Loop 1604 – North Central San Antonio
  • Tuesday, July 9 until Friday, July 12. Nightly 9 p.m. to 5 a.m. Full eastbound closure of the US 281 north exit ramp to the Redland Road entrance ramp for bridge span work. DETOUR: Use the US 281 north exit ramp through the US 281 and Gold Canyon Road intersections, use the Gold Canyon Road entrance ramp.
  • Tuesday, July 9 until Friday, July 12. Nightly 9 p.m. to 5 a.m. Full westbound mainlane closure from the north exit ramp to the US 281 entrance ramp for bridge span work. DETOUR: Use the north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Tuesday, July 9 until Friday, July 12. Nightly 9 p.m. to 5 a.m. Full westbound frontage road closure at US 281 for bridge span work. DETOUR: Take the west to eastbound turnaround at US 281 through the Gold Canyon Road intersection, use the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Tuesday, July 9 until Friday, July 12. Nightly 9 p.m. to 5 a.m. Turnaround closed on the eastbound frontage road for bridge span work. DETOUR: Make a double left at the signalized intersection.
  • Tuesday, July 9 until Friday, July 12. Nightly 9 p.m. to 5 a.m. Turnaround closure of the westbound frontage road at US 281 for bridge span work. DETOUR: Make a double left at the signalized intersection.
  • Saturday, July 13 until Monday, July 15. Full weekend closure 3 a.m. to 5 a.m. Full eastbound mainlane closure of the US 281 north exit ramp to the Redland Road entrance ramp for bridge span work. DETOUR: Use the US 281 north exit ramp through the US 281 and Gold Canyon Road intersections, use the Gold Canyon Road entrance ramp.
  • Saturday, July 13 until Monday, July 15. Full weekend closure 3 a.m. to 5 a.m. Full westbound mainlane closure from the north exit ramp to the US 281 entrance ramp for bridge span work. DETOUR: Use the north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Saturday, July 13 until Monday, July 15. Full weekend closure 3 a.m. to 5 a.m. Full westbound frontage road closure at US 281 for bridge span work. DETOUR: Take the west to eastbound turnaround at US 281 through the Gold Canyon Road intersection, use the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
Loop 1604 – Northwest San Antonio
  • Sunday, July 7 until Friday, July 12. Nightly 9 p.m. until 5 a.m. Alternating frontage road lanes in both directions between Golden Corral and Discount Tire for pavement markings and striping work.
  • Monday, July 8 until Friday, July 12. Nightly 9 p.m. until 5 a.m. Eastbound right mainlane & eastbound left frontage road lane between SH 16 (Bandera Road) and Hausman Road (including Bandera entrance ramp & Hausman exit ramp) for barrier placement work.
Loop 1604 – Northeast San Antonio
  • Monday, July 8 until Tuesday, July 9. 9 p.m. until 5 a.m. Eastbound right mainlane & eastbound left frontage road lane between Redland Road and Bulverde Road for barrier work setting up the permanent closure of entrance ramp just past Redland (it will be converted to an exit ramp).
  • Monday, July 8 until Tuesday, July 9. 9 p.m. until 5 a.m. Full eastbound mainlane closure at FM 2252 (Nacagdoches Road) for brick deck placement work. DETOUR: Traffic diverted to the frontage road.
US 281 – North Central San Antonio
  • Monday, July 8 until Tuesday, July 9. 12 a.m. to 2 a.m. Southbound right mainlane from Stone Oak Parkway to Evans Road for safety enhancements.
  • Tuesday, July 9 until Friday, July 12. Nightly 9 p.m. to 5 a.m. Full northbound closure from the Frontage Road exit ramp to the Sonterra Boulevard entrance ramp for bridge span work. DETOUR: Take the Frontage Road exit ramp, continue through the Loop 1604 intersection and take the Sonterra Boulevard entrance ramp.
  • Tuesday, July 9 until Friday, July 12. Nightly 9 p.m. to 5 a.m. Full southbound closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for bridge span work. DETOUR: Take the Sonterra Boulevard exit ramp, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Tuesday, July 9 until Friday, July 12. Nightly 9 p.m. to 5 a.m. Full northbound frontage road closure at Loop 1604 for bridge span work. DETOUR: Take the Frontage Road exit ramp, turn right on the Loop 1604 eastbound frontage road, use the turnaround at Gold Canyon Road and take a right on the US 281 northbound frontage road. If going west: drive along the eastbound frontage road through the Gold Canyon Road intersection and use the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Tuesday, July 9 until Friday, July 12. Nightly 9 p.m. to 5 a.m. Full northbound frontage road closure from the Loop 1604 westbound frontage road to Sonterra Boulevard to work on bridge caps. DETOUR: On the Loop 1604 westbound frontage road, turn left on the US 281 southbound frontage road, take the turnaround at Donella Drive and use the US 281 Donella Drive entrance ramp.
  • Tuesday, July 9 until Friday, July 12. Nightly 9 p.m. to 5 a.m. Full southbound frontage road closure at Loop 1604 for bridge span work. DETOUR: Take a right on the Loop 1604 westbound frontage road, take the turnaround at Stone Oak Parkway and turn right on the US 281 southbound frontage road.
  • Tuesday, July 9 until Friday, July 12. Nightly 9 p.m. to 5 a.m. Alternating northbound lane closure from Loop 1604 to Marshall Road for roadwork.
  • Tuesday, July 9 until Friday, July 12. Nightly 9 p.m. to 5 a.m. Full northbound to westbound direct connector ramp closure for bridge span work. DETOUR: Take the Frontage Road exit ramp, turn left on the Loop 1604 westbound frontage road and use the US 281 entrance ramp.
  • Tuesday, July 9 until Friday, July 12. Nightly 9 p.m. to 5 a.m. One of two northbound to westbound lanes at Evans Road for striping work.
  • Tuesday, July 9 until Friday, July 12. Nightly 9 p.m. to 5 a.m. One of two southbound to eastbound lanes at Evans Road for striping work.
  • Tuesday, July 9 until Friday, July 12. Nightly 9 p.m. to 5 a.m. Alternating southbound lane closure from Marshall Road to Loop 1604 for roadwork.
  • Tuesday, July 9 until Friday, July 12. Nightly 9 p.m. to 5 a.m. Turnaround closed on the southbound frontage road, southbound to northbound turnaround at Loop 1604 for bridge span work. DETOUR: Take a double left at the signalized intersection.
  • Tuesday, July 9 until Friday, July 12. Nightly 9 p.m. to 5 a.m. Alternating eastbound lane closure at Evans Road west of US 281 for striping.
  • Tuesday, July 9 until Friday, July 12. Nightly 9 p.m. to 5 a.m. Alternating eastbound lane closure at Evans Road east of US 281 for striping.
  • Tuesday, July 9 until Friday, July 12. Nightly 9 p.m. to 5 a.m. Alternating westbound lane closure at Evans Road west of US 281 for striping.
  • Tuesday, July 9 until Friday, July 12. Nightly 9 p.m. to 5 a.m. Alternating westbound lane closure at Evans Road east of US 281 for striping.
  • Saturday, July 13 until Monday, July 15. Full weekend closure 3 a.m. to 5 a.m. Full northbound closure from the Frontage Road exit ramp to the Sonterra Boulevard entrance ramp for bridge span work. DETOUR: take the Frontage Road exit ramp, continue through the Loop 1604 intersection and take the Sonterra Boulevard entrance ramp.
  • Saturday, July 13 until Monday, July 15. Full weekend closure 3 a.m. to 5 a.m. Full southbound closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for bridge span work. DETOUR: Take the Sonterra Boulevard exit ramp, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Saturday, July 13 until Monday, July 15. Full weekend closure 3 a.m. to 5 a.m. Full northbound frontage road closure at Loop 1604 for bridge span work. DETOUR: Take the Frontage Road exit ramp, turn right on the Loop 1604 eastbound frontage road, use the turnaround at Gold Canyon Road and take a right on the US 281 northbound frontage road. If going west: drive along the eastbound frontage road through the Gold Canyon Road intersection and use the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Saturday, July 13 until Monday, July 15. Full weekend closure 3 a.m. to 5 a.m. Full northbound frontage road closure from the Loop 1604 westbound frontage road to Sonterra Boulevard to work on bridge caps. DETOUR: On the Loop 1604 westbound frontage road, turn left on the US 281 southbound frontage road, take the turnaround at Donella Drive and use the US 281 Donella Drive entrance ramp.
  • Saturday, July 13 until Monday, July 15. Weekend closure 3 a.m. to 5 a.m. Full southbound frontage road closure at Loop 1604 for bridge span work. DETOUR: take a right on the Loop 1604 westbound frontage road, take the turnaround at Stone Oak Parkway and turn right on the US 281 southbound frontage road.
  • Saturday, July 13 until Monday, July 15. Weekend closure 3 a.m. to 5 a.m. Right/center southbound lane closure from Evans Road to Encino Rio for sound wall work.
I-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County
  • Sunday, July 7 until Friday, July 12. Nightly 9 p.m. until 5 a.m. Alternating mainlanes in both directions between Scenic Loop Road and SH 46 for replacing buttons/reflectors.
  • Monday, July 8 until Wednesday, July 10. Nightly 9 p.m. until 5 a.m. Westbound right mainlane from Camp Bullis Road to La Cantera Parkway for pavement marking work.
I-10 – Far East San Antonio/Bexar County/Guadalupe County
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Current until further notice. Eastbound Ackerman Road exit ramp will be closed through the summer. DETOUR: Eastbound I-10 and southbound I-410 traffic wishing to access Ackerman Road must take southbound I-410, exit at FM 1346/E. Houston St., turn around, and take the northbound frontage road to Ackerman Road.
  • Monday, July 8 until Tuesday, July 9. 9 p.m. until 5 a.m. Ackerman Road under the I-10 mainlanes as crews demolish the old eastbound mainlane bridge. DETOURS: Southbound Ackerman Road traffic will take the westbound I-10 frontage road to WW White Boulevard, turn around, and use the Ackerman detour via FM 1346/E. Houston St. described above. Northbound Ackerman Road traffic will take the eastbound frontage road to the turnaround at Foster Road and return to Ackerman Road on the westbound frontage road.
I-35 – Northeast San Antonio & Comal County
  • Monday, July 8 until Saturday, July 13. Nightly 8 p.m. until 6 a.m. Alternating frontage road lanes in both directions at FM 1103 (Exit 178) for paving work.
  • Monday, July 8. 9 a.m. until 12 noon. Frontage roads in both directions at FM 1103 for traffic signal work.
I-35 – Bexar County/Southern Region
  • Tuesday, July 9 until Thursday, July 11. Daily 9 a.m. until 4 p.m. Northbound right mainlane at Medina River (mile markers 142-143) for barrier placement work.
I-410 – West San Antonio
  • Monday, July 8 until Friday, July 12. Daily 9 a.m. to 3 p.m. One southbound frontage road lane between Demya Drive and Bertetti Drive for staging equipment.
  • Monday, July 8 until Friday, July 12. Daily 9 a.m. to 3 p.m. One northbound frontage road lane between Bronco Lane and Latigo Drive for staging equipment.
US 90 – West San Antonio
  • Monday, July 8 until Friday, July 12. Daily 9 a.m. to 3 p.m. The westbound right lane between I-410 and Hunt Lane for traffic rail foundation work.
  • Monday, July 8 until Friday, July 12. Nightly 8 p.m. to 5 a.m. All westbound frontage road lanes between I-410 and Hunt Lane for concrete barrier work. The I-410 southbound frontage road ramp to US 90 will also be closed. DETOUR: Traffic will be detoured to the south and eastbound clover leafs and continue on US 90 eastbound to the turnaround at Military Drive to access westbound US 90.
SH 151 – Far West San Antonio
  • Monday, July 8 until Friday, July 12. Nightly 9 p.m. to 5 a.m. The intersections between Wiseman Boulevard and Hunt Lane for mill and inlay work. Ramps will be closed as needed.
PA 1502 – Wurzbach Parkway
  • City of San Antonio closure for Hardberger Park Landbridge project. Monday, July 8 until Friday, July 12. Daily 9 a.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
  • City of San Antonio closure for Hardberger Park Landbridge project. Saturday, July 13. 7 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
FM 1535 – NW Military Highway
  • Monday, July 8 until Tuesday, July 9. 9 p.m. until 5 a.m. Alternating lanes in both directions at Loop 1604 for traffic signal work.
Spur 371 – General Hudnell Drive
  • Tuesday, June 9 until Friday, June 12. Daily 9 a.m. to 5 p.m. The left lane in both directions between Billy Mitchell Boulevard to Cupples Road for removing existing guardrail and installing concrete barrier.
FM 1976 – Walzem Road
  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes from Woodlake Parkway until Gibbs Sprawl Road for barrier work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
Loop 13 – WW White Road/West Military Drive
  • Monday, July 8 until Friday, July 12. Daily 9 a.m. until 4 p.m. Right lane in both directions from Springfield Road to Seale Road for sidewalk and driveway work.
SH 16 – Bandera Road
  • Sunday, July 7 until Friday, July 12. Nightly 9 p.m. until 5 a.m. Alternating lanes in both directions from Quincy Lee to Legend Trail for pavement marking and striping work.
SH 46 – Boerne/Kendall County
  • Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).