closure at Loop 1604 and Hausman Road for bridge construction: caps & beams.
  • Monday, February 14 until Saturday, February 26. Weekdays 9 a.m. until 5 p.m. Eastbound frontage road outside lane closure from Hausman Road to John Peace Boulevard /La Cantera Parkway for sidewalk construction.
  • Monday, February 14 until Saturday, February 26. Weekdays 9 a.m. until 5 p.m. eastbound to westbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, February 14 until Saturday, February 26. Weekdays 9 a.m. until 5 p.m. westbound to eastbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, February 14 until Saturday, February 26. Weekdays 9 a.m. until 5 p.m. eastbound to westbound turnaround closure at Loop 1604 and Hausman Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, February 14 until Saturday, February 26. Weekdays 9 a.m. until 5 p.m. westbound to eastbound turnaround closure at Loop 1604 and Hausman Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, February 14 until Saturday, February 26. Weekdays 9 a.m. until 5 p.m. eastbound to westbound turnaround closure at Loop 1604 and Kyle Seale Parkway for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, February 14 until Saturday, February 26. Weekdays 9 a.m. until 5 p.m. westbound to eastbound turnaround closure at Loop 1604 and Kyle Seale Parkway for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, February 14 until Saturday, February 26. Weekdays 9 a.m. until 5 p.m. eastbound to westbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, February 14 until Saturday, February 26. Weekdays 9 a.m. until 5 p.m. westbound to eastbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Friday, February 18 at 9:00 p.m. until Monday, February 21 at 5:00 a.m. Eastbound mainlane left lane closure from Babcock Road to La Cantera Parkway/John Peace Boulevard for barrier setting.
  • Friday, February 18 at 9:00 p.m. until Monday, February 21 at 5:00 a.m. Westbound mainlane left lane closure from La Cantera Parkway/John Peace Boulevard to Hausman Road for barrier setting. 

Loop 1604 – North Central San Antonio/Bexar County

US 281 – North San Antonio/Bexar County

  • Saturday, February 19 until Monday, February 21. Nightly 9 p.m. until 5 a.m. Alternating northbound frontage road closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for signage installation and lane striping.
  • Saturday, February 19 until Monday, February 21. Nightly 9 p.m. until 5 a.m. Alternating southbound frontage road closure from Stone Oak Parkway to Loop 1604 for signage installation and lane striping.
  • Monday, February 21 until Friday, February 25. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for signage installation and lane striping.
  • Monday, February 21 until Friday, February 25. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Stone Oak Parkway to Loop 1604 for signage installation and lane striping.
  • Monday, February 21 until Friday, February 25. Nightly 9 p.m. until 5 a.m. Alternating northbound frontage road closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for signage installation and lane striping.
  • Monday, February 21 until Friday, February 25. Nightly 9 p.m. until 5 a.m. Alternating southbound frontage road closure from Stone Oak Parkway to Loop 1604 for signage installation and lane striping.
  • Saturday, February 26 until Monday, February 28. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for signage installation and lane striping.
  • Saturday, February 26 until Monday, February 28. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Stone Oak Parkway to Loop 1604 for signage installation and lane striping.
  • Saturday, February 26 until Monday, February 28. Nightly 9 p.m. until 5 a.m. Alternating northbound frontage road closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for signage installation and lane striping.
  • Saturday, February 26 until Monday, February 28. Nightly 9 p.m. until 5 a.m. Alternating southbound frontage road closure from Stone Oak Parkway to Loop 1604 signage installation and lane striping.

I-10 – East San Antonio/Bexar County/Seguin/Guadalupe County 

  • Continuing through Monday, February 21. DAYTIME alternating Northbound I-410 lane closures between Houston Street and I-10 as well as I-10 EB between I-410 and Ackerman Road from 9 a.m. to 5 p.m. each day for pavement repair. 
  • Continuing through Monday, February 21. Northbound I-410 right lane closure between Houston Street and I-10 day for barrier work 
  • Continuing through Tuesday, February 22. NIGHTTIME Northbound I-410 exit to eastbound I-10 closed from 8 p.m. to 5 a.m. each night for overpass work. Click here for detour map.
  • Monday, February 21 through Friday, February 25. Southbound I-410 left lane closure between I-10 and Rigsby Avenue from 9 p.m. to 5 a.m. nightly for barrier work.
  • Friday, February 18 until Saturday, February 19. Alternating lane closures from Ackerman Rd. to Comerway Blvd. for base repairs.
  • Friday, February 18 until Saturday, February 19. 8:30 p.m. 5:30 a.m. Full closure of the eastbound mainlanes at FM 2538 for bridge work.
  • Saturday, February 19 until Sunday, February 20. 8:30 p.m. to 10:00 a.m. Full closure of the westbound mainlanes at FM 2538 for bridge work.
  • Current until further notice. Graytown Road closed at I-10. DETOURS: Graytown Road traffic may use the frontage road and the Pfeil Road underpass or Loop 1604 turnaround to cross I-10. 

I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

  • Sunday, February 20 until Friday, February 25. 9 p.m. to 5 a.m.  Northbound exit ramp (170B) and single lane frontage road lane closure from Judson Road to Toepperwein Road for geotechnical and drilling work. Drivers must use Judson Road (170A) exit ramp. Follow the detour signs.
  • Sunday, February 20 until Friday, February 25. 9 p.m. to 5 a.m.  Northbound exit ramp (171) to Pat Booker Road and single lane closure on the I-35 northbound frontage road from Toepperwein Road to Shin Oak Drive for geotechnical and drilling work. Drivers must use the Toepperwein Road exit (170B). Follow the detour signs.
  • Sunday, February 20 until Friday, February 25. 9 p.m. to 5 a.m. Northbound exit ramp (168) closure from Joe Lee Street to North Weidner Road for geotechnical and drilling work. Traffic should use the O’Connor Road exit ramp (169). Follow the detour signs.
  • Sunday, February 20 until Friday, February 25. 9 p.m. to 5 a.m. Turnaround closure from north to southbound frontage road from Joe Lee Street to North Weidner Road for geotechnical and drilling work.
  • Sunday, February 20 until Friday, February 25. 9 p.m. to 5 a.m. Turnaround closure from south to northbound frontage road from North Weidner Road to Bomar Lane for geotechnical and drilling work.
  • Sunday, February 20 until Friday, February 25. 9 p.m. to 5 a.m.  O’Connor Road exit ramp (169) closure on northbound I-35 and single lane closure on the I-35 northbound frontage road from Wayland Way to O’Connor Road for geotechnical and drilling work. Drivers must use the Weidner Road exit (168). Follow the detour signs.
  • Sunday, February 20 until Friday, February 25. 9 p.m. to 5 a.m. Northbound entrance ramp closure and single frontage road lane closure from O’Connor Road to Bladau Bishop for geotechnical and drilling work. Traffic should use the Toepperwein Road entrance ramp. Follow the detour signs.
  • Monday, February 21 until Saturday, February 26. 9 a.m. to 5:30 p.m. Single northbound frontage road lane from FM 2252 to Schwab Rd. for sidewalk, headwall and rail work.
  • Monday, February 21 until Friday, February 26. 9 a.m. to 4 p.m. Single lane closure on northbound frontage road from Judson Road to Toepperwein Road for geotechnical and drilling work.
  • Monday, February 21 until Friday, February 26. 9 a.m. to 4 p.m. Single lane closure on northbound frontage road from Forum Parkway to Forum Access for geotechnical and drilling work.
  • Monday, February 21 until Friday, February 26. 9 a.m. to 4 p.m. Single lane closure on northbound frontage road from Sandpiper Drive to Shin Oak Drive for geotechnical and drilling work.
  • Monday, February 21 until Friday, February 26. 9 a.m. to 4 p.m. Single lane closure on northbound frontage road from Shin Oak Drive to Pat Booker Road for geotechnical and drilling work.
  • Monday, February 21 until Friday, February 25. 9 a.m. to 4 p.m. Single lane closure on northbound frontage road at Pat Booker Road for geotechnical and drilling work.
  • Monday, February 21 until Friday, February 25. 9 a.m. to 4 p.m. Single lane closure on westbound Pat Booker Road at northbound frontage road for geotechnical and drilling work.
  • Monday, February 21 until Friday, February 25. 9 a.m. to 4 p.m. Single lane closure on the northbound frontage road from North Weidner Road to O’Connor Road for geotechnical and drilling work.
  • Monday, February 21 until Friday, February 25. 9 a.m. to 4 p.m. Single lane closure on the northbound frontage road of from O’Connor Road to Bladau Bishop for geotechnical and drilling work.
  • Monday, February 21 until Friday, February 25. 9 a.m. to 4 p.m. Single lane closure on northbound frontage road from O’Conner Road to Bladau Bishop for wall investigation work.
  • Monday, February 21 until Friday, February 25. 9 a.m. to 4 p.m. Single lane closure on the northbound frontage road from Joe Lee Street to North Weidner Road for geotechnical and drilling work.
  • Monday, February 21 until Friday, February 25. 9 a.m. to 4 p.m. Single lane closure on the northbound I-35 frontage road from O’Connor Road to Judson Road for geotechnical and drilling work.
  • Monday, February 21 until Friday, February 25. 9 a.m. to 4 p.m. Single lane closure on the northbound frontage road from Pasatiempo Road to Valhalla Road for geotechnical and drilling work.
  • Monday, February 21 until Wednesday, February 23. 9 a.m. to 4 p.m. Single lane closure on northbound frontage road from Judson Road exit ramp to Judson Road intersection and shoulder closure on Toepperwein Road exit ramp for wall investigation work.
  • Wednesday, February 23 until Friday, February 25. 9 a.m. to 4 p.m. Single lane closure and shoulder closure on southbound frontage road from O’Conner Road exit to O’Conner Road intersection for wall investigation work. 

I-410 – North East San Antonio

  • Sunday, February 20 until Friday, February 25. 9 p.m. to 5 a.m. Turnaround closure from east to westbound frontage road between Quail Creek Drive and Perrin Beitel Road for geotechnical and drilling work.
  • Sunday, February 20 until Friday, February 25. 9 p.m. to 5 a.m. Turnaround closure from west to eastbound frontage road between Perrin Beitel Road and Vicar Drive for geotechnical and drilling work.
  • Sunday, February 20 until Friday, February 25. 9 p.m. to 5 a.m. Mandatory left turn lane closure on Austin Highway to westbound I-410 frontage road between I-35 Frontage Road Loop and NE Interstate 410 Loop for geotechnical and drilling work. Traffic should detour south on Austin Highway to Perrin Creek Road.
  • Monday, February 20 until Friday, February 25. 9 a.m. to 4 p.m. Shoulder closure of the eastbound turnaround lane to westbound frontage road between Quail Creek Drive and Perrin Beitel Road for geotechnical and drilling work. 

I-410 – East San Antonio

  • Current through Monday, February 21. DAYTIME alternating Northbound I-410 lane closures between Houston Street and I-10 as well as I-10 EB between I-410 and Ackerman Road 9 a.m. to 5 p.m. each day for pavement repair.  

I-410 – West San Antonio

  • Monday, February 21 until Monday, February 28. 8 p.m. to 5 a.m. Full closure of the northbound frontage road from Meadow Breeze Dr. to SH 151 for bridge work.
  • Monday, February 21 until Monday, February 28. 9 p.m. to 5 a.m. Southbound exit ramp to Marbach Rd. closed for bridge work.
  • Monday, February 21 until Monday, February 28. 8 p.m. to 5 a.m. Full closure of the mainlanes, in both directions, from W. Military Dr. to Marbach Rd. for bridge work.
  • Monday, February 21 until Monday, February 28. 9 a.m. to 3 p.m. Alternating lane closures on the frontage roads, in both directions, from Marbach Rd. to Bandera Rd. for bridge work.
  • Monday, February 21 until Monday, February 28. 8 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from Marbach Rd. to Ingram Rd. for bridge work.
  • Monday, February 21 until Monday, February 28. 8 a.m. to 5 p.m. Alternating closures of the turnarounds at Culebra Rd. for concrete work.
  • Monday, February 21 until Monday, February 28. 8 p.m. to 5 a.m. Southbound exit ramp to Ingram Rd. closed for traffic switch.
  • Monday, February 21 until Monday, February 28. 9 a.m. to 3 p.m. Single southbound mainlane closure from W. Military Dr. to SH 151 for concrete work.
  • Monday, February 21 until Monday, February 28. 8 p.m. to 5 a.m. Full closure of the turnarounds at Ingram Rd. for traffic switch.
  • Monday, February 21 until Monday, February 28. 9 a.m. to 5 p.m. Southbound W. Military Dr. bypass ramp closed for concrete work.
  • Monday, February 21 until Monday, February 28. 8 p.m. to 5 a.m. Double northbound mainlane closure from Ingram Rd. to Culebra Rd. for column work. 

I-410 – Southwest San Antonio

  • Current until September 2022. Northbound frontage road turnaround to southbound frontage road closed at Medina Base Rd. 

SH 151 – West San Antonio

  • Monday, February 21 until Monday, February 28. 9 a.m. to 3 p.m. Alternating westbound mainlane closures from W. Military Dr. to Ingram Rd. for pipe installation.
  • Monday, February 21 until Monday February 28. 8 p.m. to 5 a.m. Full closure of the eastbound frontage road from Cable Ranch Rd. to Loop 410 for bridge work.
  • Monday, February 21 until Monday, February 28. 8 p.m. to 5 a.m. Alternating full closures of the mainlanes, in both directions, at Loop 410 for bridge work. 

I-37 – South East San Antonio/Bexar County

  • Monday, February 21 until Monday, February 28. Full closure of the southbound exit ramp to Fair Ave. for metal beam guard fence repairs. 

PA 1502 – Wurzbach Parkway

  • Monday, February 21 until Friday, February 25. 9 a.m. to 3 p.m. Alternating lane closures, in both directions, from N.W. Military Highway to Blanco Rd. for barrier setting. 

FM 1535 – N.W. Military Highway

  • Monday, February 21 until Friday, February 25. 7 a.m. to 5 p.m. Single lane closures, in both direction, from Loop 1604 to Huebner Rd. for utility work.
  • Monday, February 21 until Tuesday, February 22. 7 a.m. to 5 p.m. Full closure of Fawn Dr. for utility work. 

I-10 – Kendall County

  • Current until Spring 2022. Full closure of the eastbound frontage road from Menger Springs to US 87 (Main St.) for road construction. 

Loop 337 – Comal County

  • Monday, February 21 until Friday, February 25. 8 a.m. to 5 p.m. Single northbound lane closure at River Rd. for bridge work. 

FM 306 – Comal County

  • Tuesday, February 22. 9 a.m. to 4 p.m. Single lane closure westbound under I-35 and left turn lane on the northbound I-35 frontage road for concrete curb and middle island work.
  • Friday, February 25. 9 a.m. to 4 p.m. Single lane closure westbound under I-35 and left turn lane on the northbound I-35 frontage road for concrete curb and middle island work.