US 281 Phase I Expansion Project: Next Phase Of Evans Road Intersection Reconstruction


The gradual reconstruction of the US 281 & Evans Road intersection (part of the US 281 Phase I Expansion Project which goes from Loop 1604 to just north of Stone Oak Parkway) continues this weekend, prompting the need for temporary closures.

For this work, our contractor will need to reduce the westbound and eastbound lanes of Evans Road (east of US 281) down to one lane in each direction.

Work to construct the north end of Evans Road will take place over this weekend, beginning at 9 p.m. Friday, (September 20) until 5 a.m. Monday (September 23).

Two lanes of eastbound Evans and three lanes of westbound Evans will be restored by Monday morning’s commute. This work will complete the phasing of Evans Road on the east side of the intersection with US 281.

Intersection reconstruction can require multiple changes in traffic configuration to ensure construction can be completed smoothly and, more importantly, safely for drivers and construction workers. Please always remember to move over/slow down when approaching crews -- it's the law.

Want all bases covered in terms of keeping up with this construction project? Besides our blog and following us on social media, you can also get email alerts on upcoming closures. Here's the link to sign up: http://eepurl.com/cXz2kr.

As always, any scheduled work is weather permitting and subject to change.

Thursday, September 19

US 281 Expansion Phase II: Traffic Switch On Wilderness Oak

If you follow our blog regularly, you're likely used to hearing from us about construction on the US 281 Expansion Project.

Until now, most of the news out of that project has focused on Phase I, which started in 2017 and which goes from Loop 1604 to Stone Oak Parkway. There's definitely still lots of activity in that stretch, but those of you who frequently travel further north have likely noticed an uptick in work up there as well.

That's part of Phase II, which started this Spring and it picks up construction from Stone Oak Parkway up until the Bexar/Comal county line.

Thus far that project hasn't had much impact on the traveling public because work has focused on building the new southbound frontage road with minimal needed closures. If you live in or near Wilderness Oak, you likely noticed a discernible change on that street off the highway. It's what we typically call a "traffic switch," whereby drivers are diverted to one side of the road so crews can work on the closed-off portion.

The point is to ensure the highest safety both for crews working behind barrier as well as the traveling public. Here are more details about this switch (see map for visual detail:

• Before: Wilderness Oak was divided by a median, two eastbound lanes and two lanes at US 281.

• Currently: Wilderness Oak westbound lanes are closed off and shifted south of the median, so traffic will now be two-way undivided flow (one eastbound lane and one westbound lane).

Our contractor has placed electronic message boards along southbound US 281 prior to Wilderness Oak indicating “New Traffic Pattern” and on eastbound Wilderness Oak: "Two Way Traffic Ahead/ Stay Right."

The project is progressing well. Once the contractor finishes the new southbound frontage road, the next phase will be construction of the new northbound frontage road. Then, crews will move to the middle for the expansion of the mainlanes. which will keep two general purpose lanes plus one new HOV (High Occupancy Vehicle) lane in each direction.



Friday, September 13

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North Central San Antonio
  • Sunday, September 15 until Friday, September 20. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure between US 281 north exit ramp and the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Monday, September 16 until Friday, September 20. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure between the US 281 north exit ramp and the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Saturday, September 21 until Monday, September 23. Full weekend closure 3 a.m. until 5 a.m. Full eastbound mainlane closure between US 281 north exit ramp and the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Saturday, September 21 until Monday, September 23. Full weekend closure 3 a.m. until 5 a.m. Full westbound mainlane closure between the US 281 north exit ramp and the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
Loop 1604 – Northeast San Antonio
  • Current until 4 p.m. Saturday, September 14. Westbound left frontage road lane between Redland Road and Bulverde Road for truck/material access.
  • Monday, September 16 until Saturday, September 28 (except Sundays). Daily 8 a.m. until 4 p.m. Westbound left frontage road lane between Redland Road and Bulverde Road for truck/material access.
  • Monday, September 16 until Saturday, September 28 (except Sundays). Daily 8 a.m. until 4 p.m. Eastbound left frontage road lane at Redland Road for concrete work.
  • Thursday, September 19 until Friday, September 20. 9 p.m. until 5 a.m. Full westbound mainlane closure at FM 2252 (Nacagdoches Road) for barrier and overhang removal work and guard fence installation work.
  • Friday, September 20 until Saturday, September 21. 10 p.m. until 5 a.m. Full eastbound mainlane closure at FM 2252 (Nacagdoches Road) for overhang removal work.
Loop 1604 – Northwest San Antonio
  • Sunday, September 15 until Friday, September 20. Nightly 9 p.m. until 5 a.m. Alternating frontage road lanes in both directions between Golden Corral and Discount Tire for taking asphalt core work.
  • Monday, September 16 until Tuesday, September 17. 9 p.m. until 5 a.m. Alternating westbound frontage road lanes at Huebner Road for paving work.
  • Tuesday, September 17 until Wednesday, September 18. 9 p.m. until 5 a.m. Alternating westbound frontage road lanes at Bitters Road/Roger’s Ranch Road for paving work.
  • Wednesday, September 18 until Thursday, September 19. 9 p.m. until 5 a.m. Alternating eastbound frontage road lanes at Bitters Road/Roger’s Ranch Road for paving work.
Loop 1604 – West San Antonio
  • Monday, September 16 until Friday, September 20. Daily 9 a.m. to 5 p.m. Alternating lanes in both directions at FM 1957 (Potranco Road), Military Drive, and Wiseman Boulevard for sign work.
  • Monday, September 16 until Friday, September 20. Daily 9 a.m. to 7 p.m. Alternating northbound frontage road lanes between south of FM 1957 (Potranco Road) to SH 151 for driveway and sign work.
Loop 1604 -- South San Antonio
  • Monday, September 16 until Friday, September 20. Daily  9 a.m. until 3 p.m. Eastbound right mainlane from FM 1303 to I-37 for base repair work.
US 281 – North Central San Antonio
  • Saturday, September 14. 3 a.m. until 7 p.m. Right northbound mainlane closure from Sonterra Boulevard to Redland Road for sidewalk placement.
  • Sunday, September 15 until Friday, September 20. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Marshall Road for sidewalk, bridge work and safety enhancements.
  • Sunday, September 15 until Friday, September 20. Nightly 9 p.m. until 5 a.m. Right southbound frontage road closure from Sonterra Boulevard to the Loop 1604 westbound frontage road for drainage work.
  • Sunday, September 15 until Friday, September 20. Nightly 9 p.m. until 5 a.m. Full northbound frontage road closure from the Loop 1604 westbound frontage road to Sonterra Boulevard for direct connector work. DETOUR: On the Loop 1604 westbound frontage road, turn left on the US 281 southbound frontage road, take the turnaround at Donella Drive and use the US 281 Donella Drive entrance ramp.
  • Monday, September 16 until Friday, September 20. Nightly 9 p.m. until 5 a.m. Full northbound frontage road closure from the Loop 1604 westbound frontage road to Sonterra Boulevard for direct connector work. DETOUR: On the Loop 1604 westbound frontage road, turn left on the US 281 southbound frontage road, take the turnaround at Donella Drive and use the US 281 Donella Drive entrance ramp.
  • Monday, September 16 until Friday, September 20. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for bridge, retaining work and safety enhancements.
  • Friday, September 20 until Monday, September 23. Weekend closure 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Encino Rio to Evans Road for traffic phasing.
  • Friday, September 20 until Monday, September 23. Full weekend closure 9 p.m. until 5 a.m. Left turn lane southbound mainlane closure of one of the left turn lanes at Evans Road for traffic phasing.
  • Saturday, September 21 until Monday, September 23. Full weekend closure 3 a.m. until 5 a.m. Full northbound mainlane closure from the frontage road exit ramp to the Sonterra Boulevard exit ramp for direct connector work. DETOUR: Take the frontage road exit ramp, go through the Loop 1604 intersection and use the Sonterra Boulevard entrance ramp.
  • Saturday, September 21 until Monday, September 23. Full weekend closure 3 a.m. until 5 a.m. Full northbound frontage road closure from the Loop 1604 westbound frontage road to Sonterra Boulevard for direct connector work. DETOUR: On the Loop 1604 westbound frontage road, turn left on the US 281 southbound frontage road, take the turnaround at Donella Drive and use the US 281 Donella Drive entrance ramp.
US 281 – South San Antonio
  • Tuesday, September 17 until Thursday, September 19. Nightly 8 p.m. until 5 a.m. Full mainlane closure in both directions from FM 2537 to Rockport Road for beam placement work.
-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County
  • Current until Friday, September 20. Nightly 9 p.m. until 5 a.m. Alternating mainlanes in both directions between Fair Oaks Parkway and Old Fredericksburg Road (including the Fair Oaks Parkway ramp temporarily) for milling and paving work.
  • Sunday, September 15 until Thursday, September 19. Nightly 9 p.m. until 5 a.m. Alternating mainlanes in both directions between Camp Bullis Road and La Cantera Parkway for moving barrier work.
  • Sunday, September 15 until Friday, September 20. Nightly 9 p.m. until 5 a.m. Alternating mainlanes in both directions between Scenic Loop Road and SH 46 for work on the US 87 bridge/overpass.
I-10 – Far East San Antonio/Bexar County/Guadalupe County
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Current until further notice. Eastbound Ackerman Road exit ramp will be closed through the fall. DETOUR: Eastbound I-10 and southbound I-410 traffic needing to access Ackerman Road must take southbound I-410, exit at FM 1346/E. Houston St., turn around, and take the northbound frontage road to Ackerman Road.
  • Current until Friday, September 27. 5 p.m. Woodlake Parkway will be closed at the I-10 westbound frontage road. DETOUR: Traffic wishing to access the Horizon Pointe subdivision will continue traveling on the westbound frontage road, turn right on Foster Road, and take another right on Sierra Sunset to return to Woodlake Parkway.
  • Sunday, September 15 until Monday, September 16. 9 p.m. to 5 a.m. Left mainlane in both directions between Foster Road and Woodlake Parkway for concrete truck access.
  • Sunday, September 15 until Friday, September 20. Nightly 9 p.m. to 5 a.m. Left eastbound frontage road from Ackerman Road to Foster Road.
  • Sunday, September 15 until Friday, September 20. Nightly 9 p.m. to 5 a.m. Eastbound exit ramp to Foster Road. DETOUR: Eastbound motorists wishing to access Foster Road will remain on I-10 and exit to FM 1516, take the turnaround under FM 1516, enter the I-10 westbound mainlanes, and exit to Foster Road.
  • Monday, September 16 until Thursday, September 19. Daily 7:30 a.m. until 7 p.m. Alternating mainlanes in both directions between SH 130 and US 183 for asphalt and guard fence work.
I-10 – Central San Antonio
  • Sunday, September 15 until Monday, September 16. Nightly 8:30 p.m. until 5 a.m. Westbound right mainlane at I-37 (including I-37 northbound exit ramp) for guard fence installation work.
  • Monday, September 16 until Tuesday, September 17. Nightly 8:30 p.m. until 5 a.m. Westbound left mainlane at I-37 (including I-37 southbound exit ramp) for guard fence installation work.
I-35 – Northeast San Antonio & Comal County
  • Sunday, September 15 until Thursday, September 19. Nightly 9 p.m. until 5 a.m. Northbound right mainlane between FM 1103 and Schwab Road for material hauling work.
  • Wednesday, September 18 until Thursday, September 19. Daily 9 a.m. until 5 p.m. Alternating northbound frontage road lanes between Kowald Lane to Post Road for drainage work.
  • Thursday, September 19 until Saturday, September 21. Nightly 9 p.m. until 5 a.m. Southbound right mainlane between FM 1103 and Schwab Road for milling work.
I-410 – West San Antonio
  • Sunday, September 15 until Friday, September 20. Nightly 8 p.m. to 5 p.m. All northbound mainlanes between the Marbach Road exit ramp to the SH 151 entrance ramp for single slope concrete barrier work. DETOUR: Traffic will use the frontage road to access the next entrance ramp.
  • Sunday, September 15 and Friday, September 20. Nightly 8 p.m. to 5 a.m. All southbound mainlanes between the US 90 exit ramp to the US 90 bridge for removing single slope concrete barrier.
  • Monday, September 16. Daily 10 a.m. to 2 p.m. All northbound frontage road lanes between the entrance ramp past Marbach Road to SH 151 for staging concrete trucks for sidewalk work. The northbound exit ramp to SH 151 will also be closed. DETOUR: Traffic on the frontage road will enter the mainlanes and exit at the next exit.
  • Monday, September 16 until Friday, September 20. Daily 9 a.m. to 3 p.m. The left southbound frontage road lane between Demya Drive to Pilar Drive for staging equipment.
US 90 – West San Antonio
  • Monday, September 16 until Friday, September 20. Daily 9 a.m. to 3 p.m. The left westbound frontage road lane between Tomar Drive to Hunt Lane for staging trucks and rip-rap work.
  • Monday, September 16 until Friday, September 20. Daily 9 a.m. to 3 p.m. The left eastbound frontage road lane between Ray Ellison Boulevard to I-410 for staging trucks and rip-rap work.
  • Monday, September 16 until Saturday, September 21. Daily 9 a.m. to 3 p.m. The right eastbound frontage road lane between Springvale Drive to W. Military Drive for sidewalk and driveway work.
  • Monday, September 16 until Saturday, September 21. Daily 9 a.m. to 3 p.m. The right westbound frontage road lane between W. Military Drive to Colt Drive for sidewalk and driveway work.
I-37 – Central/South San Antonio
  • Monday, September 16 until Saturday, September 21. Daily 9 a.m. until 3 p.m. Southbound left mainlane from Loop 1604 to the San Antonio River for base and paving work.
  • Tuesday, September 17 until Friday, September 20. Nightly 8:30 p.m. until 5 a.m. Alternating southbound mainlanes at I-10 (including I-10 eastbound exit ramp) for guard fence installation work.
PA 1502 – Wurzbach Parkway
  • City of San Antonio closure for Hardberger Park Landbridge project. Monday, September 16 until Friday, September 20. Daily 9 a.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
  • City of San Antonio closure for Hardberger Park Landbridge project. Saturday, September 21. 7 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
Spur 371 – General Hudnell Drive
  • Monday, September 16 until Friday, September 20. Daily 7 a.m. to 3 p.m. The northbound left lane between Billy Mitchell Boulevard and Cupples Road for removing existing guardrail and installing concrete barrier.
  • Monday, September 16 until Friday, September 20. Daily 9 a.m. to 5 p.m. The southbound left lane between Billy Mitchell Boulevard and Cupples Road for removing existing guardrail and installing concrete barrier.
FM 1976 – Walzem Road
  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes from Woodlake Parkway until Gibbs Sprawl Road for barrier work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
SH 16 – Bandera Road
  • Sunday, September 15 until Friday, September 20. Nightly 9 p.m. until 5 a.m. Alternating lanes in both directions between Quincy Lee and Legend Trail for taking asphalt core work.
Loop 353 – New Laredo Highway
  • Monday, September 16. 1 p.m. until 4 p.m. Alternating lanes in both directions at Indian Creek for pouring rail walls.
SH 46 – Boerne/Kendall County
  • Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
FM 474 – Blanco Road/City of Boerne/Kendall County
  • Monday, September 16 until Friday, September 20. Daily 8:30 a.m. until 3:30 p.m. Right lane in both directions between Business 87 to Stonegate Road for tree trimming, culvert cleaning and bridge rail work.
FM 474 – Esser Road/Kendall County
  • Monday, September 16 until Friday, September 20. Daily 8:30 a.m. until 3:30 p.m. Southbound right lane between Blanco Road and Hidden Haven Road for handrail repair work.
SH 16 – McMullen County
  • Monday, September 16 until Friday, September 20. Alternating southbound lanes from FM 1962 to McMullen/Duval county line (mile markers 686-700) for barrier and excavation work.
Other Roads – Bexar County
  • Current until Friday, September 27. Full-time extended closure 7 a.m. until 5 p.m. All lanes of Woodlake Parkway at the I-10 westbound frontage road. DETOUR: Traffic wishing to access the Horizon Pointe subdivision will continue traveling on the westbound frontage road, turn right on Foster Road, and take another right on Sierra Sunset to return to Woodlake Parkway.
  • Saturday, September 14. Full weekend closure 2 a.m. until 10 a.m. Full westbound closure of Encino Rio Road approaching the US 281 intersection for column and cap work. DETOUR: Take a right on the US 281 northbound frontage road, use the northbound to southbound turnaround after Evans Road.
  • Monday, September 16 until Friday, September 20. Nightly 9 p.m. until 5 a.m. Full westbound closure of Encino Rio Road approaching the US 281 intersection for column and cap work. DETOUR: Take a right on the US 281 northbound frontage road, use the northbound to southbound turnaround after Evans Road.
  • Monday, September 16 until Monday, September 30. Daily 9 a.m. until 3 p.m. All lanes in both directions of West Byrd Lane at Loop 1604 for frontage road work.
  • Tuesday, September 17 until Thursday, September 19. Nightly 9 p.m. until 5 a.m. All lanes of Wilderness Parkway in both directions at US 281 for striping work.
  • Friday, September 20 until Monday, September 23. Weekend closure 9 p.m. until 5 a.m. Alternating eastbound lanes of Evans Road east of US 281 for traffic phasing.
  • Friday, September 20 until Monday, September 23. Weekend closure 9 p.m. until 5 a.m. Alternating westbound lanes of Evans Road east of US 281 for traffic phasing.
  • Saturday, September 21 until Monday, September 23. Full weekend closure 3 a.m. until 5 a.m. Full westbound lanes of Encino Rio Road approaching the US 281 intersection for column and cap work. DETOUR: Take a right on the US 281 northbound frontage road, use the northbound to southbound turnaround after Evans Road

Monday, September 9

I-10 & SH 46 In Boerne: 'Split Phase' Signal To Alleviate Backups


It was a tough call.

As part of our project on I-10 improvements between Scenic Loop Road and SH 46 in Boerne, our contractor (Texas Sterling Construction Company) has been steadily working on the retaining wall at the I-10 & SH 46 intersection, part of the work on that overpass and new turnaround bridges.

The tough part of this measure in terms of impact on the traveling public was that it had to take away the dedicated left-turn lane on northbound SH 46 at the overpass to get onto the I-10 westbound frontage road. That in turn created significant backups at the intersection and beyond.

That was the bad news -- now time for some good news. 

Even though it was temporary for this phase of construction, we determined the backups had to be addressed now and not left for later.

Hence the decision to bring back the northbound SH 46 dedicated left-turn option, using what our traffic folks call "split phasing." 

What does this mean? While the full dedicated left-turn lane still cannot be brought back, drivers at least will not have to keep waiting for their southbound counterparts to clear out before being able to turn. Instead, they'll have a protected turn arrow while southbound traffic waits for the light to change (see graphic for details).

The split-phase traffic light phasing change is being put in place today (Monday, September 9). 

As with just about everything else in traffic configurations, there's an upside and downside. In the case of this intersection, putting in place the protected turn arrow will of course give northbound SH 46 drivers better and quicker access to I-10 westbound. But it also means more overall delays as southbound SH 46 drivers will now have to wait their turn to go.

So again, it's all about give and take. We're hoping at least the overall flow at the intersection will improve with this move, resulting in great part from us taking public sentiment and input to heart.

Friday, September 6

Ready For This? Series Of Overnight Closures Next Week On I-10 In Far East San Antonio

Engineering fans, geek out on this.

Our ongoing work on the I-10 mainlane expansion project in Far East San Antonio will require a complex series of overnight closures of Ackerman Road, I-10 westbound mainlanes and ramps connecting I-410 and I-10. 

The process entails closures and detours revealing a method to the madness that we attempt to unpack for you here.

For starters, if you drive this are often you already know that the eastbound I-10 exit ramp to Ackerman Road remains closed to traffic while crews work on the outside eastbound mainlanes. We bring that up not just as a reminder but also for context, since this ongoing closure further complicates these additional steps that need be taken now. 

There is good news out of all of this, believe it or not -- next week’s closures are temporary and will only impact overnight traffic, plus let’s not forget that an additional (third) westbound I-10 mainlane will be opened to traffic following this work.

For those whose night travels will take them through the area during the closure period, we’ve prepared a navigation guide to help you reach your destination as quickly and painlessly as possible:

Closures of I-410 Ramps to Eastbound I-10 – Overnight Sunday, Sept. 8
Crews will be closing both the northbound and southbound I-410 ramps connecting to eastbound I-10 from 7 p.m. Sunday (Sept. 8) through 5 a.m. Monday (Sept. 9) morning to make needed asphalt repairs. Only one ramp will be closed at a time.

NORTHBOUND I-410 RAMP DETOUR: Northbound I-410 drivers accessing eastbound I-10 will take the cloverleaf exit ramp to westbound I-10, stay in the right lane and take the next cloverleaf ramp to southbound I-410, then take a third and final cloverleaf ramp from southbound I-410 to eastbound I-10 (see map below).



SOUTHBOUND I-410 RAMP DETOUR: Southbound I-410 traffic needing to access eastbound I-10 will stay on I-410, exit at FM 1346/E. Houston St., turn around, enter the northbound I-410 mainlanes and take the connecting ramp to eastbound I-10 (see map below).




Closures of Ackerman Road at I-10 – Overnight Monday, Sept. 9 & Tuesday, Sept. 10 

Crews will be placing beams for the I-10 bridge over Ackerman Road on Monday and Tuesday nights, which will require the closure of Ackerman Road in both directions under I-10 from 9 p.m. until 5 a.m. each night.

DETOUR: Northbound Ackerman Road traffic will take the I-10 eastbound frontage road to Foster Road, turn around and take the I-10 westbound frontage road back to Ackerman Road. Southbound Ackerman Road traffic will take the I-10 westbound entrance ramp just west of Ackerman, stay in the right lane, take the I-410 South connecting ramp, travel southbound on I-410, exit to FM 1346/E. Houston St., turn around and take the northbound frontage road back to Ackerman Road (map below).



Closures of I-10 Westbound Mainlanes & I-410 to Westbound I-10 Ramps – Overnight Wednesday, Sept. 11

Crews will be restriping the westbound I-10 mainlanes at I-410 on Wednesday night to allow for the opening of an additional (third) lane to traffic traveling westbound from I-410. This will require a two-phased closure that will be in place from 9 p.m. Wednesday, September 11 until 5 a.m. Thursday, September 12.

Phase 1: Beginning at 9 p.m. on Wednesday, all I-10 westbound mainlanes will be closed between the exit ramp to I-410 and the I-10 westbound entrance ramp located just west of the I-410 interchange as crews restripe the left lane.

DETOUR: All westbound I-10 traffic will be directed to the I-410 exit ramp, stay left on the parallel collector-distributor road that travels under I-410 and re-enter I-10 westbound just west of I-410 (map below).



Phase 2: Once the left (inside) westbound mainlane of I-10 has been restriped, that single lane will be reopened to traffic and the westbound parallel collector-distributor road that travels under I-410 will be closed at the I-410 interchange. The ramps connecting I-410 to westbound I-10 will also be closed (map below).

WESTBOUND I-10 DETOUR: All I-10 westbound through-traffic will be directed to the left (inside) mainlane.

SOUTHBOUND I-410 RAMP DETOUR: All southbound I-410 traffic needing to access westbound I-10 will stay on I-410, exit at FM 1346/E. Houston St., turn around, enter the northbound I-410 mainlanes, take the connecting ramp to eastbound I-10, exit to Foster Road, turn around and enter the I-10 westbound mainlanes just west of Foster.

NORTHBOUND I-410 RAMP DETOUR: All northbound I-410 traffic needing to access westbound I-10 should take the connecting ramp to eastbound I-10, exit to Foster Road, turn around and enter the I-10 westbound mainlanes just west of Foster.



As always, thank you for your patience as we make great progress on expanding and improving I-10  I-10 in this area. For more information about all improvements along I-10 in Far East San Antonio, visit https://www.txdot.gov/inside-txdot/projects/studies/san-antonio/i-10east-i410-bexar-guadalupe-county-line.html.