Pages

Friday, March 11

UPCOMING SCHEDULED CONSTRUCTION LANE CLOSURES

 


Loop 1604 – North West San Antonio/Bexar County

  • Sunday, March 6 until Friday, March 18. Weeknights 9 p.m. until 5 a.m. Northbound Kyle Seale Parkway full closure at the Loop 1604 intersection for bridge construction: caps, beams and rail demo.
  • Sunday, March 6 until Friday, March 18. Weeknights 9 p.m. until 5 a.m. Southbound Kyle Seale Parkway full closure at the Loop 1604 intersection for bridge construction: caps, beams and rail demo.
  • Sunday, March 6 until Friday, March 18. Weeknights 9 p.m. until 5 a.m. Eastbound to westbound turnaround full closure at Loop 1604 and Kyle Seale Parkway for bridge construction: caps, beams and rail demo.
  • Sunday, March 6 until Friday, March 18. Weeknights 9 p.m. until 5 a.m. Westbound to eastbound turnaround full closure at Loop 1604 and Kyle Seale Parkway for bridge construction: caps, beams and rail demo.
  • Tuesday, March 8 until Monday, March 14. Weeknights 9 p.m. until 5 a.m. Westbound Loop 1604 exit ramp to La Cantera Parkway full closure for barrier setting and striping.
  • Tuesday, March 8 until Monday, March 14. Weeknights 9 p.m. until 5 a.m. Westbound IH-10 to Westbound Loop 1604 cloverleaf ramp full closure for barrier setting and striping.
  • Tuesday, March 8 until Monday, March 14. Weeknights 9 p.m. until 5 a.m. Eastbound IH-10 to Westbound Loop 1604 ramp full closure for barrier setting and striping.
  • Sunday, March 13 until Friday, March 25. Weeknights 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Bandera Road (SH 16) to IH-10 for barrier setting.
  • Sunday, March 13 until Friday, March 25. Weeknights 9 p.m. until 5 a.m. Alternating westbound mainlane closure from IH-10 to Bandera Road (SH 16) for barrier setting.
  • Sunday, March 13 until Friday, March 25. Weeknights 9 p.m. until 5 a.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for barrier setting.
  • Sunday, March 13 until Friday, March 25. Weeknights 9 p.m. until 5 a.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for barrier setting.
  • Sunday, March 13 until Friday, March 25. Weeknights 9 p.m. until 5 a.m. Eastbound mainlane full closure from Bandera Road (SH 16) to Kyle Seale Parkway for bridge construction: caps, beams and rail demo.
  • Sunday, March 13 until Friday, March 25. Weeknights 9 p.m. until 5 a.m. Westbound mainlane full closure from Kyle Seale Parkway to Bandera Road (SH 16) for bridge construction: caps, beams and rail demo.
  • Sunday, March 13 until Friday, March 25. Weeknights 9 p.m. until 5 a.m. Northbound Hausman Road full closure at the Loop 1604 intersection for bridge construction: caps, beams and rail demo.
  • Sunday, March 13 until Friday, March 25. Weeknights 9 p.m. until 5 a.m. Southbound Hausman Road full closure at the Loop 1604 intersection for bridge construction: caps & beams.
  • Sunday, March 13 until Friday, March 25. Weeknights 9 p.m. until 5 a.m. Eastbound to westbound turnaround full closure at Loop 1604 and Hausman Road for bridge construction: caps & beams.
  • Monday, March 14 until Monday, March 28. Weekdays 9 a.m. until 3 p.m. Eastbound frontage road outside lane closure from Hausman Road to John Peace Boulevard /La Cantera Parkway for sidewalk construction.
  • Monday, March 14 until Monday, March 28. Weekdays 9 a.m. until 5 p.m. eastbound to westbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, March 14 until Monday, March 28. Weekdays 9 a.m. until 5 p.m. westbound to eastbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, March 14 until Monday, March 28. Weekdays 9 a.m. until 5 p.m. eastbound to westbound turnaround closure at Loop 1604 and Hausman Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, March 14 until Monday, March 28. Weekdays 9 a.m. until 5 p.m. westbound to eastbound turnaround closure at Loop 1604 and Hausman Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, March 14 until Monday, March 28. Weekdays 9 a.m. until 5 p.m. eastbound to westbound turnaround closure at Loop 1604 and Kyle Seale Parkway for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, March 14 until Monday, March 28. Weekdays 9 a.m. until 5 p.m. westbound to eastbound turnaround closure at Loop 1604 and Kyle Seale Parkway for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, March 14 until Monday, March 28. Weekdays 9 a.m. until 5 p.m. eastbound to westbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, March 14 until Monday, March 28. Weekdays 9 a.m. until 5 p.m. westbound to eastbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Sunday, March 13 until Friday, March 25. Weeknights 9 p.m. until 5 a.m. Westbound to eastbound turnaround full closure at Loop 1604 and Hausman Road for bridge construction: caps & beams.
  • Saturday, March 12 9 a.m. until 3 p.m. Westbound left mainlane closure from Babcock Road to Kyle Seale Parkway for storm drainage work.
  • Friday, March 18 until Monday, March 28. Weekends only 9 p.m. until 5 a.m. Northbound Babcock Road full closure at the Loop 1604 intersection for storm drains.
  • Friday, March 18 until Monday, March 28. Weekends only 9 p.m. until 5 a.m. Southbound Babcock Road full closure at the Loop 1604 intersection for storm drains.
  • Friday, March 18 until Monday, March 28. Weekends only 9 p.m. until 5 a.m. Eastbound to westbound turnaround full closure at Loop 1604 and Babcock Road for storm drains.
  • Friday, March 18 until Monday, March 28. Weekends only 9 p.m. until 5 a.m. Westbound to eastbound turnaround full closure at Loop 1604 and Babcock Road for storm drains.
  • Friday, March 18 until Monday, March 28. Weekends only 9 p.m. until 5 a.m. Southbound La Cantera Parkway/John Peace Boulevard full closure at the Loop 1604 intersection for storm drains.
  • Friday, March 18 until Monday, March 28. Weekends only 9 p.m. until 5 a.m. Eastbound to westbound turnaround full closure at Loop 1604 and La Cantera Parkway/John Peace Boulevard for storm drains.
  • Friday, March 18 until Monday, March 28. Weekends only 9 p.m. until 5 a.m. Westbound to eastbound turnaround full closure at Loop 1604 and La Cantera Parkway/John Peace Boulevard for storm drains.
  • Friday, March 25 until Monday, April 4. Weekends only 9 p.m. until 5 a.m. Northbound La Cantera Parkway/John Peace Boulevard full closure at the Loop 1604 intersection for storm drains. 

Loop 1604 – North Central San Antonio/Bexar County

US 281 – North San Antonio/Bexar County

  • Saturday, March 12 until Sunday, March 13. Daily 7 a.m. until 5 p.m. Left southbound US 281 frontage road closure from Brook Hollow Boulevard to Winding Way/Oak Shadows Drive for ITS.
  • Saturday, March 12 until Monday, March 14. Nightly 9 p.m. until 5 a.m. Alternating northbound frontage road closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for signage installation and lane striping.
  • Saturday, March 12 until Monday, March 14. Nightly 9 p.m. until 5 a.m. Alternating southbound frontage road closure from Stone Oak Parkway to Loop 1604 for signage installation and lane striping.
  • Sunday, March 13 until Monday, March 14. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for signage installation and lane striping.
  • Sunday, March 13 until Monday, March 14. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Stone Oak Parkway to Loop 1604 for signage installation and lane striping.
  • Monday, March 14 until Thursday, March 17. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for signage installation and lane striping.
  • Monday, March 14 until Thursday, March 17. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Stone Oak Parkway to Loop 1604 for signage installation and lane striping.
  • Monday, March 14 until Friday, March 18. Continuous 9 p.m. until 3 p.m. Alternating northbound frontage road closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for signage installation and lane striping.
  • Monday, March 14 until Friday, March 18. Continuous 9 p.m. until 3 p.m. Alternating southbound frontage road closure from Stone Oak Parkway to Loop 1604 for signage installation and lane striping. 

I-10 – East San Antonio/Bexar County/Seguin/Guadalupe County 

  • Current until further notice. Graytown Road closed at I-10. DETOURS: Graytown Road traffic may use the frontage road and the Pfeil Road underpass or Loop 1604 turnaround to cross I-10. 

I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

  • Sunday, March 13 until Friday, March 18. 9 p.m. to 5 a.m.  Northbound exit ramp (171) to Pat Booker Road and single lane closure on the I-35 northbound frontage road from Toepperwein Road to Shin Oak Drive for geotechnical and drilling work. Drivers must use the Toepperwein Road exit (170B). Follow the detour signs.
  • Sunday, March 13 until Friday, March 18. 9 p.m. to 5 a.m. Single mainlane and shoulder closure southbound from Toepperwein Road to Judson Road for geotechnical and drilling work.
  • Sunday, March 13 until Friday, March 18. 9 p.m. to 4 a.m. Double lane closure on northbound frontage road from Loop 1604 to Forum Parkway for geotechnical and drilling work.
  • Sunday, March 13 until Friday, March 18. 9 p.m. to 5 a.m. Northbound exit ramp (168) closure from Joe Lee Street to North Weidner Road for geotechnical and drilling work. Traffic should use the O’Connor Road exit ramp (169). Follow the detour signs.
  • Sunday, March 13 until Friday, March 18. 9 p.m. to 5 a.m. Turnaround closure from south to northbound frontage road from North Weidner Road to Bomar Lane for geotechnical and drilling work.
  • Sunday, March 13 until Friday, March 18. 9 p.m. to 5 a.m.  Northbound exit ramp for O’Connor Road (169) and single frontage road lane closure from Wayland Way to O’Connor Road for geotechnical and drilling work. Drivers must use the Weidner Road exit (168). Follow the detour signs.
  • Sunday, March 13 until Friday, March 18. 9 p.m. to 5 a.m. Northbound entrance ramp from O’Connor Road and single frontage road lane closure from O’Connor Road to Bladau Bishop for geotechnical and drilling work. Traffic should use the Toepperwein Road entrance ramp. Follow the detour signs.
  • Monday, March 14 until Wednesday, March 16. 9 a.m. to 4 p.m. Single lane closure on northbound frontage road from Judson Road exit to Judson Road intersection and shoulder closure north of the Judson Road intersection for wall investigation work.
  • Monday, March 14 until Friday, March 18. 9 a.m. to 4 p.m. Single lane closure on northbound frontage road from Judson Road to Toepperwein Road for geotechnical and drilling work.
  • Monday, March 14 until Friday, March 18. 9 a.m. to 4 p.m. Double lane closure on northbound frontage road from Sandpiper Drive to Shin Oak Drive for geotechnical and drilling work.
  • Monday, March 14 until Friday, March 18. 9 a.m. to 4 p.m. Double lane closure on northbound frontage road from Shin Oak Drive to Pat Booker Road for geotechnical and drilling work.
  • Monday, March 14 until Friday, March 18. 9 a.m. to 4 p.m. Single lane closure on northbound frontage road at Pat Booker Road for geotechnical and drilling work.
  • Monday, March 14 until Friday, March 18. 9 a.m. to 4 p.m. Single lane closure on westbound Pat Booker Road at northbound frontage road for geotechnical and drilling work.
  • Monday, March 14 until Friday, March 18. 9 a.m. to 4 p.m. Single lane closure on northbound frontage road from I-35 Access Road to Converse Road for geotechnical and drilling work.
  • Monday, March 14 until Friday, March 18. 9 a.m. to 4 p.m. Single lane closure on the northbound frontage road from North Weidner Road to O’Connor Road for geotechnical and drilling work.
  • Monday, March 14 until Friday, March 18. 9 a.m. to 4 p.m. Single lane closure on the northbound frontage road of from O’Connor Road to Bladau Bishop for geotechnical and drilling work.
  • Monday, March 14 until Friday, March 18. 9 a.m. to 4 p.m. Single lane closure on the northbound I-35 frontage road from O’Connor Road to Judson Road for geotechnical and drilling work.
  • Monday, March 14 until Friday, March 18. 9 a.m. to 4 p.m. Single lane closure on the northbound frontage road from Pasatiempo Road to Valhalla Road for geotechnical and drilling work.
  • Monday, March 14 until Friday, March 18. 9 a.m. to 4 p.m. Single lane closure on the northbound frontage road from Chelsea Place to Legacy Oaks Parkway for geotechnical and drilling work.
  • Monday, March 14 until Friday, March 18. 9 a.m. to 4 p.m. Single lane closure on the northbound frontage road from Legacy Oaks Parkway to Schertz Parkway for geotechnical and drilling work.
  • Monday, March 14 until Friday, March 18. 9 a.m. to 4 p.m. Single lane closure on the northbound frontage road from Schertz Parkway to Plaza Drive for geotechnical and drilling work.
  • Monday, March 14 until Friday, March 18. 9 a.m. to 4 p.m. Single lane closure on the southbound frontage road from Fratt Road to Walzem Road for geotechnical and drilling work.
  • Monday, March 14 until Friday, March 18. 9 a.m. to 4 p.m. Single lane closure on Fratt Road from the southbound frontage road to Interchange Parkway for geotechnical and drilling work.
  • Monday, March 14 until Friday, March 18. 9 p.m. to 5 a.m. Single lane closure on southbound frontage road from Fratt Road to Walzem Road for geotechnical and drilling work.
  • Monday, March 14 until Friday, March 18. 9 p.m. to 5 a.m. Single lane closure on northbound mainlanes from Fratt Road to Windcrest Drive for geotechnical and drilling work.
  • Monday, March 14 until Friday, March 18. 9 a.m. to 5:30 p.m. Single northbound frontage road lane from FM 2252 to Schwab Rd. for sidewalk, headwall work.
  • Tuesday, March 15. 9 a.m. to 4 p.m. CPS Energy will close the right lane between Racker Alley and Innovation Way for transformer and cable work.
  • Tuesday, March 15 until Wednesday, March 16. 9 a.m. to 4 p.m. Single lane and entrance ramp closure for crash cushion work.
  • Wednesday, March 16 until Friday, March 18. 9 a.m. to 4 p.m. Single lane closure on southbound frontage road from Judson Road exit to the Judson Road intersection for wall investigation work. 

I-35 – South West San Antonio/Bexar County

  • Sunday, March 13. 7 a.m. to 4 p.m. Full closure in both directions at Kahlig Drive for CPS Energy for line crossing. 

I-410 – North East San Antonio

  • Sunday, March 13 until Friday, March 18. 9 p.m. to 5 a.m. Turnaround closure from the west to eastbound frontage road between Perrin Beitel Road and Vicar Drive for geotechnical and drilling work.
  • Sunday, March 13 until Friday, March 18. 9 p.m. to 5 a.m. Mandatory left turnaround lane closure on Austin Highway to westbound I-410 frontage road between I-35 Frontage Road Loop and NE Interstate 410 Loop for geotechnical and drilling work. Traffic should detour south on Austin Highway to Perrin Creek Road.
  • Sunday, March 13 until Friday, March 18. 9 p.m. to 4 a.m. Single lane closure on I-410 westbound from Ira Lee Road to Starcrest Drive for geotechnical and drilling work.

I-410 – East San Antonio

  • Continuing through Saturday, March 12. NIGHTTIME Northbound I-410 exit to eastbound I-10 closed from 8 p.m. to 5 a.m. each night for overpass work. Click here for detour map.
  • Continuing through Monday, March 28. DAYTIME alternating northbound I-410 lane closures between Houston Street and I-10 as well as I-10 EB between I-410 and Ackerman Road from 9 a.m. to 5 p.m. each day for detour work. 
  • Continuing through Monday, March 14. Southbound I-410 alternating lane closures between I-10 and Rigsby Avenue from 9 p.m. to 5 a.m. nightly for stripping. Ramps closed as needed when right lane closed. Detour: Southbound I-410 traffic may exit at East Southcross Boulevard, turn around at intersection and return on northbound I-410 frontage road.
  • Monday, March 14 through Monday, March 28. Northbound I-410 left lane closures between Rigsby Avenue and I-10 from 9 p.m. to 5 a.m. on Monday through Thursday nights for barrier work.
  • Current through Monday, March 14. Southbound I-410 alternating lane closures between I-10 and Rigsby Avenue from 9 p.m. to 5 a.m. nightly for stripping. Ramps closed as needed when right lane closed. Detour: Southbound I-410 traffic may exit at East Southcross Boulevard, turn around at intersection and return on northbound I-410 frontage road. 

I-410 – West San Antonio

  • Current until Monday, March 14. 8 a.m. to 5 p.m. Alternating closures of the turnarounds, in both directions, at Culebra Rd. for concrete work.
  • Current until Monday, March 14. 8 p.m. to 5 a.m. Full closure of the turnarounds, in both directions, at Ingram Rd. for traffic switch.
  • Current until Monday, March 14. 9 a.m. to 5 p.m. Closure of the southbound bypass ramp to W. Military Dr. for concrete work.
  • Current until Monday, March 14. 8 p.m. to 5 a.m. Alternating lane closures, in both directions, from Marbach Rd. to Ingram Rd. for bridge work.
  • Current until Monday, March 14. 9 a.m. to 3 p.m. Alternating lane closures on frontage roads, in both directions, from Marbach Rd. to Bandera Rd. for bridge work.
  • Current until Monday, March 14. 8 p.m. to 5 a.m. Full closure of the northbound frontage road from Meadow Breeze Dr. to SH 151 for bridge work.
  • Current until Monday, March 14. 8 p.m. to 5 a.m. Single northbound mainlane closure from Ingram Rd. to Culebra Rd. for column work.
  • Current until Monday, March 14. 8 p.m. to 5 a.m. Full closure of the mainlanes, in both directions, from W. Military Dr. to Marbach Rd. for bridge work.
  • Current until Monday, March 14. 9 p.m. to 5 a.m. Southbound exit ramp closed to Marbach Rd. for bridge work.
  • Current until Monday, March 14. 9 a.m. to 3 p.m. Single southbound mainlane closure from W. Military Dr. to SH 151 for concrete work.
  • Current until Monday, March 14. 8 p.m. to 5 a.m. Closure of the southbound exit ramp to Ingram Rd. for traffic switch.
  • Monday, March 14 until Monday, March 28. 9 a.m. to 5 p.m. Closure of the southbound bypass ramp to W. Military Dr. for concrete work.
  • Monday, March 14 until Monday, March 28. 8 p.m. to 5 a.m. Double northbound mainlane closures from Ingram Rd. to Culebra Rd. for column work.
  • Monday, March 14 until Monday, March 28. 9 p.m. to 5 a.m. Full closure of the southbound exit ramp to Marbach Rd. for bridge work.
  • Monday, March 14 until Monday, March 28. 9 a.m. to 3 p.m. Single southbound mainlane closure from W. Military Dr. to SH 151 for concrete work.
  • Monday, March 14 until Monday, March 28. 8 a.m. to 5 p.m. Alternating closures of the turnarounds, in both directions, at Culebra Rd for concrete work.
  • Monday, March 14 until Monday, March 28. 9 a.m. to 3 p.m. Alternating lane closures on the frontage roads, in both directions, from Marbach Rd. to Bandera Rd. for signal and curb work.
  • Monday, March 14 until Monday, March 28. 8 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from Marbach Rd. to Ingram Rd for concrete work.
  • Monday, March 14 until Monday, March 28. 8 p.m. to 5 a.m. Full closure of the northbound frontage road from Meadow Breeze Dr. to SH 151 for barrier removal.
  • Wednesday, March 16 until Saturday, March 19. 8 p.m. to 5 a.m. Full closure of the southbound mainlanes from Ingram Rd. to SH 151 for sign installations. 

I-410 – Southwest San Antonio

  • Current until September 2022. Northbound frontage road turnaround to southbound frontage road closed at Medina Base Rd. 

US 90 – West San Antonio/Bexar County

  • Monday, March 21 until Friday, March 25. 9 p.m. to 5 a.m. Alternating full closures of the mainlanes, in both directions, from loop 1604 to SH 211 for bridge work. 

SH 151 – West San Antonio

  • Current until Monday, March 14. 8 p.m. to 5 a.m. Full alternating closures of the mainlanes, in both directions, at Loop 410 for bridge work.
  • Current until Monday, March 14. 8 p.m. to 5 a.m. Full closure of the eastbound frontage road from Cable Ranch Rd. to Loop 410 for bridge work.
  • Current until Monday, March 14. 9 a.m. to 3 p.m. Alternating westbound mainlane closure from W. Military Dr. to Ingram Rd. for pipe work.
  • Monday, March 14 until Monday, March 28. 8 p.m. to 5 a.m. Full alternating closure of the mainlanes, in both directions, at Loop 410 for bridge work.
  • Monday, March 14 until Monday, March 28. 9 a.m. to 3 p.m. Alternating westbound mainlane closure at Loop 410 for pipe work. 

PA 1502 – Wurzbach Parkway

  • Monday, March 14 until Friday, March 25. 9 a.m. to 3 p.m. Single lane closures, in both directions, from N.W. Military Highway to Vista Del Norte for guard fence work.
  • Monday, March 14 until Friday, March 25. 9 a.m. to 3 p.m. Various lane closures, in both directions, at the Blanco Rd. intersection for pothole and bore work.
  • Sunday, March 20. 9 p.m. to 5 a.m. Full closure of the eastbound lanes from N.W. Military Highway to Blanco Rd. for sign removal.
  • Current until Friday, March 31. Eastbound ramp closure at Vista Del Norte for rail improvements.
  • Current until Friday, March 11. 9 a.m. to 4 p.m. Single eastbound lane closure at Lockhill Selma Rd. intersection for island construction. 

FM 306 – Comal County

  • Tuesday, March 15 until Wednesday, March 16. 9 a.m. to 4 p.m. The south to northbound turnaround at I-35 closure for crash cushion installation work. 

Loop 337 – Comal County

  • Monday, March 14 until Friday, March 18. 8 a.m. to 5 p.m. Single northbound lane closure at River Rd. for bridge work. 

I-10 – Kendall County

  • Tuesday, March 15 until Friday, March 18. 9 a.m. to 3 p.m. Westbound exit ramp 542 closed for illumination work.
  • Current until Spring 2022. Full closure of the eastbound frontage road from Menger Springs to US 87 (Main St.) for road construction.