Friday, July 6

A look ahead to next weekend

We do not have any major construction closures this coming weekend due to the 4th of July. However, we do have a few major FULL main lane closures next weekend that can impact travelers:

I-35 at FM 1103 in Schertz
Starting at 9 p.m. on Saturday, July 14, I-35 both north and southbound will be closed to demolish the existing FM 1103 bridge structure. Demolition of the bridge is expected to be complete by late Sunday morning with cleanup and restoration to original main lane configuration by 3 p.m. Sunday afternoon.
Detours:
I-35 Northbound
Traffic will exit I-35 northbound main lane traffic to the frontage road at FM 1103. Traffic to remain on frontage road thru FM 1103. The entrance ramp from FM 1103 to I-35 northbound will be open to traffic.
I-35 Southbound 
Traffic will exit I-35 southbound main lanes to the frontage road at FM 1103 and enter I-35 southbound at the entrance ramp past FM 1103. 
The new FM 1103 portion of the bridge will be open to traffic for westbound traffic only once demolition of the old bridge is complete.

Redland Road at US 281
This full closure will be necessary to construct the Redland Road intersection. Work includes installation of drainage structures, removal of some existing utility, new base and asphalt pavement. Also, temporary pavement will be constructed to tie-in to existing travel lanes.
Work is scheduled to take place in two weekends:
  • From Saturday, July 14, 2018, at 3 a.m. to Monday, July 16, 2018, at 5 a.m. 
  • From Saturday, July 21, 2018, at 3 a.m. to Monday, July 23, 2018, at 5 a.m. 
During the execution of this work, full closures will be required as follows:
Full Closure of eastbound and westbound Redland Road at the approach of US 281 – Public to detour by using Ridgewood Parkway and Sonterra Boulevard.
During this closure, traffic will be detoured to allow workers full access to the roadway to allow them to work quickly and uninterrupted. Complete closure of the roadway can result in increased productivity, reduced construction time, reduced impact to traffic, increased safety for both traveling public & workers, and in some cases a cost saving. Off-duty police will be used to assist with traffic control. Work is weather permitting.
You can receive information on lane closures straight to your e-mail inbox by registering here http://eepurl.com/cXz2kr.

I-10 at Dominion Drive
Crews will close the eastbound main lanes of I-10 between Boerne Stage Road and Camp Bullis Road Saturday, July 14 at 3 a.m. until 5 a.m. Sunday, July 15 to continue work that was previously done this past weekend. The underpass at Dominion Drive and entrance ramps will also be closed. DETOUR for I-10: Eastbound main lane traffic will exit at Dominion Drive and enter highway at Camp Bullis Road. DETOUR for Dominion Drive: Westbound traffic will detour at Boerne Stage Road and eastbound traffic will detour at Camp Bullis Road.