Friday, August 30

UPCOMING SCHEDULED CLOSURES -- NONE OVER LABOR DAY WEEKEND

Loop 1604 – North Central San Antonio
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure of the US 281 north exit ramp to the Redland Road entrance ramp for bridge span work. DETOUR: Use the US 281 north exit ramp through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for bridge span work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 Entrance Ramp.
  • Friday, September 6 until Monday, September 9. Full weekend closure 9 p.m. until 5 a.m. Full westbound frontage road closure from Gold Canyon Road to the US 281 northbound frontage road for utility work. DETOUR: Take a double left at Gold Canyon Road, take a double left at Redland Road, use the Redland Road entrance ramp, take the Stone Oak Parkway exit ramp, use the turnaround at Stone Oak Parkway.
  • Saturday, September 7 until Monday, September 9. Full weekend closure 2 a.m. until 5 a.m. Full eastbound mainlane closure of the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Saturday, September 7 until Monday, September 9. Full weekend closure 2 a.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 Entrance Ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
Loop 1604 – Northeast San Antonio
  • Tuesday, September 3 until Saturday, September 14 (excluding Sundays). Daily 8 a.m. until 4 p.m. Westbound left frontage road lane between Redland Road and Bulverde Road for truck/material access.
Loop 1604 – Northwest San Antonio
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Eastbound frontage road from SH 16 (Bandera Road) to Roger’s Ranch Road for pavement marking installation work.
  • Tuesday, September 3 until Friday, September 6. Daily 9 a.m. until 5 p.m. Eastbound frontage road from SH 16 (Bandera Road) to Roger’s Ranch Road for riprap and mow strip work.
Loop 1604 – West San Antonio
  • Tuesday, September 3 until Saturday, September 7. Daily 9 a.m. to 3 p.m. Alternating northbound frontage road between south of US 90 to just south of FM 1957 (Potranco Road) for closeout item work.
  • Tuesday, September 3 until Saturday, September 7. Daily 9 a.m. to 3 p.m. Alternating northbound mainlanes between south of US 90 to just south of FM 1957 (Potranco Road) for closeout item work.
  • Tuesday, September 3 until Saturday, September 7. Daily 9 a.m. to 3 p.m. Alternating southbound mainlanes between south of FM 1957 (Potranco Road) to just south of US 90 for closeout item, sidewalk, curb, mow strip and rip rap work.
  • Tuesday, September 3 until Saturday, September 7. Daily 9 a.m. to 5 p.m. The northbound Wiseman Boulevard exit ramp for beam curb work.
  • Tuesday, September 3 until Saturday, September 7. Daily 9 a.m. to 7 p.m. Alternating northbound frontage road lanes between south of FM 1957 (Potranco Road) to SH 151 for driveway and sign work.
  • Tuesday, September 3 until Saturday, September 7. Daily 9 a.m. to 7 p.m. Alternating southbound frontage road lanes between SH 151 to south of FM 1957 (Potranco Road) for driveway and sign work.
  • Tuesday, September 3 until Saturday, September 7. Nightly 7 p.m. to 5 a.m. Alternating northbound frontage road lanes between SH 151 to south of FM 1957 (Potranco Road) for milling and paving work.
  • Tuesday, September 3 until Saturday, September 7. Nightly 7 p.m. to 5 a.m. Alternating lanes in both directions at FM 1957 (Potranco Road), Military Drive and Wiseman Boulevard for milling and final pavement work.
US 281 – North Central San Antonio
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Full northbound mainlane closure from the Frontage Road exit ramp to the Sonterra Boulevard entrance ramp for direct connector work. DETOUR: Take the Frontage Road exit ramp, continue on the US 281 northbound frontage road through the Loop 1604 intersections and and use the Sonterra Boulevard entrance ramp.
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the Southbound Frontage Road through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Marshall Road for utility work and safety enhancements.
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for bridge, PCP, retaining wall work and safety enhancements.
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure of one of two left turn lanes at Evans Road for utility work.
  • Saturday, September 7 until Monday, September 9. Weekend continuous 2 a.m. until 5 a.m. Full northbound mainlane closure from the Frontage Road exit ramp to the Sonterra Boulevard entrance ramp for direct beam work. DETOUR: Take the Frontage Road exit ramp, if heading north on US 281, take a right on the Loop 1604 eastbound frontage road, use the turnaround at Gold Canyon Road and take a right at the Northbound Frontage Road. If heading west on the Eastbound Frontage Road, go through the Gold Canyon Road intersection, use the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Saturday, September 7 until Monday, September 9. Weekend continuous 2 a.m. until 5 a.m. Full northbound mainlane closure from the Frontage Road exit ramp to the Sonterra Boulevard entrance ramp for direct beam work. DETOUR: Take the Frontage Road exit ramp, continue on the US 281 Northbound Frontage Road through the Loop 1604 intersections and use the Sonterra Boulevard entrance ramp.
  • Saturday, September 7 until Monday, September 9. Weekend continuous 2 a.m. until 5 a.m. Full northbound frontage road closure from the Loop 1604 westbound frontage road to Sonterra Boulevard for beam work. DETOUR: On the Loop 1604 westbound frontage road, turn left on the US 281 Southbound Frontage Road, take the turnaround at Donella Drive and use the US 281 Donella Drive entrance ramp.
I-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County
  • Tuesday, September 3 until Thursday, September 5. Nightly 9 p.m. until 6 a.m. One frontage road lane in both directions at Balcones Creek for barrier setting work.
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Alternating mainlanes in both directions from SH 46 to Scenic Loop Road for barrier placement and pavement marking work in preparation for traffic switch.
I-10 – Far East San Antonio/Bexar County/Guadalupe County
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Current until further notice. Eastbound Ackerman Road exit ramp will be closed through the summer. DETOUR: Eastbound I-10 and southbound I-410 traffic wishing to access Ackerman Road must take southbound I-410, exit at FM 1346/E. Houston St., turn around and take the northbound frontage road to Ackerman Road.
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Left eastbound mainlane from Rosillo Creek bridge to Woodlake Parkway for concrete truck access and drainage work.
  • Wednesday, September 4 until Thursday, September 5. 7:30 a.m. until 7 p.m. Alternating eastbound mainlanes from SH 130 to US 183 for asphalt work.
  • Monday, September 9 until Wednesday, September 11. Nightly 7 p.m. until 5 a.m. Ackerman Road will be closed in both directions under I-10 for concrete beam placement. DETOUR: Northbound Ackerman Road traffic will take the I-10 eastbound frontage road to Foster Road, turn around, and take the I-10 westbound frontage road back to Ackerman Road. Southbound Ackerman Road traffic will take the I-10 westbound entrance ramp just west of Ackerman, stay in the right lane, take the I-410 South connecting ramp, travel southbound on I-410, exit to FM 1346/E. Houston St., turn around, and take the northbound frontage road back to Ackerman Road.
  • Monday, September 9 until Friday, September 27. Daily 7 a.m. until 5 p.m. Woodlake Parkway will be closed at the I-10 westbound frontage road. DETOUR: Traffic wishing to access the Horizon Pointe subdivision will continue traveling on the westbound frontage road, turn right on Foster Road, and take another right on Sierra Sunset to return to Woodlake Parkway.
I-10 – Central San Antonio
  • Tuesday, September 3 until Friday, September 6. Nightly 8:30 p.m. until 5 a.m. Westbound left mainlane at I-37 (including I-37 southbound ramp) for guard fence installation work.
I-35 – Northeast San Antonio & Comal County
  • Tuesday, September 3 until Saturday, September 7. Daily 9 a.m. until 3 p.m. Right frontage road lane in both directions between Austin Street and New Braunfels Avenue for sidewalk and driveway work.
  • Tuesday, September 3 until Wednesday, September 4. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlanes between Schwab Road and FM 1103 for barrier installation work.
  • Wednesday, September 4 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Alternating northbound frontage road lanes between FM 1103 and Schwab Road for barrier installation work.
  • Friday, September 6 until Saturday, September 7. 9 p.m. until 5 a.m. Alternating southbound frontage road lanes between Schwab Road and FM 1103 for barrier installation work.
I-410 – West San Antonio
  • Tuesday, September 3 until Thursday, September 5. Daily 9 a.m. to 3 p.m. The left eastbound frontage road between Ray Ellison Drive to I-410 to set equipment for work under the connector.
  • Tuesday, September 3 until Saturday, September 7. Daily 8 a.m. to 7 p.m. The left westbound mainlane between just east of Loop 1604 to just west of US 90 for mowstrip work.
  • Tuesday, September 3 until Saturday, September 7. Daily 9 a.m. to 3 p.m. Alternating eastbound frontage road between west of Loop 1604 to east of Loop 1604 island ramp work.
  • Tuesday, September 3 until Friday, September 6. Nightly 8 p.m. to 5 a.m. All westbound mainlanes between I-410 to Hunt Lane for rail and single slope concrete barrier work. DETOUR: Traffic will continue on the frontage road to access the next entrance ramp.
US 90 – West San Antonio
  • Tuesday, September 3 until Thursday, September 5. Daily 9 a.m. to 3 p.m. The left eastbound frontage road between Ray Ellison Drive to I-410 to set equipment for work under the connector.
  • Tuesday, September 3 until Saturday, September 7. Daily 8 a.m. to 7 p.m. The left westbound mainlane between just east of Loop 1604 to just west of US 90 for mowstrip work.
  • Tuesday, September 3 until Saturday, September 7. Daily 9 a.m. to 3 p.m. Alternating eastbound frontage road between west of Loop 1604 to east of Loop 1604 island ramp work.
  • Tuesday, September 3 until Friday, September 6. Nightly 8 p.m. to 5 a.m. All westbound mainlanes between I-410 to Hunt Lane for rail and single slope concrete barrier work. DETOUR: Traffic will continue on the frontage road to access the next entrance ramp.
  • Tuesday, September 3 until Saturday, September 7. Daily 9 a.m. until 3 p.m. Eastbound right frontage road lane from Springvale Drive to West Military Road for sidewalk and driveway work.
PA 1502 – Wurzbach Parkway
  • City of San Antonio closure for Hardberger Park Landbridge project. Monday, September 2 until Friday, September 6. Daily 9 a.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
  • City of San Antonio closure for Hardberger Park Landbridge project. Saturday, September 7. 7 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
FM 1560 – Hausman Road
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Eastbound left lane from SH 16 to Loop 1604 for utility work.
Spur 371 – General Hudnell Drive
  • Tuesday, September 3 until Friday, September 6. Daily 7 a.m. to 3 p.m. The northbound left lane between Billy Mitchell Boulevard and Cupples Road for removing existing guardrail and installing concrete barrier.
  • Tuesday, September 3 until Friday, September 6. Daily 9 a.m. to 5 p.m. The southbound left lane between Billy Mitchell Boulevard and Cupples Road for removing existing guardrail and installing concrete barrier.
Loop 13 – WW White Road
  • Tuesday, September 3 until Saturday, September 7. Daily 9 a.m. until 4 p.m. Northbound right lane from Emil Road to Springfield Road for sidewalk and driveway work.
FM 1976 – Walzem Road
  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes from Woodlake Parkway until Gibbs Sprawl Road for barrier work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
SH 46 – Boerne/Kendall County
  • Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
I-37 – Atascosa County
  • Current until 10 p.m. Saturday, August 31. Alternating northbound mainlanes from Mile Marker 108 to Mile Marker 117 for paving work.
Other Roads – Bexar County
  • Wednesday, September 4 until Friday, September 6. Nightly 9 p.m. until 5 a.m. All lanes in both directions of Wilderness Parkway at US 281 for restriping work.
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Alternating eastbound crossing closure East of US 281 for traffic phasing.
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Alternating westbound crossing closure East of US 281 for traffic phasing.

Friday, August 23

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North Central San Antonio
  • Monday, August 26 until Friday, August 30. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure of the US 281 northbound exit ramp to the Redland Road entrance ramp for bridge span work. DETOUR: Use the US 281 northbound exit ramp through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Monday, August 26 until Friday, August 30. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure from the US 281 northbound exit ramp to the US 281 Entrance Ramp for bridge span work. DETOUR: Use the US 281 northbound exit ramp, continue through the US 281 intersection and use the US 281 Entrance Ramp.
Loop 1604 – Northeast San Antonio
  • Monday, August 26 until Thursday, August 29. Daily 8 a.m. until 4 p.m. Westbound frontage road left lane between Redland Road and Bulverde Road for truck/material access.
  • Current until 9 a.m. Saturday, Full eastbound mainlane closure at FM 2252 (Nacagdoches Road) for barrier removal work and guard fence and rail installation work.
  • Sunday, August 25 until Friday, August 30. Nightly 9 p.m. to 5 a.m. The right mainlane in both directions between Lakeview Parkway to FM 2252 (Nacogdoches Road) for pavement bore work.
  • Sunday, August 25 until Friday, August 30. Nightly 9 p.m. to 5 a.m. Alternating mainlanes in both directions between I-35 to FM 2252 (Nacogdoches Road) for pavement bore work.
  • Monday, August 26 until Wednesday, August 28. Nightly 9 p.m. until 5 a.m. Left mainlane in both directions from Kitty Hawk to Palisades for barrier resetting work.
Loop 1604 – West San Antonio
  • Sunday, August 25 until Thursday, August 29. Nightly 7 p.m. to 5 a.m. Alternating northbound frontage road lanes between SH 151 to south of FM 1957 (Potranco Road) for milling and paving work.
  • Sunday, August 25 until Thursday, August 29. Nightly 7 p.m. to 5 a.m. Alternating lanes in both directions at FM 1957 (Potranco Road), Military Drive, and Wiseman Boulevard for milling and final pavement work.
  • Monday, August 26 until Friday, August 30. Daily 9 a.m. to 5 p.m. Alternating lanes in both directions at FM 1957 (Potranco Road), Military Drive, and Wiseman Boulevard for sign and curb/directional island work.
  • Monday, August 26 until Thursday, August 30. Daily 9 a.m. to 5 p.m. The northbound Wiseman Boulevard exit ramp for beam curb work.
  • Monday, August 26 until Friday, August 30. Daily 9 a.m. to 5 p.m. Alternating northbound frontage road lanes between south of FM 1957 (Potranco Road) to SH 151 for driveway and curb work.
  • Monday, August 26 until Friday, August 30. Daily 9 a.m. to 5 p.m. Alternating southbound frontage road lanes between SH 151 to south of FM 1957 (Potranco Road) for final paving and rip rap work.
US 281 – North Central San Antonio
  • Friday, August 23 until Sunday, August 25. Full weekend closure 9 p.m. until 5 a.m. Full northbound frontage road closure from the Loop 1604 westbound frontage road to Sonterra Boulevard for bridge cap work. DETOUR: On the Loop 1604 westbound frontage road, turn left on the US 281 Southbound Frontage Road, take the turnaround at Donella Drive and use the US 281 Donella Drive entrance ramp.
  • Friday, August 23 until Monday, August 26. Full weekend closure 9 p.m. until 5 a.m. Alternating northbound mainlane closure of one of two left turn lanes at Evans Road for phasing work.
  • Friday, August 23 until Monday, August 26. Full weekend closure 9 p.m. until 5 a.m. Alternating southbound mainlane closure at Evans Road for phasing work.
  • Monday, August 26 until Friday, August 30. Nightly 9 p.m. until 5 a.m. Full northbound mainlane closure from the Frontage Road exit ramp to the Sonterra Boulevard entrance ramp for direct connector work. DETOUR: Take the Frontage Road exit ramp, if heading north on US 281, take a right on the Loop 1604 Eastbound Frontage Road, use the turnaround at Gold Canyon Road and take a right at the Northbound Frontage Road. If heading west on the Eastbound Frontage Road, go through the Gold Canyon Road intersection, use the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Monday, August 26 until Friday, August 30. Nightly 9 p.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound frontage road through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Monday, August 26 until Friday, August 30. Nightly 9 p.m. until 5 a.m. Full northbound frontage road closure from the Loop 1604 westbound frontage road to Sonterra Boulevard for bridge cap work. DETOUR: On the Loop 1604 westbound frontage road, turn left on the US 281 southbound frontage road, take the turnaround at Donella Drive and use the US 281 Donella Drive entrance ramp.
  • Monday, August 26 until Friday, August 30. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Marshall Road for utility work and safety enhancements.
  • Monday, August 26 until Friday, August 30. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for bridge, PCP, retaining wall work and safety enhancements.
US 281 – Southern Region
  • Sunday, August 25 until Thursday, August 29. Nightly 8 p.m. to 5 a.m. Alternating northbound lanes 0.25 miles south and 0.25 north of Mission Del Lago for concrete barrier work
I-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County
  • Sunday, August 25 until Friday, August 30. Nightly 9 p.m. until 5 a.m. Alternating mainlanes in both directions between Scenic Loop and SH 46 for barrier resetting and pavement marking work.
  • Sunday, August 25 until Friday, August 30. Nightly 9 p.m. until 5 a.m. Full mainlane closure in both directions between Fair Oaks Parkway and Old Fredericksburg Road (exits 546-548, including entrance/exit ramps) for milling and paving work.
  • Sunday, August 25 until Friday, August 30. Nightly 9 p.m. until 6 a.m. Eastbound right mainlane from Scenic Loop to Balcones Creek Road (including Boerne Stage entrance ramp) for milling and paving work.
I-10 – Far East San Antonio/Bexar County/Guadalupe County
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Current until further notice. Eastbound Ackerman Road exit ramp will be closed through the summer. DETOUR: Eastbound I-10 and southbound I-410 traffic wishing to access Ackerman Road must take southbound I-410, exit at FM 1346/E. Houston St., turn around, and take the northbound frontage road to Ackerman Road.
  • Monday, August 26 until Friday, August 30. Nightly/daily 9 p.m. to 5 a.m. Left eastbound frontage road lane from Rosillo Creek to Foster Road for traffic barrier placement.
I-10 – Central San Antonio
  • Sunday, August 25 until Wednesday, August 28. Nightly 8:30 p.m. until 5 a.m. Westbound left mainlane at I-37 (including I-37 southbound ramp) for guard fence installation work.
I-35 – Northeast San Antonio & Comal County
  • Current until Friday, August 30. Nightly 9 p.m. to 5 a.m. Left mainlane in both directions between Walters Street just north of FM 1103 for pavement bore work.
  • Monday, August 26 until Friday, August 30. Daily 9 a.m. until 3 p.m. Right frontage road lane in both directions between Austin Street and New Braunfels Avenue for sidewalk and driveway work.
  • Sunday, August 25 until Monday, August 26. 9 p.m. until 5 a.m. Right mainlane in both directions between Walters Street and I-410 for pavement bore work.
  • Sunday, August 25 until Thursday, August 29. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlanes between Schwab Road and FM 1103 for barrier installation work.
  • Sunday, August 25 until Friday, August 30. Nightly 9 p.m. to 5 a.m. Left mainlane shoulder and alternating frontage road lanes in both directions between Walters Street to just north of FM 1103 for pavement bore work.
  • Wednesday, August 28 until Friday, August 30. Nightly 8:30 p.m. until 5 a.m. Northbound left mainlane at I-10 (including US 90 westbound exit ramp) for guard fence installation work.
I-410 – West San Antonio
  • Friday, August 23 until Saturday, August 24. Nightly 8 p.m. to 5 a.m. All northbound mainlanes between US 90 exit ramp to SH 151 restriping the mainlanes, open the new Marbach Road ramp, and ramp reversal on the SH 151 on and off ramp. DETOUR: All traffic will be detoured the northbound frontage road to access the next on-ramp.
  • Saturday, August 24 until Monday, August 26. Nightly 8 p.m. to 5 a.m. All southbound mainlanes between Lakeside exit ramp to US 90 bridge for traffic switch. The Marbach Road, US 90 exit ramp and south/westbound connector ramp will also be closed. DETOUR: All traffic will be detoured to continue on the southbound frontage road to Valley Hi Drive.
  • Sunday, August 25 until Tuesday, August 27. Nightly 8 p.m. to 5 a.m. The left northbound mainlane between US 90 exit ramp to SH 151 entrance ramp for staging equipment and mill asphalt.
  • Sunday, August 25 until Tuesday, August 27. Nightly 8 p.m. to 5 a.m. The left southbound mainlane between Lakeside exit ramp to US 90 bridge at I-410 for staging equipment and mill asphalt work.
  • Monday, August 26 until Thursday, August 29. Daily 9 a.m. to 3 p.m. The right northbound frontage road lane between Meadow Leaf to Meadow Glade Drive for staging equipment and sidewalk work.
  • Monday, August 26 until Thursday, August 29. Daily 9 a.m. to 3 p.m. The left southbound frontage road lane between Waters Edge to Marbach Road for staging equipment and ditch work.
I-410 – Northeast San Antonio
  • Sunday, August 25 until Friday, August 30. Nightly 9 p.m. to 5 a.m. The left frontage road lane in both directions between Wehman Drive to Nacogdoches Road for pavement bore work.
  • Sunday, August 25 until Friday, August 30. Nightly 9 p.m. to 5 a.m. The right mainlane in both directions between Wehman Drive to Nacogdoches Road for pavement bore work.
PA 1502 – Wurzbach Parkway
  • City of San Antonio closure for Hardberger Park Landbridge project. Monday, August 26 until Friday, August 30. Daily 9 a.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
  • City of San Antonio closure for Hardberger Park Landbridge project. Saturday, August 31. 7 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
SH 218 – Pat Booker Road
  • Wednesday, August 28 until Friday, August 30. Nightly 9 p.m. until 5 a.m. Full westbound closure at Loop 1604 for bridge work.
Spur 371 – General Hudnell Drive
  • Monday, August 26 until Thursday, August 29. Daily 7 a.m. to 3 p.m. The northbound left lane between Billy Mitchell Boulevard and Cupples Road for removing existing guardrail and installing concrete barrier.
  • Monday, August 26 until Thursday, August 29. Daily 9 a.m. to 5 p.m. The southbound left lane between Billy Mitchell Boulevard and Cupples Road for removing existing guardrail and installing concrete barrier.
Loop 13 – WW White Road
  • Current until 5 a.m. Saturday, August 24. Southbound left lane at Martin Luther King Boulevard for sidewalk and driveway work.
FM 1976 – Walzem Road
  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes from Woodlake Parkway until Gibbs Sprawl Road for barrier work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
SH 46 – Boerne/Kendall County
  • Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
  • Monday, August 26 until Friday, August 30. Daily 7 a.m. until 7 p.m. Intersections with Copper Creek, Herff Ranch and Charger for reconstruction and paving. Work will be performed on the side roads so traffic on SH 46 should not be impacted.
I-37 – Atascosa County
  • Current until Saturday, August 31. Daily 6 a.m. until 10 p.m. Alternating northbound mainlanes from Mile Marker 108 to Mile Marker 117 for paving work.
SH 16 – Atascosa/McMullen County
  • Current until Friday, August 30. Daily 5:30 a.m. until 7 p.m. Alternating lanes in both directions from FM 1332 to the Atascosa/McMullen County line for milling and inlay, bridge rail and guard fence work.
  • Monday, August 26 until Friday, August 30. Daily 8 a.m. until 5 p.m. Alternating southbound lanes from Tilden to FM 624 (Mile Markers 686-696) for excavation work.
Other Roads – Bexar County
  • City of San Antonio project. Current until Friday, August 30. Daily 9 a.m. until 4 p.m. Southbound left lane of North Pecos Street at Buena Vista for sidewalk and curb work.
  • Current until Monday, August 26. Full weekend closure 9 p.m. until 5 a.m. Alternating eastbound crossing closure of Evans Road west of US 281 for intersection work.
  • Friday, August 23 until Monday, August 26. Full weekend closure 9 p.m. until 5 a.m. Alternating westbound crossing closure of Evans Road west of US 281 for intersection work.
  • Wednesday, August 28 until Friday, August 30. Nightly 9 p.m. until 5 a.m. All lanes in both directions of Wilderness Parkway at US 281 for restriping work.

I-410/US 90 Interchange Project: Traffic Switch & Ramp Work

New exit for SH 151 on I-410 northbound
For our peeps on San Antonio's West Side, listen up, this one's for you!

There will be quite a bit of construction activity taking place this weekend on the I-410/US 90 interchange project.

Friday night
Starting tonight (Friday 8/23) at 8 p.m., all northbound mainlanes between the US 90 exit ramp to SH 151 will be closed to restripe the northbound mainlanes and open up the new exit ramps for Marbach Road and SH 151.

A third frontage road lane will also open up for the exit and entrance ramps. Traffic will be detoured to the frontage road. The new configuration will be open to traffic tomorrow (Saturday 8/24) at 5 a.m.

Saturday night
Later that same day (Saturday) starting at 8 p.m. and running through Monday (8/26) morning at 5 a.m. all southbound mainlanes between the Lakeside exit ramp to the US 90 bridge will be closed to prepare for a traffic switch and to open up the new Marbach Road entrance ramp.
Crews working on the new southbound entrance ramp near Marbach Road


A look ahead
We are gradually approaching the last phase of this project (yay!) that is expected to be completed in 2020. We know, we know, that should prompt a round of applause for everyone!

But we're not quite there yet. We still have work at Marbach Road that includes demolishing the middle section of the current bridge.

Weather permitting, we are planning for the bridge to be demolished the weekend after Labor Day. Stay tuned here and on our social media channel for further updates on this project!

Wednesday, August 21

US 281 Phase I Expansion Project: Evans Road Traffic Switch Scheduled This Weekend


Important step taking place this weekend on the US 281 Phase I Expansion project!

We've been working on the reconstruction of Evans Road a bit a time. This weekend, our contractor (Webber) will be putting in place  traffic switch on the westbound side of the Evans & 281 intersection (see adjacent illustration).

As a result, both westbound and eastbound will be reduced to one lane in both directions at the 281 intersection. 

This is so crews can finish the intersection reconstruction process on the west side of the intersection.

The switch will start this Friday, August 23, at 9 p.m. and will be in place for the weekend, until  5 a.m. Monday, August 26. The goal is to have Evans fully reopened with two lanes in each direction by the Monday morning commute.

Intersection reconstruction can require multiple changes in traffic flow/configuration to ensure construction can be completed smoothly and -- most importantly -- safely for drivers and crews. We appreciate your patience during this switch.

As always, we remind you that any scheduled work is subject to change due to weather and other factors that could prompt a delay.

Tuesday, August 20

I-10 & SH 46 in Boerne: Retaining Wall Work Requires Turn Lane Change

Lots and lots of work going on in Boerne, we know!

As part of our project on I-10 improvements between Scenic Loop Road and SH 46, our contractor has begun working on the retaining wall at the I-10 & SH 46 intersection.

You may have noticed this has had an impact on the existing SH 46 bridge/overpass over I-10.
 itself. In order to safely conduct this retaining wall work, the contractor was required to remove the northbound SH 46 right lane, which in turn forced to take away the dedicated left-turn lane to get on the I-10 westbound frontage road (see map above). 

So the one open lane is being used both for left turns as well as for through-traffic continuing on SH 46 past I-10. The traffic light has been adjusted to reflect this traffic flow change. As you may expect, this necessary move will cause delays, as drivers waiting to go straight through will have to wait until those making the left turn clear out (these in turn have to yield to southbound SH 46 traffic coming the other way).

Friday, August 16

Hausman Road Expansion Project: Temporary Dedicated Left-Turn Lane Closure

Work progresses on the FM 1560 (Hausman Road) expansion project in Helotes,which goes from Loop 1604 to SH 16 (Bandera Road).

We hope you're enjoying the return of the dedicated right-turn lane from Hausman to Bandera. As part of continuing construction, the contractor will need to close the dedicated left- turn lane from Bandera to Hausman for approximately week starting Monday (August 19).

Don't worry, though! Drivers will still be able to make that left turn, keeping the protected left-turn traffic signal arrow. But for this week of work, the same lane will be used for going left as well as for those looking to continue straight across Bandera (see graphic below).

Rest assured that the contractor has taken every step to make this work as efficient and safe as possible. 

We believe it is in the best interest of the public to close, pave and open this lane now before the Northside Independent School District starts classes on August 26. 

Kuentz Elementary and Sandra Day O’Connor High School are just beyond this intersection and there would undoubtedly be long back-ups at drop-off and pick-up times if we were to wait and complete the work later as the original plans called.

That's why, just as we did with the dedicated right-turn lane issue (closure was originally supposed be permanent for the entire duration of the project) we're doing our best to prioritize mobility and minimize disruption. So we're changing the plan by moving up this work, the goal being to do our best to complete this phase before classes start. 

It probably doesn't feel like it to everyday commuters on Hausman, but this extremely complex projects (lots and lots of utility work underground must be worked out before major construction begins) is actually ahead of schedule.

That said, we do want folks out there to expect delays during peak hours during this period of about one week while the dedicated left-turn lane is closed, particularly on southbound Hausman.

As always, we appreciate everyone’s patience as our contractor continues to make significant progress and addresses necessary construction phases.

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North Central San Antonio
  • Saturday, August 17 until Sunday, August 18. Continuous 2 a.m. until 5 a.m. Full eastbound mainlane closure of the US 281 North exit ramp to the Redland Road entrance ramp for deck pour work. DETOUR: Use the US 281 North exit ramp through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Saturday, August 17 until Sunday, August 18. Continuous 2 a.m. until 5 a.m. Full westbound mainlane closure from the US 281 North exit ramp to the US 281 entrance ramp for overhang work. DETOUR: Use the US 281 North exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Sunday, August 18 until Friday, August 23. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure of the US 281 North Exit Ramp to the Redland Road entrance ramp for overhang work. DETOUR: Use the US 281 North exit ramp through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Sunday, August 18 until Friday, August 23. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure from the US 281 North Exit Ramp to the US 281 Entrance Ramp for overhang work. DETOUR: Use the US 281 North exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Saturday, August 24 until Monday, August 26. Continuous 3 a.m. until 5 a.m. Full eastbound mainlane closure of the US 281 North Exit Ramp to the Redland Road entrance ramp for deck pour work. DETOUR: Use the US 281 North exit ramp through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Saturday, August 24 until Monday, August 26. Continuous 3 a.m. until 5 a.m. Full westbound mainlane closure from the US 281 North Exit Ramp to the US 281 entrance ramp for overhang work. DETOUR: Use the US 281 North exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
Loop 1604 – Northwest San Antonio
  • Monday, August 19 until Friday, August 23. Nightly 9 p.m. until 5 a.m. One eastbound left mainlane from SH 16 (Bandera Road) to FM 1560 (Hausman Road) including Hausman exit ramp for barrier setting work.
  • Monday, August 19 until Thursday, August 22. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure between FM 2696 (Blanco Road) and Bitters Road including entrance ramps for barrier removal and illumination work.
  • Thursday, August 22 until Friday, August 23. 9 p.m. until 5 a.m. Full eastbound mainlane closure from NW Military Highway to FM 2696 (Blanco Road) for barrier removal work.
Loop 1604 – Northeast San Antonio
  • Current until 4 p.m. Saturday, August 17. Westbound frontage road left lane between Redland Road and Bulverde Road for truck/material access.
  • Current until 9 a.m. Saturday, August 17. Full westbound mainlane closure at FM 2252 (Nacagdoches Road) for barrier removal and placement work.
  • Monday, August 19 until Saturday, August 24. Westbound frontage road left lane between Redland Road and Bulverde Road for truck/material access.
  • Monday, August 12 until Friday, August 16. Daily 9 a.m. until 3 p.m. Alternating frontage road lanes in both directions at FM 2252 (Nacagdoches Road) for utility work.
  • Monday, August 19 & Tuesday, August 20. Daily 9 a.m. until 3 p.m. Alternating frontage road lanes in both directions at FM 2252 (Nacagdoches Road) for signage work.
  • Thursday, August 22. 9 a.m. until 3 p.m. Alternating frontage road lanes in both directions at FM 2252 (Nacagdoches Road) for signage work.
  • Friday, August 23 until Saturday, August 24. 9:30 p.m. until 9 a.m. Full eastbound mainlane closure at FM 2252 (Nacagdoches Road) for barrier removal work and guard fence and rail installation work.
Loop 1604 – West San Antonio
  • Sunday, August 18 until Sunday, August 25. Nightly 7 p.m. to 5 a.m. Alternating northbound frontage road lanes between SH 151 to south of FM 1957 (Potranco Road) for milling and paving work.
  • Sunday, August 18 until Sunday, August 25. Nightly 7 p.m. to 5 a.m. Alternating lanes in both directions at FM 1957 (Potranco Road), Military Drive, and Wiseman Boulevard for milling and final pavement work.
  • Monday, August 19 until Friday, August 23. Daily 9 a.m. to 5 p.m. Alternating lanes in both directions at FM 1957 (Potranco Road), Military Drive, and Wiseman Boulevard for sign and curb/directional island work.
  • Monday, August 19 until Friday, August 23. Daily 9 a.m. to 7 p.m. Alternating northbound frontage road lanes between south of FM 1957 (Potranco Road) to SH 151 for driveway and curb work.
  • Monday, August 19 until Friday, August 23. Daily 9 a.m. to 7 p.m. Alternating southbound frontage road lanes between SH 151 to south of FM 1957 (Potranco Road) for final paving and rip rap work.
  • Monday, August 19 until Thursday, August 29. Daily 9 a.m. to 3 p.m. Alternating northbound frontage road lanes south of US 90 to FM 1957 (Potranco Road) for punch list work.
  • Monday, August 19 until Thursday, August 29. Daily 9 a.m. to 3 p.m. Alternating southbound frontage road lanes south of US 90 to FM 1957 (Potranco Road) for punch list and mow strip work.
  • Monday, August 19 until Saturday, August 31. Daily 9 a.m. to 3 p.m. Alternating northbound mainlanes south of US 90 to FM 1957 (Potranco Road) for punch list and mow strip work.
  • Monday, August 19 until Saturday, August 31. Daily 9 a.m. to 3 p.m. Alternating northbound frontage road lanes south of US 90 to FM 1957 (Potranco Road) for sidewalk, curb, mowstrip and rip rap work.
US 281 – North Central San Antonio
  • Saturday, August 17 until Monday, August 19. Full weekend closure 3 a.m. until 5 a.m. Full northbound mainlane closure from the Frontage Road exit ramp to the Sonterra Boulevard entrance ramp for overhang work. DETOUR: Take the Frontage Road exit ramp, if heading north on US 281, take a right on the Loop 1604 Eastbound Frontage Road, use the turnaround at Gold Canyon Road and take a right at the northbound Frontage Road. If heading west on the eastbound Frontage Road, go through the Gold Canyon Road intersection, use the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Saturday, August 17 until Monday, August 19. Full weekend closure 3 a.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for overhang work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound Frontage Road through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Saturday, August 17 until Monday, August 19. Full weekend closure 3 a.m. until 5 a.m. Full northbound Frontage Road closure from the Loop 1604 Westbound Frontage Road to Sonterra Boulevard to work on bridge caps. DETOUR: On the Loop 1604 Westbound Frontage Road, turn left on the US 281 southbound Frontage Road, take the turnaround at Donella Drive and use the US 281 Donella Drive entrance ramp.
  • Sunday, August 18 until Friday, August 23. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Marshall Road for utility and safety enhancements.
  • Sunday, August 18 until Monday, August 19. 9 p.m. until 5 a.m. Southbound right mainlane between Overlook Parkway to Wilderness Oak for barrier setting work.
  • Monday, August 19 until Friday, August 23. Nightly 9 p.m. until 5 a.m. Full northbound mainlane closure from the Frontage Road exit ramp to the Sonterra Boulevard entrance ramp for overhang work. DETOUR: Take the Frontage Road exit ramp, if heading north on US 281, take a right on the Loop 1604 eastbound Frontage Road, use the turnaround at Gold Canyon Road and take a right at the Northbound Frontage Road. If heading west on the eastbound Frontage Road, go through the Gold Canyon Road intersection, use the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Monday, August 19 until Friday, August 23. Nightly 9 p.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for overhang work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the Southbound Frontage Road through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Monday, August 19 until Friday, August 23. Nightly 9 p.m. until 5 a.m. Full northbound Frontage Road closure from the Loop 1604 westbound Frontage Road to Sonterra Boulevard to work on bridge caps. DETOUR: On the Loop 1604 Westbound Frontage Road, turn left on the US 281 southbound Frontage Road, take the turnaround at Donella Drive and use the US 281 Donella Drive entrance ramp.
  • Monday, August 19 until Friday, August 23. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for bridge, retaining wall and safety enhancements.
  • Saturday, August 24 until Monday, August 26. Weekend continuous 3 a.m. until 5 a.m. Full northbound mainlane closure from the Frontage Road exit ramp to the Sonterra Boulevard entrance ramp for overhang work. DETOUR: Take the Frontage Road exit ramp, if heading north on US 281, take a right on the Loop 1604 eastbound Frontage Road, use the turnaround at Gold Canyon Road and take a right at the Northbound Frontage Road. If heading west on the eastbound Frontage Road, go through the Gold Canyon Road intersection, use the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Saturday, August 24 until Monday, August 26. Weekend continuous 3 a.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for overhang work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the Southbound frontage Road through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Saturday, August 24 until Monday, August 26. Weekend continuous 3 a.m. until 5 a.m. Full northbound frontage road closure from the Loop 1604 Westbound Frontage Road to Sonterra Boulevard to work on bridge caps. DETOUR: On the Loop 1604 westbound Frontage Road, turn left on the US 281 southbound Frontage Road, take the turnaround at Donella Drive and use the US 281 Donella Drive entrance ramp.
I-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County
  • Sunday, August 18 until Wednesday, August 21. Nightly 10 p.m. until 6 a.m. Right mainlane in both directions between Scenic Loop and Balcones Creek (including westbound Scenic Loop exit ramp) for paving work.
  • Sunday, August 19 until Friday, August 23. Nightly 9 p.m. until 5 a.m. Alternating mainlanes in both directions between Scenic Loop and SH 46 for barrier resetting and pavement marking work.
I-10 – Far East San Antonio/Bexar County/Guadalupe County
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Current until further notice. Eastbound Ackerman Road exit ramp will be closed through the summer. DETOUR: Eastbound I-10 and southbound I-410 traffic wishing to access Ackerman Road must take southbound I-410, exit at FM 1346/E. Houston St., turn around, and take the northbound frontage road to Ackerman Road.
  • Monday, August 19 until Thursday, August 22. Daily 7:30 a.m. until 7 p.m. Alternating mainlanes in both directions between SH 130 and US 183 for paving work.
I-10 – Central San Antonio
  • Sunday, August 18 until Tuesday, August 20. Nightly 8:30 p.m. until 5 a.m. Westbound left mainlane at I-37 (including I-37 southbound ramp) for guard fence installation work.
I-35 – Northeast San Antonio & Comal County
  • Current until 5 a.m. Saturday, August 17. Alternating southbound mainlanes from Schwab Road to FM 1103 for striping work.
  • Sunday, August 18 until Friday, August 30. Nightly 9 p.m. to 5 a.m. Left mainlane in both directions between Walters Street just north of FM 1103 for pavement bore work.
  • Monday, August 19 until Saturday, August 24. Daily 9 a.m. until 3 p.m. Right frontage road lane in both directions between Austin Street and New Braunfels Avenue for sidewalk and driveway work.
  • Sunday, August 25 until Monday, August 26. 9 p.m. until 5 a.m. Right mainlane in both directions between Walters Street and I-410 for pavement bore work.
I-410 – West San Antonio
  • Friday, August 16 until Monday, August 19. Nightly 8 p.m. to 5 a.m. All northbound mainlanes between US 90 exit ramp to SH 151 entrance ramp for traffic switch. DETOUR: All traffic will be detoured the northbound frontage road to access the mainlanes after Marbach Road.
  • Sunday, August 18 until Friday, August 23. Nightly 8 p.m. to 5 a.m. All southbound mainlanes between US 90 exit ramp to US 90 bridge at I-410 for rail and concrete barrier work.
  • Sunday, August 18 until Friday, August 23. Nightly 8 p.m. to 5 a.m. All northbound mainlanes and frontage road between US 90 exit ramp to SH 151 entrance ramp for concrete barrier and restripe the mainlanes. The US 90 exit ramp and Marbach on-ramp will also be closed. Mainlanes and frontage road will not be closed at the same time. DETOUR: Traffic will be detoured to the frontage road frontage road to SH 151.
  • Monday, August 19 until Friday, August 23. Daily 9 a.m. to 3 p.m. The left southbound frontage road between Waters Edge to Marbach Road for removing low profile concrete work.
  • Monday, August 19 until Friday, August 23. Daily 9 a.m. to 3 p.m. The right southbound frontage road between Waters Edge to Marbach Road for staging equipment and for driveway pour work.
  • Monday, August 19 until Friday, August 23. Daily 9 a.m. to 3 p.m. The left northbound frontage road between Marbach Road to Meadow Bend for removing low profile concrete work.
  • Friday, August 23 until Monday, August 26. Nightly 8 p.m. to 5 a.m. All southbound mainlanes between Lakeside exit ramp to US 90 bridge for traffic switch. The Marbach Road, US 90 exit ramp and south/westbound connector ramp will also be closed. DETOUR: All traffic will be detoured to continue on the southbound frontage road to Valley Hi Drive.
US 90 – West San Antonio
  • Sunday, August 18 until Friday, August 23. Nightly 8 p.m. to 5 a.m. All west frontage road lanes between I-410 to Hunt Lane for removing low profile concrete barrier work. The I-410 southbound frontage road ramp to US 90 westbound frontage road will also be closed. DETOUR: Traffic will be detoured to the south and eastbound cloverleafs; continue on US 90 eastbound to the turnaround at Military to access the westbound mainlanes.
  • Monday, August 19 until Friday, August 23. Daily 9 a.m. to 3 p.m. The left eastbound frontage road between Hunt Lane to I-410 for staging equipment.
  • Monday, August 19 until Friday, August 23. Daily 9 a.m. to 3 p.m. The left westbound frontage road lane between Tomar Drive and Hunt Lane for staging equipment.
  • Monday, August 19 until Saturday, August 31. Daily 9 a.m. to 3 p.m. The center eastbound frontage road lane between at the Loop 1604 intersection for island work.
PA 1502 – Wurzbach Parkway
  • City of San Antonio closure for Hardberger Park Landbridge project. Monday, August 19 until Friday, August 23. Daily 9 a.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
  • City of San Antonio closure for Hardberger Park Landbridge project. Saturday, August 24. 7 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
FM 1560 – Hausman Road
  • Tuesday, August 20 until Friday, August 23. Nightly 9 p.m. until 5 a.m. Eastbound left lane from SH 16 (Bandera Road) and Loop 1604 including long-term closure of the dedicated left-turn lane from Hausman to Bandera for utility work.
Spur 371 – General Hudnell Drive
  • Monday, August 19 until Friday, August 23. Daily 7 a.m. to 3 p.m. The northbound left lane between Billy Mitchell Boulevard and Cupples Road for removing existing guardrail and installing concrete barrier.
  • Monday, August 12 until Friday, August 16. Daily 9 a.m. to 5 p.m. The southbound left lane between Billy Mitchell Boulevard and Cupples Road for removing existing guardrail and installing concrete barrier.
Loop 13 – WW White Road
  • Monday, August 19 until Saturday, August 24. Nightly 11 p.m. until 5 a.m. Southbound left lane at Martin Luther King Boulevard for sidewalk and driveway work.
FM 1976 – Walzem Road
  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes from Woodlake Parkway until Gibbs Sprawl Road for barrier work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
SH 46 – Boerne/Kendall County
  • Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
I-37 – Atascosa County
  • Tuesday, August 20 until Saturday, August 31. Daily 6 a.m. until 10 p.m. Alternating northbound mainlanes from mile marker 108 to mile marker 117 for paving work.
SH 16 – Atascosa/McMullen County
  • Current until Saturday, August 30. Daily 5:30 a.m. until 7 p.m. Alternating lanes in both directions from FM 1332 to the Atascosa/McMullen County line for milling and inlay, bridge rail and guard fence work.
Other Roads – Bexar County
  • City of San Antonio project. Current until Friday, August 30. Daily 9 a.m. until 4 p.m. Southbound left lane of North Pecos Street at Buena Vista for sidewalk and curb work.
  • Monday, August 19 until Friday, August 23. Nightly 9 p.m. until 5 a.m. Alternating eastbound crossing closure west of US 281 for storm sewer utility work and traffic phasing.
  • Monday, August 19 until Friday, August 23. Nightly 9 p.m. until 5 p.m. Alternating eastbound crossing closure east of US 281 for storm utility work and traffic phasing.
  • Monday, August 19 until Friday, August 23. Nightly 9 p.m. until 5 p.m. Alternating westbound crossing closure east of US 281 for storm utility work and traffic phasing.

Monday, August 12

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North Central San Antonio
  • Monday, August 12 until Friday, August 16. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure of the US 281 North Exit Ramp to the Redland Road entrance ramp for overhang work. DETOUR: Use the US 281 North Exit Ramp through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Monday, August 12 until Friday, August 16. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure from the US 281 North Exit Ramp to the US 281 Entrance Ramp for overhang work. DETOUR: Use the US 281 North Exit Ramp, continue through the US 281 intersection and use the US 281 Entrance Ramp.
  • Saturday, August 17 until Monday, August 19. Full weekend closure 2 a.m. until 5 a.m. Full eastbound mainlane closure of the US 281 North Exit Ramp to the Redland Road entrance ramp for overhang work. DETOUR: Use the US 281 North Exit Ramp through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Saturday, August 17 until Monday, August 19. Full weekend closure 2 a.m. until 5 a.m. Full westbound mainlane closure from the US 281 North Exit Ramp to the US 281 Entrance Ramp for overhang work. DETOUR: Use the US 281 North Exit Ramp, continue through the US 281 intersection and use the US 281 Entrance Ramp..
Loop 1604 – Northwest San Antonio
  • Monday, August 12 until Friday, August 16. Nightly 9 p.m. until 5 a.m. Eastbound left mainlane and one eastbound frontage road lane from SH 16 (Bandera Road) to FM 1560 (Hausman Road) including Bandera entrance ramp and Hausman exit ramp for barrier setting work.
Loop 1604 – Northeast San Antonio
  • Monday, August 12 until Saturday, August 17. Daily 8 a.m. until 4 p.m. Left frontage road lane in both directions between Redland Road and Bulverde Road for truck/material access.
  • Monday, August 12 until Friday, August 16. Daily 9 a.m. until 3 p.m. Alternating frontage road lanes in both directions at FM 2252 (Nacagdoches Road) for utility work.
  • Friday, August 16 until Saturday, August 17. 10 p.m. until 9 a.m. Full westbound mainlane closure at FM 2252 (Nacagdoches Road) for barrier removal and placement work.
Loop 1604 – West San Antonio
  • Current until Sunday, August 18. Nightly 7 p.m. to 5 a.m. Alternating northbound frontage road lanes between SH 151 to south of FM 1957 (Potranco Road) for milling and paving work.
  • Ciurrent until Sunday, August 18. Nightly 7 p.m. to 5 a.m. All lanes (except the right turn lane) in both directions at FM 1957 (Potranco Road), Military Drive, and Wiseman Boulevard for milling and final pavement work.
  • Monday, August 12 until Friday, August 16. Daily 9 a.m. to 5 p.m. Alternating lanes in both directions at FM 1957 (Potranco Road), Military Drive, and Wiseman Boulevard for sign, curb/directional island work.
  • Monday, August 12 until Friday, August 16. Daily 9 a.m. to 5 p.m. The northbound exit ramp at Wiseman Boulevard for concrete curb work.
  • Monday, August 12 until Friday, August 16. Daily 9 a.m. to 7 p.m. Alternating northbound frontage road lanes between south of FM 1957 (Potranco Road) to SH 151 for driveway and curb work.
  • Monday, August 12 until Friday, August 16. Daily 9 a.m. to 7 p.m. Alternating southbound frontage road lanes between SH 151 to south of FM 1957 (Potranco Road) for final paving and rip rap work.
US 281 – North Central San Antonio
  • Monday, August 12 until Friday, August 16. Nightly 9 p.m. until 5 a.m. Full northbound mainlane closure from the Frontage Road exit ramp to the Sonterra Boulevard entrance ramp for deck pour work. DETOUR: Take the Frontage Road exit ramp, if heading north on US 281, take a right on the Loop 1604 Eastbound Frontage Road, use the turnaround at Gold Canyon Road and take a right at the Northbound Frontage Road. If heading west on the Eastbound Frontage Road, go thru the Gold Canyon Road intersection, use the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Monday, August 12 until Friday, August 16. Nightly 9 p.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for overhang work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the Southbound Frontage Road through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Monday, August 12 until Friday, August 16. Nightly 9 p.m. until 5 a.m. Full northbound frontage road closure from the Loop 1604 Westbound Frontage Road to Sonterra Boulevard to work on bridge caps. DETOUR: on the Loop 1604 Westbound Frontage Road, turn left on the US 281 Southbound Frontage Road, take the turnaround at Donella Drive and use the US 281 Donella Drive entrance ramp.
  • Monday, August 12 until Friday, August 16. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Marshall Road for concrete work and safety enhancements.
  • Monday, August 12 until Friday, August 16. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for concrete work and safety enhancements.
  • Saturday, August 17 until Monday, August 19. Full weekend closure 3 a.m. until 5 a.m. Full northbound mainlane closure from the Frontage Road exit ramp to the Sonterra Boulevard entrance ramp for deck pour work. DETOUR: Take the Frontage Road exit ramp, if heading north on US 281, take a right on the Loop 1604 Eastbound Frontage Road, use the turnaround at Gold Canyon Road and take a right at the Northbound Frontage Road. If heading west on the Eastbound Frontage Road, go thru the Gold Canyon Road intersection, use the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Saturday, August 17 until Monday, August 19. Full weekend closure 3 a.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for overhang work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the Southbound Frontage Road through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Saturday, August 17 until Monday, August 19. Full weekend closure 3 a.m. until 5 a.m. Full northbound Frontage Road closure for bridge cap work. DETOUR: Take a right on Loop 1604 Eastbound Frontage Road, use the turnaround at Gold Canyon Road and take a right at the Northbound Frontage Road.
  • Saturday, August 17 until Monday, August 19. Full weekend closure 3 a.m. until 5 a.m. Right/Center southbound mainlane closure from Evans Road to Encino Rio for retaining wall work.
I-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County
  • Tuesday, August 13 until Wednesday, August 14. 9 p.m. until 5 a.m. All westbound mainlanes from Scenic Loop Road to SH 46 for beam installation work.
  • Wednesday, August 14 until Thursday, August 15. 9 p.m. until 5 a.m. All eastbound mainlanes from Scenic Loop Road to SH 46 for beam installation work.
  • Thursday, August 15 until Friday, August 16. 9 p.m. until 5 a.m. Alternating eastbound mainlanes from Scenic Loop Road to SH 46 traffic barrier resetting work and pavement marking work.
I-10 – Far East San Antonio/Bexar County/Guadalupe County
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Current until further notice. Eastbound Ackerman Road exit ramp will be closed through the summer. DETOUR: Eastbound I-10 and southbound I-410 traffic wishing to access Ackerman Road must take southbound I-410, exit at FM 1346/E. Houston St., turn around, and take the northbound frontage road to Ackerman Road.
  • Monday, August 12 until Wednesday, August 14. Nightly 9 p.m. to 5 a.m. FM 1516 will be closed under I-10 for demolition of the existing I-10 mainlane bridge. DETOUR: Northbound FM 1516 traffic will take the I-10 eastbound frontage road to Loop 1604, turn around, and take the I-10 westbound frontage road back to FM 1516. Southbound FM 1516 traffic will take the I-10 westbound frontage road to Foster Road, turn around, and take the I-10 eastbound frontage road back to FM 1516.
I-35 – Northeast San Antonio & Comal County
  • Monday, August 12 until Tuesday, August 13. 9 p.m. until 5 a.m. Alternating southbound mainlanes from Schwab Road to FM 1103 for pavement marking work.
  • Tuesday, August 13 until Wednesday, August 14. 9 p.m. until 5 a.m. Alternating southbound mainlanes from Schwab Road to FM 1103 for striping work.
I-410 – West San Antonio
  • Monday, August 12 until Friday, August 16. Daily 9 a.m. to 3 p.m. The left southbound frontage road between Waters Edge to Marbach Road for removing low profile concrete work.
  • Monday, August 12 until Friday, August 16. Daily 9 a.m. to 3 p.m. The left northbound frontage road between Marbach Road to Meadow Bend for removing low profile concrete work.
  • Friday, August 16 until Monday, August 19. Nightly 8 p.m. to 5 a.m. All northbound mainlanes between US 90 exit ramp to SH 151 entrance ramp for traffic switch. DETOUR: All traffic will be detoured the northbound frontage road to access the mainlanes after Marbach Road.
US 90 – West San Antonio
  • Current until Friday, August 16. Nightly 8 p.m. to 5 a.m. All west frontage road lanes between I-410 to Hunt Lane for removing low profile concrete barrier work. The I-410 southbound frontage road ramp to US 90 westbound frontage road will also be closed. DETOUR: Traffic will be detoured to the south and eastbound cloverleafs; continue on US 90 eastbound to the turnaround at Military to access the westbound mainlanes.
  • Monday, August 12 until Friday, August 16. Daily 9 a.m. to 3 p.m. The left eastbound frontage road between Hunt Lane to I-410 for staging equipment.
  • Monday, August 12 until Friday, August 16. Daily 9 a.m. to 3 p.m. The left westbound frontage road lane between Tomar Drive and Hunt Lane for staging equipment.
PA 1502 – Wurzbach Parkway
  • City of San Antonio closure for Hardberger Park Landbridge project. Monday, August 12 until Friday, August 16. Daily 9 a.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
  • City of San Antonio closure for Hardberger Park Landbridge project. Saturday, August 17. 7 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
Spur 371 – General Hudnell Drive
  • Monday, August 12 until Friday, August 16. Daily 7 a.m. to 3 p.m. The northbound left lane between Billy Mitchell Boulevard and Cupples Road for removing existing guardrail and installing concrete barrier.
  • Monday, August 12 until Friday, August 16. Daily 9 a.m. to 5 p.m. The southbound left lane between Billy Mitchell Boulevard and Cupples Road for removing existing guardrail and installing concrete barrier.
FM 1976 – Walzem Road
  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes from Woodlake Parkway until Gibbs Sprawl Road for barrier work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
SH 46 – Boerne/Kendall County
  • Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
  • Current until Sunday, August 18. Full time at intersections with Herff Ranch Boulevard and with Esperanza Boulevard/Copper Creek for closure and traffic switch associated with reconstruction of both intersections (including milling, striping, etc.).
SH 16 – Atascosa/McMullen County
  • Current until Saturday, August 30. Daily 5:30 a.m. until 7 p.m. Alternating lanes in both directions from FM 1332 to the Atascosa/McMullen County line for milling and inlay, bridge rail and guard fence work.
Other Roads – Bexar County
  • City of San Antonio project. Current until Wednesday, August 14. Daily 9 a.m. until 4 p.m. Southbound left lane of North Pecos Street at Buena Vista for sidewalk and curb work.

Monday, August 5

I-10 Improvement Project in Boerne: Ramp Closure & Traffic Switch Coming Up

Our contractor working on the I-10 improvement project in Boerne from SH 46 to Cascade Caverns/Scenic Loop is progressing into the next phase of construction. 

During this new phase, contractor Texas Sterling will be enhancing the westbound I-10 frontage road and Business US 87 bridge, prompting necessary traffic closures and detours August 15-18, (weather permitting). These closures are required for safety to divert traffic away from construction work.

Closures and Detours:

The westbound I-10 mainlanes between Parkway and Crosspoint will be closed and I-10 traffic will be diverted to the temporary pavement in the median.



In addition, the westbound Business US 87 Exit 542 Ramp into Boerne will be permanently closed. Westbound drivers seeking to access US 87 should:

1) Take Exit 540 to SH 46 and Use eastbound SH 46 to access US 87.

OR

2) Take Scenic Loop (Exit 543) to the westbound frontage road and merge onto existing US 87.




What is being constructed:
  • The new Business US 87 and westbound I-10 frontage road intersection,
  • The new westbound frontage road.
  • The new Backstage Rd. #3 (The Tower at Boerne Center and O’Reilly Auto Parts).
  • New retaining walls.
What to expect:

Drivers should expect slower travel times and increased traffic flows along the existing westbound frontage road and the SH 46 intersection during this phase of construction. We appreciate everyone’s patience as our contractors continue to make significant progress on this I-10 improvement project.

Friday, August 2

SH 46 Project Milestone Phase 2: Closure/Switch For Intersection Reconstruction

Hopefully this one will go as smoothly as the first!

Folks in Boerne likely encountered the first part of the closure/traffic switch being implemented on SH 46 in town with the objective of reconstructing major intersections to fit the future expanded roadway.

Last week, our contractor put in place the closure/switch at SH 46 and Charger Boulevard. It was originally estimated to take 11 days but the contractor worked 24 hours a day and completed the reconstruction in just two days! Nice!

Now they move on to the second phase of the closure/switch process, next up are the intersections of SH 46 at Herff Ranch Boulevard and at Esperanza Boulevard (see graphic). As they did at Charger, it will be necessary to close the turn lanes at both intersections.

Once again, one lane of travel per direction will be provided through the intersections and off-duty law enforcement officers will be on site helping direct traffic for the duration to minimize delays to the traveling public.

The construction is scheduled to begin Tuesday, August 6th, and is projected to last approximately 11 days (same as the estimated time with the previous phase at Charger).

The contractor will be using this lane closure/traffic switch to repave the next section of SH 46, between Brentwood Drive and Ammann Road.

The contractor has taken every step to make this phase of construction as efficient as possible,and will once again have crews working 24 hours a day to accelerate its completion (hopefully, again, ahead of the estimated completion date).

During this phase of construction, eastbound traffic will remain in its current place while westbound drivers will be shifted to the northern edge of the road, creating a work zone in the middle of SH 46 (see graphic above).

If you frequently use SH 46, you've likely already seen electronic message signs placed along the work zone by the contractor to help alert you to this coming work.

As always, for everyone's safety, we remind drivers about the "Move Over/Slow Down" state law which requires to move over if you can or at least slow down in construction zones.


UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North Central San Antonio
  • Sunday, August 4 until Friday, August 9. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure of the US 281 north exit ramp to the Redland Road entrance ramp for overhang work. DETOUR: Use the US 281 north exit ramp through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Sunday, August 4 until Friday, August 9. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for overhang work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
Loop 1604 – Northwest San Antonio
  • Sunday, August 4 until Friday, August 9. Nightly 9 p.m. until 5 a.m. One frontage road lane in both directions from SH 16 (Bandera Road) to Roger’s Ranch Road for pavement marking installation work.
  • Monday, August 5 until Wednesday, August 7. 9 p.m. until 5 a.m. Alternating frontage road lanes in both directions between 7-11 and Chili’s for traffic signal and light pole work.
  • Monday, August 5 until Friday, August 9. Daily 9 a.m. until 3 p.m. Eastbound left mainlane from SH 16 (Bandera Road) to FM 1560 (Hausman Road) including Bandera entrance ramp and Hausman exit ramp for barrier setting work.
Loop 1604 – Northeast San Antonio
  • Monday, August 5 until Saturday, August 10. Daily 8 a.m. until 4 p.m. Left frontage road lane in both directions between Redland Road and Bulverde Road for truck/material access.
Loop 1604 – West San Antonio
  • Sunday, August 4 until Sunday, August 11. Nightly 7 p.m. to 5 a.m. The northbound frontage road shoulder and center lane between SH 151 to south of FM 1957 (Potranco Road) for milling and paving work.
  • Sunday, August 4 until Saturday, August 11. Nightly 7 p.m. to 5 a.m. All lanes (except the right turn lane) at FM 1957 (Potranco Road), Military Drive, and Wiseman Boulevard for milling and final pavement work.
  • Monday, August 5 until Friday, August 9. Daily 9 a.m. to 5 p.m. Alternating lanes at FM 1957 (Potranco Road), Military Drive, and Wiseman Boulevard for sign, curb/directional island work.
  • Monday, August 5 until Friday, August 9. Daily 9 a.m. to 5 p.m. The northbound exit ramp at Wiseman Boulevard for concrete curb work.
  • Monday, August 5 until Friday, August 9. Daily 9 a.m. to 7 p.m. Alternating northbound frontage road lanes between south of FM 1957 (Potranco Road) to SH 151 for driveway and curb work.
  • Monday, August 5 until Friday, August 9. Daily 9 a.m. to 7 p.m. Alternating southbound frontage road lanes between SH 151 to south of FM 1957 (Potranco Road) for final paving and rip rap work.
US 281 – North Central San Antonio
  • Sunday, August 4 until Friday, August 9. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlanes from Loop 1604 to Marshall Road for concrete work and safety enhancements.
  • Sunday, August 4 until Friday, August 9. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlanes from Marshall Road to Loop 1604 for concrete work and safety enhancements.
  • Sunday, August 4 until Friday, August 9. Nightly 9 p.m. until 5 a.m. Alternating southbound frontage road lanes from Sonterra Boulevard to the US 281 westbound frontage road for drainage work.
  • Monday, August 5 until Friday, August 9. Nightly 9 p.m. until 5 a.m. Full northbound mainlane closure from the Frontage Road exit ramp to the Sonterra Boulevard entrance ramp for overhang work. DETOUR: Take the Frontage Road exit ramp, if heading north on US 281, take a right on Loop 1604 eastbound frontage road, use the turnaround at Gold Canyon Road and take a right at the northbound frontage road. If heading west on Loop 1604, take a right on the Loop 1604 eastbound frontage road, go thru the Gold Canyon Road intersection, use the turnaround at Redland Road and take the Redland Road entrance ramp.
  • Monday, August 5 until Friday, August 9. Nightly 9 p.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for overhang work. DETOUR: Take the Sonterra Boulevard exit ramp, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Monday, August 5 until Friday, August 9. Nightly 9 p.m. until 5 a.m. Full northbound frontage road closure under Loop 1604 for overhang work. DETOUR: Take a right on Loop 1604 eastbound frontage road, use the turnaround at Gold Canyon Road and take a right at the northbound frontage road.
  • Monday, August 5 until Friday, August 9. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlanes from Evans Road to Encino Rio for soundwall work.
  • Monday, August 5 until Friday, August 9. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlanes at Redland Road and US 281 for overhang work.
I-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County
  • Sunday, August 4 until Monday, August 5. 9 p.m. until 5 a.m. Left mainlane in both directions between FM 3351 (Ralph Fair Road) and Dominion Drive for traffic barrier resetting work.
  • Sunday, August 4 until Tuesday, August 6. 9 p.m. until 5 a.m. All eastbound mainlanes from one mile east to one mile west of Fair Oaks Parkway for overhang bracket removal work.
  • Monday, August 5 until Tuesday, August 6. 9 p.m. until 5 a.m. Westbound left mainlane from La Cantera Parkway to Camp Bullis Road for traffic barrier resetting work.
  • Monday, August 5 until Tuesday, August 6. 9 p.m. until 5 a.m. All westbound mainlanes from one mile east of Fair Oaks Parkway to one mile west of Scenic Loop Road for overhang bracket removal work.
  • Tuesday, August 6 until Wednesday, August 7. 9 p.m. until 5 a.m. Westbound left mainlane from Old Fredericksburg Road to FM 3351 (Ralph Fair Road) for traffic barrier resetting work.
  • Tuesday, August 13 until Wednesday, August 14. 9 p.m. until 5 a.m. All westbound mainlanes from Scenic Loop Road to SH 46 for beam installation work.
  • Wednesday, August 14 until Thursday, August 15. 9 p.m. until 5 a.m. All eastbound mainlanes from Scenic Loop Road to SH 46 for beam installation work.
  • Thursday, August 15 until Friday, August 16. 9 p.m. until 5 a.m. Alternating eastbound mainlanes from Scenic Loop Road to SH 46 traffic barrier resetting work and pavement marking work.
I-10 – Far East San Antonio/Bexar County/Guadalupe County
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Current until further notice. Eastbound Ackerman Road exit ramp will be closed through the summer. DETOUR: Eastbound I-10 and southbound I-410 traffic wishing to access Ackerman Road must take southbound I-410, exit at FM 1346/E. Houston St., turn around, and take the northbound frontage road to Ackerman Road.
  • Monday, August 5 until Friday, August 9. 9 a.m. to 3:30 p.m. daily. Eastbound left frontage road lane at Ackerman Road for truck and equipment access to work area. One right lane of northbound Ackerman Road under I-10 will also be closed during this time.
  • Tuesday, August 6. 12 a.m. to 6 a.m. Westbound right mainlane at FM 1516 exit ramp.
  • Wednesday, August 7. 9 p.m. to 12 a.m. Eastbound left mainlane at Loop 1604.
  • Thursday, August 8 until Friday, August 9. 9 p.m. to 5 a.m. Eastbound frontage road from the entrance ramp after Foster Road to Woodlake Parkway for beam placement. DETOUR: Eastbound frontage road motorists must enter the mainlanes after the Foster Road intersection unless they need to access properties or businesses located east of the entrance ramp. This traffic will be slowed and directed to pass to the right of construction equipment on the frontage road.
  • Sunday, August 11 until Tuesday, August 13. 9 p.m. to 5 a.m. nightly. FM 1516 under I-10 for demolition of the existing I-10 mainlane bridge. DETOUR: Northbound FM 1516 traffic will take the I-10 eastbound frontage road to Loop 1604, turn around, and take the I-10 westbound frontage road back to FM 1516. Southbound FM 1516 traffic will take the I-10 westbound frontage road to Foster Road, turn around, and take the I-10 eastbound frontage road back to FM 1516.
  • Monday, August 5 until Thursday, August 8. Daily 7:30 a.m. until 7 p.m. Alternating mainlanes in both directions from SH 130 to US 183 for milling/asphalt and guard fence installation work.
I-35 – Northeast San Antonio & Comal County
  • Current until 5 a.m. Saturday, August 3. Northbound right and center mainlanes (and shoulder) FM 2252 to Schwab Road for traffic barrier installation work.
  • Monday, August 5 until Saturday, August 10. Daily 9 a.m. until 3 p.m. Right frontage road lane in both directions from Austin Street to New Braunfels Avenue for sidewalk and driveway work.
I-410 – West San Antonio
  • Monday, August 5 until Friday, August 9. Daily 9 a.m. to 4 p.m. The left southbound frontage road between Waters Edge to Marbach Road for staging equipment for hot mix work.
  • Monday, August 5 until Friday, August 9. Daily 9 a.m. to 4 p.m. The right northbound frontage road between Meadow Bend to Meadow Glade for staging equipment for sidewalk work.
  • Monday, August 5 until Tuesday, August 6. Nightly 9 p.m. to 5 a.m. Westbound left mainlane between Salado Creek to S. Presa Street for illumination work.
  • Monday, August 5 until Tuesday, August 6. Nightly 9 p.m. to 5 a.m. North and southbound exit ramps to I-37 from the eastbound mainlanes for illumination work.
  • Tuesday, August 6 until Wednesday, August 7. Nightly 9 p.m. to 5 a.m. North and southbound exit ramps to I-37 from the westbound mainlanes for illumination work.
US 90 – West San Antonio
  • Sunday, August 4 until Friday, August 9. Nightly 8:30 p.m. to 5 a.m. Westbound right mainlane shoulder between South Flores and I-35 north and southbound exit ramp for mowstrip work. The I-35 northbound entrance ramp will also be closed. DETOUR: Exit to I-35 southbound, continue to Theo/Malone Avenue, take left to Malone Avenue and left on I-35 northbound frontage road to I-35 northbound.
  • Monday, August 5 until Friday, August 9. Daily 9 a.m. to 4 p.m. The left eastbound frontage road lane between Ray Ellison Drive to I-410 for staging equipment to haul material and rock placement.
  • Monday, August 5 until Friday, August 9. Daily 9 a.m. to 4 p.m. One westbound frontage road lane between Tomar Drive and Hunt Lane for staging equipment.
I-37 – South San Antonio
  • Wednesday, August 7 until Thursday, August 8. Nightly 9 p.m. to 5 a.m. East and westbound exit ramp to I-410 from the northbound mainlanes for illumination work.
  • Thursday, August 8 until Friday, August 9. Nightly 9 p.m. to 5 a.m. East and westbound exit ramp to I-410 from the southbound mainlanes for illumination work.
SH 16 – Bandera Road
  • Monday, August 5 until Wednesday, August 7. 9 p.m. until 5 a.m. Alternating lanes in both directions from Quincy Lee to Legend Trail for traffic signal and light pole work.
PA 1502 – Wurzbach Parkway
  • City of San Antonio closure for Hardberger Park Landbridge project. Monday, August 5 until Friday, August 9. Daily 9 a.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
  • City of San Antonio closure for Hardberger Park Landbridge project. Saturday, August 10. 7 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
Spur 371 – General Hudnell Drive
  • Monday, August 5 until Friday, August 9. Daily 7 a.m. to 3 p.m. The northbound left lane between Billy Mitchell Boulevard and Cupples Road will be closed for removing existing guardrail and installing concrete barrier.
  • Monday, August 5 until Friday, August 9. Daily 9 a.m. to 5 p.m. The southbound left lane between Billy Mitchell Boulevard and Cupples Road will be closed for removing existing guardrail and installing concrete barrier.
FM 1976 – Walzem Road
  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes from Woodlake Parkway until Gibbs Sprawl Road for barrier work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
Loop 13 – WW White Road/West Military Drive
  • Current until 4 p.m. Saturday, August 3. Right lane in both directions from Springfield Road to Seale Road for sidewalk and driveway work.
SH 46 – Boerne/Kendall County
  • Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
  • Tuesday, August 6 until Sunday, August 18. Full time at intersections with Herff Ranch Boulevard and with Esperanza Boulevard/Copper Creek for closure and traffic switch associated with reconstruction of both intersections (including milling, striping, etc.).
SH 16 – Atascosa/McMullen County
  • Current until Saturday, August 30. Daily 5:30 a.m. until 7 p.m. Alternating lanes in both directions from FM 1332 to the Atascosa/McMullen County line for milling and inlay, bridge rail and guard fence work.
  • Monday, August 5 until Friday, August 9. Daily 8 a.m. until 5 p.m. Alternating southbound lanes from Tilden to FM 624 (mile markers 680-690) for guard fence installation and excavation work.
Other Roads – Bexar County
  • City of San Antonio project. Current until Wednesday, August 14. Daily 9 a.m. until 4 p.m. Southbound left lane of North Pecos Street at Buena Vista for sidewalk and curb work.