UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North West San Antonio/Bexar County

  • Monday, April 1 until Monday, April 15. Weeknights 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Bandera Road (SH 16) to IH-10 for portable concrete traffic barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weeknights 9 p.m. until 5 a.m. Alternating westbound mainlane closure from IH-10 to Bandera Road (SH 16) for portable concrete barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weeknights 9 p.m. until 5 a.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for portable concrete traffic barrier installation. Nightly alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weeknights 9 p.m. until 5 a.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for portable concrete traffic barrier installation. Nightly alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weeknights 9 p.m. until 5 a.m. IH-10 eastbound mainlane exit ramp closure to Loop 1604 westbound for westbound collector-distributor bridge construction on the bridge at Leon Creek. Nightly closure. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weeknights 9 p.m. until 5 a.m. Ramp/cloverleaf closure from IH-10 westbound to Loop 1604 westbound for westbound collector-distributor bridge construction on the bridge at Leon Creek. Nightly closure. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weeknights 9 p.m. until 5 a.m. Eastbound frontage road lane full closure from John Peace Boulevard/La Cantera Parkway to IH-10 for eastbound direct connector bridge construction. Nightly frontage road full closure. Only one full frontage lane closure to occur per direction. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weeknights 9 p.m. until 5 a.m. Westbound frontage road lane full closure from IH-10 to John Peace Boulevard/La Cantera Parkway for westbound collector-distributor bridge construction. Nightly frontage road full closure. Only one full frontage lane closure to occur per direction. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weeknights 9 p.m. until 5 a.m. Loop 1604 westbound mainlane exit ramp to La Cantera Parkway closure for westbound direct connector bridge construction. Nightly closure. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weeknights 9 p.m. until 5 a.m. Loop 1604 eastbound mainlane exit ramp to IH-10 eastbound closure for westbound direct connector bridge construction. Nightly closure. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weeknights 9 p.m. until 5 a.m. Loop 1604 westbound frontage road entrance ramp from IH-10 closure for westbound direct connector bridge construction. Nightly closure. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weeknights 9 p.m. until 5 a.m. Loop 1604 and Hausman Road full intersection closure (both directions, including turnarounds) for demolition work/bridge construction. Only one intersection to be closed at a time. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weeknights 9 p.m. until 5 a.m. Loop 1604 and Kyle Seale Parkway full intersection closure (both directions, including turnarounds) for demolition work/bridge construction. Only one intersection to be closed at a time. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weeknights 9 p.m. until 5 a.m. Loop 1604 and Babcock Road full intersection closure (both directions, including turnarounds) for demolition work/bridge construction. Only one intersection to be closed at a time. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weeknights 9 p.m. until 5 a.m. Loop 1604 and Chase Hill Boulevard full intersection closure (both directions, including turnarounds) for demolition work/bridge construction. Only one intersection to be closed at a time. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weeknights 9 p.m. until 5 a.m. Loop 1604 and La Cantera Parkway full intersection closure (both directions, including turnarounds) for demolition work/bridge construction. Only one intersection to be closed at a time. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weeknights 9 p.m. until 5 a.m. Westbound mainlane full closure from the Kyle Seale Parkway exit ramp to the Hausman Road temporary entrance ramp for overhead sign bridge installation. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weeknights 9 p.m. until 5 a.m. Eastbound mainlane full closure from Hausman Road exit ramp to the Kyle Seale Parkway temporary entrance ramp for overhead sign bridge installation. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weekdays 9 a.m. until 3 p.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for traffic barrier, sidewalk construction and beam placement/bridge construction. Daily alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weekdays 9 a.m. until 3 p.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for traffic barrier, sidewalk construction and beam placement/bridge construction. Daily alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Hausman Road for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Hausman Road for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, April 1 until Monday, April 15. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Friday, March 29 until Saturday, March 30. Nightly 9 p.m. until 7 a.m. Loop 1604 eastbound frontage road full closure from Valero Way to the IH-10 interchange for bridge construction.
  • Monday, April 1 until Monday, April 15. Daily/Nightly 24 hours a day. Eastbound to westbound turnaround closure at Loop 1604 and La Cantera Parkway/John Peace Boulevard for bridge construction/retaining walls. Only one turnaround to be closed at a time on each direction.
  • Monday, April 1 until Monday, April 15. Daily/Nightly 24 hours a day. Westbound to eastbound turnaround closure at Loop 1604 and La Cantera Parkway/John Peace Boulevard for bridge construction/retaining walls. Only one turnaround to be closed at a time on each direction.
  • Monday, April 1 until Monday, April 15. Daily/Nightly 24 hours a day. Eastbound to westbound turnaround closure at Loop 1604 and Kyle Seale Parkway for bridge construction/retaining walls. Only one turnaround to be closed at a time on each direction.
  • Monday, April 1 until Monday, April 15. Daily/Nightly 24 hours a day. Westbound to eastbound turnaround closure at Loop 1604 and Kyle Seale Parkway for bridge construction/retaining walls. Only one turnaround to be closed at a time on each direction. 

Loop 1604 – North Central San Antonio/Bexar County

  •  Monday, April 1 until Friday, April 5. Nightly. 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Tradesman Road to Stone Oak Parkway exit ramp for barrier setting and striping.
  • Monday, April 1 until Friday, April 5. Nightly. 9 p.m. until 5 a.m. Alternating westbound mainlane closure from Stone Oak Parkway exit ramp to Tradesman Road for barrier setting and striping.
  • Monday, April 1 until Friday, April 5. Nightly. 9 p.m. until 5 a.m. Alternating eastbound frontage road closure from IH-10 to Stone Oak Parkway exit ramp for barrier setting and striping.
  • Monday, April 1 until Friday, April 5. Nightly. 9 p.m. until 5 a.m. Alternating westbound frontage road closure from Stone Oak Parkway exit ramp to IH-10 for barrier setting and striping.
  • Monday, April 1 until Friday, April 5. Nightly. 9 p.m. to 5 a.m. Westbound mainlanes from Lockhill Selma Road to IH-10 full closure to install overhangs and deck panels.
  • Thursday, April 4 until Friday, April 5. Nightly. 9 p.m. to 5 a.m. Eastbound mainlane full closure from Vance Jackson Road to the Lockhill Selma Road entrance ramp for setting girders on the direct connector.
  • Thursday, April 4 until Friday, April 5. Nightly. 9 p.m. to 5 a.m. IH-10 westbound exit ramp/direct connector to Loop 1604 eastbound full closure for setting girders on the direct connector.
  • Thursday, April 4 until Friday, April 5. Nightly. 9 p.m. to 5 a.m. IH-10 eastbound cloverleaf exit ramp (southwest cloverleaf) to Loop 1604 westbound full closure for setting girders on the direct connector.
  • Sunday, March 31 until Sunday, April 7. Daily/Nightly 24 hours a day. Westbound to Eastbound turnaround long term closure at Loop 1604 and Lockhill Selma Road for wall construction under bridge. 

Loop 1604 – North East San Antonio/Bexar County

  • Current until Friday, April 5, long-term closure (24/7). Left lane closure on eastbound frontage road of Loop 1604 from Lookout Road to IKEA-RBFCU Parkway for construction work.
  • Current through Sunday, April 7, long-term closure (24/7). Westbound to eastbound Loop 1604 turnaround closure from Lookout Road to Union Pacific Railroad for construction work.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Full closure on eastbound Loop 1604 connector ramps to I-35 and entrance ramp closure of Loop 1604 from Lookout Road to IKEA-RBFCU Parkway for bridge work. Traffic should follow detour signs.
  • Monday, April 1 until Friday, April 5, 9 a.m. to 3 p.m. Eastbound to westbound Loop 1604 turnaround closure from Nacogdoches Road to Union Pacific Railroad for bridge maintenance. Traffic should follow detour signs?
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Full closure on eastbound frontage road of Loop 1604 and exit ramp closure from Lookout Road to IKEA-RBFCU Parkway for column cap work. Traffic should follow detour signs.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Full closure on westbound frontage road of Loop 1604 from Gateway Boulevard to Gateway Place, full closure on southbound I-35 to westbound Loop 1604 connector ramp, and exit ramp closure to frontage road for column cap work. Traffic should follow detour signs. 

I-10 – North West San Antonio/Bexar County

  • Monday, April 1 until Friday, April 12. Weeknights 9 p.m. until 5 a.m. Alternating IH-10 westbound frontage road closure from De Zavala Road to Camp Bullis Road for portable concrete traffic barrier installation. Nightly alternating frontage closures. One lane to remain open at all times. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weeknights 9 p.m. until 5 a.m. Alternating IH-10 eastbound frontage road closure from Camp Bullis Road to De Zavala Road for portable concrete traffic barrier installation. Nightly alternating frontage closures. One lane to remain open at all times. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weeknights 9 p.m. until 5 a.m. Alternating IH-10 westbound mainlane closure from De Zavala Road to Camp Bullis Road for portable concrete traffic barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weeknights 9 p.m. until 5 a.m. Alternating IH-10 eastbound mainlane closure from Camp Bullis Road to De Zavala Road for portable concrete traffic barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weeknights 9 p.m. until 5 a.m. Exit ramp full closure from Loop 1604 eastbound to IH-10 eastbound for portable concrete traffic barrier installation. Nightly closures. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weeknights 9 p.m. until 5 a.m. Exit ramp full closure from IH-10 westbound to Loop 1604 eastbound for portable concrete traffic barrier installation. Nightly closures. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weeknights 9 p.m. until 5 a.m. Ramp/cloverleaf full closure from IH-10 eastbound to Loop 1604 eastbound for bridge construction. Nightly closures. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weeknights 9 p.m. until 5 a.m. Ramp/cloverleaf full closure from Loop 1604 eastbound to IH-10 westbound for bridge construction. Nightly closures. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weeknights 9 p.m. until 5 a.m. IH-10 eastbound frontage road, at the Loop 1604 interchange full closure for drill shaft construction. Nightly closures. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weeknights 9 p.m. until 5 a.m. Alternating IH-10 westbound mainlane closure from the Loop 1604 interchange to the Camp Bullis Road exit ramp for striping. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weeknights 9 p.m. until 5 a.m. Loop 1604 eastbound frontage road right turn lane full closure onto IH-10 eastbound frontage road for bridge construction. Nightly closures. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weeknights 9 p.m. until 5 a.m. Loop 1604 westbound frontage road full closure at the IH-10 intersection for bridge construction. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weeknights 9 p.m. until 5 a.m. IH-10 eastbound frontage road full closure from the Loop 1604 interchange to UTSA Boulevard for bridge construction. Nightly closures. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weeknights 9 p.m. until 5 a.m. IH-10 eastbound mainlanes full closure from the La Cantera Parkway entrance ramp to the Loop 1604 Interchange for bridge construction. Nightly closures. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weeknights 9 p.m. until 5 a.m. IH-10 westbound mainlanes full closure from the Loop 1604 Interchange to the La Cantera Parkway entrance ramp for bridge construction. Nightly closures. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weeknights 9 p.m. until 5 a.m. Loop 1604 eastbound mainlanes full closure at the IH-10 interchange for bridge construction. Nightly closures. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weeknights 9 p.m. until 5 a.m. Loop 1604 westbound mainlanes full closure at the IH-10 interchange for bridge construction. Nightly closures. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weeknights 9 p.m. until 5 a.m. IH-10 westbound cloverleaf exit ramp to Loop 1604 westbound full closure for placement of steel girders. Nightly closures.
  • Monday, April 1 until Friday, April 12. Weeknights 9 p.m. until 5 a.m. Loop 1604 westbound cloverleaf exit ramp to IH-10 eastbound full closure for placement of steel girders. Nightly closures.
  • Monday, April 1 until Friday, April 12. Weeknights 9 p.m. until 5 a.m. Loop 1604 westbound collector-distributor for placement of steel girders. Nightly closures.
  • Monday, April 1 until Friday, April 12. Weeknights 9 p.m. until 5 a.m. IH-10 westbound exit ramp to Loop 1604 westbound full closure for placement of steel girders. Nightly closures.
  • Monday, April 1 until Friday, April 12. Weeknights 9 p.m. until 5 a.m. Loop 1604 westbound exit ramp to IH-10 westbound full closure for placement of steel girders. Nightly closures.
  • Monday, April 1 until Friday, April 12. Weekdays 9 a.m. until 3 p.m. Alternating IH-10 westbound frontage road lane closure from De Zavala Road to Camp Bullis Road to set portable concrete barrier. Daily alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weekdays 9 a.m. until 3 p.m. Alternating IH-10 eastbound frontage road lane closure from Camp Bullis Road to De Zavala Road to set portable concrete barrier. Daily alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weekdays 9 a.m. until 3 p.m. Loop 1604 eastbound frontage road full closure at the IH-10 intersection for bridge construction. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weekdays 9 a.m. until 3 p.m. Loop 1604 westbound frontage road full closure at the IH-10 intersection for bridge construction. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weekdays 9 a.m. until 3 p.m. Loop 1604 eastbound frontage road full closure from the IH-10 eastbound frontage road to the IH-10 westbound frontage road for bridge construction. Daily closures. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weekdays 9 a.m. until 3 p.m. Loop 1604 westbound frontage road full closure from the IH-10 eastbound frontage road to the IH-10 westbound frontage road for bridge construction. Daily closures. Excluding weekends.
  • Monday, April 1 until Friday, April 12. Weekdays 9 a.m. until 3 p.m. IH-10 eastbound frontage road right turn lane full closure onto Loop 1604 westbound frontage road for temporary pavement construction. Daily closures.
  • Monday, April 1 until Friday, April 12. Daily/Nightly 24 hours a day. IH-10 westbound frontage road right lane closure from the Loop 1604 interchange to the IH-10 westbound mainlane entrance ramp for bridge construction.
  • Monday, April 1 until Friday, April 12. Daily/Nightly 24 hours a day. Loop 1604 eastbound frontage road left lane closure between the IH-10 eastbound frontage road and the IH-10 westbound frontage road for bridge construction. 

I-10 – East San Antonio/Bexar County/Guadalupe County

  • Current through April. The westbound I-10 entrance ramp from Ackerman will be closed from 9 a.m. January 18 through March. Detour: Westbound I-10 frontage road traffic to westbound I-10 mainlanes may turn around at Ackerman, continue on the eastbound frontage road, and use the Foster turnaround to access the westbound I-10 entrance ramp at Foster.
  • Current until Friday, April 19. 8 p.m. to 5 a.m. Alternating lane closures on the mainlanes and frontage roads, in both directions, from Ackerman Rd. to W.W. White Rd. for barrier and striping operations.
  • Monday, April 1 until Friday, April 5. 9 p.m. to 5 a.m. Full closure of the westbound mainlanes from FM 1518 to FM 2538 for earwall construction.
  • Thursday, April 25 until Friday, April 26. 9 p.m. to 5 a.m. Full closure of the westbound mainlanes from Zuehl Rd. to FM 2538 for beam setting.
  • Friday, April 26 until Saturday, April 27. 9 p.m. to 5 a.m. Full closure of the westbound frontage road at Cibolo Creek for beam setting.
  • Tuesday, April 2 until Friday, April 5. 9 p.m. to 5 a.m. Full closure of northbound mainlanes at I-10 for drainage work. 

I-35 – Northeast San Antonio/New Braunfels/Comal County

  • Current through Friday, April 5, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Judson Road to Toepperwein Road for drainage, column, and cap work.
  • Current until Friday, April 5, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Bludau-Bishop Road to Judson Road for permanent widening and drainage work.
  • Current through Wednesday, April 24, long term closure (24/7). Left lane closure on southbound frontage road of I-35 from Forum Parkway to Old Austin Road for bridge and roadway work.
  • Current through Monday, May 20, long-term closure (24/7). Alternating lane closures on southbound I-35 frontage road between Thousand Oaks Drive and Whirlwind Drive for roadway reconstruction and structural work.
  • Current through Thursday, July 4, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Starlight Terrace to Weidner Road for construction work.
  • Current through Friday, July 12, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from Randolph Boulevard to Fratt Road for construction work.
  • Current through Thursday, July 18, long term closure (24/7). Exit ramp closure of Weidner Road on I-35 for construction work.
  • Current until Sunday, September 8, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from McMorris Boulevard to Pat Booker Road for construction.
  • Current until Saturday, August 2, 2025, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Forum Parkway to Forum Access Road for construction work.
  • Current through Saturday, August 3, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Weidner Road to O'Connor Road for construction work.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Full closure of eastbound and westbound lanes and full closure of northbound to southbound turnaround of Evans Road at I-35 for construction work. Traffic should follow detour signs.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound mainlanes of I-35 from Forum Parkway to Ferrell Road for bridge structure work.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Full closure on southbound frontage road of I-35 from Corporate Drive to Evans Road and full closure of eastbound and westbound lanes of Evans Road for bridge substructure work. Traffic should follow detour signs.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Full closure on southbound frontage road, exit ramp closure of I-35 from Evans Road to Arcadia Drive, a full closure on northbound to southbound turnaround at Evans Road and a full closure on the westbound lanes on Evans Road for substructure work. Traffic should follow detour signs.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Full closure on eastbound Loop 1604 to northbound I-35 connector ramp for construction work. Traffic should follow detour signs.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Full closure on westbound I-35 collector ramp at the Loop 1604 interchange and full closure on northbound I-35 to westbound Loop 1604 connector ramp for construction work. Traffic should follow detour signs.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Full closure on eastbound Loop 1604 to southbound I-35 connector ramp for column cap work. Traffic should follow the detour signs to southbound I-35.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Full closure on eastbound Loop 1604 collector ramp at I-35 interchange and full closure on southbound I-35 to eastbound Loop 1604 connector ramp for barrier work. Traffic should follow detour signs.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Multiple mainlane closures (3) on northbound I-35, multiple lanes closures (2) northbound frontage road, entrance ramp closure, and alternating exit ramps closure from Toepperwein Road to Pat Booker Road for structures work. Traffic should use next entrance and exit ramps.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Full closure on southbound frontage road and entrance ramp of I-35 from Shin Oak Drive to Toepperwein Road for cap form erection work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp closure, and exit ramp closure from Pat Booker Road to Toepperwein Road for structures work. Traffic should use next entrance and exit ramps.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound mainlanes, multiple lane closures (2) on northbound frontage road, and entrance ramp closure of I-35 from O’Connor Road to Bludau-Bishop Road for structures work. Traffic should use next entrance ramp.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound mainlanes, multiple lane closures (2) on northbound frontage road, and alternating exit ramps closure from Judson Road to Toepperwein Road for structures work. Traffic should use next entrance and exit ramps.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Full closure on southbound frontage road and exit ramp of I-35 from Toepperwein Road to Judson Road for cap form erection work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp closure, and exit ramp closure from Toepperwein Road to Judson Road for structures work. Traffic should use next entrance and exit ramps.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp closure, and exit ramp closure from Judson Road to O’Connor Road for structures work. Traffic should use next entrance and exit ramps.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound mainlanes, multiple lane closures (2) on northbound frontage road, entrance ramp closure, and exit ramp closure of I-35 form Thousand Oaks Drive to Weidner Road for drainage and structures work. Traffic should use the next exit and entrance ramps.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound mainlanes, multiple lane closures (2) on northbound frontage road, entrance ramp closure, and exit ramp closure of I-35 from Weidner Road to O’Connor Road for drainage and structures work. Traffic should use the next exit and entrance ramps.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Full closure on southbound frontage road and entrance ramp closure of I-35 from O’Connor Road to Tech Com Drive for cap form erection work. Accommodations will be made for local traffic. Traffic must follow detour signs.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Full closure on southbound frontage road and exit ramp closure of I-35 from Tech Com Drive to Weidner Road for cap form erection work. Accommodations will be made for local traffic. Traffic must follow detour.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, alternating lane closures on southbound frontage road, and entrance ramp closure from O’Connor Road to Weidner Road for drainage and barrier work. Traffic should use next entrance and exit ramps.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Multiple lane closure (3) on southbound mainlanes, multiple lane closures (2) on southbound frontage road, entrance ramp closure, and exit ramp closure of I-35 from Weidner Road to Thousand Oaks Drive for drainage and structures work. Traffic should use the next exit and entrance ramps.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Full closure on southbound frontage road and northbound to southbound turnaround closure of I-35 from Thousand Oaks Drive to Whirlwind Drive for drilling work. Traffic should follow detour signs. Accommodations will be made for local traffic.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Multiple lane closures (2) on southbound frontage road of I-35 from Whirlwind Drive to Randolph Boulevard for construction work.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Full closure on southbound frontage road, exit ramp closure, and northbound to southbound turnaround closure of I-35 from Thousand Oaks Drive to Randolph Boulevard for bridge cap work. Traffic should follow detour signs.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Full closure of northbound I-35 to westbound I-410 connector ramp for drilling work. Traffic should follow detour signs.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Full closure of northbound I-35 to westbound I-410 connector ramp and entrance ramp closure from Randolph Boulevard for column work. Traffic should follow detour signs.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Full closure of eastbound I-410 connector ramp to southbound I-35 for bridge work. Traffic should follow detour signs.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Southbound to northbound turnaround closure at Walzem Road, alternating lane closures on northbound frontage road, and alternating entrance and exit ramp closures of I-35 from Walzem Road to Crestway Drive for striping and barrier work. Traffic should follow detour signs for available ramps.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Full closure on Fratt Road from Austin Highway (Loop 368) to Interchange Parkway, alternating lane closures on southbound Interchange parkway from Austin Highway (Loop 368) to Fratt Road, and full closure on Interchange Parkway from Fratt Road and Walzem Road for utility, columns, and striping work. Traffic should follow detour signs.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Full closure on southbound frontage road, exit ramp, and entrance ramp of I-35 from Randolph Boulevard to Fratt Road for drilled shaft work. Traffic should follow detour signs.
  • Monday, April 1 until Friday, April 5, 9 p.m. to 5 a.m. Full closure of Randolph Boulevard and southbound frontage road at I-35 for construction work. Traffic should follow detour signs 

I-410 – North East San Antonio

I-410 – East San Antonio/Bexar County

  • Current until Friday, April 19. 8 p.m. to 5 a.m. Alternating lane closures on the mainlanes and frontage roads, in both directions, from Rigsby Ave. to I-10 for barrier and striping operations. 

I-410 – West San Antonio/Bexar County

  • Monday, April 1 until Tuesday, April 2. 9 p.m. to 5 a.m. Single northbound mainlane closure from Medina Base Rd. to Old Pearsall Rd. for bridge work. 

PA 1502 – Wurzbach Parkway

  • Current until Sunday, March 31. 9 a.m. to 3 p.m. Alternating lane closures, in both directions, from N.W. Military Highway to Weidner Rd. for construction work.
  • Current until Sunday, March 31. 8 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from N.W. Military Highway to Weidner Rd. for paving operations. 

FM 1535 – Northwest Military Highway

  • Current until Friday, April 5. 7 a.m. to 6 p.m. Alternating lane closures, in both directions, from Loop 1604 to Huebner Rd. for curb and sidewalk construction. 

US 90 – West San Antonio

  • Current until Thursday, April 4. 8:30 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from I-35 to Loop 410 for guard rail construction.
  • Monday, April 1 until Friday, April 5. 9 a.m. to 3 p.m. Single westbound mainlane closure from Callaghan Rd. to W. Military Dr. for bridge work.
  • Monday, April 1 until Thursday, May 2. 8 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from 36th St. to I-35 for guard rail repairs and paving operations. 

SL 368 – Broadway

  • Monday, April 1 until Tuesday, April 2. 9 p.m. to 5 a.m. Alternating lane closures, in both directions, from Funston Pl. to Mulberry Ave. for barrier installation.
  • Tuesday, April 2 until Friday, April 5. Single lane closures, in both directions, from Funston Pl. to Mulberry Ave. for bus pad installations. 

FM 1516 – Bexar County

  • Current until Monday, April 8. 9 a.m. to 3 p.m. Single northbound lane closure from Hayes Parc Rd. to Martinez Converse Rd. for material haul-off. 

SH 16 – Bandera Road

  • Monday, April 1 until Friday, April 5. 9 a.m. to 3 p.m. Alternating lane closures, in both directions, from Loop 1604 to Circle A for curb and sidewalk construction. 

SH 151 – West Bexar County

  • Wednesday, April 3 until Thursday, April 4. 9 a.m. to 3 p.m. Single eastbound mainlane closure from Loop 1604 to Wiseman for column work.
  • Wednesday, April 3 until Thursday, April 4. 9 a.m. to 3 p.m. Westbound ramp closure between Westover Hills and Wiseman for column work.
  • Monday, April 1 until Thursday, April 4. Single lane closure on the westbound frontage road from Westover Hills to SH 151 for bore work. 

FM 2252 – Comal County

  • Monday, April 1 until Tuesday, April 2 9 p.m. to 5:00 a.m. Full lane closure at Marbach and FM 2252, between Bracken Drive South and Bracken Drive North for drainage work. 

FM 725 – Guadalupe County

  • Current until Monday, April 15 8:00 a.m. until 3:30 p.m. Alternating lane closures on FM 725 between FM 78 and Ferry Boat Lane for paving. 

I-10 -Guadalupe County

  • Current until Saturday, April 6 9 p.m. until 5 a.m. Alternating lane closures on I-10 between SH 123 and FM 464 for placement of construction detour.
  • Monday, April 1 until Monday, April 22, 7:00 a.m. until 5:00 a.m. South side of Santa Clara Road will be closed for the eastbound frontage to southbound Santa Clara movement. Detour will be to continue eastbound on the frontage road, then take a right on FM 465, followed by another right at Gin Road. Note that the northbound Santa Clara will remain open. 
  • Friday, April 12, until Saturday, April 13, 9:00 p.m. until 5:00 a.m. WBFR Closure from Santa Clara Rd to Zuehl Rd and closure of WB Zuehl Exit Ramp to demo existing Zuehl overpass.
  • Friday, April 12, until Saturday, April 13, 9:00 p.m. until 5:00 a.m. WBML RT Lane Closure from Santa Clara Rd to Zuehl Rd and closure of WB Zuehl Exit Ramp to demo existing Zuehl overpass.
  • Saturday, April 13 until Sunday, April 14, 9:00 a.m. until 9:00 a.m. EBML FULL Closure from FM 2538 to Zuehl Rd and closure of WB Zuehl Exit Ramp while the contractor demo the existing Zuehl overpass.
  • Saturday, April 13 until Sunday, April 14, 12:00 p.m. until 5:00 p.m. EBFR Closure from Zuehl Rd to Santa Clara Rd. while the contractor demo existing Zuehl overpass. 

FM 3351 – Kendall County

  • Current until Tuesday, April 30, 8 p.m. until 5 a.m. Alternating lane closures between Cibolo Creek and SH 46 for repairs and paving.