Friday, March 27

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North Central San Antonio
  • Saturday, March 28 until Monday, March 30. Weekend closure 2 a.m. until 5 a.m. Right lane westbound mainlane frontage road closure from US 281 to the Stone Oak Parkway exit ramp for safety work.
  • Monday, March 30 until Friday, April 3. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure from the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Monday, March 30 until Friday, April 3. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Monday, March 30 until Friday, April 3. Nightly 9 p.m. until 5 a.m. Left lane westbound frontage road closure from the north US 281 exit ramp to the US 281 northbound frontage road for concrete work.
  • Saturday, April 4 until Monday, April 6. Full weekend closure 3 a.m. until 5 a.m. Full eastbound mainlane closure of the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Saturday, April 4 until Monday, April 6. Full weekend closure 3 a.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Saturday, April 4 until Monday, April 6. Continuous 3 a.m. until 5 a.m. Eastbound frontage road closure of the east- to westbound turnaround at US 281 for direct connector work.
Loop 1604 – Northeast San Antonio
  • Sunday, March 29 until Friday, April 3. Nightly 8 p.m. until 5 a.m. One mainlane in both directions between Green Mountain Road and I-35 for guard rail and mow strip work.
  • Sunday, March 29 until Thursday, April 2. Nightly 9 p.m. until 5 a.m. One mainlane in both directions between Bulverde Road and Green Mountain Road for guard fence work.
  • Monday, March 30 until Thursday, April 2. Daily 9 a.m. until 5 p.m. Eastbound left mainlane at Lookout Road (including turnaround) for concrete bridge rail work.
Loop 1604 – Northwest San Antonio
  • None scheduled.
Loop 1604 – Far East San Antonio
  • None scheduled.
Loop 1604 – South San Antonio
  • None scheduled.
US 281 – North Central San Antonio/Bexar County
  • Saturday, March 28 until Monday, March 30. Continuous 2 a.m. until 5 a.m. Northbound mainlane closure from the north- to southbound turnaround at Evans Road for bridge work. DETOUR: Use the next turnaround at Stone Oak/Tournament Players Club (TPC) Parkway.
  • Saturday, March 28 until Monday, March 30. Continuous 2 a.m. until 5 a.m. Southbound mainlane closure from the south- to northbound turnaround at Evans Road for bridge work. DETOUR: Use the next turnaround at Encino Rio.
  • Saturday, March 28 until Monday, March 30. Continuous 2 a.m. until 5 a.m. Left turn lane northbound mainlane closure at Evans Road both north- to westbound turn lanes for bridge work. DETOUR: Use the next turnaround at Stone Oak/Tournament Players Club (TPC) Parkway.
  • Saturday, March 28 until Monday, March 30. Continuous 2 a.m. until 5 a.m. Left turn lane southbound mainlane closure at Evans Road both south- to eastbound turn lanes for bridge work. DETOUR: Use the next turnaround at Encino Rio.
  • Monday, March 30 until Friday, April 3. Nightly 9 p.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound frontage road, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Monday, March 30 until Friday, April 3. Nightly 9 p.m. until 5 a.m. Full northbound mainlane ramp closure of the north- to westbound Loop 1604 direct connector ramp for bridge work. DETOUR: Use the frontage road exit ramp, turn left on the Loop 1604 westbound frontage road, and continue on the US 281 entrance ramp.
  • Monday, March 30 until Friday, April 3. Nightly 9 p.m. until 5 a.m. Full northbound frontage road closure from Loop 1604 to Sonterra Boulevard for bridge work. DETOUR: Turn left on the southbound US 281 frontage road, take the turnaround at Donella Drive and use the Donella Drive entrance ramp.
  • Monday, March 30 until Friday, April 3. Nightly 9 p.m. until 5 a.m. Northbound mainlane closure from the north- to southbound turnaround at Evans Road for bridge work. DETOUR: Use the next turnaround at Stone Oak/Tournament Players Club (TPC) Parkway.
  • Monday, March 30 until Friday, April 3. Nightly 9 p.m. until 5 a.m. Southbound mainlane closure from the south- to northbound turnaround at Evans Road for bridge work. DETOUR: Use the next turnaround at Encino Rio.
  • Monday, March 30 until Friday, April 3. Nightly 9 p.m. until 5 a.m. Left turn lane northbound mainlane closure at Evans Road both north- to westbound turn lanes for bridge work. DETOUR: Use the next turnaround at Stone Oak/Tournament Players Club (TPC) Parkway.
  • Monday, March 30 until Friday, April 3. Nightly 9 p.m. until 5 a.m. Left turn lane southbound mainlane closure at Evans Road both south- to eastbound turn lanes for bridge work. DETOUR: Use the next turnaround at Encino Rio.
  • Monday, March 30 until Friday, April 3. Nightly 9 p.m. until 5 a.m. Left turn lane southbound mainlane closure at Encino Rio both south- to eastbound turn lanes for bridge work. DETOUR: Use the turnaround south of Encino Rio.
  • Monday, March 30 until Friday, April 3. Nightly 9 p.m. until 5 a.m. Left turn lane northbound mainlane closure at Encino Rio both north- to westbound turn lanes for bridge work. DETOUR: Use the turnaround north of Evans Road.
  • Monday, March 30 until Friday, April 3. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Marshall Road for bridge work and safety enhancements.
  • Monday, March 30 until Friday, April 3. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for bridge work and safety enhancements.
  • Saturday, April 4 until Monday, April 6. Continuous 3 a.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound frontage road, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Saturday, April 4 until Monday, April 6. Continuous 3 a.m. until 5 a.m. Full northbound mainlane closure from the frontage road exit ramp to the Sonterra Boulevard entrance ramp. DETOUR: Use the frontage road exit ramp, turn right on the Loop 1604 eastbound frontage road, if heading north, take the turnaround at Gold Canyon Road, turn right on the northbound frontage road and use the Stone Oak Parkway exit ramp.
  • Saturday, April 4 until Monday, April 6. Continuous 3 a.m. until 5 a.m. Full southbound frontage road closure at Loop 1604 for direct connector work. DETOUR: Turn right on the westbound frontage road, take the turnaround at Stone Oak Parkway and turn right on the southbound frontage road.
  • Saturday, April 4 until Monday, April 6. Continuous 3 a.m. until 5 a.m. Northbound Redland Road bypass ramp mainlane closure from Sonterra Boulevard to Encino Rio for ramp work.
  • Saturday, April 4 until Monday, April 6. Continuous 3 a.m. until 5 a.m. Left turn lane southbound mainlane closure at Encino Rio both south- to eastbound turn lanes for bridge work. DETOUR: Use the turnaround south of Encino Rio.
  • Saturday, April 4 until Monday, April 6. Continuous 3 a.m. until 5 a.m. Left turn lane northbound mainlane closure at Encino Rio both north- to westbound turn lanes for bridge work. DETOUR: Use the turnaround north of Evans Road.
US 281 – South San Antonio
  • Current until Friday, April 3. Daily 9 a.m. until 5 p.m. Alternating mainlanes in both directions at Loop 1604 for mow strip and guard fence installation work.
I-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County
  • Current until Thursday, April 9. Daily 7 a.m. until 7 p.m. Eastbound right mainlane and shoulder between Kerr/Gillespie county line and Kerr/Kimble county line for paving work.
  • Current until 4 p.m. Saturday, March 28. Westbound right mainlane between US 87 and Scenic Loop Road for milling and asphalt work.
  • Sunday, March 29 until Friday, April 3. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure between Camp Bullis Road and Boerne Stage Road for overhead sign bridge and sign structure installation work.
  • Sunday, April 5 until Friday, April 10. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure between Dominion Drive and Two Creeks for overhead sign bridge and sign structure installation work.
  • Friday, April 18. 6:30 a.m. until 5 p.m. Right frontage road lane in both directions between Scenic Loop Road and Balcones Creek (Bexar/Kendall county line) including turnaround for beam delivery work.
I-10 – Far East San Antonio/Bexar County/Seguin/Guadalupe County
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Current until further notice. Eastbound entrance ramp from Foster Road. DETOUR: Take next entrance ramp east of Woodlake Parkway.
  • Friday, March 27 until Monday, March 30. Daily 9 a.m. to 3 p.m. The westbound right mainlane between Loop 1604 and Woodlake Pkwy will be closed each day to remove/relocate barriers. DETOUR: Westbound traffic will have access to the left mainlane.
  • Saturday, March 28. 6:30 a.m. until 12 noon. Eastbound right mainlane between Scenic Loop Road and Balcones Creek for traffic switch.
  • Monday, March 30 until Friday, April 3. Daily 9 a.m. to 3 p.m. One alternating lane of Ackerman Road in each direction under I-10 for bridge construction activities.
  • Friday, April 3 until Monday, April 6. 9 p.m. to 5 a.m. All eastbound I-10 mainlanes from just east of W.W. White to Ackerman Road will be closed for traffic switch activities. DETOUR: Eastbound I-10 mainlane drivers will be directed to take the I-410 South/Ackerman Road exit, remain on the collector-distributor road that travels under I-410, exit to the frontage road at Ackerman Road, and re-enter the I-10 mainlanes east of Ackerman.
I-10 – Central San Antonio
  • None scheduled.
I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County
  • Monday, March 30 until Friday, April 3. Daily 8:30 a.m. until 4 p.m. Alternating southbound frontage road lanes at George Beach for sidewalk and curb installation work.
I-37 – Central San Antonio
  • None scheduled.
I-410 – West San Antonio
  • Current until Monday, March 30. Weekend 8 p.m. to 5 a.m. Two alternating lanes in each direction between SH 151 to Valley Hi Drive for mill and inlay work.
  • Friday, March 27 until Monday, March 30. Full weekend closure 8 p.m. to 5 a.m. All northbound mainlanes between US 90 and Marbach Road for mill and inlay operations. DETOUR: Traffic will exit to US 90 and re-enter before SH 151.
  • Monday, March 30 until Tuesday, March 31. Daily 8:30 a.m. to 3 p.m. The left southbound frontage road between Zabra Street to US 90 bridge for metal beam guard fence work. DETOUR: Traffic will be detoured to the US 90 westbound frontage road, turnaround at Hunt Lane bridge, continue on the US 90 eastbound frontage road to access I-410 southbound frontage road.
  • Monday, March 30 until Friday, April 3. Nightly 9 p.m. to 5 a.m. The left lane in both direction between the exit ramp of SH 151 to just south of SH 151 for placing concrete traffic barrier and striping work.
  • Tuesday, March 31 until Thursday, April 2. Daily 8:30 a.m. to 3 p.m. Two southbound frontage road lanes at US 90 westbound frontage road for metal beam guard fence work. DETOUR: Traffic will be detoured to take the southbound to eastbound cloverleaf, continue on the US 90 eastbound frontage, turnaround at W. Military Drive and continue on the US 90 westbound frontage road
  • Friday, April 3 until Monday, April 6. Weekend 8 p.m. to 5 a.m. All lanes in both directions for setting trusses on overhead sign structures. The east/northbound and south/westbound connector will also be closed. NORTHBOUND DETOUR: Traffic traveling north will detoured to the exit to US 90, continue on the I-410 northbound frontage road, travel through the Marbach Road intersection, and continue on the I-410 northbound frontage road to utilize the next available on ramp. SOUTHBOUND DETOUR: Traffic traveling south will be detoured to exit at Marbach Road, continue on the frontage road, travel through the Marbach Road intersection, continue on frontage road to utilize the next available on-ramp before Valley Hi Drive.
US 90 – West San Antonio
  • Friday, March 27 until Saturday, March 28. Nightly 7 p.m. to 5 a.m. The right westbound mainlane between I-410 bridge to Hunt Lane bridge for staging equipment and striping work.
  • Current until 5 p.m. Monday, March 30. Eastbound left mainlane at SH 211, westbound right mainlane at SH 211, westbound exit to SH 211 for pavement work.
SH 16 – Bandera Road
  • None scheduled.
FM 3351 – Ralph Fair Road
  • None scheduled.
PA 1502 – Wurzbach Parkway
  • City of San Antonio/TCI closure for Hardberger Park Landbridge project. Monday, March 30 until Friday, April 3. 9 a.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
  • City of San Antonio/TCI closure for Hardberger Park Landbridge project. Monday, April 6 until Friday, April 10. 9 a.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
FM 2252 – Nacagdoches Road
  • None scheduled.
FM 1560 – Hausman Road
  • Exit ramp from Loop 1604 eastbound closed for approximately two months starting Monday, March 16.
SH 218 – Pat Booker Road
  • None scheduled.
Spur 371 – General Hudnell Drive
  • None scheduled.
US 87 – Roland Avenue
  • Current until 4 p.m. Sunday, March 29. One southbound lane between I-10 and Rigsby Avenue for placing sod, manhole and electrical work.
Spur 421 – Bandera Road
  • Sunday, March 29 until Saturday, April 4. Nightly 7 p.m. to 7 a.m. One lane in both directions between I-410 to Cheryl Drive for milling and paving work.
FM 1976 – Walzem Road/Gibbs Sprawl Road
  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes between Woodlake Parkway and Gibbs Sprawl Road for barrier/pavement work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
  • Current until further notice. Full-day closure. Southbound lane between Toepperwein Road and Walzem Road for barrier setting work and road rehab work.
Loop 353 – New Laredo Highway
  • None scheduled.
Other Roads – Bexar County
  • Monday, March 30 until Friday, April 3. Nightly 9 p.m. until 5 a.m. Full westbound closure of Encino Rio at US 281 for bridge work. DETOUR: Head right on US 281 and take the next turnaround.
  • Saturday, April 4. 8 a.m. until 5 p.m. Full closure of Mountain Lodge Road in both directions at US 281 for traffic switch.
Loop 337 – New Braunfels/Comal County
  • Current until Tuesday, April 7. Full-time closure. Northbound access road to Landa Street for road widening, traffic island removal, sidewalk and curb work.
FM 1863 – Comal County
  • Current until Friday, April 3. Daily 7 a.m. until 6 p.m. One lane in both directions between FM 3009 and FM 311 (one-way traffic control) for pavement repair work.
FM 2673 – Canyon Lake/Comal County
  • None scheduled.
FM 1516 – South Seguin Road/Converse
  • None scheduled.
FM 2252 – Comal County
  • None scheduled.
SH 46 – Guadalupe County
  • None scheduled.
FM 78 – Guadalupe County
  • None scheduled.

FM 1518 – Schertz/Cibolo Guadalupe County
  • None scheduled.
US 90A – Seguin/Guadalupe County
  • None scheduled.
SH 123 – Seguin/Guadalupe County
  • None scheduled.
Business 123 – South Austin Street/Seguin/Guadalupe County
  • None scheduled.
I-35 – Atascosa County/Frio County
  • None scheduled.
US 181 – Floresville/Wilson County
  • None scheduled.
US 87 – Wilson County
  •  None scheduled.
SH 46 – Boerne/Kendall County
  • Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
RM/FM 1376 – Kendall County
  • None scheduled.
FM 1333 – Atascosa County
  • Current until Friday, May 1. Full closure (all day) in both directions at Atascosa River (between FM 476 and SH 173) for culvert removal and replacement work.
FM 140 – Atascosa County
  • None scheduled.
SH 16 – McMullen County
  • Monday, March 30 until April 3. Daily 7 a.m. until 6 p.m. Alternating lanes in both directions between Ben Franklin Road and McMullen/Duval County line for paving work.

Thursday, March 26

Long-Term Lane Closure In Effect On US 281 Segment I Expansion Project

We continue making great progress on the ever-complex US 281 Segment I Expansion Project, which involves many moving targets within its limits of Loop 1604 to just north of Stone Oak Parkway.

Work on the new mainlanes in the center continues as traffic continues to flow on the new frontage roads.

In order to keep this large-scale project on schedule, our contractor has put in effect a long-term closure of the right northbound lane between Evans Road and Encino Commons (see graphic to the right) for concrete work.

Please note that the closure is just for the right northbound lane -- all other lanes will remain open except for when they're closed during scheduled temporary closures (most of these taking place overnight).

The right northbound lane closure is full time (day and night) and is expected to last approximately two to three weeks, possibly to be extended (we'll be sure to let you know if that's the case).

As always, please remember that all closures are weather permitting and implementation and timeline are subject to change.

To stay updated on project developments, you can always come here to our blog as well as follow us on Twitter. You can also sign up for email updates right into your inbox. Just click here;
http://eepurl.com/cXz2kr.

Friday, March 20

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North Central San Antonio
  • Monday, March 23 until Friday, March 27. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure from the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Monday, March 23 until Friday, March 27. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Monday, March 23 until Tuesday, March 24. Overnight 9 p.m. until 5 a.m. Left lane westbound frontage road closure from the north US 281 exit ramp to the US 281 northbound frontage road for concrete work. DETOUR: Take the US 281 turnaround, continue taking the Redland Road turnaround, use the Redland Road entrance ramp and take the Stone Oak Parkway exit ramp.
  • Saturday, March 28 until Monday, March 30. Full weekend closure 3 a.m. until 5 a.m. Full eastbound mainlane closure of the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Saturday, March 28 until Monday, March 30. Full weekend closure 3 a.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Saturday, March 28 until Monday, March 30. Full weekend closure 3 a.m. until 5 a.m. Full eastbound frontage road closure of the east- to westbound turnaround at US 281 for direct connector work.
  • Loop 1604 – Northeast San Antonio
  • Sunday, March 22 until Thursday, March 26. Nightly 9 p.m. until 5 a.m. Full mainlane closure in both directions between Bulverde Road and Green Mountain Road for milling and overlay work. DETOUR: Traffic diverted to the frontage roads in both directions.
  • Sunday, March 22 until Friday, March 27. Nightly 8 p.m. until 5 a.m. One mainlane in both directions between Green Mountain Road and I-35 for guard rail and mow strip work.
  • Sunday, March 15 until Thursday, March 19. Nightly 9 p.m. until 5 am. One westbound mainlane between Redland Road and Bulverde Road for striping work.
  • Wednesday, March 26. 9 a.m. until 5 p.m. Eastbound turnaround bridge at FM 2252 (Nacagdoches Road) for bridge joint repair work.
Loop 1604 – Northwest San Antonio
  • None scheduled.
Loop 1604 – Far East San Antonio
  • None scheduled.
Loop 1604 – South San Antonio
  • None scheduled.
US 281 – North Central San Antonio/Bexar County
  • Friday, March 20 until Monday, March 23. Full weekend closure 9 p.m. until 5 a.m. Full northbound frontage road closure from Loop 1604 to Sonterra Boulevard for bridge work. DETOUR: Turn left on the southbound US 281 frontage road, take the turnaround at Donella Drive and use the Donella Drive entrance ramp.
  • Saturday, March 21 until Sunday, March 22. Continuous 2 a.m. until 5 a.m. Left northbound mainlane closure at Encino Rio for bridge work.
  • Sunday, March 22 until Friday, March 27. Nightly 9 p.m. until 5 a.m. Full northbound frontage road closure from Loop 1604 to Sonterra Boulevard for bridge work. DETOUR: Turn left on the southbound US 281 frontage road, take the turnaround at Donella Drive and use the Donella Drive entrance ramp.
  • Monday, March 23 until Thursday, March 26. Daily 9 a.m. until 5 p.m. Southbound left mainlane at Cibolo Creek for bridge rail work.
  • Monday, March 23 until Friday, March 27. Nightly 9 p.m. until 5 a.m. Full northbound mainlane ramp closure of the north- to westbound Loop 1604 direct connector ramp for bridge work. DETOUR: Use the frontage road exit ramp, turn left on the Loop 1604 westbound frontage road, and continue on the US 281 entrance ramp.
  • Monday, March 23 until Friday, March 27. Nightly 9 p.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound frontage road, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Monday, March 23 until Friday, March 27. Nightly 9 p.m. until 5 a.m. Left turn lane northbound mainlane closure at Stone Oak/Tournament Players Club (TPC) Parkway both north- to westbound turn lanes for bridge work. DETOUR: Use the turnaround north of Stone Oak/Tournament Players Club (TPC) Parkway.
  • Monday, March 23 until Friday, March 27. Nightly 9 p.m. until 5 a.m. Left turn lane southbound mainlane closure at Stone Oak/Tournament Players Club (TPC) Parkway both south- to eastbound turn lanes for bridge work. DETOUR: Use the turnaround south of Stone Oak/Tournament Players Club (TPC) Parkway.
  • Monday, March 23 until Friday, March 27. Nightly 9 p.m. until 5 a.m. Full northbound mainlane closure from the north- to southbound turnaround at Stone Oak/Tournament Players Club (TPC) Parkway for bridge work. DETOUR: Use the turnaround north of Stone Oak/Tournament Players Club (TPC) Parkway.
  • Monday, March 23 until Friday, March 27. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Marshall Road for bridge work and safety enhancements.
  • Monday, March 23 until Friday, March 27. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for bridge work and safety enhancements.
  • Saturday, March 28 until Monday, March 30. Full weekend closure 3 a.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound frontage road, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Saturday, March 28 until Monday, March 30. Full weekend closure 3 a.m. until 5 a.m. Full northbound mainlane closure from the frontage road exit ramp to the Sonterra Boulevard entrance ramp. DETOUR: Use the frontage road exit ramp, turn right on the Loop 1604 eastbound frontage road, if heading north, take the turnaround at Gold Canyon Road, turn right on the northbound frontage road and use the Stone Oak Parkway exit ramp.
  • Saturday, March 28 until Monday, March 30. Full weekend closure 3 a.m. until 5 a.m. Full southbound frontage road closure at Loop 1604 for direct connector work. DETOUR: Turn right on the westbound frontage road, take the turnaround at Stone Oak Parkway and turn right on the southbound frontage road.
  • Saturday, March 28 until Monday, March 30. Continuous 3 a.m. until 5 a.m. Northbound Redland Road bypass ramp mainlane closure from Sonterra Boulevard to Encino Rio for ramp work.
  • Saturday, March 28 until Monday, March 30. Continuous 3 a.m. until 5 a.m. Left turn lane northbound mainlane closure at Evans Road both north- to westbound turn lanes for bridge work. DETOUR: Use the turnaround north of Evans Road.
  • Saturday, March 28 until Monday, March 30. Continuous 3 a.m. until 5 a.m. Left turn lane southbound mainlane closure at Evans Road both south- to eastbound turn lanes for bridge work. DETOUR: Use the turnaround south of Evans Road.
US 281 – South San Antonio
  • Monday, March 23 until Friday, April 3. Daily 9 a.m. until 5 p.m. Alternating mainlanes in both directions at Loop 1604 for mow strip and guard fence installation work.
I-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County
  • Current until Thursday, April 9. Daily 7 a.m. until 7 p.m. Eastbound right mainlane and shoulder between Kerr/Gillespie county line and Kerr/Kimble county line for paving work.
  • Current until Friday, March 27. Daily 9 a.m. until 3 p.m. Westbound left frontage road lane between Dominion Drive and Boerne Stage Road for retaining wall work.
  • Friday, March 27 until Saturday, March 28. 9 p.m. until 4 p.m. Westbound right mainlane between US 87 and Scenic Loop Road for milling and asphalt work.
  • Sunday, March 29 until Friday, April 3. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure between Camp Bullis Road and Boerne Stage Road for overhead sign bridge and sign structure installation work.
  • Sunday, April 5 until Friday, April 10. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure between Dominion Drive and Two Creeks for overhead sign bridge and sign structure installation work.
I-10 – Far East San Antonio/Bexar County/Seguin/Guadalupe County
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Current until further notice. Eastbound entrance ramp from Foster Road. DETOUR: Take next entrance ramp east of Woodlake Parkway.
  • Friday, March 20 until Monday, March 23. 9 p.m. to 5 a.m. FM 1516 in both directions under I-10 for bridge reconstruction activities. DETOUR: Northbound FM 1516 traffic will take the eastbound I-10 frontage road and turn around at Loop 1604. Southbound FM 1516 traffic will take the westbound I-10 frontage road and turn around at Woodlake Parkway.
  • Monday, March 23 until Wednesday, March 25. Full-time, all-day closure. Westbound exit ramp to Loop 1604 for drainage and frontage road widening work. DETOUR: Westbound traffic needing to access Loop 1604 will need to exit Graytown Road and continue on the westbound frontage road to Loop 1604.
  • Monday, March 23 until Friday, March 27. Daily 9 a.m. to 3 p.m. One alternating lane of Ackerman Road in each direction under I-10 for bridge construction activities.
  • Monday, March 23 until Friday, March 27. Daily 9 a.m. to 3 p.m. One alternating lane of Woodlake Parkway in each direction under I-10 for bridge construction activities.
I-10 – Central San Antonio
  • Sunday, March 22 until Monday, March 23. 9 p.m. until 5 a.m. Eastbound entrance ramp from Roland Avenue for milling and inlay work.
I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County
  • Monday, March 23 until Friday, March 27. Daily 8:30 a.m. until 4 p.m. Right frontage road lane in both directions at Rittiman Road for sidewalk and curb installation work. DETOUR: Traffic diverted to turn around at George Beach Road to get on I-35 southbound.
  • Monday, March 23 until Friday, March 27. Daily 9 a.m. until 3 p.m. Northbound right frontage road lane between Business 35 and Emerald Lane for grading and sidewalk work.
  • Monday, March 23 until Friday, March 27. Daily 8:30 a.m. until 5:30 p.m. Northbound right frontage road lane between Schwab Road and Hubertus Road for sidewalk work.
I-37 – Central San Antonio
  • Sunday, March 22 until Wednesday, March 25. Nightly 8 p.m. until 5 a.m. Westbound exit ramp to I-10 westbound for new guard rail installation work.
  • Wednesday, March 25 until Friday, March 27. Nightly 8 p.m. until 5 a.m. Southbound right mainlane between Cesar Chavez and Boyer for new guard rail installation work.
I-410 – West San Antonio
  • Friday, March 20 until Monday, March 23. Weekend 8 p.m. to 5 a.m. All northbound mainlanes between US 90 and Marbach Road for mill and inlay operations. DETOUR: Traffic will exit at US 90 and continue on the frontage road and re-enter at the next ramp.
  • Friday, March 20 until Monday, March 23. Weekend 8 p.m. to 5 a.m. All southbound mainlanes between Waters Edge Drive to US 90 for mill and inlay operations. DETOUR: Traffic will take the US 90 eastbound exit to I-410 southbound frontage road.
  • Sunday, March 22 until Tuesday, March 24. Nightly 8 p.m. to 5 a.m. Two left southbound frontage road between SH 151 to Marbach Road including ramps for mill and inlay work. DETOUR: Traffic on I-410 will exit US 90, use cloverleafs and continue on frontage road to access Marbach Road.
  • Monday, March 23 until Saturday, March 28. Daily 9 a.m. until 3 p.m. Alternating frontage road lanes in both directions between SH 151 and Ingram Road (including turnarounds in both directions at Military Drive) for electrical work, excavation work and underground work.
  • Current until Friday, March 27. Daily 9 a.m. to 3 p.m. Alternating frontage road lanes in both directions between US 90 bridge to SH 151 for mill and inlay work.
  • Current until Monday, March 30. Weekend 8 p.m. to 5 a.m. Two alternating lanes in each direction between SH 151 to Valley Hi Drive for mill and inlay work.
  • Friday, March 27 until Monday, March 30. Weekend 8 p.m. to 5 a.m. All northbound mainlanes between US 90 and Marbach Road for mill and inlay operations. DETOUR: Traffic will exit to US 90 and re-enter before SH 151.
US 90 – West San Antonio
  • Current until Friday, March 27. Daily 9 a.m. to 3 p.m. Alternating frontage road lanes between Ray Ellison Drive to US 90 bridge (eastbound) and Tomar Drive to Hunt Lane bridge (westbound) for staging equipment and rock placement.
SH 16 – Bandera Road
  • None scheduled.
FM 3351 – Ralph Fair Road
  • None scheduled.
PA 1502 – Wurzbach Parkway
  • City of San Antonio/TCI closure for Hardberger Park Landbridge project. Monday, March 23 until Friday, March 27. 9 a.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
  • City of San Antonio/TCI closure for Hardberger Park Landbridge project. Saturday, March 28. 7 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
FM 2252 – Nacagdoches Road
  • None scheduled.
FM 1560 – Hausman Road
  • Exit ramp from Loop 1604 eastbound closed for approximately two months starting Monday, March 16.
SH 218 – Pat Booker Road
  • None scheduled.
Spur 371 – General Hudnell Drive
  • None scheduled.
US 87 – Roland Avenue
  • Sunday, March 22 until Sunday, March 29. Daily 9 a.m. until 4 p.m. One southbound lane between I-10 and Rigsby Avenue for placing sod, manhole and electrical work
Spur 421 – Bandera Road
  • Sunday, March 22 until Friday, March 27. Nightly 8 p.m. to 6 p.m. One lane in both directions between I-410 to Cheryl Drive for milling and paving work.
FM 1976 – Walzem Road/Gibbs Sprawl Road
  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes between Woodlake Parkway and Gibbs Sprawl Road for barrier/pavement work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
  • Current until further notice. Full-day closure. Southbound lane between Toepperwein Road and Walzem Road for barrier setting work and road rehab work.
Loop 353 – New Laredo Highway
  • None scheduled.
Other Roads – Bexar County
  • Saturday, March 21 until Sunday, March 22. Continuous 2 a.m. until 5 a.m. Full westbound closure of Encino Rio at US 281 for bridge work. DETOUR: Head right on US 281 and take the next turnaround.
  • Sunday, March 22 until Friday, March 27. Nightly 9 p.m. until 5 a.m. Full westbound closure of Encino Rio at US 281 for bridge work. DETOUR: Head right on US 281 and take the next turnaround.
Loop 337 – New Braunfels/Comal County
  • Current until Tuesday, April 7. Full-time closure. Northbound access road to Landa Street for road widening, traffic island removal, sidewalk and curb work.
FM 1863 – Comal County
  • Current until Friday, April 3. Daily 7 a.m. until 6 p.m. One lane in both directions between FM 3009 and FM 311 (one-way traffic control) for pavement repair work.
FM 2673 – Canyon Lake/Comal County
  • None scheduled.
FM 1516 – South Seguin Road/Converse
  • None scheduled.
FM 2252 – Comal County
  • None scheduled.
SH 46 – Guadalupe County
  • None scheduled.
FM 78 – Guadalupe County
  • None scheduled.
FM 1518 – Schertz/Cibolo Guadalupe County
  • None scheduled.
US 90A – Seguin/Guadalupe County
  • None scheduled.
SH 123 – Seguin/Guadalupe County
  • None scheduled.
Business 123 – South Austin Street/Seguin/Guadalupe County
  • None scheduled.
I-35 – Atascosa County/Frio County
  • None scheduled.
US 181 – Floresville/Wilson County
  • None scheduled.
US 87 – Wilson County
  • None scheduled.
SH 46 – Boerne/Kendall County
  • Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
RM/FM 1376 – Kendall County
  • Current until Saturday, March 21. Daily 7 a.m. until 7 p.m. One lane at various locations between North School Street and Wasp Creek Road for culvert work.
FM 1333 – Atascosa County
  • Current until Friday, May 1. Full closure (all day) in both directions at Atascosa River (between FM 476 and SH 173) for culvert removal and replacement work.
FM 140 – Atascosa County
  • Current until 7 p.m. Saturday, March 21. Alternating lanes in both directions (flagging operations) between SH 16 and La Parita Creek for paving work.
SH 16 – McMullen County
  • Monday, March 23 until Friday, March 27. Daily 7 a.m. until 6 p.m. Alternating lanes in both directions between Ben Franklin Road and McMullen/Duval County line for paving work.

Friday, March 13

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North Central San Antonio
  • Sunday, March 15 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure from the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Sunday, March 15 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Monday, March 16 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Left lane eastbound frontage road closure at US 281 for concrete work.
  • Monday, March 16 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Alternating westbound frontage road closure from the US 281 north exit ramp to the US 281 northbound frontage road.
  • Saturday, March 21 until Monday, March 23. Weekend full closure 3 a.m. until 5 a.m. Full eastbound mainlane closure of the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Saturday, March 21 until Monday, March 23. Full weekend closure 3 a.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Saturday, March 21 until Monday, March 23. Full Weekend closure 3 a.m. until 5 a.m. Full eastbound frontage road closure of the east- to westbound turnaround at US 281 for direct connector work.
Loop 1604 – Northeast San Antonio
  • Sunday, March 15 until Thursday, March 19. Nightly 9 p.m. until 5 a.m. Eastbound frontage road at O’Connor Road (including intersection) for pavement repair work.
  • Sunday, March 15 until Thursday, March 19. Nightly 9 p.m. until 5 a.m. Frontage road in both directions at Bulverde Road for pavement repair work.
  • Sunday, March 15 until Thursday, March 19. Nightly 9 p.m. until 5 a.m. One mainlane in both directions between Redland Road and Green Mountain Road for guard fence replacement work and mow strip work.
  • Sunday, March 15 until Thursday, March 19. Nightly 9 p.m. until 5 a.m. Westbound frontage road between Bulverde Road and Redland Road for barrier resetting work.
  • Sunday, March 15 until Thursday, March 19. Nightly 9 p.m. until 5 am. One westbound mainlane between Redland Road and Bulverde Road for striping work.
Loop 1604 – Northwest San Antonio
  • Friday, March 13 until Saturday, March 14. 9 p.m. until 5 a.m. Westbound left mainlane between SH 16 (Bandera Road) and FM 1560 (Hausman Road) for barrier setting work.
  • Friday, March 13 until Sunday, March 15. Full weekend closure 9 a.m. until 5 p.m. Eastbound left frontage road lane between Champions Gate and FM 1560 (Hausman Road) for barrier setting work.
  • Friday, March 13 until Monday, March 16. Full weekend closure 9 p.m. until 5 a.m. Eastbound right mainlane and shoulder between SH 16 (Bandera Road) and FM 1560 (Hausman Road) including the Hausman exit ramp (2-month closure) for barrier and traffic rail work.
Loop 1604 – Far East San Antonio
  • None scheduled.
Loop 1604 – South San Antonio
  • Monday, March 9 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Eastbound mainlane at US 281 for barrier removal work.
US 281 – North Central San Antonio/Bexar County
  • Sunday, March 15 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for paving and bridge work.
  • Monday, March 16 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Full northbound mainlane ramp closure of the north- to westbound Loop 1604 direct connector ramp for bridge work. DETOUR: Use the frontage road exit ramp, turn left on the Loop 1604 westbound frontage road, and continue on the US 281 entrance ramp.
  • Monday, March 16 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Full southbound mainlane closure from the south- to northbound turnaround at Stone Oak/Tournament Players Club (TPC) Parkway for bridge work. DETOUR: Use the turnaround south of Stone Oak/Tournament Players Club (TPC) Parkway.
  • Monday, March 16 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Left turn lane northbound mainlane closure at Stone Oak/Tournament Players Club (TPC) Parkway both north- to westbound turn lanes for bridge work. DETOUR: Use the turnaround north of Stone Oak/Tournament Players Club (TPC) Parkway.
  • Monday, March 16 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Left turn lane southbound mainlane closure at Stone Oak/Tournament Players Club (TPC) Parkway both south- to eastbound turn lanes for bridge work. DETOUR: Use the turnaround south of Stone Oak/Tournament Players Club (TPC) Parkway.
  • Monday, March 16 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Marshall Road for soundwall work and safety enhancements.
  • Saturday, March 21 until Monday, March 23. Weekend full closure 3 a.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound frontage road, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Saturday, March 21 until Monday, March 23. Full weekend closure 3 a.m. until 5 a.m. Full northbound mainlane closure from the frontage road exit ramp to the Sonterra Boulevard entrance ramp. DETOUR: Use the frontage road exit ramp, turn right on the Loop 1604 eastbound frontage road, if heading north, take the turnaround at Gold Canyon Road, turn right on the northbound frontage road and use the Stone Oak Parkway exit ramp.
  • Saturday, March 21 until Monday, March 23. Full weekend closure 3 a.m. until 5 a.m. Full southbound frontage road closure at Loop 1604 for direct connector work. DETOUR: Turn right on the westbound frontage road, take the turnaround at Stone Oak Parkway and turn right on the southbound frontage road.
  • Saturday, March 21 until Monday, March 23. Continuous full closure 3 a.m. until 5 a.m. Northbound Redland Road bypass ramp mainlane closure from Sonterra Boulevard to Encino Rio for ramp work.
  • Saturday, March 21 until Monday, March 23. Continuous full closure 3 a.m. until 5 a.m. Left turn lane northbound mainlane closure at Evans Road both north- to westbound turn lanes for bridge work. DETOUR: Use the turnaround north of Evans Road.
  • Saturday, March 21 until Monday, March 23. Continuous full closure 3 a.m. until 5 a.m. Left turn lane southbound mainlane closure at Evans Road both south- to eastbound turn lanes for bridge work. DETOUR: Use the turnaround south of Evans Road.
US 281 – South San Antonio
  • Monday, March 16 until Thursday, March 19. Daily 9 a.m. until 4 p.m. Right mainlane in both directions at FM 1937 for traffic light pole installation work.
I-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County
  • Current until Wednesday, March 18. Daily 9 a.m. until 3 p.m. Eastbound left frontage road lane between Two Creeks and FM 3351 (Ralph Fair Road) for drainage work.
  • Tuesday, March 3 until Thursday, April 9. Daily 7 a.m. until 7 p.m. Westbound right mainlane and shoulder between Kerr/Gillespie county line and Kerr/Kimble county line for paving work.
  • Monday, March 9 until Friday, March 20. Daily 9 a.m. until 3 p.m. Westbound left frontage road lane between FM 3351 (Ralph Fair Road) and Buckskin Drive for drainage work.
  • Tuesday, March 10 until Thursday, April 9. Daily 7 a.m. until 7 p.m. Eastbound right mainlane and shoulder between Kerr/Gillespie county line and Kerr/Kimble county line for paving work.
  • Monday, March 16 until Friday, March 27. Daily 9 a.m. until 3 p.m. Westbound left frontage road lane between Dominion Drive and Boerne Stage Road for retaining wall work.
I-10 – Far East San Antonio/Bexar County/Seguin/Guadalupe County
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Friday, March 13 until Monday, March 16. 8 p.m. to 5 a.m. The left westbound I-10 mainlane from just east of Loop 1604 to just west of Woodlake Parkway will be closed for traffic switch activities. Following the traffic switch, two mainlanes will re-open in the median area and the existing westbound mainlanes and westbound exit ramp to FM 1516 will be closed. DETOUR: Westbound I-10 mainlane drivers needing to access FM 1516 may take either the Loop 1604 exit and travel west on the frontage road to FM 1516 or take the Ackerman Road exit, turn around, and travel back to FM 1516.
  • Monday, March 16 until Wednesday, March 18. Westbound exit ramp to Loop 1604 will be closed to finish drainage and road work. DETOUR: Westbound traffic needing to access Loop 1604 will need to exit Graytown road and continue on the westbound frontage road to Loop 1604.
  • Monday, March 16 until Friday, March 20. Daily 9 a.m. to 3 p.m. One alternating lane in each direction of Ackerman Road under I-10 for bridge construction activities.
I-10 – Central San Antonio
  • None scheduled.
I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County
  • Monday, March 16 until Friday, March 20. Daily 8:30 a.m. until 4 p.m. Right frontage road lane in both directions at Rittiman Road for sidewalk and curb installation work.
  • Monday, March 16 until Saturday, March 21. Daily 8:30 a.m. until 5:30 p.m. Northbound frontage road between FM 1103 and Schwab Road for sidewalk construction work.
  • Wednesday, March 18. 9 a.m. until 4 p.m. Southbound left mainlane and shoulder between Schwab Road and FM 2252 for illumination repair work.
I-37 – Central San Antonio
  • Sunday, March 15 until Tuesday, March 17. Nightly 8 p.m. until 5 a.m. Southbound right mainlane between Cesar Chavez and Boyer for new guard rail installation work.
  • Tuesday, March 17 until Friday, March 20. Nightly 8 p.m. until 5 a.m. Westbound exit ramp to I-10 westbound for new guard rail installation work..
I-410 – West San Antonio
  • Current until Saturday, March 14. Daily 9 a.m. to 3 p.m. One frontage road in both directions between SH 151 to FM 471 (Culebra Road) and the turnarounds at West Military Drive for electrical service work. DETOUR: Traffic will need to use the SH 151 and FM 471 (Culebra Road) turnarounds.
  • Friday, March 13 until Monday, March 16. Weekend 8 p.m. to 5 a.m. All southbound mainlanes between Waters Edge Drive to US 90 for mill and inlay operations. DETOUR: Traffic will take the US 90 eastbound exit to I-410 southbound frontage road.
  • Friday, March 20 until Monday, March 23. Weekend 8 p.m. to 5 a.m. All southbound mainlanes between Waters Edge Drive to US 90 for mill and inlay operations. DETOUR: Traffic will take the US 90 eastbound exit to I-410 southbound frontage road.
  • Current until Monday, March 30. Weekend 8 p.m. to 5 a.m. Two alternating lanes in each direction between SH 151 to Valley Hi Drive for mill and inlay work.
  • Current until Friday, March 27. Daily 9 a.m. to 3 p.m. Alternating frontage road lanes in both directions between US 90 bridge to SH 151 for mill and inlay work.
US 90 – West San Antonio
  • Current until Friday, March 27. Daily 9 a.m. to 3 p.m. Alternating frontage road lanes between Ray Ellison Drive to US 90 bridge (eastbound) and Tomar Drive to Hunt Lane bridge (westbound) for staging equipment and rock placement.
SH 16 – Bandera Road
  • None scheduled.
FM 3351 – Ralph Fair Road
  • None scheduled.
PA 1502 – Wurzbach Parkway
  • City of San Antonio/TCI closure for Hardberger Park Landbridge project. Monday, March 16 until Friday, March 20. 9 a.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
  • City of San Antonio/TCI closure for Hardberger Park Landbridge project. Saturday, March 21. 7 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
FM 2252 – Nacagdoches Road
  • Current until Friday, March 20. Daily 8 a.m. until 5 p.m. Eastbound right lane and shoulder between Loop 1604 and Dolente Road for sidewalk, curb and shoulder work.
FM 1560 – Hausman Road
  • Exit ramp from Loop 1604 eastbound closed for approximately two months starting Monday, March 16.
FM 1516 – South Seguin Road/Converse
  • None scheduled.
SH 218 – Pat Booker Road
  • None scheduled.
Spur 371 – General Hudnell Drive
  • None scheduled.
US 87 – Roland Avenue
  • Current until Sunday, March 15. Daily 9 a.m. until 4 p.m. One lane in both directions between I-10 and Rigsby Avenue for placing sod, manhole and electrical work.
Spur 421 – Bandera Road
  • None scheduled.
FM 1976 – Walzem Road/Gibbs Sprawl Road
  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes between Woodlake Parkway and Gibbs Sprawl Road for barrier/pavement work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
  • Current until further notice. Full-day closure. Southbound lane between Toepperwein Road and Walzem Road for barrier setting work and road rehab work.
Loop 353 – New Laredo Highway
  • None scheduled.
Other Roads – Bexar County
  • None scheduled.
Loop 337 – New Braunfels/Comal County
  • Current until Tuesday, April 7. Full-time closure. Northbound access road to Landa Street for road widening, traffic island removal, sidewalk and curb work.
FM 2673 – Canyon Lake/Comal County
  • None scheduled.
FM 2252 – Comal County
  • None scheduled.
SH 46 – Guadalupe County
  • None scheduled.
FM 78 – Guadalupe County
  • None scheduled.
FM 1518 – Schertz/Cibolo Guadalupe County
  • None scheduled.
US 90A – Seguin/Guadalupe County
  • None scheduled.
SH 123 – Seguin/Guadalupe County
  • None scheduled.
Business 123 – South Austin Street/Seguin/Guadalupe County
  • None scheduled.
I-35 – Atascosa County/Frio County
  • Friday, March 13. 8 a.m. until 5 p.m. One northbound mainlane between FM 3175 and FM 2790 for barrier resetting work.
US 181 – Floresville/Wilson County
  • None scheduled.
US 87 – Wilson County
  • None scheduled.
SH 46 – Boerne/Kendall County
  • Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
RM/FM 1376 – Kendall County
  • Current until 7 p.m. Saturday, March 14. One lane at various locations between North School Street and Wasp Creek Road for culvert work.
  • Current until Sunday, March 15. Full time all-day closure. All lanes in both directions at Wasp Creek Road for road reconstruction work. DETOUR: Roadway open to local traffic but drivers wishing to travel between Boerne and Sisterdale will be diverted to FM 474 and FM 473.
  • Monday, March 16 until Saturday, March 21. Daily 7 a.m. until 7 p.m. One lane at various locations between North School Street and Wasp Creek Road for culvert work.
FM 1333 – Atascosa County
  • Current until Friday, May 1. Full closure (all day) in both directions at Atascosa River (between FM 476 and SH 173) for culvert removal and replacement work.
FM 140 – Atascosa County
  • Current until Saturday, March 21. Daily 7 a.m. until 7 p.m. Alternating lanes in both directions (flagging operations) between SH 16 and La Parita Creek for paving work.
SH 16 – McMullen County
  • Monday, March 16 until Friday, March 20. Daily 7 a.m. until 6 p.m. Alternating lanes in both directions between Ben Franklin Road and McMullen/Duval County line for paving work.

Thursday, March 12

Wild Wild Far East Side: Traffic Switch Set For This Weekend On I-10 Westbound


The project to widen and reconstruct I-10 between I-410 and Loop 1604 on San Antonio’s Far East Side continues to progress, with our contractor currently making traffic switches left and right – literally. 

Last weekend, eastbound I-10 traffic was moved from the median area to the newly reconstructed outside mainlanes and shoulders between Woodlake Parkway and Loop 1604.
That traffic switch was necessary to make way for work on the westbound mainlanes in the eastern-most section of the project area – set to kick off this weekend. 

Beginning at 8 p.m. tomorrow (Friday, March 13) through 5 a.m. Monday (March 16), westbound I-10 drivers can expect the following closures/sequence of activities between Loop 1604 and Woodlake Parkway as part of the next traffic switch: 
  • The left westbound mainlane of I-10 will be closed from just east of Loop 1604 to just west of Woodlake Parkway as crews place barriers for the traffic switch. 
  • Once all traffic barriers are in place, two westbound I-10 mainlanes will be opened to traffic in the median area and the outside mainlanes/shoulders will be closed.
  • The westbound exit ramp to FM 1516 (see photo above) will be closed as crews construct a temporary tie-in from the relocated westbound mainlanes to the exit ramp. DETOUR: Westbound I-10 mainlane drivers needing to access FM 1516 may take either the Loop 1604 exit and travel west on the frontage road to FM 1516 or take the Ackerman Road exit, turn around and travel back to FM 1516.
  • The westbound FM 1516 exit ramp will reopen as soon as the tie-in is complete, which is anticipated by no later than 5 a.m. Monday (March 16).
This weekend’s traffic switch ushers the beginning of more work to come on the westbound side of I-10. 

Next weekend (starting March 20), crews will switch eastbound I-10 traffic from the median area to the outside mainlanes and shoulders between WW White and Ackerman Road. This is necessary to make yet another traffic switch the following weekend (starting March 27) to move westbound I-10 mainlane traffic to the median area. 

All these moves may prompt you to ask: Are we overseeing a construction project or a game of chess? There are admittedly quite a few similarities, with a series of strategic traffic moves required to achieve the ultimate goal – in this case, to free up sections of the westbound I-10 mainlanes for reconstruction while continuously maintaining two lanes of traffic in each direction. 

As always, these closures are weather permitting and subject to scheduling changes. 

For more information, visit the project website for I-10 East from I-410 to the Bexar/Guadalupe County Line. You may also join our email list to receive updates on major changes and progress on the I-10 improvement projects and follow our Twitter feed (@TxDOTSanAntonio) for ongoing traffic updates.

Wednesday, March 11

Frontage Road Conversion, New Overpass & More: Improvements On The Way For I-35 In Comal County

If you drive often on I-35 in Northeast San Antonio and New Braunfels, you've seen improvements we're putting in place in that area.

We recently finished work on the expanded FM 1103 overpass and are currently doing frontage road work in that area as well.

Additionally, we also have relief coming to the increasingly busy I-35/FM 306 intersection, with Buc-ee's and Creekside commercial development drawing lots of traffic.

Next up, starting Monday (March 16), we're kicking off our next project in this corridor.

The new $64 million project will improve roughly six miles of I-35 mainlanes and frontage roads between FM 306 and the Hays/Comal County line.

The project is intended to improve and increase traffic capacity at various intersections and provide ramp upgrades. Estimated completion is slated for March 2023.

One of the most significant improvements is the conversion of the frontage roads from two-way traffic to one-way operation in both directions between Kohlenberg Road to the bridge crossing at Watson Lane. 

The conversion will take place in the first phase of the project, ushering a speed limit reduction from 55 to 45 mph.

This will allow room to relocate frontage road traffic out towards the right-of-way to provide room for mainlane detours.

Appropriate signs, pavement markings and construction barrels will be put in place to guide traffic safely through the work zone.

Some additional project highlights:

The I-35 mainlanes at Conrads Lane/Kohlenberg Road will change from an underpass to an overpass. The existing intersection will be converted to a signalized intersection with turnarounds.

A new mainlane overpass between Conrads Lane/Kohlenberg Road and Watson Lane with dedicated turnarounds on the frontage roads will be built. This will be called the "Parkway intersection."

Want to keep up with the latest on this project? Continue to check here for blog updates, as well as follow us on social media. Additionally, you can sign up for email updates by subscribing here http://eepurl.com/gRtrwn.

Friday, March 6

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North Central San Antonio
  • Monday, March 9 until Friday, March 13. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure from the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Monday, March 9 until Friday, March 13. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Monday, March 9 until Friday, March 13. Nightly 9 p.m. until 5 a.m. Full westbound frontage road closure from the US 281 southbound frontage road to the Stone Oak Parkway exit ramp. DETOUR: Take the turnaround at US 281, continue east using the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Monday, March 9 until Friday, March 13. Nightly 9 p.m. until 5 a.m. Full eastbound frontage road closure of the east- to westbound turnaround at US 281 for direct connector work. DETOUR: Turn left at the US 281 intersection then turn left again onto the westbound Loop 1604 frontage road.
  • Saturday, March 14 until Monday, March 16. Full weekend closure 3 a.m. until 5 a.m. Full eastbound mainlane closure of the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Saturday, March 14 until Monday, March 16. Full weekend closure 3 a.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Saturday, March 14 until Monday, March 16. Full weekend closure 3 a.m. until 5 a.m. Full eastbound frontage road closure of the east- to westbound turnaround at US 281 for direct connector work.
Loop 1604 – Northeast San Antonio
  • Sunday, March 1 until Friday, March 6. Nightly 9 p.m. until 5 a.m. Eastbound right mainlane between Redland Road and Bulverde Road for ramp work.
  • Sunday, March 8 until Friday, March 13. Nightly 9 p.m. until 5 a.m. One mainlane in both directions between Green Mountain Road and I-35 for milling and paving work.
  • Sunday, March 1 until Monday, March 2. Nightly 8 p.m. until 5 a.m. Southbound ramp to I-35 (including I-35 northbound shoulder) for rail work and retaining wall repair work.
  • Sunday, March 8 until Friday, March 13. Nightly 9 p.m. until 5 a.m. One mainlane in both directions between Green Mountain Road and I-35 for guard rail and mow strip work.
  • Wednesday, March 4. 9 a.m. until 5 p.m. Eastbound frontage road and turnaround at FM 2252 (Nacagdoches Road) for bridge repair work.
  • Sunday, March 8 until Thursday, March 12. Nightly 9 p.m. until 5 a.m. Eastbound frontage road at O’Connor Road (including intersection) for pavement repair work.
  • Sunday, March 8 until Thursday, March 12. Nightly 9 p.m. until 5 a.m. Frontage road in both directions at Bulverde Road for pavement repair work.
  • Sunday, March 8 until Thursday, March 12. Nightly 9 p.m. until 5 a.m. One mainlane in both directions between Redland Road and Green Mountain Road for guard fence and mow strip work.
  • Thursday, March 12 until Friday, March 13. 9 p.m. until 5 a.m. Full eastbound mainlane closure between Redland Road and Bulverde Road for Overhead Sign Bridge removal work and guard fence installation work.
  • Sunday, March 15 until Thursday, March 19. Nightly 9 p.m. until 5 a.m. One mainlane in both directions between Redland Road and Green Mountain Road for guard fence replacement work and mow strip work.
  • Sunday, March 15 until Thursday, March 19. Nightly 9 p.m. until 5 a.m. Westbound frontage road between Bulverde Road and Redland Road for barrier resetting work.
Loop 1604 – Northwest San Antonio
  • Friday, March 13 until Sunday, March 15. Full weekend closure 9 a.m. until 5 p.m. Eastbound left frontage road lane between Champions Gate and FM 1560 (Hausman Road) for barrier setting work.
  • Friday, March 13 until Monday, March 16. Full weekend closure 9 p.m. until 5 a.m. Eastbound right mainlane and shoulder between SH 16 (Bandera Road) and FM 1560 (Hausman Road) including the Hausman exit ramp (2-month closure) for barrier and traffic rail work.
Loop 1604 – Far East San Antonio
  • Friday, March 6 until Saturday, March 7. 9 p.m. until 5 p.m. Full mainlane closure in both directions between FM 1346 and Schuwirth Road for paving work. DETOUR: Loop 1604 northbound traffic diverted to FM 1346 westbound to Schuwirth Road; Loop 1604 southbound traffic diverted to Schuwirth Road to FM 1346 eastbound.
Loop 1604 – South San Antonio
  • Monday, March 9 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Eastbound mainlane at US 281 for barrier removal work.
US 281 – North Central San Antonio/Bexar County
  • Saturday, March 7. 7 a.m. until 5 p.m. Southbound right mainlane at Mountain Lodge for striping work and traffic switch
  • Sunday, March 8 until Friday, March 13. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for paving and bridge work.
  • Monday, March 9 until Friday, March 13. Nightly 9 p.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound frontage road, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Monday, March 9 until Friday, March 13. Nightly 9 p.m. until 5 a.m. Full closure of the northbound-to- eastbound direct connector for bridge work. DETOUR: Use the frontage road exit ramp, turn right on the Loop 1604 eastbound frontage road, if heading north, take the turnaround at Gold Canyon Road, turn right on the northbound frontage road and use the Stone Oak Parkway exit ramp.
  • Monday, March 9 until Friday, March 13. Nightly 9 p.m. until 5 a.m. Full northbound closure of the northbound-to-westbound Loop 1604 direct connector r bridge work. DETOUR: Use the frontage road exit ramp, turn left on the Loop 1604 westbound frontage road, and continue on the US 281 entrance ramp.
  • Monday, March 9 until Friday, March 13. Nightly 9 p.m. until 5 a.m. Full northbound frontage road closure from Loop 1604 to Sonterra Boulevard for direct connector work. DETOUR: Turn left on the southbound frontage road, use the turnaround at Donella Drive and take the Donella Drive entrance ramp.
  • Monday, March 9 until Friday, March 13. Nightly 9 p.m. until 5 a.m. Full southbound frontage road closure at Loop 1604 for direct connector work. DETOUR: Turn right on the westbound frontage road, take the turnaround at Stone Oak Parkway and turn right on the southbound frontage road.
  • Monday, March 9 until Friday, March 13. Nightly 9 p.m. until 5 a.m. Full southbound frontage road closure from the south- to northbound turnaround at Loop 1604 for direct connector work. DETOUR: Turn left at the intersection then turn left again.
  • Monday, March 9 until Friday, March 13. Nightly 9 p.m. until 5 a.m. Left turn lane northbound mainlane closure at Stone Oak/Tournament Players Club (TPC) Parkway both north- to westbound turn lanes for bridge work. DETOUR: Use the turnaround north of Stone Oak/Tournament Players Club (TPC) Parkway.
  • Monday, March 9 until Friday, March 13. Nightly 9 p.m. until 5 a.m. Left turn lane southbound mainlane closure at Stone Oak/Tournament Players Club (TPC) Parkway both south- to eastbound turn lanes for bridge work. DETOUR: Use the turnaround south of Stone Oak/Tournament Players Club (TPC) Parkway.
  • Monday, March 9 until Friday, March 13. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Marshall Road for paving and bridge work.
  • Saturday, March 14 until Monday, March 16. Weekend full closure 3 a.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound frontage road, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Saturday, March 14 until Monday, March 16. Full weekend closure 3 a.m. until 5 a.m. Full northbound mainlane closure from the frontage road exit ramp to the Sonterra Boulevard entrance ramp. DETOUR: Use the frontage road exit ramp, turn right on the Loop 1604 eastbound frontage road, if heading north, take the turnaround at Gold Canyon Road, turn right on the northbound frontage road and use the Stone Oak Parkway exit ramp.
  • Saturday, March 14 until Monday, March 16. Full weekend closure 3 a.m. until 5 a.m. Full southbound frontage road closure at Loop 1604 for direct connector work. DETOUR: Turn right on the westbound frontage road, take the turnaround at Stone Oak Parkway and turn right on the southbound frontage road.
  • Saturday, March 14 until Monday, March 16. Full weekend closure 3 a.m. until 5 a.m. Northbound Redland Road bypass ramp mainlane closure from Sonterra Boulevard to Encino Rio for ramp work.
  • Saturday, March 14. 7 a.m. until 5 p.m. Southbound right mainlane at Mountain Lodge for barrier setting work.
  • Monday, March 16 until Thursday, March 19. Daily 9 a.m. until 5 p.m. Southbound left mainlane at Cibolo Creek for bridge repair work.
US 281 – South San Antonio
  • None scheduled.
I-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County
  • Current until Wednesday, March 18. Daily 9 a.m. until 3 p.m. Eastbound left frontage road lane between Two Creeks and FM 3351 (Ralph Fair Road) for drainage work.
  • Tuesday, March 3 until Thursday, April 9. Daily 7 a.m. until 7 p.m. Westbound right mainlane and shoulder between Kerr/Gillespie county line and Kerr/Kimble county line for paving work.
  • Monday, March 9 until Friday, March 20. Daily 9 a.m. until 3 p.m. Westbound left frontage road lane between FM 3351 (Ralph Fair Road) and Buckskin Drive for drainage work.
  • Tuesday, March 10 until Thursday, April 9. Daily 7 a.m. until 7 p.m. Eastbound right mainlane and shoulder between Kerr/Gillespie county line and Kerr/Kimble county line for paving work.
I-10 – Far East San Antonio/Bexar County/Seguin/Guadalupe County
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Friday, March 6 until Monday, March 9. Full weekend closure 8 p.m. to 5 a.m. Right eastbound mainlane will be closed from Woodlake Parkway to Loop 1604 as crews implement a traffic switch. Intermittent closures of the eastbound entrance ramp from Foster Road and the eastbound exit ramp to FM 1516 will also be required during the traffic switch. Following the traffic switch, the existing eastbound entrance ramp from Foster Road will be closed and a new entrance ramp will open just east of Woodlake Parkway. DETOURS: During the intermittent ramp closures, drivers needing to access the I-10 mainlanes from Foster Road must continue eastbound on the frontage road and enter the mainlanes after the Loop 1604 intersection. Drivers needing to access FM 1516 from I-10 may take the Loop 1604 exit, turn around, and travel back to FM 1516. Following the traffic switch, drivers needing to access the I-10 mainlanes from Foster Road must continue eastbound on the frontage road and enter the mainlanes after Woodlake Parkway.
I-10 – Central San Antonio
  • Wednesday, March 11 until Thursday, March 12. 8 p.m. until 5 a.m. Westbound exit ramp to I-37 southbound for guard rail and illumination work.
I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County
  • Monday, March 9 until Friday, March 13. Daily 8:30 a.m. until 4 p.m. Right frontage road lane in both directions at Rittiman Road (including right-turn lane from Rittiman to the frontage road and right-turn from frontage road to Rittiman) for sidewalk and curb installation work.
  • Monday, March 9 until Friday, March 13. Daily 8:30 a.m. until 4 p.m. Right frontage road lane in both directions at Eisenhauer Road (including right-turn lane from Eisenhauer to frontage road and right turn from frontage Road to frontage road) for sidewalk and curb installation work.
  • Tuesday, March 10 until Wednesday, March 11. 9 p.m. until 5 a.m. Northbound center and left mainlanes between Schwab Road and Hubertus Road for striping removal work.
  • Tuesday, March 10 until Wednesday, March 11. 8 p.m. until 5 p.m. Southbound exit ramp to I-10 eastbound for guard rail installation work.
  • Wednesday, March 11. 9 a.m. until 4 p.m. Southbound right mainlane between North Walters Street and New Braunfels Avenue (including entrance ramps before AT&T Center Parkway & after New Braunfels Avenue) for landscaping work.
I-37 – Central San Antonio
  • Monday, March 9 until Tuesday, March 10. 8 p.m. until 5 a.m. Southbound exit ramp to I-10 westbound for guard rail work.
  • Thursday, March 12 until Friday, March 13. 8 p.m. until 5 a.m. Northbound right mainlane and shoulder at Florida Street/Carolina Street exit ramp for guard rail work.
I-410 – West San Antonio
  • Current until Monday, March 9. Full weekend closure 8 p.m. to 5 a.m. Two left mainlanes in both directions between the exit ramp to Marbach Road and the entrance ramp past Marbach Road for concrete barrier work.
  • Friday, March 6 until Monday, March 30. Weekend 8 p.m. to 5 a.m. Two alternating lanes in each direction between SH 151 to Valley Hi Drive for mill and inlay work.
  • Monday, March 9 until Friday, March 13. Daily 7 a.m. to 5 p.m. The northbound exit ramp to Marbach Road for mill and inlay work. DETOUR: Traffic will be detoured to the exit SH 151 and turnaround.
  • Current until Saturday, March 14. Daily 9 a.m. to 3 p.m. One frontage road in both directions between SH 151 to FM 471 (Culebra Road) and the turnarounds at West Military Drive for electrical service work. DETOUR: Traffic will need to use the SH 151 and FM 471 (Culebra Road) turnarounds.
  • Current until Friday, March 27. Daily 9 a.m. to 3 p.m. Alternating frontage road lanes in both directions between US 90 bridge to SH 151 for mill and inlay work.
US 90 – West San Antonio
  • Sunday, March 8 until Friday, March 13. Nightly 8 p.m. to 5 a.m. The eastbound exit to Ray Ellison Drive to the I-410 direct connector ramp for painting the connector ramp. DETOUR: Traffic will be detoured to exit at Ray Ellison, stay on the frontage road to access the east to northbound cloverleaf; continue on the I-410 frontage road and use the next entrance ramp for I-410 northbound.
  • Monday, March 9 until Friday, March 13. Daily 7 a.m. to 5 p.m. Two westbound frontage road lanes between Observation Drive (US 90) and Landing Avenue (I-410) for mill and inlay work. DETOUR: Traffic will be detoured to use cloverleafs to access frontage road.
  • Current until Friday, March 27. Daily 9 a.m. to 3 p.m. Alternating frontage road lanes between Ray Ellison Drive to US 90 bridge (eastbound) and Tomar Drive to Hunt Lane bridge (westbound) for staging equipment and rock placement.
SH 16 – Bandera Road
  • None scheduled.
FM 3351 – Ralph Fair Road
  • None scheduled.
PA 1502 – Wurzbach Parkway
  • City of San Antonio/TCI closure for Hardberger Park Landbridge project. Monday, March 9 until Friday, March 13. 9 a.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
  • City of San Antonio/TCI closure for Hardberger Park Landbridge project. Saturday, March 14. 7 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
FM 2252 – Nacagdoches Road
  • Current until Friday, March 20. Daily 8 a.m. until 5 p.m. Eastbound right lane and shoulder between Loop 1604 and Dolente Road for sidewalk, curb and shoulder work.
FM 1560 – Hausman Road
  • None scheduled.
FM 1516 – South Seguin Road/Converse
  • None scheduled.
SH 218 – Pat Booker Road
  • None scheduled.
Spur 371 – General Hudnell Drive
  • Sunday, March 8 until Friday, March 13. Nightly 9 p.m. to 5 a.m. One lane in each direction between Billy Mitchell to US 90 for mill and paving work.
US 87 – Roland Avenue
  • Current until 4 p.m. Saturday, March 7. Alternating lanes in both directions between Rigsby Avenue and Super 8 for paving, sod placement, manhole and sign installation work.
Spur 421 – Bandera Road
  • None scheduled.
FM 1976 – Walzem Road/Gibbs Sprawl Road
  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes between Woodlake Parkway and Gibbs Sprawl Road for barrier/pavement work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
Loop 353 – New Laredo Highway
  • None scheduled.
Other Roads – Bexar County
  • Friday, March 6. 2 a.m. until 5 p.m. Full closure of Boerne Stage Road in both directions at I-10 for bridge deck pour work. DETOUR: Westbound traffic diverted to the FM 3351 (Ralph Fair Road) turnaround; eastbound traffic diverted to the Dominion Drive turnaround.
  • Monday, March 9. 2 a.m. until 5 p.m. Full closure of Boerne Stage Road in both directions at I-10 for bridge deck pour work. DETOUR: Westbound traffic diverted to the FM 3351 (Ralph Fair Road) turnaround; eastbound traffic diverted to the Dominion Drive turnaround.
Loop 337 – New Braunfels/Comal County
  • Tuesday, March 10 until Tuesday, April 7. Full-time closure. Northbound access road to Landa Street for road widening, traffic island removal, sidewalk and curb work.
FM 2673 – Canyon Lake/Comal County
  • None scheduled.
FM 2252 – Comal County
  • None scheduled.
SH 46 – Guadalupe County
  • Current until Friday, March 6. Daily 7 a.m. until 5:30 p.m. Alternating lanes/shoulders in both directions between I-10 and SH 123 for topsoil work.
FM 78 – Guadalupe County
  • Current until Friday, March 6. Daily 7 a.m. until 5:30 p.m. Alternating lanes/shoulders between ½-mile west of FM 725 and 1 mile east of FM 1620 for paving work.
FM 1518 – Schertz/Cibolo Guadalupe County
  • None scheduled.
US 90A – Seguin/Guadalupe County
  • None scheduled.
SH 123 – Seguin/Guadalupe County
  • None scheduled.
Business 123 – South Austin Street/Seguin/Guadalupe County
  • None scheduled.
I-35 – Frio County
  • None scheduled.
US 181 – Floresville/Wilson County
  • None scheduled.
US 87 – Wilson County
  • None scheduled.
SH 46 – Boerne/Kendall County
  • Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
RM/FM 1376 – Kendall County
  • Saturday, March 7 until Sunday, March 15. Full time all-day closure. All lanes in both directions at Wasp Creek Road for road reconstruction work. DETOUR: Roadway open to local traffic but drivers wishing to travel between Boerne and Sisterdale will be diverted to FM 474 and FM 473.
FM 1333 – Atascosa County
  • Current until Friday, May 1. Full closure (all day) in both directions at Atascosa River (between FM 476 and SH 173) for culvert removal and replacement work.
FM 140 – Atascosa County
  • Current until Saturday, March 21. Daily 7 a.m. until 7 p.m. Alternating lanes in both directions (flagging operations) between SH 16 and La Parita Creek for paving work.
SH 16 – McMullen County
  • Monday, March 9 until Friday, March 13. Daily 7 a.m. until 6 p.m. Alternating lanes in both directions between Ben Franklin Road and McMullen/Duval County line for paving work.

I-10 Far East San Antonio: Eastbound Traffic Switch This Weekend

As construction progresses on improvements to I-10 between I-410 and Loop 1604 on San Antonio’s Far East Side, eastbound drivers will soon experience another traffic pattern shift in the eastern-most portion of the project area.

Since Summer 2019, commuters have been driving on new concrete pavement in what was formerly the center median area of I-10 from just west of I-410 to Loop 1604. 

The traffic switch to this new pavement is necessary to allow crews to widen and reconstruct the outside eastbound mainlanes and shoulders of I-10, a key step in achieving an ultimate I-10 footprint that includes one additional mainlane in each direction.

This weekend, eastbound mainlane traffic is scheduled to be moved from the median area back to the newly reconstructed outside mainlanes/shoulders (see picture) in the eastern-most section of the project between Woodlake Parkway and Loop 1604.

This will free up the median area pavement for a future westbound traffic shift – currently planned for next weekend – which will allow crews to begin reconstructing the outside westbound mainlanes and shoulders from Loop 1604 to Woodlake Parkway.

From 8 p.m. today (Friday, March 6) until 5 a.m. Monday (March 9), drivers in this area can expect the following closures/sequence of activities:
  • The right eastbound mainlane of I-10 will be closed from Woodlake Parkway to Loop 1604 as crews place barriers for the traffic switch.
  • The eastbound I-10 entrance ramp from Foster Road will be closed intermittently. DETOUR: During these intermittent closures, drivers needing to access the I-10 mainlanes from Foster Road must continue eastbound on the frontage road and enter the mainlanes after the Loop 1604 intersection.
  • The eastbound I-10 exit ramp to FM 1516 will be closed intermittently. DETOUR: During these intermittent closures, drivers needing to access FM 1516 from I-10 may take the Loop 1604 exit, turn around and travel back to FM 1516.
  • Once all traffic barriers are in place, two eastbound mainlanes will be opened to traffic in the outside mainlane/shoulder area and the eastbound mainlanes in the median area will be closed.
  • The existing eastbound entrance ramp from Foster Road will also be closed and a new entrance ramp will open just east of Woodlake Parkway.
Following the traffic switch, drivers needing to access the I-10 mainlanes from Foster Road must continue eastbound on the frontage road and enter the mainlanes after Woodlake Parkway.

Additional traffic shifts in both directions will be required as new sections of concrete pavement are completed.

For more information on our work in this area, visit the project site for I-10 East from I-410 to the Bexar/Guadalupe County Line. You may also join our email list to receive updates on major changes and progress on the I-10 improvement projects and follow our Twitter feed (@TxDOTSanAntonio) for ongoing updates and alerts.

Tuesday, March 3

Hill Country News: RM 1376 Full Closure Over Spring Break

If you live in or drive up in the Hill Country often, this one's for you.

Particularly for those who often make the drive between Boerne and Sisterdale, please be aware that our contractor on the RM 1376 project, Curran, will be doing a full roadway closure in both directions in a portion of this roadway.

The full roadway closure will take place in a 1/2-mile section starting just north of Wasp Creek Road, starting on Saturday, March 7 through Sunday, March 15.

The roadway will actually remain open to local traffic outside of the closure area. That means between Boerne and Wasp Creek Road and between Sisterdale down to the closure section.

However, folks intending of making the usual drive on RM 1376 between Boerne and Sisterdale will be diverted to an established detour using FM 474 and FM 473 (see map).

This closure is being put in place during Spring Break, when there is a reduction in regular traffic. The reason the contractor is doing a full closure in both directions is to expedite the widening of the roadway to enhance safety for the traveling public. Additionally, workers will be installing new guard fence in this area.

Other alternatives to the full closure were considered but they would have implied closures during a longer period of time, which would not serve the public well since safety enhancements cannot wait.

We understand this will cause an inconvenience to drivers, particularly to locals used to the trip between Boerne and Sisterdale on RM 1376. We appreciate your patience and understanding as we our best to improve this roadway in a timely manner.