Pages

Friday, May 19

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North West San Antonio/Bexar County

  • Sunday, May 21 until Monday, June 5. Weeknights 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Bandera Road (SH 16) to IH-10 for portable concrete traffic barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, May 21 until Monday, June 5. Weeknights 9 p.m. until 5 a.m. Alternating westbound mainlane closure from IH-10 to Bandera Road (SH 16) for portable concrete barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, May 21 until Monday, June 5. Weeknights 9 p.m. until 5 a.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for portable concrete traffic barrier installation. Nightly alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, May 21 until Monday, June 5. Weeknights 9 p.m. until 5 a.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for portable concrete traffic barrier installation. Nightly alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, May 21 until Monday, June 5. Weeknights 9 p.m. until 5 a.m. Westbound to eastbound turnaround closure at Loop 1604 and La Cantera Parkway/John Peace Boulevard for bridge construction. Only one turnaround to be closed at a time on each direction. Excluding weekends.
  • Sunday, May 21 until Monday, June 5. Weeknights 9 p.m. until 5 a.m. Loop 1604 and Bandera Road (SH 16) full intersection closure (both directions, including turnarounds) for bridge construction – concrete rail demolition. Only one intersection to be closed at a time. Excluding weekends.
  • Sunday, May 21 until Monday, June 5. Weeknights 9 p.m. until 5 a.m. Loop 1604 and Hausman Road full intersection closure (both directions, including turnarounds) for bridge construction – concrete rail demolition. Only one intersection to be closed at a time. Excluding weekends.
  • Sunday, May 21 until Monday, June 5. Weeknights 9 p.m. until 5 a.m. Loop 1604 and Kyle Seale Parkway full intersection closure (both directions, including turnarounds) for bridge construction – concrete rail demolition. Only one intersection to be closed at a time. Excluding weekends.
  • Sunday, May 21 until Monday, June 5. Weeknights 8 p.m. until 5 a.m. Eastbound frontage road lane full closure from John Peace Boulevard/La Cantera Parkway to IH-10 for eastbound direct connector bridge construction. Nightly frontage road full closure. Only one full frontage lane closure to occur per direction. Excluding weekends.
  • Sunday, May 21 until Monday, June 5. Weeknights 8 p.m. until 5 a.m. Westbound frontage road lane full closure from IH-10 to John Peace Boulevard/La Cantera Parkway for westbound collector distributor bridge construction. Nightly frontage road full closure. Only one full frontage lane closure to occur per direction. Excluding weekends.
  • Sunday, May 21 until Monday, June 5. Weeknights 9 p.m. until 5 a.m. Eastbound mainlane entrance ramp closure after La Cantera Parkway for eastbound direct connector bridge construction. Excluding weekends.
  • Sunday, May 21 until Monday, June 5. Weeknights 9 p.m. until 5 a.m. Eastbound I-10 mainlane exit ramp closure to westbound Loop 1604 for westbound collector distributor bridge construction on the bridge at Leon Creek. Nightly closure. Excluding weekends.
  • Sunday, May 21 until Monday, June 5. Weeknights 9 p.m. until 5 a.m. Ramp/cloverleaf closure from westbound IH-10 to westbound Loop 1604 for westbound collector distributor bridge construction on the bridge at Leon Creek. Nightly closure. Excluding weekends.
  • Monday, May 22 until Monday, June 5. Weekdays 9 a.m. until 3 p.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for traffic barrier, sidewalk construction and beam placement/bridge construction. Daily alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Monday, May 22 until Monday, June 5. Weekdays 9 a.m. until 3 p.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for traffic barrier, sidewalk construction and beam placement/bridge construction. Daily alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Monday, May 22 until Monday, June 5. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Kyle Seale Parkway for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, May 22 until Monday, June 5. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Kyle Seale Parkway for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, May 22 until Monday, June 5. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, May 22 until Monday, June 5. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, May 22 until Monday, June 5. Weekdays 9 a.m. until 3 p.m. Eastbound to Westbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, May 22 until Monday, June 5. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and La Cantera Parkway for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, May 22 until Monday, June 5. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and La Cantera Parkway for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Sunday, May 21 until Monday, June 5. 12 a.m. until 12 a.m. Eastbound to westbound turnaround closure at Loop 1604 and Hausman Road for bridge widening/retaining walls. Only one turnaround to be closed at a time.
  • Sunday, May 21 until Monday, June 5. 12 a.m. until 12 a.m. Westbound to eastbound turnaround closure at Loop 1604 and Hausman Road for bridge widening/retaining walls. Only one turnaround to be closed at a time.
  • Sunday, May 21 until Monday, June 5. 12 a.m. until 12 a.m. Eastbound to westbound turnaround closure at Loop 1604 and Babcock Rd for bridge widening/retaining walls. Only one turnaround to be closed at a time.
  • Sunday, May 21 until Monday, June 5. 12 a.m. until 12 a.m. Westbound to eastbound turnaround closure at Loop 1604 and Babcock Rd for bridge widening/retaining walls. Only one turnaround to be closed at a time. 

Loop 1604 – North Central San Antonio/Bexar County

  • Sunday, May 21 until Friday, May 26. Nightly 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Tradesman Road to US 281 exit ramp for barrier setting and striping.
  • Sunday, May 21 until Friday, May 26.  Nightly 9 p.m. until 5 a.m. Alternating westbound mainlane closure from US 281 exit ramp to Tradesman Road for barrier setting and striping.
  • Sunday, May 21 until Friday, May 26. Nightly 9 p.m. until 5 a.m. Alternating eastbound frontage road closure from IH-10 to US 281 for barrier setting and striping.
  • Sunday, May 21 until Friday, May 26. Nightly 9 p.m. until 5 a.m. Alternating westbound frontage road closure from US 281 to IH-10 for barrier setting and striping.
  • Monday, May 22 until Friday, May 26. Daily 9 a.m. until 3 p.m. Westbound to eastbound turnaround full closure at Loop 1604 and Lockhill Selma Road for drainage work.
  • Thursday, May 25 until Friday, May 26 Nightly 9 p.m. until 5 a.m. Eastbound mainlane full closure from the Lockhill Selma Road exit ramp to the Lockhill Selma Road entrance ramp for bridge deck pour at Lockhill Selma.
  • Thursday, May 25 until Friday, May 26 Nightly 9 p.m. until 5 a.m. Westbound mainlane full closure from the Lockhill Selma Road exit ramp to the Lockhill Selma Road entrance ramp for bridge deck pour at Lockhill Selma.
  • Thursday, May 25 until Friday, May 26 Nightly 9 p.m. until 5 a.m. The Lockhill Selma Road intersection full closure at Loop 1604, including turnarounds for bridge deck pour at Lockhill Selma. 

Loop 1604 – North East San Antonio/Bexar County

  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Eastbound to westbound Loop 1604 turnaround closure from Nacogdoches Road to Union Pacific Railroad for retaining wall demolition work. Traffic should use Lookout Road intersection.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound frontage road of Loop 1604, right lane entrance ramp closure, and turnaround closure from Nacogdoches Road to Union Pacific Railroad for striping work. Traffic should use Lookout Road intersection.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound frontage road of Loop 1604 from Lookout Road to I-35 for barrier work.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Eastbound to westbound Loop 1604 turnaround closure at Lookout Road for drilled shaft work. Traffic should use Lookout Road intersection.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Alternating mainlane closures on eastbound Loop 1604 from Nacogdoches Road to I-35 and exit ramp closure to Nacogdoches Road for barrier work. Traffic should use next exit ramp.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Exit ramp closure on eastbound mainlanes of Loop 1604 to Lookout Road for striping work. Traffic should use prior exit ramp.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound bypass ramp and entrance ramp closure of Loop 1604 from Nacogdoches Road to Lookout Road for striping work. Traffic should use next entrance ramp.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Alternating mainlane closures on eastbound Loop 1604, entrance ramp closure, and exit ramp closure on eastbound Loop 1604 from Nacogdoches Road to I-35 for striping work. Traffic should use prior exit and next entrance ramps. 

I-10 – North West San Antonio/Bexar County

  • Sunday, May 21 until Friday, June 2. Weeknights 9 p.m. until 5 a.m. Alternating IH-10 westbound frontage road closure from De Zavala Road to Camp Bullis Road for portable concrete traffic barrier installation. Nightly alternating frontage closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, May 21 until Friday, June 2. Weeknights 9 p.m. until 5 a.m. Alternating IH-10 eastbound frontage road closure from Camp Bullis Road to De Zavala Road for portable concrete traffic barrier installation. Nightly alternating frontage closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, May 21 until Friday, June 2. Weeknights 9 p.m. until 5 a.m. Alternating IH-10 westbound mainlane closure from De Zavala Road to Camp Bullis Road for portable concrete traffic barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, May 21 until Friday, June 2. Weeknights 9 p.m. until 5 a.m. Alternating IH-10 eastbound mainlane closure from Camp Bullis Road to De Zavala Road for portable concrete traffic barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, May 21 until Friday, June 2. Weeknights 9 p.m. until 5 a.m. Exit ramp full closure from Loop 1604 eastbound to IH-10 eastbound for portable concrete traffic barrier installation. Nightly closures. Excluding weekends.
  • Sunday, May 21 until Friday, June 2. Weeknights 9 p.m. until 5 a.m. IH‑10 westbound mainlane exit ramp to La Cantera Parkway (braided ramp) full closure for portable concrete traffic barrier installation. Nightly closures. Excluding weekends.
  • Sunday, May 21 until Friday, June 2. Weeknights 9 p.m. until 5 a.m. IH‑10 westbound frontage road entrance ramp to IH-10 mainlanes before La Cantera Parkway (braided ramp) full closure for portable concrete traffic barrier installation. Nightly closures. Excluding weekends.
  • Sunday, May 21 until Friday, June 2. Weeknights 9 p.m. until 5 a.m. IH‑10 westbound mainlane exit ramp to Camp Bullis Road closure for portable concrete traffic barrier installation. Nightly closures. Excluding weekends.
  • Sunday, May 21 until Friday, June 2. Weeknights 9 p.m. until 5 a.m. IH‑10 eastbound frontage road entrance ramp to IH-10 mainlanes after Loop 1604 interchange full closure for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, May 21 until Friday, June 2. Weeknights 9 p.m. until 5 a.m. Exit ramp full closure from IH-10 westbound to Loop 1604 eastbound for portable concrete traffic barrier installation. Nightly closures. Excluding weekends.
  • Sunday, May 21 until Friday, June 2. Weeknights 9 p.m. until 5 a.m. Ramp/cloverleaf full closure from eastbound IH-10 to eastbound Loop 1604 for portable concrete traffic barrier installation. Nightly closures. Excluding weekends.
  • Sunday, May 21 until Friday, June 2. Weeknights 9 p.m. until 5 a.m. Ramp/cloverleaf full closure from westbound Loop 1604 to eastbound IH-10 for portable concrete traffic barrier installation. Nightly closures. Excluding weekends.
  • Sunday, May 21 until Friday, June 2. Weeknights 9 p.m. until 5 a.m. Ramp/cloverleaf full closure from westbound IH-10 to westbound Loop 1604 for portable concrete traffic barrier installation. Nightly closures. Excluding weekends.
  • Sunday, May 21 until Friday, June 2. Weeknights 9 p.m. until 5 a.m. Alternating Loop 1604 westbound mainlane closure from the exit ramp at Lockhill Selma Road to Valero Way overhead sign bridge removal. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, May 21 until Friday, June 2. Weeknights 9 p.m. until 5 a.m. Alternating Loop 1604 eastbound mainlane closure from the Valero Way exit ramp to the Lockhill Selma Road entrance ramp for overhead sign bridge removal. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, May 21 until Thursday, May 25. Weeknights 9 p.m. until 5 a.m. Loop 1604 westbound mainlane full closure from Lockhill Selma Road to IH-10 for overhead sign removal. Nightly closures. Excluding weekends.
  • Monday, May 22 until Friday, June 2. Weekdays 9 a.m. until 3 p.m. Alternating westbound IH-10 frontage road lane closure from De Zavala Road to Camp Bullis Road to set portable concrete barrier. Daily alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Monday, May 22 until Friday, June 2. Weekdays 9 a.m. until 3 p.m. Alternating eastbound IH-10 frontage road lane closure from Camp Bullis Road to De Zavala Road to set portable concrete barrier. Daily alternating frontage road closures. One lane to remain open at all times. Excluding weekends. 

US 281 – North San Antonio/Bexar County

  • Monday, May 15 until Sunday, May 21. 9 a.m. to 3 p.m. Alternating lane closures on the frontage roads, in both directions, at Overlook Parkway for asphalt work.
  • Monday, May 15 until Sunday, May 21. 9 a.m. to 3 p.m. Alternating lane closures on the frontage roads, in both directions, at Borgfeld Rd. for asphalt work.
  • Monday, May 15 until Sunday, May 21. 9 a.m. to 3 p.m. Alternating lane closures on the frontage roads, in both directions, at Bulverde Rd. for asphalt work.
  • Monday, May 15 until Sunday, May 21. 9 a.m.to 3 p.m. Northbound left turn lane closure at Wilderness Oak intersection. 

I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

  • Current until Wednesday, August 2, long term closure (24/7). Left lane closure on southbound I-35 frontage road between Toepperwein Road and Judson Road for soil nail wall, drill shaft, column, and cap work.
  • Current until Monday, December 14 long-term closure (24/7). Alternating lane closures on southbound I-35 frontage road between Thousand Oaks Drive and Whirlwind Drive for roadway reconstruction and structural work.
  • Sunday, May 21. 9:00 p.m. to 5:00 a.m. Closure of Old Austin Road at southbound frontage road of I-35 for CCTV temporary pole installation. Traffic should follow detour signs.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Rolling closure project-wide for pothole repair.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Right shoulder closure on northbound mainlanes, left lane closure on northbound frontage road, and entrance ramp closure of I-35 from Schertz Parkway to Roy Richard Drive for pothole work. Traffic should use next entrance ramp.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road, northbound to southbound turnaround closure, exit ramp closure, traffic shift to the left on Evans Road, and entrance ramp closure of I-35 from Schertz Parkway to Evans Road for striping, barrier, and temporary pavement work. Traffic should use next exit and entrance ramps.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road, exit ramp closure, and entrance ramp closure of I-35 from Roy Richard Drive to Schertz Parkway for striping, barrier, and temporary pavement work. Traffic should use next exit and entrance ramps.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on southbound mainlanes and entrance ramp closure of I-35 from Roy Richard Drive to Evans Road for striping, barrier, and temporary pavement work. Traffic should use next entrance ramp.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35 mainlanes, exit ramp closure, and left lane closure on southbound frontage road of I-35 from Schertz Parkway to Corporate Drive for survey work. Traffic should use next exit ramp.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Alternating lane closures on northbound frontage road, exit ramp closure, and entrance ramp closure of I-35 from Forum Parkway to Evans Road for striping, barrier, and temporary pavement work. Traffic should use next exit and entrance ramp.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on northbound I-35 mainlanes from Forum Parkway to Evans Road for striping, barrier, and temporary pavement work.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on southbound mainlanes and entrance ramp closure of I-35 from Retama Parkway to Forum Parkway for striping work. Traffic should use next entrance ramp.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road of I-35 from Corporate Drive to Retama Parkway for striping, barrier, and temporary pavement work.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on southbound mainlanes and exit ramp closure of I-35 from Corporate Drive to Retama Parkway for striping, barrier, and temporary pavement work. Traffic should use prior exit ramp.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road of I-35 from Olympia Parkway to Gateway Boulevard for bridge foundation, temporary pavement, striping and barrier work.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road of I-35 from Evans Road to Olympia Parkway for bridge foundation, striping, barrier work, and temporary pavement work.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road of I-35 from IKEA-RBFCU Parkway to Pat Booker Road for striping and barrier work.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Multiple right lane closures (3) on southbound mainlanes of I-35 from Pat Booker Road to I-35 Access Road for bridge substructure work.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Multiple right lane closures (2) on southbound I-35 mainlanes from Forum Parkway to Ferrell Road for striping, barrier, and temporary pavement work.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Alternating ramp closures on southbound I-35 connector ramp to Pat Booker Road for striping, barrier, and bridge substructure work. Traffic must exit Loop 1604 (exit 172) and follow the detour signs to Pat Booker Road.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Southbound I-35 entrance ramp closure from Old Austin Road to Forum Parkway for striping and barrier work. Traffic must use the Forum Parkway turnaround and follow detour signs to access southbound I-35.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Eastbound Loop 1604 to southbound I-35 connector ramp closure for striping and barrier work. Traffic must exit at IKEA-RBFCU Parkway and follow the detour signs to southbound I-35.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Westbound Loop 1604 to southbound I-35 connector ramp closure for earthwork. Traffic must exit at Lookout Road and follow the detour signs to southbound I-35.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Southbound I-35 to eastbound Loop 1604 connector ramp closure for striping, barrier, and earthwork. Traffic must exit at westbound Loop 1604 and follow the detour signs to access eastbound Loop 1604.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Closure on southbound I-35 collector ramp at the Loop 1604 interchange for striping, barrier, and construction entrance work. Traffic must use Loop 1604 (exit 172) to access southbound I-35 and follow detour signs.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Southbound I-35 to westbound Loop 1604 connector ramps closure and alternating lane closures on southbound mainlanes of I-35 at the exit to Loop 1604 for striping and barrier work. Southbound I-35 to Loop 1604 traffic should exit at Retama Parkway and follow the detour signs to Loop 1604.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Right lane closure on northbound mainlanes of I-35, alternating exit ramp closures, and entrance ramp closure from Toepperwein Road to Loop 1604 for barrier setting and structures work. Traffic should follow the detour signs to the available ramps.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Full closure on southbound frontage road and entrance ramp of I-35 from Shin Oak Drive to Toepperwein Road for cap form erection work. Accommodations will be made for local traffic. Southbound frontage road of I-35 traffic must follow detour.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Right lane closure on northbound mainlanes of I-35, entrance ramp closure, and alternating exit ramp closures from O’Connor Road to Toepperwein Road for barrier setting and structures work. Traffic should follow the detour signs to the available ramps.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Alternating lane closures on northbound frontage road, entrance ramp closure, and alternating exit ramp closures of I-35 from Judson Road to Shin Oak Drive for barrier work. Traffic should follow the detour sign to the available ramps.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Alternating lane closures on northbound frontage road, right lane closure on northbound mainlanes, and exit ramp closure of I-35 from Bludau-Bishop Road to Gunn Road, right lane closure on the eastbound and westbound at the intersection of Judson Road and Randolph Boulevard and left lane closure on Randolph Boulevard at Judson Road for temporary pavement and signal works. Traffic should use the next exit ramp.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road of I-35 from Judson Road to O’Connor Road for earthwork, paving, striping, and barrier work.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35 mainlanes, exit ramp closure, and left lane closure on southbound frontage road of I-35 at O’Connor Road for tree removal work. Traffic should use next exit.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Multiple right lane closures (2) on southbound I-35 mainlanes, entrance ramp closure, and exit ramp closure from Pat Booker Road to Judson Road for structures work. Traffic should use next entrance and exit ramps.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Multiple right lane closures (2) on southbound I-35 mainlanes, entrance ramp closure, exit ramp closure, and left lane closures (2) on southbound frontage road of I-35 from Judson Road to O’Connor Road for striping, barrier, and paving work. Traffic should use next entrance and exit ramps.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Multiple left lane closures (3) on southbound I-35 mainlanes from Judson Road to O’Connor Road for striping work.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Right lane closure on westbound and eastbound of Toepperwein Road at I-35 for barrier work.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound mainlanes of I-35, exit ramp closure, and left lane closure on southbound frontage road of I-35 from Toepperwein Road to Judson Road for earthwork and barrier work. Traffic should use next exit ramp.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road of I-35, entrance ramp closure, and exit ramp closure from O’Connor Road to Weidner Road for earthwork, paving, striping, and barrier work. Traffic should use next entrance and exit ramps.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Right lane closure on westbound and eastbound of Weidner Road at I-35 for barrier work.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road of I-35 and entrance ramp closure from Weidner Road to Thousand Oaks Drive for earthwork and barrier work. Traffic should use prior entrance ramp.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on southbound mainlanes, alternating entrance and exit ramp closures, and alternating lane closures on southbound frontage road of I-35 from O’Connor Road to Weidner Road for striping work. Traffic should use the next exit and entrance ramps.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on southbound mainlanes, alternating entrance and exit ramp closures, and alternating lane closures on southbound frontage road of I-35 from Weidner Road to Thousand Oaks Drive for striping work. Traffic should use the next exit and entrance ramps.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Full closure on southbound frontage road and northbound to southbound turnaround closure of I-35 from Thousand Oaks Drive to Whirlwind Drive for permanent widening, striping, and barrier work. Traffic should follow detour signs. Accommodations will be made for local traffic.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Alternating lane closures (2) on southbound frontage road of I-35 from Thousand Oaks Drive to Randolph Boulevard for permanent widening work.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Full closure on southbound frontage road and northbound to southbound turnaround closure of I-35 from Thousand Oaks Drive to Whirlwind Drive for permanent widening, striping, and barrier work. Traffic should follow detour signs. Accommodations will be made for local traffic.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Exit ramp closure on northbound mainlanes and left lane closure on northbound frontage road of I-35 from Walzem Road to Crestwind Drive for drilled shaft work. Traffic should use prior exit ramp.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Exit ramp closure on southbound mainlanes and alternating lane closures on southbound frontage road of I-35 from Randolph Boulevard to Walzem Road for geotechnical, drilled shaft, and column work. Traffic to use next exit ramp.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound mainlanes of I-35 from Randolph Boulevard to Walzem Road for cap work.
  • Wednesday, May 24 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Left lane closure on northbound frontage road of I-35 from Agora Parkway to Pasatiempo for pothole work.
  • Sunday, June 4 until Saturday, June 10. 9:00 p.m. to 5:00 a.m. Full closure on southbound frontage road of I-35 from Old Austin Road to Forum Parkway for substructure, temporary pavement, striping, and barrier work. Traffic should follow detour signs. 

I-10 – East San Antonio/Bexar County

  • Sunday, May 21 until Monday, May 22. 9 p.m. to 5 a.m. Full eastbound mainlane closure at FM 1518 for repairs.
  • Monday, May 22 until Saturday May 27. 8 p.m. to 6 a.m. Single westbound mainlane closure from Zuehl Rd. to Cibolo Creek for pavement operations.
  • Continuing through Monday, June 26. Westbound I-10 frontage road left lane closure from Graytown Road to Loop 1604 until 3 p.m Monday, June 26.
  • Continuing through Thursday, June 1. DAYTIME westbound I-10 frontage road alternating lane closures at Ackerman from 9 a.m. to 4 p.m. for overpass work. (No closures on Sunday) 

I-410 – North East San Antonio

  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound frontage road of I-410, entrance ramp closure, and eastbound to westbound turnaround closure between Starcrest Drive and Perrin Beitel for striping and barrier work. Traffic should use next entrance ramp.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Westbound to eastbound I-410 turnaround closure from Austin Highway (Loop 368) to Perrin Beitel for pothole work.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on westbound mainlanes and exit ramp closure of I-410 from I-35 to Perrin Beitel for striping and barrier work. Traffic should use next exit ramp.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Multiple right lane closures (2) on westbound of I-410 mainlanes from I-35 to Austin Highway (Loop 368) for cap work.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound frontage road and exit ramp closure of I-410 from Perrin Creek to Perrin Beitel for drilled shaft work. Traffic to use next exit ramp.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Multiple left lane closures (2) and entrance ramp closure on eastbound frontage road of I-410 from Nacogdoches Road to Harry Wurzbach Road for striping and barrier work. Traffic should use next entrance ramp.
  • Sunday, May 21 until Friday, May 26. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound frontage road of I-410, entrance ramp closure, and exit ramp closure from Harry Wurzbach Road to Starcrest Drive for striping and barrier work. Traffic should use prior entrance and exit ramps. 

I-410 – East San Antonio

  • Tuesday, May 23. NIGHTTIME northbound I-410 frontage road closure between E. Houston St. and Eunice St. from 6 p.m. to 5 a.m. Peggy Drive will remain open for local traffic. Detour: Northbound I-410 frontage road traffic to I-410 mainlane will turn left on E. Houston Street, turn right at W. W. White Rd., and right onto I-10 eastbound frontage road to eastbound I-10.
  • Saturday, May 20. Southbound I-410 left lane closure at I-10 interchange from 4 a.m. to 7 p.m. for bridge work.
  • Sunday, May 21. NIGHTTIME southbound I-410 mainlane closures at I-10 interchange from 7 p.m. to 5 a.m. for bridge work. Detour: SB I-410 traffic can take exit towards I-10 collector ramp and continue straight to reenter I-410.
  • Continuing through Thursday, June 1. DAILY alternating northbound and southbound I-410 frontage road closures between I-10 and Rigsby Ave. from 9 a.m. to 4 p.m. for bridge and road work. (No closures on Sundays)
  • Monday, May 22 through Friday, May 26. NIGHTLY. Full southbound I-410 mainlane closure at I-10 interchange from 9 p.m. to 5 a.m. each night. Also westbound I-10 cloverleaf ramp to southbound I-410, eastbound I-10 ramp to southbound I-410, and southbound I-410 cloverleaf ramp to east I-10 closed. Detour: I-410 southbound traffic wishing to continue south may take westbound I-10 exit ramp, use the W.W. White exit, continue on the I-10 eastbound frontage road to I-410 southbound frontage road, and take next entrance ramp to southbound I-410. I-410 southbound traffic to eastbound I-10 may take westbound I-10 exit ramp, exit at W.W. White, continue on the I-10 eastbound frontage road, and enter eastbound I-10 at the next entrance ramp. (No closures on Friday and Saturday nights.) 

SH 151 – West Bexar County

  • Monday, May 22 until Friday, May 26. 9 p.m. to 5 a.m. Single lane closure on the frontage roads, in both directions, from Wiseman Rd. to Loop 1604 for barrier installation. 

FM 1535 – N.W. Military Highway

  • Monday, May 22 until Friday, May 26. 7 a.m. to 6 p.m. Alternating lane closures, in both directions, from Loop 1604 to Huebner Rd. for curb and sidewalk improvements. 

PA 1502 – Wurzbach Parkway

  • Current until Saturday, May 27. 9 p.m. to 5 a.m. Various lane closures, in both directions, from N.W. Military Highway to Weidner Rd. for barrier movement. 

US 90 – West San Antonio/Bexar County/Medina County

  • Current until Friday, May 26. 8:30 p.m. to 5 a.m. Alternating closures of the entrance and exit ramps from Nogalitos St. to 36th St. for repairs.
  • Sunday, May 21 until Wednesday, May 24. 8:30 p.m. to 5 a.m. Eastbound ramp closure to I-35 for removal of overhead signs. 

LP 345 – Fredericksburg Road

  • Current until Friday, May 26. 9 p.m. to 5 a.m. Double southbound lane closures from I-10 to Loop 410 for repairs and pavement operations. 

SH 46 – Kendall County

  • Sunday, May 21 until Tuesday, May 23. 9 p.m. to 5 a.m. Full closure of the northbound intersection at I-10 for signal and radar installations.