Loop 1604 – North West San Antonio/Bexar County

  • Sunday, Oct. 15 until Monday, Oct. 23. Weeknights 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Bandera Road (SH 16) to IH-10 for portable concrete traffic barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, Oct. 15 until Monday, Oct. 23. Weeknights 9 p.m. until 5 a.m. Alternating westbound mainlane closure from IH-10 to Bandera Road (SH 16) for portable concrete barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, Oct. 15 until Monday, Oct. 23. Weeknights 9 p.m. until 5 a.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for portable concrete traffic barrier installation. Nightly alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, Oct. 15 until Monday, Oct. 23. Weeknights 9 p.m. until 5 a.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for portable concrete traffic barrier installation. Nightly alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, Oct. 15 until Monday, Oct. 23. Weeknights 9 p.m. until 5 a.m. IH-10 eastbound mainlane exit ramp closure to Loop 1604 westbound for westbound collector-distributor bridge construction on the bridge at Leon Creek. Nightly closure. Excluding weekends.
  • Sunday, Oct. 15 until Monday, Oct. 23. Weeknights 9 p.m. until 5 a.m. Ramp/cloverleaf closure from IH-10 westbound to Loop 1604 westbound for westbound collector-distributor bridge construction on the bridge at Leon Creek. Nightly closure. Excluding weekends.
  • Sunday, Oct. 15 until Monday, Oct. 23. Weeknights 8 p.m. until 5 a.m. Eastbound frontage road lane full closure from John Peace Boulevard/La Cantera Parkway to IH-10 for eastbound direct connector bridge construction. Nightly frontage road full closure. Only one full frontage lane closure to occur per direction. Excluding weekends.
  • Sunday, Oct. 15 until Monday, Oct. 23. Weeknights 8 p.m. until 5 a.m. Westbound frontage road lane full closure from IH-10 to John Peace Boulevard/La Cantera Parkway for westbound collector-distributor bridge construction. Nightly frontage road full closure. Only one full frontage lane closure to occur per direction. Excluding weekends.
  • Sunday, Oct. 15 until Monday, Oct. 23. Weeknights 9 p.m. until 5 a.m. Loop 1604 westbound mainlane exit ramp to La Cantera Parkway closure for westbound direct connector bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Oct. 15 until Monday, Oct. 23. Weeknights 9 p.m. until 5 a.m. Loop 1604 westbound frontage road entrance ramp from IH-10 closure for westbound direct connector bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Oct. 15 until Monday, Oct. 23. Weeknights 9 p.m. until 5 a.m. Loop 1604 and Hausman Road full intersection closure (both directions, including turnarounds) for demolition work/bridge construction. Only one intersection to be closed at a time. Excluding weekends.
  • Sunday, Oct. 15 until Monday, Oct. 23. Weeknights 9 p.m. until 5 a.m. Loop 1604 and Kyle Seale Parkway full intersection closure (both directions, including turnarounds) for demolition work/bridge construction. Only one intersection to be closed at a time. Excluding weekends.
  • Sunday, Oct. 15 until Monday, Oct. 23. Weeknights 9 p.m. until 5 a.m. Loop 1604 and Babcock Road full intersection closure (both directions, including turnarounds) for demolition work/bridge construction. Only one intersection to be closed at a time. Excluding weekends.
  • Sunday, Oct. 15 until Monday, Oct. 23. Weeknights 9 p.m. until 5 a.m. Loop 1604 and Chase Hill Boulevard full intersection closure (both directions, including turnarounds) for demolition work/bridge construction. Only one intersection to be closed at a time. Excluding weekends.
  • Sunday, Oct. 15 until Monday, Oct. 23. Weeknights 9 p.m. until 5 a.m. Loop 1604 and La Cantera Parkway full intersection closure (both directions, including turnarounds) for demolition work/bridge construction. Only one intersection to be closed at a time. Excluding weekends.
  • Monday, Oct. 16 until Monday, Oct. 23. Weekdays 9 a.m. until 3 p.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for traffic barrier, sidewalk construction and beam placement/bridge construction. Daily alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Monday, Oct. 16 until Monday, Oct. 23. Weekdays 9 a.m. until 3 p.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for traffic barrier, sidewalk construction and beam placement/bridge construction. Daily alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Monday, Oct. 16 until Monday, Oct. 23. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Hausman Road for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, Oct. 16 until Monday, Oct. 23. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Hausman Road for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, Oct. 16 until Monday, Oct. 23. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, Oct. 16 until Monday, Oct. 23. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, Oct. 16 until Monday, Oct. 23. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, Oct. 16 until Monday, Oct. 23. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, Oct. 16 until Monday, Oct. 23. Daily/Nightly 24 hours a day. Westbound to eastbound turnaround closure at Loop 1604 and La Cantera Parkway/John Peace Boulevard for bridge construction/retaining walls. Only one turnaround to be closed at a time on each direction.
  • Monday, Oct. 16 until Monday, Oct. 23. Daily/Nightly 24 hours a day. Eastbound to westbound turnaround closure at Loop 1604 and La Cantera Parkway/John Peace Boulevard for bridge construction/retaining walls. Only one turnaround to be closed at a time on each direction.
  • Monday, Oct. 16 until Monday, Oct. 23. Daily/Nightly 24 hours a day. Eastbound to westbound turnaround closure at Loop 1604 and Kyle Seale Parkway for bridge widening/retaining walls. Only one turnaround to be closed at a time.
  • Monday, Oct. 16 until Monday, Oct. 23. Daily/Nightly 24 hours a day. Westbound to eastbound turnaround closure at Loop 1604 and Kyle Seale Parkway for bridge widening/retaining walls. Only one turnaround to be closed at a time. 

Loop 1604 – North Central San Antonio/Bexar County

  • Sunday, October 15 until Friday, October 20. Nightly 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Tradesman Road to Stone Oak Parkway exit ramp for barrier setting and striping.
  • Sunday, October 15 until Friday, October 20. Nightly 9 p.m. until 5 a.m. Alternating westbound mainlane closure from Stone Oak Parkway exit ramp to Tradesman Road for barrier setting and striping.
  • Sunday, October 15 until Friday, October 20. Nightly 9 p.m. until 5 a.m. Alternating eastbound frontage road closure from IH-10 to Stone Oak Parkway exit ramp for barrier setting and striping.
  • Sunday, October 15 until Friday, October 20. Nightly 9 p.m. until 5 a.m. Alternating westbound frontage road closure from Stone Oak Parkway exit ramp to IH-10 for barrier setting and striping.
  • Monday, October 16 until Saturday, October 21. Nightly 9 p.m. until 5 a.m. Westbound mainlane full closure from the Blanco Road exit ramp to the Blanco Road entrance ramp for substructure at Blanco Road.
  • Friday, October 20 at 9 p.m. until Saturday, Oct. 21 at 8 a.m. Weekend closure. Loop 1604 eastbound mainlanes from the Vance Jackson Road exit ramp to the Lockhill Selma entrance ramp will be fully closed to set girders for the eastbound direct connector.
  • Friday, October 20 at 9 p.m. until Saturday, Oct. 21 at 8 a.m.  Weekend closure. IH-10 westbound exit ramp / direct connector to the Loop 1604 eastbound mainlanes will be closed to set girders for the eastbound direct connector.
  • Friday, October 20 at 9 p.m. until Saturday, Oct. 21 at 8 a.m.  Weekend closure. IH-10 eastbound mainlane cloverleaf exit ramp (southwest cloverleaf) to the Loop 1604 eastbound mainlanes will be closed to set girders for the eastbound direct connector.
  • Friday, October 20 at 9 p.m. until Saturday, October 21 at 12 p.m. Weekend closure. Loop 1604 eastbound left and middle mainlanes from the Blanco Road entrance ramp to Stone Oak Parkway will be closed for Slip SSTR rail work.
  • Sunday, October 15 until Sunday, October 22. Daily/Nightly 24 hours a day. Westbound to Eastbound turnaround long term closure at Loop 1604 and NW Military Highway for bridge substructure. This closure will remain in place for approximately 4 weeks.
  • Sunday, October 15 until Sunday, October 22. Daily/Nightly 24 hours a day. Westbound to Eastbound turnaround long term closure at Loop 1604 and Lockhill Selma Road for wall construction under bridge. This closure will remain in place for approximately 4 weeks. 

Loop 1604 – North East San Antonio/Bexar County

  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Exit ramp closure on eastbound mainlanes of Loop 1604 to Lookout Road for striping work. Traffic should use next exit ramp.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Full closure on eastbound mainlanes of Loop 1604 from Lookout Road to I-35 for striping. Traffic should follow signs.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Eastbound to westbound Loop 1604 turnaround closure from Nacogdoches Road to Union Pacific Railroad for retaining wall demolition work. Traffic should use Lookout Road intersection.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound frontage road of Loop 1604, right lane entrance ramp closure, and turnaround closure from Nacogdoches Road to Union Pacific Railroad for striping work. Traffic should use Lookout Road intersection.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound frontage road of Loop 1604 from Lookout Road to I-35 for striping and barrier work.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Eastbound to westbound Loop 1604 turnaround closure at Lookout Road for construction work. Traffic should use Lookout Road intersection.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating mainlane closures on eastbound Loop 1604 and alternating exit ramp closures from Nacogdoches Road to I-35 for barrier work. Traffic should use next exit ramp.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating mainlane closures on eastbound Loop 1604, entrance ramp closure, and exit ramp closure on eastbound Loop 1604 from Nacogdoches Road to I-35 for striping work. Traffic should use prior exit and next entrance ramps.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Exit ramp closure on eastbound mainlanes of Loop 1604 from Lookout Road to IKEA-RBFCU Parkway for striping work. Traffic should use prior exit ramp.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on the eastbound Loop 1604 collector ramp at the I-35 interchange for striping work.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Exit ramp closure on eastbound mainlanes of Loop 1604 to IKEA-RBFCU Parkway for striping work. Traffic should prior exit ramp.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Exit ramp closure on westbound mainlanes of Loop 1604 to Lookout Road for pavement and striping work. Traffic should use next exit ramp.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Westbound Loop 1604 collector ramp closure at I-35 interchange for geotechnical work. Traffic should follow the detour signs.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Full closure on westbound mainlanes of Loop 1604 from Pat Booker Road to Lookout Road for striping. Traffic should follow signs and use next entrance ramp.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Westbound to eastbound Loop 1604 turnaround closure at Lookout Road for demolition work. Traffic should use Lookout Road intersection.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating mainlane closures, exit ramp closure, and entrance ramp closure on westbound Loop 1604 from I-35 to Nacogdoches Road for barrier work. Traffic should use prior exit and next entrance ramps.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound frontage road, exit ramp closure, and entrance ramp closure of Loop 1604 from Union Pacific Railroad and Nacogdoches Road for barrier work. Traffic should use next available ramps.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound frontage road and westbound bypass ramp of Loop 1604 from I-35 to Nacogdoches Road for construction entrance and temporary pavement work.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Westbound to eastbound Loop 1604 turnaround closure from Lookout Road to Union Pacific Railroad for retaining wall demolition work. Traffic must use Nacogdoches Road turnaround.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Full closure of Lookout Road intersection and turnarounds at Loop 1604 for striping work. Traffic should follow detour signs.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Full closure on westbound frontage road of Loop 1604 from Gateway Boulevard to Gateway Place for setting caps. Traffic should follow detour signs. 

I-10 – North West San Antonio/Bexar County

  • Sunday, Oct. 15 until Friday, Oct. 20. Weeknights 9 p.m. until 5 a.m. Alternating IH-10 westbound frontage road closure from De Zavala Road to Camp Bullis Road for portable concrete traffic barrier installation. Nightly alternating frontage closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, Oct. 15 until Friday, Oct. 20. Weeknights 9 p.m. until 5 a.m. Alternating IH-10 eastbound frontage road closure from Camp Bullis Road to De Zavala Road for portable concrete traffic barrier installation. Nightly alternating frontage closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, Oct. 15 until Friday, Oct. 20. Weeknights 9 p.m. until 5 a.m. Alternating IH-10 westbound mainlane closure from De Zavala Road to Camp Bullis Road for portable concrete traffic barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, Oct. 15 until Friday, Oct. 20. Weeknights 9 p.m. until 5 a.m. Alternating IH-10 eastbound mainlane closure from Camp Bullis Road to De Zavala Road for portable concrete traffic barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, Oct. 15 until Friday, Oct. 20. Weeknights 9 p.m. until 5 a.m. Exit ramp full closure from Loop 1604 eastbound to IH-10 eastbound for portable concrete traffic barrier installation. Nightly closures. Excluding weekends.
  • Sunday, Oct. 15 until Friday, Oct. 20. Weeknights 9 p.m. until 5 a.m. Exit ramp full closure from IH-10 westbound to Loop 1604 eastbound for portable concrete traffic barrier installation. Nightly closures. Excluding weekends.
  • Sunday, Oct. 15 until Friday, Oct. 20. Weeknights 9 p.m. until 5 a.m. Ramp/cloverleaf full closure from IH-10 eastbound to Loop 1604 eastbound for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, Oct. 15 until Friday, Oct. 20. Weeknights 9 p.m. until 5 a.m. Ramp/cloverleaf full closure from Loop 1604 eastbound to IH-10 westbound for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, Oct. 15 until Friday, Oct. 20. Weeknights 9 p.m. until 5 a.m. IH-10 eastbound frontage road, at the Loop 1604 interchange full closure for drill shaft construction. Nightly closures. Excluding weekends.
  • Sunday, Oct. 15 until Friday, Oct. 20. Weeknights 9 p.m. until 5 a.m. Loop 1604 eastbound to westbound turnaround at IH-10 full closure for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, Oct. 15 until Friday, Oct. 20. Weeknights 9 p.m. until 5 a.m. Alternating IH-10 westbound mainlane closure from the Loop 1604 interchange to the Camp Bullis Road exit ramp for striping. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, Oct. 15 until Friday, Oct. 20. Weeknights 9 p.m. until 5 a.m. Loop 1604 eastbound frontage road right turn lane full closure onto IH-10 eastbound frontage road for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, Oct. 15 until Friday, Oct. 20. Weeknights 9 p.m. until 5 a.m. IH-10 westbound mainlane full closure from La Cantera Parkway entrance ramp to the Camp Bullis Road exit ramp for overhead sign bridge removal. Nightly closures. Excluding weekends.
  • Monday, Oct. 16 until Friday, Oct. 20. Weekdays 9 a.m. until 3 p.m. Alternating IH-10 westbound frontage road lane closure from De Zavala Road to Camp Bullis Road to set portable concrete barrier. Daily alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Monday, Oct. 16 until Friday, Oct. 20. Weekdays 9 a.m. until 3 p.m. Alternating IH-10 eastbound frontage road lane closure from Camp Bullis Road to De Zavala Road to set portable concrete barrier. Daily alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Friday, Oct. 13 at 9 p.m. until Monday, Oct. 16 at 5 a.m. Loop 1604 westbound mainlanes inside lane closure at the IH-10 interchange for bridge construction.
  • Friday, Oct. 13 at 9 p.m. until Monday, Oct. 16 at 5 a.m. Loop 1604 eastbound mainlanes inside lane closure at the IH-10 interchange for bridge construction.
  • Friday, Oct. 13 at 9 p.m. until Monday, Oct. 16 at 5 a.m. IH-10 eastbound frontage road closure between Loop 1604 eastbound frontage road and Loop 1604 westbound frontage road closure for bridge construction.
  • Friday, Oct. 13 at 9 p.m. until Monday, Oct. 16 at 5 a.m. Ramp/cloverleaf from Loop 1604 eastbound to IH-10 eastbound closure for bridge construction.
  • Friday, Oct. 13 at 9 p.m. until Monday, Oct. 16 at 5 a.m. Ramp/cloverleaf from Loop 1604 westbound to IH-10 eastbound closure for bridge construction.
  • Friday, Oct. 20 at 9 p.m. until Monday, Oct. 23 at 5 a.m. Loop 1604 eastbound frontage road at the IH-10 interchange closure for steel erection.
  • Friday, Oct. 20 at 9 p.m. until Monday, Oct. 23 at 5 a.m. IH-10 eastbound frontage road closure between Loop 1604 eastbound frontage road and Loop 1604 westbound frontage road closure for steel erection.
  • Friday, Oct. 20 at 9 p.m. until Monday, Oct. 23 at 5 a.m. Loop 1604 eastbound collector-distributor at the IH-10 interchange closure for steel erection.
  • Friday, Oct. 20 at 9 p.m. until Monday, Oct. 23 at 5 a.m. Ramp/cloverleaf from IH-10 eastbound to Loop 1604 eastbound closure for steel erection.
  • Friday, Oct. 20 at 9 p.m. until Monday, Oct. 23 at 5 a.m. Loop 1604 eastbound mainlanes right lane closure at the IH-10 interchange for steel erection. 

I-10 – East San Antonio/Bexar County/Guadalupe County

  • Friday, October 20 until Saturday, October 21. 9 p.m. to 5 a.m. Full closure of the mainlanes and intersection, in both directions, at FM 1518 for bridge construction.
  • Tuesday, October 17. 2 a.m. to 5 a.m. Single westbound mainlane closure from Santa Clara to FM 465 for concrete work.
  • Sunday, October 15. Possible I-10 alternating westbound I-10 mainline closure to load cranes.
  • Monday, October 16 through Friday, October 20. NIGHTLY northbound and southbound Loop 1604 closures at I-10 intersection from 8 p.m. to 5 a.m. each night. Detour:
  • Southbound Loop 1604 traffic may take I-10 westbound frontage road, turn around at FM 1516, and use I-10 eastbound frontage road back to Loop 1604.
  • Northbound Loop 1604 traffic may take I-10 eastbound frontage road, turn around at Pfeil Road, and use I-10 westbound frontage road back to Loop 1604. 

I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

  • Sunday, October 15 until Thursday, October 19.9 p.m. to 5 a.m. Full closure of the northbound mainlanes at AT&T Center Parkway for bridge repairs.
  • Current until Saturday, November 25, long-term closure (24/7). Left lane closure on southbound I-35 frontage road between Toepperwein Road and Judson Road for retaining wall, drilled shaft, column, and cap work.
  • Current until Sunday, December 10, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 at Fratt Road for construction work.
  • Current until Saturday, December 23 long-term closure (24/7). Alternating lane closures on southbound I-35 frontage road between Thousand Oaks Drive and Whirlwind Drive for roadway reconstruction and structural work.
  • Current until Saturday, December 30, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from Retama Parkway to Old Austin Road for temporary pavement, striping, barrier, column, and cap work.
  • Current until Sunday, September 8, 2024, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from McMorris Boulevard to Pat Booker Road for construction.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on northbound frontage road, exit ramp closure, and entrance ramp closure of I-35 from Schertz Parkway to Roy Richard Drive for barrier work. Traffic should use next exit and entrance ramps.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on northbound mainlanes, exit ramp closure, and entrance ramp closure of I-35 from Evans Road to Roy Richard Drive for barrier work. Traffic should use next available ramps.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on northbound frontage road, exit ramp closure, and entrance ramp closure of I-35 from Evans Road to Schertz Parkway for barrier work. Traffic should use next exit and entrance ramps.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, entrance ramp closure, and exit ramp closure from Roy Richard Drive to Schertz Parkway for bridge structure work. Traffic should use next entrance and exit ramps.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road, exit ramp closure, and entrance ramp closure of I-35 from Roy Richard Drive to Schertz Parkway for striping, barrier, and temporary pavement work. Traffic should use next exit and entrance ramps.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Southbound to northbound I-35 turnaround closure at Corporate Drive for striping, barrier, and temporary pavement work. Traffic should use Corporate Drive intersection.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Right lane closure on northbound Gateway Boulevard at Loop 1604 for column and cap work.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Northbound to southbound I-35 turnaround closure at Evans Road for striping, barrier, and temporary pavement work. Traffic should use Evans Road intersection.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures of northbound frontage road of I-35 from Loop 1604 to Forum Parkway for striping, barrier, and temporary pavement work. Traffic should follow signs.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on northbound mainlanes and exit ramp closure of I-35 from Forum Parkway to Evans Road for drainage work. Traffic should use next exit ramp.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on northbound frontage road, exit ramp closure, and entrance ramp closure of I-35 from Forum Parkway to Evans Road for drainage and barrier work. Traffic should use next exit and entrance ramps.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Full closure on southbound frontage road of I-35 from Retama Parkway to Olympia Parkway for bridge substructure work. Traffic should follow detour signs.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Full closure on southbound frontage road of I-35 from Old Austin Road to Forum Parkway for bridge work. Traffic should follow detour signs.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Southbound I-35 entrance ramp closure from Old Austin Road to Forum Parkway for construction work. Traffic must use the Forum Parkway turnaround and follow detour signs to access southbound I-35.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on southbound I-35 mainlanes from Forum Parkway to Ferrell Road for bridge structure work.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on southbound I-35 mainlanes from Schertz Parkway to Forum Parkway for bridge structure work.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Full closure on southbound frontage road of I-35 and entrance ramp closure from Olympia Parkway to Forum Parkway for bridge work. Traffic should follow detour signs.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road of I-35 from Olympia Parkway to Gateway Boulevard for bridge foundation, temporary pavement, striping and barrier work.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road, exit ramp closure, and entrance ramp closure of I-35 from Schertz Parkway to Evans Road for striping, barrier, and temporary pavement work. Traffic should use next exit and entrance ramps.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road and entrance ramp and exit ramp closures of I-35 from Evans Road to Olympia Parkway for bridge foundation, striping, barrier work, and temporary pavement work. Traffic should use prior exit ramp and next entrance ramp.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Eastbound Loop 1604 to northbound I-35 connector ramp closure for striping and barrier work. Traffic should follow detour signs.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Full closure on northbound I-35 collector ramp at the Loop 1604 interchange for striping, barrier, and construction entrance work. Traffic should follow detour signs.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Eastbound Loop 1604 to southbound I-35 connector ramp closure for striping and barrier work. Traffic must exit at IKEA-RBFCU Parkway and follow the detour signs to southbound I-35.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Southbound I-35 to westbound Loop 1604 connector ramp closure and alternating lane closures on southbound mainlanes of I-35 at the exit to Loop 1604 for bridge substructure work. Southbound I-35 to Loop 1604 traffic should exit at Retama Parkway and follow the detour signs to Loop 1604.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Southbound I-35 collector ramp closure at the Loop 1604 interchange for striping and barrier work. Traffic must use west Loop 1604 (exit 172) to access southbound I-35 and follow detour signs.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Westbound Loop 1604 to southbound I-35 connector ramp closure for earthwork. Traffic must exit at Lookout Road and follow the detour signs to southbound I-35.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (2) on northbound mainlanes of I-35, alternating exit ramp closures, and entrance ramp closure from Toepperwein Road to Loop 1604 for barrier setting and structures work. Traffic should follow the detour signs to the available ramps.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on northbound mainlanes of I-35 from I-35 Access Road near Shin Oak Drive to Forum Parkway for striping, barrier, and temporary pavement work.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Full closure on northbound frontage road of I-35 and entrance ramp closure from Shin Oak Road to Pat Booker Road for striping, barrier, and temporary pavement work. Traffic should follow detour signs.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Full closure of northbound frontage road, exit ramp closure, and entrance ramp closure of I-35 from Pat Booker Road to Loop 1604 interchange for striping, barrier, and temporary pavement work. Traffic should follow detour signs.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Full closure of I-35 Access Road bridge from I-35 northbound frontage road to I-35 southbound frontage road, near Shin Oak Drive for construction work. Traffic should follow detour signs.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound Pat Booker Road at I-35 for striping work.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Full closure of eastbound and westbound lanes of Pat Booker Road at I-35 for construction work. Traffic should follow detour signs.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Full closure of southbound frontage road from IKEA-RBFCU Parkway to Pat Booker Road, eastbound Loop 1604 to southbound I-35 connector ramp closure, and southbound I-35 collector ramp closure at the Loop 1604 interchange for striping and barrier work. Traffic should follow detour signs.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating ramp closures on southbound I-35 connector ramp to Pat Booker Road for striping, barrier, and bridge substructure work. Traffic must exit Loop 1604 (exit 172) and follow the detour signs to Pat Booker Road.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound Pat Booker Road at I-35 for striping work.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Full closure on southbound frontage road and entrance ramp of I-35 from Shin Oak Drive to Toepperwein Road for bridge work. Accommodations will be made for local traffic. Southbound frontage road of I-35 traffic must follow detour.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple right lane closures (2) on northbound mainlanes of I-35, entrance ramp closure, and alternating exit ramp closures from O’Connor Road to Toepperwein Road for barrier setting and structures work. Traffic should follow the detour signs to the available ramps.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on northbound frontage road, right lane closure on northbound mainlanes, and exit ramp closure of I-35 from Bludau-Bishop Road to Gunn Road, right lane closure on the eastbound and westbound at the intersection of Judson Road and Randolph Boulevard and left lane closure on Randolph Boulevard at Judson Road for temporary pavement and signal works. Traffic should use the next exit ramp.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on northbound frontage road, entrance ramp closure, and alternating exit ramp closures of I-35 from Judson Road to Shin Oak Drive for barrier work. Traffic should follow the detour sign to the available ramps.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on southbound mainlanes of I-35, exit ramp closure, and left lane closure on southbound frontage road of I-35 from Toepperwein Road to Judson Road for earthwork and barrier work. Traffic should use next exit ramp.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, entrance ramp closure, and exit ramp closure from Pat Booker Road to Judson Road for structures work. Traffic should use next entrance and exit ramps.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple right lane closures (3) on southbound I-35 mainlanes, entrance ramp closure, exit ramp closure, and left lane closures (2) on southbound frontage road of I-35 from Judson Road to O’Connor Road for striping, barrier, and paving work. Traffic should use next entrance and exit ramps.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on southbound I-35 mainlanes from Judson Road to O’Connor Road for striping work.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road of I-35 from Judson Road to O’Connor Road for earthwork, paving, striping, and barrier work.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound mainlanes of I-35, exit ramp closure, and left lane closure on southbound frontage road of I-35 at O’Connor Road for barrier work. Traffic should use next exit.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (2) on northbound frontage road, entrance ramp closure, and exit ramp closures of I-35 from Thousand Oaks Drive to Weidner Road for earthwork and striping. Traffic should follow the detour signs to the available ramps.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (2) on northbound frontage road, alternating entrance ramp closures, and exit ramp closure of I-35 from Weidner Road to Bludau-Bishop Road for earthwork and striping. Traffic should follow the detour signs to the available ramps.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on northbound frontage road of I-35 from Crestway Drive to Starlight Terrace for barrier work.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on northbound mainlanes of I-35 from Thousand Oaks Drive to Weidner Road for striping and barrier work.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on northbound mainlanes of I-35 from Weidner Road to Bludau-Bishop Road for striping and barrier work.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on southbound mainlanes, alternating entrance and exit ramp closures, and alternating lane closures on southbound frontage road of I-35 from O’Connor Road to Weidner Road for striping work. Traffic should use the next exit and entrance ramps.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (2) on southbound mainlanes, entrance ramp closure, exit ramp closure, and alternating lane closures on southbound frontage road of I-35 from Weidner Road to Thousand Oaks Drive for striping work. Traffic should use the next exit and entrance ramps.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road of I-35 and entrance ramp closure from Weidner Road to Thousand Oaks Drive for earthwork, drainage and barrier work. Traffic should use prior entrance ramp.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road of I-35, entrance ramp closure, and exit ramp closure from O’Connor Road to Weidner Road for drainage and barrier work. Traffic should use next entrance and exit ramps.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (2) on northbound mainlanes of I-35 from Randolph Boulevard to Thousand Oaks for barrier setting.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Full closure on southbound frontage road and northbound to southbound turnaround closure of I-35 from Thousand Oaks Drive to Whirlwind Drive for drilling work. Traffic should follow detour signs. Accommodations will be made for local traffic.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on exit ramp from I-410 eastbound to I-35 southbound mainlanes and alternating lane closures on southbound frontage road of I-35 from Randolph Boulevard to Walzem Road for geotechnical, drilled shaft, and column work. Traffic to use next exit ramp.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road of I-35 and exit ramp closure from Thousand Oaks Drive to Randolph Boulevard for permanent widening work. Traffic should use prior exit ramp.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (2) on northbound mainlanes of I-35 from Randolph Boulevard to Thousand Oaks for barrier setting.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (2) on northbound and southbound of Interchange Parkway from Austin Highway (Loop 368) to Walzem Road and multiple lane closures (2) on eastbound and westbound of Fratt Road from I-35 southbound frontage road to Austin Highway (Loop 368) for barrier work.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Southbound to northbound turnaround closure at Walzem Road, alternating lane closures on northbound frontage road, and alternating entrance and exit ramp closures of I-35 from Walzem Road to Crestway Drive for striping and barrier work. Traffic should follow detour signs for available ramps.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound mainlanes of I-35 from Randolph Boulevard to Walzem Road for cap work.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Entrance ramp closure on southbound frontage road of I-35 from Fratt Drive to Walzem Road for drilled shaft and column work. Traffic to use next entrance ramp.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Full closure on southbound frontage road, exit ramp, and entrance ramp of I-35 from Randolph Boulevard to Fratt Road for drilled shaft work. Traffic should follow detour signs.
  • Monday, October 16 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple right lane closures (3) on southbound I-35 mainlanes and left lane closure (1) on southbound frontage road of I-35 from Pat Booker Road to Toepperwein Road for beam setting.
  • Monday, October 16 until Saturday, October 21. 12:00 p.m. to 12:00 a.m. Right lane closure on southbound frontage road of I-35 from FM 2252 to Cibolo Valley Drive and rolling closures on southbound mainlanes of I-35 from Cibolo Valley Drive to Toepperwein Road for beam staging.
  • Tuesday, October 17 until Saturday, February 3, 2024, long-term closure (24/7). Left lane closure on northbound I-35 frontage road between Toepperwein Road and Judson Road for retaining wall, drilled shaft, column, and cap work.  

I-35 – South San Antonio/Bexar County

  • Current until October 20. 9 p.m. to 5 a.m. Alternating northbound mainlane closures from Kinney Rd. to Loop 410 for road repairs.

I-410 – North East San Antonio

  • Current until Friday, February 16, 2024, long-term closure (24/7). Left lane closure on westbound frontage road of I-410 from Perrin Creek to Austin Highway (Loop 368) for construction.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Entrance ramp closure on northbound Austin Highway (Loop 368) to eastbound I-410 for barrier work. Traffic should use next entrance ramp.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on northbound Austin Highway (Loop 368) from Walzem Road to Interchange Parkway for barrier work.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on northbound Austin Highway (Loop 368) connector ramp to westbound I-410 for barrier work.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound frontage road of I-410, entrance ramp closure, and eastbound to westbound turnaround closure between Starcrest Drive and Perrin Beitel for striping and barrier work. Traffic should use next entrance ramp.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound frontage road of I-410, entrance ramp closure, and right mainlane closure from Perrin Beitel to Austin Highway (Loop 368) for striping and barrier work. Traffic should follow detour signs.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (2) on eastbound mainlanes of I-410 from Starcrest Drive to Randolph Boulevard for barrier setting.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (2) on eastbound mainlane of I-410 from Austin Highway (Loop 368) to Randolph Boulevard for barrier work.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound frontage road and exit ramp closure of I-410 from Randolph Boulevard to Perrin Beitel for drilled shaft work. Traffic to use next exit ramp.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (2) on westbound I-410 mainlanes from I-35 to Austin Highway (Loop 368) for cap and barrier work.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on westbound mainlanes and exit ramp closure of I-410 from I-35 to Perrin Beitel for striping and barrier work. Traffic should use next exit ramp.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Entrance ramp closure on westbound frontage road and exit ramp closure of I-410 westbound to Austin Highway (Loop 368) for barrier work. Traffic should follow detour signs.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Multiple left lane closures (2) and entrance ramp closure on eastbound frontage road of I-410 from Nacogdoches Road to Harry Wurzbach Road for striping and barrier work. Traffic should use next entrance ramp.
  • Sunday, October 15 until Saturday, October 21. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound frontage road of I-410, entrance ramp closure, and exit ramp closure from Harry Wurzbach Road to Starcrest Drive for striping and barrier work. Traffic should use prior entrance and exit ramps.  

I-410 – South San Antonio/Bexar County

  • Friday, October 13 until Sunday, October 15. 7 p.m. to 7 p.m. Full closure of the intersection at FM 2790 for reconstruction. 

FM 1535 – Northwest Military Highway

  • Monday, October 16 until Friday, October 20. 7 a.m. to 6 p.m. Alternating lane closures, in both directions, from Loop 1604 to Huebner Rd. for curb and sidewalk construction. 

US 90 – West San Antonio/Bexar County

  • Sunday, October 15 until Friday, October 20. 8:30 p.m. to 5 a.m. Single westbound mainlane closure from 36th St. to W. Military Dr. for metal beam guard replacement.
  • Wednesday, October 18. 9 a.m. to 3 p.m. Single westbound mainlane closure from Callaghan Rd. to W. Military Dr. for rail operations.
  • Monday, October 16 until Friday, October 20. 9 a.m. to 3 p.m. Single eastbound mainlane closure from W. Military Dr. to General McMullen for mow strip operations.
  • Sunday, October 15 until Friday, October 20. 8:30 p.m. to 5 a.m. Multiple eastbound mainlane closures from Loop 410 to General McMullen for mill and inlay operations.
  • Monday, October 16 until Friday, October 20. 9 a.m. to 3 p.m. Turnarounds closed, in both directions, at Leon Creek bridge for bridge work.
  • Monday, October 16 until Friday, October 20. 8:30 p.m. to 5 a.m. Multiple westbound mainlane closures from General McMullen to Callaghan Rd. for mill and overlay operations. 

PA 1502 – Wurzbach Parkway

  • Current until Tuesday, October 31. 9 a.m. to 3 p.m. Alternating lane closures, in both directions, from N.W. Military Highway to Weidner Rd. for roadway construction. 

SH 151 – West San Antonio/Bexar County

  • Current until Tuesday, October 31. 9 a.m. to 3 p.m. Single lane closure on the westbound frontage road from Hunt Lane to W. Military Dr. for utility work.
  • Current until Tuesday, October 31. 9 a.m. to 3 p.m. Single lane closure on the westbound frontage road from Potranco Rd. to Hunt Lane for utility work.
  • Current until Tuesday, October 31. 9 a.m. to 3 p.m. Single lane closure on the westbound frontage road from W. Military Dr. to Westover Hills for utility work.
  • Wednesday, October 18 until Friday, November 3. 9 a.m. to 3 p.m. Single lane closure on the frontage roads, in both directions, at Potranco Rd. for utility work.
  • Wednesday, October 18 until Friday, November 3. 9 a.m. to 3 p.m. Single lane closures on the frontage roads, in both directions, at Ingram Rd. for utility work.
  • Wednesday, October 18 until Friday, November 3. 9 a.m. to 3 p.m. Single lane closure on the eastbound frontage road from Wiseman to Loop 1604.