Next week's construction-related closures

I-10 – Kerrville

  • Monday, July 2 until Friday, July 6. 9 a.m. until 5 p.m. Alternating westbound main lanes between FM 1338 (Goat Creek Road) to SH 16 will be closed for guardrail and asphalt repair work.

I-10 – Boerne

  • Sunday, July 1 until Friday, July 6. 9 p.m. until 5 a.m. The right westbound main lane between ½ mile west of Bus 87 to Scenic Loop will be closed for concrete traffic barrier work.

I-35 – North San Antonio

  • Saturday, June 30 until Monday, July 2. 3 a.m. until 5 a.m. All northbound lanes between George Beach and I-410 south will be closed for illumination work. Traffic will exit at the new Rittiman exit ramp and travel on the frontage road and enter the highway at Binz-Engleman/George Beach entrance ramp. The left lane on southbound between I-410 south and Walzem Road will also be closed for median work.

I-410 – West San Antonio

  • Current and continuous until December 2018. Turnarounds, both directions, at Marbach Road. The turnarounds will remain closed while crews construct the new Marbach overpass bridge. Traffic will use the signalized intersection.
  • Current and continuous until December 2018. Northbound exit ramp to Marbach. The ramp will remain closed while crews reconstruct the road. Traffic will exit US Hwy 90 and continue along the frontage road to reach its destination.
  • Friday, June 29 until Saturday, June 30. 9 p.m. until 12 noon. All southbound main lanes between Ingram Road and Military Drive will be closed restriping to final configuration. Traffic will need to exit Culebra Road; travel through the intersection and enter highway at SH 151.
  • Sunday, July 1 until Friday, July 6. 8 p.m. until 5 a.m. All southbound main lanes between Marbach Road and US 90 will be closed for bridge deck work. Traffic will be detoured to I-410 southbound frontage road and take the next entrance ramp.
  • Sunday, July 1 until Friday, July 20. 9 p.m. until 5 a.m. All northbound main lanes between SH 151 and Culebra Road will be closed for asphalt overlay work. Traffic will need to exit SH 151; travel through the intersection and enter highway at Culebra Road.

SH 151 – West San Antonio

  • Sunday, July 1 until Monday, July 2. 9 p.m. until 5 a.m. All westbound main lanes between I-410 and Hunt Lane will be closed for bridge joint work. Traffic will need to exit I-410; travel through intersection and enter highway at Hunt Lane.

I-10 – West San Antonio

  • Friday, June 29 until Monday, July 2. 9 p.m. until 5 a.m. All lanes in both directions closed between Camp Bullis Road and Boerne Stage Road for beam work at Dominion Drive. The underpass at Dominion Drive and entrance ramps will also be closed. Westbound traffic will detour at Boerne Stage Road and eastbound traffic will detour at Camp Bullis.

I-10 – East San Antonio

  • Friday, June 29 until Monday, July 2. 9 p.m. until 5 a.m. All westbound main lanes between Exit 587 ramp to the I-10 entrance ramp west of Loop 1604 will be closed for existing approach slab repair work. Traffic will need to exit at Exit 587 and continue past Loop 1604 and enter the highway and the next entrance.

U.S. Hwy 281 – Far North San Antonio

  • Current until Friday, July 6. 9 p.m. until 5 a.m. Northbound frontage road between east and westbound Loop 1604 frontage road. The right lane will be closed for bridge, traffic signal and pothole work.
  • Current until Friday, July 6. 9 p.m. until 5 a.m. Northbound main lanes between Sonterra Boulevard exit ramp and entrance ramp. The right and center lane will be closed for bridge work.
  • Sunday, July 1 until Tuesday, July 3. 9 p.m. until 5 a.m. Alternating southbound lanes between Redland Road and Sonterra Boulevard exit ramp. Alternating lanes will be closed for restriping. Traffic will need to exit at Donella Drive.
  • Sunday, July 1 until Tuesday, July 3. 9 p.m. until 5 a.m. Alternating northbound lanes between Donella Drive entrance ramp to Sonterra Boulevard entrance ramp will be closed. Traffic will need to use the Donella Drive exit.
  • Sunday, July 1 until Tuesday, July 3. 9 p.m. until 5 a.m. Alternating lanes on both directions of Encino Rio east of US 281 will be closed for restriping and setting barrier rail work.
  • Thursday, July 5 until Friday, July 6. 9 p.m. until 5 a.m. Northbound full frontage road closure between Loop 1604 and Sonterra Boulevard exit ramp for bridge work. Traffic will need to use southbound frontage road; use Donella Drive turnaround and take Donella Drive entrance ramp.
  • Thursday, July 5 until Friday, July 6. 9 p.m. until 5 a.m. Alternating northbound main lanes between Donella Drive entrance ramp and Sonterra Boulevard entrance ramp will be closed for restriping. The Sonterra Boulevard exit ramp will also be closed. Traffic will need to use the Donella Drive exit.
  • Thursday, July 5 until Friday, July 6. 9 p.m. until 5 a.m. Alternating southbound main lanes between Redland Road and Sonterra Boulevard exit ramp will be closed for restriping. The Sonterra Boulevard exit ramp will also be closed. Traffic will need to use the Donella Drive exit.
  • Thursday, July 5 until Friday, July 6. 9 p.m. until 5 a.m. Alternating lanes on both directions of Encino Rio east of US 281 will be closed for restriping and setting barrier rail work.

Other roads – Boerne

  • Monday, July 2 until Tuesday, July 31. 9 a.m. until 4 p.m. Alternating main lanes closed in both directions of SH 46 between I-10 to the Kendall/Bandera County Line for guardrail work.

Other roads – Converse

  • Current and continuous until Friday, August 24. FM 78 at FM 1516. The right turn lane will close while crews do road work. Oversized vehicles will use FM 3502 to reach its destination.

Other roads – Helotes

  • Current and continuous until Monday, July 2. Riggs Road, both directions, at FM 1560. All lanes are restricted while crews reconstruct the intersection. The turn radius is tight and trucks with trailers should not use this intersection.
  • Current and continuous until Friday, September 28. Northbound Bandera Road at FM 1560. The left turn lane will close while crews do road work. No left turns will be permitted. Traffic will continue to the next intersection and turn around to reach its destination. Cross traffic from Circle A is also blocked.

Thursday, June 28

I-10/Dominion Drive closure this weekend

Even though summer officially started a few days ago, someone forgot to tell the weather that. With it being at least 90 degrees every day for the foreseeable future, we can all be thankful for air-conditioning.
Beginning the evening of June 29th and finishing up the morning of July 2nd, the mainlanes of I-10 at Dominion Dr. along with the eastbound and westbound traffic of Dominion Dr. will be closed. This is the same process that occurred at Camp Bullis Rd. just a few weeks ago. To get caught up on what has been going on, please read our previous blog. This time we are upping the ante with the weight of the beams. The previous beams placed at Camp Bullis Rd. had a length of 100 ft. and weighed a measly 83,200 lbs. (41.6 tons). The beams that are going up at Dominion Dr. may have a shorter length at 91 ft., but they weigh a whopping 93,000 lbs. (46.5 tons). The difference in weight is a whole extra African elephant!
Of course, with the closures come the detours, but we strive to make them as easy as possible. Westbound traffic of I-10 will exit at Dominion Dr., continue thru the Dominion intersection, and re-enter the westbound mainlanes at the entrance ramp before Boerne Stage Rd. Similarly, eastbound traffic of I-10 will exit at Dominion Dr., continue thru the Dominion intersection, and re-enter the eastbound mainlanes at the entrance ramp before Camp Bullis Rd. Westbound and eastbound traffic on Dominion Dr. will be re-routed. Westbound traffic will turn and proceed on the westbound frontage road and continue to the westbound entrance ramp or the turnaround at Boerne Stage Rd. Eastbound traffic will turn and proceed on the eastbound frontage road and continue to the eastbound entrance ramp or the turnaround at Camp Bullis Rd.
We will again have sufficient uniformed officer presence to safely move and direct traffic through the intersection, along with message boards and signs. We are striving to repeat and improve upon the success we have had during the entire construction process.
If you are ever wondering what’s going on, you can check out the TransGuide cameras. 

Friday, June 22

Next Week's Construction-Related Closures

I-10 – Boerne
  • Sunday, June 24 until Wednesday, June 27. 9 p.m. until 5 a.m. Eastbound main lanes between ½ mile east of SH 46 to Bus 87. The right lane will be closed for concrete traffic barrier placement. 
  • Monday, June 25 until Wednesday, June 27. 9 a.m. until 4 p.m. Westbound frontage road between Bus 87 and Cascade Cavern. The right lane will be closed for right of way work. 
  • Tuesday, June 26 until Wednesday, June 27. 9 p.m. until 5 a.m. Eastbound main lanes between ½ mile west of SH 46 to Bus 87. The right lane will be closed for concrete traffic barrier placement. 
  • Wednesday, June 27 until Thursday, June 28. 9 p.m. until 5 a.m. Westbound main lanes between SH 46 to Frederick Creek entrance ramp. The right lane will be closed for concrete traffic barrier placement. 
I-410 – West San Antonio
  • Current and continuous until December 2018. Turnarounds, both directions, at Marbach Road. The turnarounds will remain closed while crews construct the new Marbach overpass bridge. Traffic will use the signalized intersection. 
  • Current and continuous until December 2018. Northbound exit ramp to Marbach. The ramp will remain closed while crews reconstruct the road. Traffic will exit US Hwy 90 and continue along the frontage road to reach its destination. 
  • Current until Friday, June 29. 9 a.m. until 5 a.m. The right frontage road lane on both directions between Culebra Road and SH 151 for handrail work. 
  • Friday, June 23 until Saturday, June 24. 9 p.m. until 7 a.m. All I-410 northbound main lanes between Ingram Road and SH 151 will be closed to remove barrier and restripe. Northbound I-410 traffic will need to exit SH 151 and travel through the intersection to enter I-410 at the Culebra Road entrance ramp. Also, crews will be removing barrier on one lane on I-410 southbound between Ingram Road and Military Drive. 
I-10 – West San Antonio
  • Friday, June 29 until Monday, July 2. 9 p.m. until 5 a.m. All lanes in both directions closed between Camp Bullis Road and Boerne Stage Road for beam work at Dominion Drive. The underpass at Dominion Drive and entrance ramps will also be closed. Westbound traffic will detour at Boerne Stage Road and eastbound traffic will detour at Camp Bullis. 
U.S. Hwy 281 – Far North San Antonio
  • Current until Friday, June 29. 9 p.m. until 5 a.m. nightly. Northbound main lanes at Sonterra Boulevard. The right lane will close while crews do bridge work. This closure includes the Sonterra exit. Traffic will follow the posted detour. 
  • Current until Friday, June 29. 9 p.m. until 5 a.m. The right and center lanes of northbound US 281 between the Sonterra Boulevard exit ramp and the Sonterra Boulevard entrance ramp, and the Sonterra Boulevard exit ramp, will be closed nightly. Off-duty police will assist with traffic control as needed. 
  • Sunday, June 24 until Tuesday, June 26. 9 p.m. until 5 a.m. TPC Parkway at US 281 on both directions. Alternating lanes will be closed for restriping and setting barrier rail. 
  • Sunday, June 24 until Friday, July 6. 9 p.m. until 5 a.m. Northbound frontage road between east and westbound Loop 1604 frontage road. The right lane will be closed for bridge, traffic signal and pothole work. 
  • Tuesday, June 25 until Friday, June 29. 9 p.m. until 5 a.m. Eastbound Loop 1604 between the direct connector exit ramp to southbound US 281 and Gold Canyon Drive exit ramp. Alternating lanes will be closed for bridge work. 
  • Tuesday, June 25 until Friday, June 29. 9 p.m. until 5 a.m. Westbound Loop 1604 between US 281 north exit ramp to Stone Oak Parkway exit ramp. Alternating lanes closed for bridge work. 
  • Monday, June 25 until Friday, July 6. 9 p.m. until 5 a.m. Northbound main lanes between Sonterra Boulevard exit ramp and entrance ramp. The right and center lane will be closed for bridge work. 
  • Monday, June 25 until Friday, July 6. 9 p.m. until 5 a.m. All lanes on southbound main lanes between Sonterra Boulevard entrance ramp and Loop 1604 frontage road closed for bridge work. Traffic will use the Sonterra Boulevard entrance ramp and exit at Donella Drive, take turnaround and turn left on the westbound frontage road. 
  • Wednesday, June 27 until Friday, June 29. 8 p.m. until 5 a.m. All westbound frontage road lanes on Loop 1604 between US 281 southbound to Stone Oak Parkway exit ramp closed for bridge beam work. Traffic will take the turnaround at US 281 and continue west to Redland Road and take turnaround; use Redland Road entrance ramp and exit at Stone Oak Parkway. 
Loop 1604 – West San Antonio
  • Current until Saturday, June 23. 9 p.m. until 5 a.m. All main lanes in both directions over the bridge at US 90 will be closed for bracket work. Traffic will take US 90 westbound and exit on Montgomery and take the turnaround. 
  • Current until Saturday, June 23. 9 p.m. until 5 a.m. Westbound US 90 turnaround to eastbound turnaround will be closed for bracket work. 
  • Current until Saturday, June 23. 9 p.m. until 5 a.m. Both directions at US 90. Two lanes closed for bracket work. 
  • Monday, June 25 until Friday, June 29. 9 a.m. until 3 p.m. Southbound at Alamo Ranch Parkway exit ramp. The exit ramp will be closed for concrete barrier work. Traffic will need to use the Culebra Road exit. 
  • Monday, June 25 until Friday, June 29. 9 a.m. until 3 p.m. Wiseman Boulevard, both directions at Loop 1604. The right lane will be close for traffic signal pole foundation work, and concrete curb and median work. 
  • Monday, June 25 until Friday, June 29. 9 a.m. until 3 p.m. Military Drive, both directions at Loop 1604. The right lane will be close for traffic signal pole foundation work. 
  • Monday, June 25 until Friday, June 29. 9 a.m. until 3 p.m. FM 1957 (Potranco Road), both directions at Loop 1604. The right lane will be close for traffic signal pole foundation work. 
Other roads – Boerne
  • Current until Friday, 29. 8 a.m. until 5 p.m. Alternating main lanes closed in both directions of SH 46 just 4 miles south of I-10 to the Kendall/Bandera County Line 
Other roads – Converse
  • Current and continuous until Friday, August 24. FM 78 at FM 1516. The right turn lane will close while crews do road work. Oversized vehicles will use FM 3502 to reach its destination. 
Other roads – Helotes
  • Current and continuous until Monday, July 2. Riggs Road, both directions, at FM 1560. All lanes are restricted while crews reconstruct the intersection. The turn radius is tight and trucks with trailers should not use this intersection. 
  • Current and continuous until Friday, September 28. Northbound Bandera Road at FM 1560. The left turn lane will close while crews do road work. No left turns will be permitted. Traffic will continue to the next intersection and turn around to reach its destination. Cross traffic from Circle A is also blocked. 
Other roads – Northwest San Antonio
  • Current until Friday, June 29. 9 a.m. until 3 p.m. Spur 345 (Fredericksburg Road), both directions, between Clarke Drive and Bluemel. The right lane will be closed for sidewalk and driveway work. 
  • Current until Friday, June 29. 9 a.m. until 3 p.m. Spur 345 (Fredericksburg Road), both directions, between Bluemel and Callaghan Road. The right lane will be closed for sidewalk and driveway work.  
All closures are pending weather

Thursday, June 21

Upcoming weekend major closures

We have a couple of upcoming major full main lane closures happening over the next couple of weeks:

I-410/SH 151 - UPDATED
Starting Friday, June 22 at 9 p.m. until Saturday, June 23 at 7 a.m., crews will be closing all I-410 northbound main lanes between Ingram Road and SH 151 to remove barrier and restripe. Northbound I-410 traffic will need to exit SH 151 and travel through the intersection to enter I-410 at the Culebra Road entrance ramp. Also, crews will be removing barrier on one lane on I-410 southbound between Ingram Road and Military Drive.


I-10 at Dominion Drive
Starting Friday, June 29 at 9 p.m. until Monday, July 2 at 5 a.m., crews will be closing all main lanes both directions on I-10 between Camp Bullis Road and Boerne Stage Road for beam work at Dominion Drive. The underpass at Dominion Drive and entrance ramps will also be closed. Westbound traffic will detour at Boerne Stage Road and eastbound traffic will detour at Camp Bullis.

Loop 337 Summer Update

As summer goes into full swing in New Braunfels (hooray for weekend tubing down the river!), our 4-year project to widen Loop 337 from two lanes to a four-lane divided highway continues to progress. This project will increase driver and pedestrian safety on the 6.7-mile stretch between I-35 and Hillcrest Drive and keep traffic flowing in our expanding city. We want you to be able to navigate your summer plans safely, so here’s what is happening now.

We’re making steady progress on the new bridges that are part of the Loop 337 widening. Construction on the Guadalupe River, Blieders Creek, Dry Comal Creek, and Landa Street bridges will continue this month, and we’re gearing up for placing new concrete girders—which are basically bridge support beams—at the Gruene Road/Rock Street overpass. Crews also recently completed some paving work near River Road to California Boulevard. Drainage work is ongoing throughout the area, with some sections being recently completed.

Some other activities that you can expect to see us working on in the next few months include the installation of traffic signals at Hanz Drive, SH 46, Oak Run Parkway, and San Antonio Street, as well as performing entrance and exit ramp work at several locations including Gruene Road and Rock Street.

We understand construction can be tough on everyone. We’re happy to report that no safety issues have been reported at this time. TxDOT and the contractor are committed to minimizing impacts to travelers and traffic flow and we appreciate your patience and safe driving during this project.

Friday, June 15

Next week's construction-related closures

I-35 – New Braunfels
  • Current until Friday, June 22. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, at FM 306. The right lane will close while crews survey the road bed. This closure includes the exit ramps to FM 306. Traffic will use the next ramp and turn around to reach its destination. 
I-35 – Schertz
  • Current and continuous until October 2018. Frontage roads, both directions, at FM 1103. One lane will close while crews replace the FM 1103 overpass bridge. 
I-35 – Northeast San Antonio
  • Current until Monday, June 18. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between Thousand Oaks and George Beach. Alternating lanes will close while crews install highway signs. 
I-410 – West San Antonio
  • Current and continuous until December 2018. Turnarounds, both directions, at Marbach Road. The turnarounds will remain closed while crews construct the new Marbach overpass bridge. Traffic will use the signalized intersection. 
  • Current and continuous until December 2018. Northbound exit ramp to Marbach. The ramp will remain closed while crews reconstruct the road. Traffic will exit US Hwy 90 and continue along the frontage road to reach its destination. 
  • Current until Friday, June 22. 9 p.m. until 5 a.m. nightly. Southbound connector ramp to westbound Hwy 151. The ramp will close while crews do roadwork. Traffic will exit Military Drive and follow the frontage road to reach its destination. 
  • Sunday, June 17 until Friday, June 22. 9 p.m. until 5 a.m. Eastbound frontage road between Ray Ellison Boulevard and Valley Hi Drive. Alternating lanes closed for mill and overlay work. 
  • Monday, June 18 until Friday, June 22. 9 a.m. until 3 p.m. Eastbound frontage road at Old Pearsall Road. Alternating lanes closed for concrete work. 
  • Monday, June 18 until Friday, June 22. 9 a.m. until 4 p.m. Southbound frontage road at Ray Ellison Boulevard and Lake Valley Street. Alternating lanes closed for concrete work. 
I-10 – West San Antonio
  • Current until Friday, June 22. 9 a.m. until 3 p.m. Westbound frontage road lane between Boerne Stage Road and Dominion Drive. One lane closed for retaining wall work. 
U.S. Hwy 281 – Far North San Antonio
  • Current until Friday, June 29. 9 p.m. until 5 a.m. nightly. Northbound main lanes at Sonterra Boulevard. The right lane will close while crews do bridge work. This closure includes the Sonterra exit. Traffic will follow the posted detour. 
  • Monday, June 11 until Friday, June 29. 9 p.m. until 5 a.m. The right and center lanes of northbound US 281 between the Sonterra Boulevard exit ramp and the Sonterra Boulevard entrance ramp, and the Sonterra Boulevard exit ramp, will be closed nightly. Off-duty police will assist with traffic control as needed.
  • Monday, June 18 until Friday, June 22. 9 p.m. until 5 a.m. All frontage road lanes on southbound US 281 between Sonterra Boulevard entrance ramp to the westbound frontage road of Loop 1604 for setting beams and bridge work on the southbound to westbound direct connector. 
  • Monday, June 18 until Friday, June 22. 8 p.m. until 5 a.m. All frontage road lanes on northbound US 281 from Loop 1604 to Sonterra Boulevard exit ramp will be closed for setting beams on the westbound to northbound direct connector. 
State Hwy 151
  • Current until Friday, June 22. 9 p.m. until 5 a.m. nightly. Westbound main lanes between I-410 and Military Drive. All lanes will close while crews resurface the road. Traffic will exit I-410, continue along the frontage road and use the next available ramp to reach its destination. 
Loop 1604 – North San Antonio
  • Saturday, June 16. 12 midnight until 12 noon. All main lanes on eastbound Loop 1604 from the US 281 northbound exit ramp to the Gold Canyon Drive entrance ramp will be closed for setting beams on the southbound to eastbound direct connector. 
  • Monday, June 18 until Friday, June 22. 8 p.m. until 5 a.m. All frontage road lanes on westbound Loop 1604 from Gold Canyon Drive to US 281 will be closed for setting beams on the westbound to northbound direct connector. 
Other roads – Converse
  • Current and continuous until Friday, August 24. FM 78 at FM 1516. The right turn lane will close while crews do road work. Oversized vehicles will use FM 3502 to reach its destination. 
Other roads – Helotes
  • Current and continuous until Monday, July 2. Riggs Road, both directions, at FM 1560. All lanes are restricted while crews reconstruct the intersection. The turn radius is tight and trucks with trailers should not use this intersection. 
  • Current and continuous until Friday, September 28. Northbound Bandera Road at FM 1560. The left turn lane will close while crews do road work. No left turns will be permitted. Traffic will continue to the next intersection and turn around to reach its destination. Cross traffic from Circle A is also blocked. 
Other roads – Northwest San Antonio
  • Monday, June 18 until Friday, June 22. 9 a.m. until 3 p.m. Spur 345 (Fredericksburg Road), both directions, between Clarke Drive and Bluemel. The right lane will be closed for sidewalk and driveway work. 
  • Monday, June 18 until Friday, June 22. 9 a.m. until 3 p.m. Spur 345 (Fredericksburg Road), both directions, between Bluemel and Callaghan Road. The right lane will be closed for sidewalk and driveway work.

Wednesday, June 13

Temporary entrance ramp on I-410/SH 151 project

Be on the lookout for something different Thursday morning. The existing I-410 southbound entrance ramp from SH 151 just north of Marbach Road will be closed. Traffic will use the new temporary entrance ramp just south of the existing exit to Lakeside Parkway. The purpose of this is to allow the contractor to work on the Marbach Road bridge and retaining wall. The temporary entrance ramp will be in place until the end of the year.

Saturday, June 9

Next week's construction-related closures

I-35 – New Braunfels
  • Current until Friday, June 22. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, at FM 306. The right lane will close while crews survey the road bed. This closure includes the exit ramps to FM 306. Traffic will use the next ramp and turn around to reach its destination. 

I-35 – Schertz
  • Current and continuous until October 2018. Frontage roads, both directions, at FM 1103. One lane will close while crews replace the FM 1103 overpass bridge. 

I-35 – Northeast San Antonio
  • Current until Monday, June 18. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between Thousand Oaks and George Beach. Alternating lanes will close while crews install highway signs. 

I-410 – West San Antonio
  • Sunday, June 10 until Monday, June 11. 9 p.m. until 5 a.m. Southbound main lanes between Culebra Road and W. Military Drive complete closure for concrete pour and paving. Traffic will exit at W. Military Drive and re-enter at next entrance. 
  • Current and continuous until December 2018. Turnarounds, both directions, at Marbach Road. The turnarounds will remain closed while crews construct the new Marbach overpass bridge. Traffic will use the signalized intersection. 
  • Current and continuous until December 2018. Northbound exit ramp to Marbach. The ramp will remain closed while crews reconstruct the road. Traffic will exit US Hwy 90 and continue along the frontage road to reach its destination. 
  • Current and continuous until Friday, June 15. North and south connector ramps to westbound US Hwy 90. The ramps will remain closed while crews work on an overhead bridge structure. Traffic will go east to Military and turn around to reach westbound US 90. 
  • Current until Friday, June 22. 9 p.m. until 5 a.m. nightly. Southbound connector ramp to westbound Hwy 151. The ramp will close while crews do roadwork. Traffic will exit Military Drive and follow the frontage road to reach its destination. 
  • Current and continuous until Wednesday, June 13. 9 a.m. until 4 p.m. daily. Northbound exit ramp to Culebra Road. The ramp will close while crews do concrete work. Traffic will take the next exit and turn around to reach its destination. 

I-410 – North San Antonio
  • Monday, June 11 until Friday, June 15. 9 a.m. until 3 p.m. Alternating main lanes closed between Crossroads Boulevard and Interchange Parkway for concrete work. 

U.S. Hwy 281 – Far North San Antonio
  • Sunday, June 10 until Monday, June 11. 9 p.m. until 5 a.m. The left lane of the southbound US 281 frontage road under Loop 1604 will be closed. Off-duty police will assist with traffic control, as needed. 
  • Current until Friday, June 29. 9 p.m. until 5 a.m. nightly. Northbound main lanes at Sonterra Boulevard. The right lane will close while crews do bridge work. This closure includes the Sonterra exit. Traffic will follow the posted detour. 
  • Monday, June 11 until Friday, June 29. 9 p.m. until 5 a.m. The right and center lanes of northbound US 281 between the Sonterra Boulevard exit ramp and the Sonterra Boulevard entrance ramp, and the Sonterra Boulevard exit ramp, will be closed nightly. Off-duty police will assist with traffic control as needed. 
  • Monday, June 11 until Tuesday, June 12. 9 a.m. until 5 a.m. The right and center lanes of southbound US 281 between the Redland Road and the Sonterra Boulevard exit ramp will be closed nightly. Off-duty police will assist with traffic control as needed. 
  • Wednesday, June 13 until Friday, June 15. 9 p.m. until 5 a.m. All lanes of the southbound US 281 frontage road between the Sonterra Boulevard entrance ramp and the westbound frontage road of Loop 1604 will be. Drivers should use the Sonterra Boulevard entrance ramp; use the Donella Drive turnaround, and then take a left at the westbound frontage road. Off-duty police will assist with traffic control as needed. 
State Hwy 151
  • Current until Friday, June 22. 9 p.m. until 5 a.m. nightly. Westbound main lanes between I-410 and Military Drive. All lanes will close while crews resurface the road. Traffic will exit I-410, continue along the frontage road and use the next available ramp to reach its destination. 

Loop 1604 – North San Antonio
  • Monday, June 11 until Friday, June 15. 9 p.m. until 5 a.m. Alternating lanes of westbound Loop 1604 from the US 281 north exit ramp and the Stone Oak Parkway exit ramp will be closed nightly. Off-duty police will assist with traffic control as needed. 

Loop 1604 – West San Antonio
  • Tuesday, June 12 until Saturday, June 16. 9 p.m. until 5 a.m. All lanes on both sides of Loop 1604 bridge over US 90 will be closed for installing overhang brackets. Traffic needs to tale US 90 west and exit on WT Montgomery and take turnaround. US 90 eastbound entrance ramp from Loop 1604 will also be closed. Closure will be done nightly. 

SH 16 – Northwest San Antonio
  • Monday, June 11 until Friday, June 15. 9 p.m. until 5 a.m. Alternating lanes closed between Legend Trail and Loop 1604 frontage road for striping and concrete traffic barrier placement. Closure will be done nightly. 

SH 46 – Boerne
  • Monday, June 11 until Tuesday, June 12. 9 p.m. until 5 a.m. Alternating lanes on both side of SH 46 ½ mile west of Coveney Trail and Cordillera Trace will be closed for placing concrete barrier on the shoulder. 

Other roads – Converse
  • Monday, June 11 until Friday, August 24. FM 78 at FM 1516. The right turn lane will close while crews do road work. Oversized vehicles will use FM 3502 to reach its destination. 

Other roads – Helotes 
  • Current and continuous until Monday, July 2. Riggs Road, both directions, at FM 1560. All lanes are restricted while crews reconstruct the intersection. The turn radius is tight and trucks with trailers should not use this intersection.
  • Current and continuous until Friday, September 28. Northbound Bandera Road at FM 1560. The left turn lane will close while crews do road work. No left turns will be permitted. Traffic will continue to the next intersection and turn around to reach its destination. Cross traffic from Circle A is also blocked. 

Other roads – North San Antonio
  • Monday, June 11 until Friday, June 15. 9 p.m. until 5 a.m. Alternating lanes of eastbound Loop 1604 from the Loop 1604 direct connect exit ramp to southbound US 281 and the Gold Canyon Drive exit ramp will be closed nightly. Off-duty police will assist with traffic control as needed. 
  • Monday, June 11 until Friday, June 15. 9 p.m. until 5 a.m. The left lane of eastbound TPC Parkway east of US 281 will be closed nightly. Off-duty police will assist with traffic control as needed. 
  • Monday, June 11 until Friday, June 15. 9 p.m. until 5 a.m. The left lane of westbound TPC Parkway east of US 281 will be closed nightly. Off-duty police will assist with traffic control as needed. 
  • Monday, June 11, until 5 a.m. on Friday, June 15. 9 p.m. until 5 a.m. Alternating lanes of westbound Encino Rio east of US 281 will be closed nightly. Off-duty police will assist with traffic control as needed. 
  • Monday, June 11, until 5 a.m. on Friday, June 15. 9 p.m. until 5 a.m. Alternating lanes of eastbound Encino Rio east of US 281 will be closed nightly. Off-duty police will assist with traffic control as needed. 

Other roads – Northwest San Antonio

  • Monday, June 11 until Friday, June 15. 9 a.m. until 3 p.m. Spur 345 (Fredericksburg Road), both directions, between Clarke Drive and Bluemel. The right lane will be closed for sidewalk and driveway work. 
  • Monday, June 11 until Friday, June 15. 9 a.m. until 3 p.m. Spur 345 (Fredericksburg Road), both directions, between Bluemel and Callaghan Road. The right lane will be closed for sidewalk and driveway work. 



All closures are pending weather

Friday, June 1

Next week's construction-related closures

I-10 – Leon Springs
  • Friday, June 1 at 9 p.m. until Monday, June 4 at 5 a.m. Eastbound main lanes at Camp Bullis. All lanes will close while crews set bridge support beams. Traffic will exit Camp Bullis, continue along the frontage road and re-enter the highway at the next available ramp.
I-35 – New Braunfels
  • Monday, June 4 until Friday, June 22. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, at FM 306. The right lane will close while crews survey the road bed. This closure includes the exit ramps to FM 306. Traffic will use the next ramp and turn around to reach its destination.
I-35 – Schertz
  • Current and continuous until October 2018. Frontage roads, both directions, at FM 1103. One lane will close while crews replace the FM 1103 overpass bridge.
I-35 – Northeast San Antonio
  • Saturday, June 2. 9 a.m. until 3 p.m. Frontage roads, both directions, between Thousand Oaks and George Beach. Alternating lanes will close while crews do finishing road work.
  • Monday, June 4 until Monday, June 18. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between Thousand Oaks and George Beach. Alternating lanes will close while crews install highway signs.
I-410 – West San Antonio
  • Current and continuous until December 2018. Turnarounds, both directions, at Marbach Road. The turnarounds will remain closed while crews construct the new Marbach overpass bridge. Traffic will use the signalized intersection.
  • Current and continuous until December 2018. Northbound exit ramp to Marbach. The ramp will remain closed while crews reconstruct the road. Traffic will exit US Hwy 90 and continue along the frontage road to reach its destination.
  • Current and continuous until Friday, June 15. North and south connector ramps to westbound US Hwy 90. The ramps will remain closed while crews work on an overhead bridge structure. Traffic will go east to Military and turn around to reach westbound US 90.
  • Monday, June 3 until Friday, June 22. 9 p.m. until 5 a.m. nightly. Southbound connector ramp to westbound Hwy 151. The ramp will close while crews do roadwork. Traffic will exit Military Drive and follow the frontage road to reach its destination.
  • Tuesday, June 4 until Wednesday, June 13. 9 a.m. until 4 p.m. daily. Northbound exit ramp to Culebra Road. The ramp will close while crews do concrete work. Traffic will take the next exit and turn around to reach its destination.
U.S. Hwy 281 – Far North San Antonio
  • Current until Thursday, June 7. 9 p.m. until 5 a.m. nightly. Northbound main lanes at Loop 1604. The right lane will close while crews do road work.
  • Current until Thursday, June 7. 9 p.m. until 5 a.m. nightly. Northbound frontage road at Loop 1604. The right lane will close while crews set barrier.
  • Monday, June 4 until Friday, June 8. 9 p.m. until 5 a.m. nightly. Northbound frontage roads at Loop 1604. The right lane will close while crews work on traffic signals.
  • Monday, June 4 until Friday, June 8. 9 p.m. until 5 a.m. nightly. Southbound main lanes between Redland Road and Sonterra Boulevard. The right lane will close while crews do bridge work.
  • Monday, June 4 until Friday, June 8. 9 p.m. until 5 a.m. nightly. Northbound main lanes at TPC Parkway. The right-turn lane will close while crews work on the concrete median.
  • Monday, June 4 until Friday, June 29. 9 p.m. until 5 a.m. nightly. Northbound main lanes at Sonterra Boulevard. The right lane will close while crews do bridge work. This closure includes the Sonterra exit. Traffic will follow the posted detour.
State Hwy 151
  • Current until Friday, June 8. 9 p.m. until 5 a.m. nightly. Westbound main lanes between West Military Drive and I-410. All lanes will close while crews resurface the roadway. Traffic will exit I-410, continue through the intersections and re-enter the highway at the next available ramp.
  • Sunday, June 3 until Wednesday, June 6. 9 p.m. until 5 a.m. nightly. Eastbound main lanes between I-410 and Military Drive. All lanes will close while crews do overhead bridge work. Traffic will exit I-410, continue along the frontage road and use the next available ramp to reach its destination.
  • Sunday, June 3 until Friday, June 22. 9 p.m. until 5 a.m. nightly. Westbound main lanes between I-410 and Military Drive. All lanes will close while crews resurface the road. Traffic will exit I-410, continue along the frontage road and use the next available ramp to reach its destination.
Loop 1604 – North San Antonio
  • Monday, June 4 until Friday, June 8. 9 p.m. until 5 a.m. nightly. Eastbound main lanes between US 281 and Gold Canyon. The left lane will close while crews do overhead bridge work.
Other roads – Converse
  • Monday, June 11 until Friday, August 24. FM 78 at FM 1516. The right turn lane will close while crews do road work. Oversized vehicles will use FM 3502 to reach its destination.
Other roads – Helotes
  • Current and continuous until Monday, July 2. Riggs Road, both directions, at FM 1560. All lanes are restricted while crews reconstruct the intersection. The turn radius is tight and trucks with trailers should not use this intersection.
  • Current and continuous until Friday, September 28. Northbound Bandera Road at FM 1560. The left turn lane will close while crews do road work. No left turns will be permitted. Traffic will continue to the next intersection and turn around to reach its destination. Cross traffic from Circle A is also blocked.
Other roads – Leon Springs
  • Friday, June 1 at 9 p.m. until Monday, June 4 at 5 a.m. Camp Bullis, both directions, at I-10. All lanes will close while crews set bridge support beams overhead. Traffic will turn right onto the frontage road and turn around at the next intersection to reach its destination.
Other roads – North San Antonio
  • Monday, June 4 until Friday, June 15. 9 p.m. until 5 a.m. nightly. TPC Parkway, both directions, at US Hwy 281. The left lane will close while crews work on the concrete median.
All closures are pending weather.