UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North Central San Antonio
  • Sunday, November 10 until Friday, November 15. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure from the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Sunday, November 10 until Friday, November 15. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Sunday, November 10 until Friday, November 15. Nightly 9 p.m. until 5 a.m. Full westbound frontage road closure at from the US 281 southbound frontage road to the Stone Oak Parkway exit ramp. DETOUR: Take the turnaround at US 281, continue eastusing the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Sunday, November 10 until Friday, November 15. Nightly 9 p.m. until 5 a.m. Eastbound frontage road turnaround closure at US 281 for direct connector work. DETOUR: Turn left at the US 281 intersection then turn left again onto the westbound Loop 1604 frontage road.
  • Saturday, November 16 until Monday, November 18. Full weekend closure 2 a.m. until 5 a.m. Full eastbound mainlane closure from the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Saturday, November 16 until Monday, November 18. Full weekend closure 2 a.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
Loop 1604 – Northeast San Antonio
  • Sunday, November 10 until Friday, November 15. Nightly 9 p.m. until 5 a.m. Westbound right mainlane between Bulverde Road and Redland Road for paving work on the new entrance ramp.
  • Sunday, November 10 until Friday, November 15. Daily 9 a.m. until 5 p.m. Right frontage road lane in both directions between Bulverde Road and Redland Road for guardrail work.
Loop 1604 – West San Antonio
  • Monday, November 11 until Friday, November 15. Daily 9 a.m. to 5 p.m. Alternating lanes in both directions at FM 1957 (Potranco Road), Military Drive, and Wiseman Boulevard for sign work.
  • Monday, November 11 until Friday, November 15. Daily 9 a.m. to 5 p.m. Alternating northbound frontage road lanes between south of FM 1957 (Potranco Road) to SH 151 for sidewalk/curb and sign work.
  • Monday, November 11 until Friday, November 15. Daily 9 a.m. to 5 p.m. Alternating southbound frontage road lanes between SH 151 to south of FM 1957 (Potranco Road) for sidewalk/curb and sign work.
Loop 1604 – Northwest San Antonio
  • Sunday, November 10 until Thursday, November 14. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure (as well as entrance ramps from westbound I-10 to eastbound Loop 1604 and from eastbound Loop 1604 to eastbound Loop 1604 mainlanes) at Tradesman for bridge beam repair work.
US 281 – North Central San Antonio
  • Saturday, November 9. 7 a.m. until 12 p.m. Right lane northbound frontage road closure from the Loop 1604 westbound frontage road to Sonterra Boulevard for safety enhancements.
  • Sunday, November 10 until Friday, November 15. Nightly 9 p.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound frontage road, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Sunday, November 10 until Friday, November 15. Nightly 9 p.m. until 5 a.m. Full southbound frontage road closure at Loop 1604 for direct connector work. DETOUR: Turn right on the westbound frontage road, take the turnaround at Stone Oak Parkway and turn right on the southbound frontage road.
  • Sunday, November 10 until Friday, November 15. Nightly 9 p.m. until 5 a.m. Northbound mainlane ramp closure of the north- to eastbound direct connector ramp for direct connector work. DETOUR: Use the frontage road exit ramp, turn right on the Loop 1604 eastbound frontage road, if heading north, take the turnaround at Gold Canyon Road and turn right on the northbound frontage road. If heading west, continue on the eastbound frontage road through the Gold Canyon Road intersection, use the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Sunday, November 10 until Friday, November 15. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Marshall Road for paving and bridge work.
  • Sunday, November 10 until Friday, November 15. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for paving and bridge work.
  • Saturday, November 16 until Monday, November 18. Full weekend closure 2 a.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound frontage road through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Saturday, November 16 until Monday, November 18. Full weekend closure 2 a.m. until 5 a.m. Full southbound frontage road closure at Loop 1604 for direct connector work. DETOUR: Turn right on the westbound frontage road, take the turnaround at Stone Oak Parkway and turn right on the southbound frontage road.
US 281 – Southeast San Antonio
  • Friday, November 8 until Friday, November 15. Nightly 8 p.m. until 4 a.m. All lanes in both directions at Loop 1604 for bridge deck pour work. SOUTHBOUND DETOUR: Traffic diverted to frontage road. NORTHBOUND DETOUR: Traffic diverted to Rockport Road.
I-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County
  • Current until Tuesday, December 19. Daily 8 a.m. until 3 p.m. Westbound-to-eastbound turnaround at Boerne Stage Road long-term closure for bridge work.
  • Monday, November 11 until Friday, November 15. Daily 9 a.m. until 4 p.m. Full frontage road closure in both directions at Balcones Creek for equipment access/installation work.
  • Tuesday, November 12 until Friday, November 15. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure at Boerne Stage Road for pavement marking work.
  • Friday, November 15 until Monday, November 18. Full weekend closure 9 p.m. until 5 a.m. Full mainlane closure in both directions at Boerne Stage Road for overpass/bridge work.
  • Friday, November 15 until Saturday, November 16. Daily 9 a.m. until 3 p.m. Alternating frontage road lanes in both directions at Camp Bullis Road for pavement marking work.
I-10 – Far East San Antonio/Bexar County/Seguin/Guadalupe County
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Current until further notice. Eastbound Ackerman Road exit ramp will be closed through the fall. DETOUR: Eastbound I-10 and southbound I-410 traffic needing to access Ackerman Road must take southbound I-410, exit at FM 1346/E. Houston St., turn around, and take the northbound frontage road to Ackerman Road.
  • Sunday, November 10 until Tuesday, November 12. Nightly 9 p.m. until 5 a.m. Left eastbound mainlane from Rosillo Creek to Woodlake Parkway for striping work.
  • Friday, November 15 until Saturday, November 16. 9 p.m. until 7 p.m. FM 1516 in both directions under I-10 for bridge beam placement. DETOUR: Southbound FM 1516 traffic will take the westbound frontage road and turn around at Foster Road. Northbound FM 1516 traffic will take the eastbound frontage road and turn around at Loop 1604. Police officers will provide traffic control at the FM 1516 and Loop 1604 intersections.
I-10 – Central San Antonio
  • Tuesday, November 12 and Friday, November 15. Daily 9 a.m. until 3 p.m. Westbound right mainlane and shoulder from Probandt to I-35 interchange (including I-35 northbound exit ramp) for guard fence installation work.
I-35 – Central San Antonio/Northeast San Antonio/Comal County
  • Sunday, November 10 until Tuesday, November 11. 8:30 p.m. until 5 a.m. Northbound left mainlane and shoulder at I-10//US 90 interchange (including US 90 westbound ramp) for guard fence installation work.
  • Monday, November 11 until Saturday, November 16. Daily 9 a.m. to 3 p.m. The right lane in both directions between Austin Street and New Braunfels Avenue for sidewalk and driveway work.
I-410 – West San Antonio
  • Sunday, November 10 until Wednesday, November 13. Nightly 8 p.m. to 5 a.m. Two southbound mainlanes between US 90 exit ramp to the US 90 bridge for staging equipment and concrete barrier removal.
  • Monday, November 11 until Thursday, November 14. Nightly 8 p.m. to 5 a.m. The southbound left frontage road lane between Demya Drive and Bertetti Drive for staging equipment, removing low profile barrier and striping.
  • Monday, November 11 until Friday, November 15. Daily 9 a.m. to 3 p.m. Alternating northbound frontage road lanes between Bronco Lane to SH 151 for staging equipment and trucks.
  • Monday, November 11 until Friday, November 15. Daily 9 a.m. to 3 p.m. Alternating southbound frontage road lanes between SH 151 to US 90 for staging equipment and trucks.
US 90 – West San Antonio
  • Saturday, November 9 until Sunday, November 10. Continuous 9 a.m. to 5 p.m. Eastbound US 90 between Ray Ellison Drive to I-410 for hot mix work. The east and northbound connectors will also be closed.
  • Monday, November 11 until Saturday, November 16. Daily 9 a.m. to 3 p.m. The westbound right frontage road lane between W. Military Drive to Colt Drive for sidewalk and driveway work.
  • Monday, November 11 until Friday, November 15. Daily 9 a.m. to 3 p.m. The left frontage road lane in both directions between I-410 to Hunt Lane for staging equipment and trucks.
I-37 – Central & South San Antonio
  • Monday, November 11 until Friday, November 15. Nightly 8:30 p.m. until 5 a.m. Northbound left mainlane and shoulder at I-10 interchange (including I-10 westbound exit ramp) for guard rail installation work.
PA 1502 – Wurzbach Parkway
  • City of San Antonio closure for Hardberger Park Landbridge project. Monday, November 11 until Friday, November 15. Daily 9 a.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
  • City of San Antonio closure for Hardberger Park Landbridge project. Saturday, November 16. 7 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
SH 218 – Pat Booker Road
  • Tuesday, November 12 until Wednesday, November 13. 9 a.m. until 3 p.m. Alternating westbound lanes at Loop 1604 for bridge/overpass work.
  • Thursday, November 14 until Friday, November 15. Daily 9 a.m. until 3 p.m. Alternating eastbound lanes at Loop 1604 for bridge/overpass work.
Spur 371 – General Hudnell Drive
  • Sunday, November 10 until Friday, November 15. Nightly 9 p.m. to 5 a.m. Alternating lanes in both directions between Frio City Road and Quintana Road for asphalt patching work.
  • Monday, November 11 until Friday, November 15. Daily 9 a.m. to 5 p.m. The left lane in both directions between Billy Mitchell Boulevard to US 90 for removing existing guardrail and installing concrete barrier.
FM 1976 – Walzem Road/Gibbs Sprawl Road
  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes between Woodlake Parkway and Gibbs Sprawl Road for barrier/pavement work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
Other Roads – Bexar County
  • Sunday, November 10 until Friday, November 15. Nightly 9 p.m. until 5 a.m. Full westbound closure of Encino Rio approaching the US 281 intersection for bridge work. DETOUR: Turn right on the US 281 northbound frontage road and use the north- to southbound turnaround after Evans Road.
  • Saturday, November 16 until Monday, November 18. Weekend full closure 2 a.m. until 5 a.m. Full westbound closure of Encino Rio approaching the US 281 intersection for bridge work. DETOUR: Turn right on the US 281 northbound frontage road and use the north- to southbound turnaround after Evans Road.
SH 46 – Boerne/Kendall County
  • Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
FM 1376 – Kendall County
  • Monday, November 11 until Friday, November 15. Daily 7 a.m. until 7 p.m. Alternating lanes in both directions at various culvert locations in the work zone for temporary pavement work.
US 87 – Wilson County
  • Current until Monday, November 18. Daily 7 a.m. until 6 p.m. Northbound right lane at SH 97 for barrier setting and crash cushion installation work.
SH 16 – McMullen County
  • Monday, November 11 until Friday, November 15. Daily 8 a.m. until 5 p.m. Alternating southbound lanes from FM 1962 to McMullen/Duval county line (mile markers 686-700) for barrier, excavation work