- Saturday, June 1. 3 a.m. until 7 a.m. Full eastbound closure from the US 281 northbound exit ramp to the Redland Road entrance ramp to profile beams. DETOUR: Use the US 281 northbound exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon entrance ramp.
- Saturday, June 1. 3 a.m. until 7 a.m. Full westbound closure from the US 281 northbound exit ramp to the US 281 entrance ramp to set steel girders. DETOUR: Use the US 281 northbound exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
- Monday, June 3 until Friday, June 7. Nightly 9 p.m. to 5 a.m. Full eastbound closure from the US 281 northbound exit ramp to the Redland Road entrance ramp to install life lines. DETOUR: Use the US 281 northbound exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
- Monday, June 3 until Friday, June 7. Nightly 9 p.m. to 5 a.m. Full westbound closure from US 281 northbound exit ramp to the US 281 entrance ramp to install life lines. DETOUR: Use the US 281 northbound exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
- Saturday, June 8 until Monday, June 10. Full weekend closure 3 a.m. to 5 a.m. Full eastbound closure from the US 281 northbound exit ramp to the Redland Road entrance ramp to install life lines. DETOUR: Use the US 281 northbound exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
- Saturday, June 8 until Monday, June 10. Full weekend closure 3 a.m. to 5 a.m. Full westbound frontage road westbound to eastbound turnaround closure at US 281. DETOUR: Make a double left at the signalized intersection.
- Saturday, June 8 until Monday, June 10. Full weekend closure 3 a.m. to 5 a.m. Full westbound frontage road closure at US 281 for deck pour.
- Saturday, June 8 until Monday, June 10. Full weekend closure 3 a.m. to 5 a.m. Full westbound closure from the US 281 northbound exit ramp to the US 281 entrance ramp to install life lines. DETOUR: Use the US 281 northbound exit ramp, continue through the US 281 intersections and use the US 281 entrance ramp.
- Monday, June 10 until Tuesday, June 11. 7 p.m. until 5 a.m. Southbound mainlane closure and full closure of SH 218 (Pat Booker Road) at Loop 1604 as well as turnarounds for bridge/overpass work.
Loop 1604 – Northwest San Antonio
- Friday, May 31 until Sunday, June 2. Full weekend closure 9 p.m. until 5 a.m. Eastbound right mainlane from Braun exit to Bandera exit (including the Bandera exit ramp) for reconfiguration striping work.
- Sunday, June 2 until Friday, June 7. Nightly 9 p.m. until 5 a.m. Eastbound frontage road from I-10 to Roger’s Ranch Road for milling and paving work.
- Sunday, June 2 until Friday, June 7. Nightly 9 p.m. until 5 a.m. One mainlane in both directions from Bandera Road to Roger’s Ranch Road for bridge joint work.
- Monday, June 3 until Wednesday, June 5. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure from Blanco Road to Bitters Road (including entrance ramps from US 281, Stone Oak Boulevard and Blanco Road) for work on new Huebner Road turnaround bridge.
- Monday, June 3 until Friday, June 7. Daily 9 a.m. until 3 p.m. One westbound frontage road lane from Vance Jackson Road to I-10 for mow strip work.
- Monday, June 3 until Friday, June 7. Daily 9 a.m. until 3 p.m. One eastbound frontage road lane at Kyle Seale Parkway and at Hausman Road for traffic signal work.
- Monday, June 3 until Friday, June 7. Daily 9 a.m. until 4 p.m. One eastbound frontage road lane at Babcock Road for traffic signal work.
- Wednesday, June 5 until Friday, June 7. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure from NW Military Highway to Blanco Road (including entrance ramps from NW Military Highway and Bitters Road) for work on new Huebner Road turnaround bridge.
- Saturday, June 1, 9 a.m. to 3 p.m. Northbound right frontage road lane between US 90 to north of Medio Creek will be closed for asphalt work.
- Monday, June 3 until Friday, June 7. 9 a.m. to 3 p.m. Southbound frontage road shoulder between Misty Woods Street and Wiseman Boulevard will be closed for metal beam guard fence work.
- Monday, June 3 until Saturday, June 8. Nightly 9 p.m. to 5 a.m. All lanes at Wiseman Boulevard for painting beams under the bridge deck and installing clearance signs. DETOUR: Traffic will be detoured to Military Drive or FM 471 (Culebra Road) to access east or westbound Wiseman Road.
- Monday, June 3 until Saturday, June 8. Nightly 9 p.m. to 5 a.m. All lanes at Military Drive closed for painting beams under the bridge deck and installing clearance signs. DETOUR: Traffic will be detoured to Military Drive or FM 471 (Culebra Road) to access east or westbound Wiseman Road.
- Monday, June 3 until Saturday, June 8. Nightly 9 p.m. to 5 a.m. All lanes at FM 1957 (Potranco Road) for painting beams under the bridge deck and installing clearance. DETOUR: Traffic will be detoured to Military Drive or FM 471 (Culebra Road) to access east or westbound Wiseman Road.
- Monday, June 3 until Saturday, June 8. Daily 9 a.m. to 7 p.m. Alternating southbound frontage lanes between SH 151 and FM 1957 (Potranco Road) for seal coat and paving final surface work.
- Monday, June 3 until Saturday, June 8. Daily 9 a.m. to 3 p.m. The southbound exit ramp shoulder to Wiseman Boulevard for concrete beam curb work.
- Monday, June 3 until Saturday, June 8. Daily 9 a.m. to 7 p.m. Alternating northbound frontage road lanes between FM 1957 (Potranco Road) to SH 151 for sidewalk work.
- Current until Friday, June 7. Full-time closure. The ramp on southbound US 281 to westbound Loop 1604 for ramp work. DETOUR: Traffic on US 281 SB will need to use Loop 1604 EB to access Loop 1604 WB.
- Sunday, June 2 until Friday, June 7. Nightly 9 p.m. to 5 a.m. Alternating northbound lane closure from Loop 1604 to Marshall Road for miscellaneous construction.
- Sunday, June 2 until Friday, June 7. Nightly 9 p.m. to 5 a.m. Alternating southbound lane closure from Marshall Road to Loop 1604 for miscellaneous construction.
- Monday, June 3 until Friday, June 7. Nightly 9 p.m. to 5 a.m. Full northbound closure from the Frontage Road exit ramp to the Sonterra Boulevard entrance ramp to set steel girders. DETOUR: take the Frontage Road exit ramp, continue through the Loop 1604 intersection and take the Sonterra Boulevard entrance ramp.
- Monday, June 3 until Friday, June 7. Nightly 9 p.m. to 5 a.m. Full closure of the northbound to westbound direct connector to install life lines. DETOUR: take the Frontage Road exit ramp, take a left on the loop 1604 westbound frontage road and use the US 281 entrance ramp.
- Monday, June 3 until Friday, June 7. Nightly 9 p.m. to 5 a.m. Full southbound closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp to install life lines. DETOUR: take the Sonterra Boulevard exit ramp, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
- Monday, June 3 until Friday, June 7. Nightly 9 p.m. to 5 a.m. Full southbound frontage road closure from the Sonterra Boulevard exit ramp to the Frontage Road entrance ramp to install life lines. DETOUR: Sonterra Boulevard traffic; go north on US 281 and take the turnaround south of Encino Rio. All southbound traffic; take the Donella Drive exit ramp, use the turnaround at Donella Drive and stay on the northbound frontage road.
- Saturday, June 8 until Monday, June 10. Full weekend closure 3 a.m. to 5 a.m. Full northbound closure from the Frontage Road exit ramp to the Sonterra Boulevard entrance ramp for a deck pour. DETOUR: take the Frontage Road exit ramp, take a right on the Loop 1604 eastbound frontage road. If going north; use the turnaround at Gold Canyon Road and take a right on the northbound frontage road. If going west, drive along the eastbound frontage road through the Gold Canyon Road intersection, use the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
- Saturday, June 8 until Monday, June 10. Full weekend closure 3 a.m. to 5 a.m. Full northbound frontage road closure at Loop 1604 for deck pour. DETOUR: take the Frontage Road exit ramp and make a right on the Loop 1604 eastbound frontage road. If going north, use the turnaround at Gold Canyon Road and take a right on the northbound frontage road. If going west; continue on the eastbound frontage road through the Gold Canyon Road intersection, use the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
- Saturday, June 8 until Monday, June 10. Full weekend closure 3 a.m. to 5 a.m. Full southbound closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for deck pour. DETOUR: take the Sonterra Boulevard exit ramp, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
- Saturday, June 8 until Monday, June 10. Full weekend closure 3 a.m. to 5 a.m. Full southbound to northbound turnaround closure at Loop 1604 for deck pour. DETOUR: take the double left at the signalized intersection.
- Saturday, June 8 until Monday, June 10. Full weekend closure 3 a.m. to 5 a.m. Alternating southbound frontage road lanes from Sonterra Boulevard to the westbound frontage road for deck pour.
- Saturday, June 8 until Monday, June 10. Full weekend closure 3 a.m. to 5 a.m. Full southbound frontage road closures from the Sonterra Boulevard exit ramp to the Frontage Road entrance ramp to install life lines. DETOUR: Sonterra Boulevard traffic; go north on US 281 and take the turnaround south of Encino Rio. All southbound traffic; take the Donella Drive exit ramp, use the turnaround at Donella Drive and stay on the northbound frontage road.
- Current until Friday, June 7. Daily 9 a.m. until 3 p.m. Left eastbound frontage road at Boerne Stage Road for barrier work.
- Current until Friday, June 7. Daily 9 a.m. until 3 p.m. Left westbound frontage road lane at Dominion Drive for retaining wall work.
- Wednesday, June 5 until Thursday, June 6. 9 p.m. until 5 a.m. Alternating mainlanes in both directions between SH 46 and Scenic Loop Road for pavement marking work.
- Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
- CPS Energy closure. Sunday, June 2. 6 a.m. until 1 p.m. Intermittent (5 to 15 minutes) mainlane closures in both directions from FM 1516 to Loop 1604 power line installation work.
- Sunday, June 2 until Monday, June 3. 9 p.m. until 5 a.m. One alternating eastbound mainlane from Foster Road to Woodlake Parkway for temporary traffic shift. When the right lane is closed, the entrance ramp from Ackerman Road will also be closed; drivers should instead use the entrance ramp after Foster Road.
- Monday, June 3 until Thursday, June 6. Daily 7:30 a.m. until 7 p.m. Alternating mainlanes in both directions between SH 130 and US 183 for guard fence work.
- Wednesday, June 5 until Thursday, June 6. 7 p.m. until 5 a.m. All westbound mainlanes at FM 1516 and all lanes of FM 1516 underneath I-10 as crews install precast concrete panels for the new overpass bridge. DETOUR: Westbound mainlane traffic will exit at FM 1516 and re-enter the mainlanes just west of FM 1516. Southbound FM 1516 traffic will take the westbound frontage road and turn around at Foster Road. Northbound FM 1516 traffic will take the eastbound frontage road and turn around at Loop 1604.
- Thursday, June 6 until Friday, June 7. 9 p.m. until 5 a.m. All eastbound mainlanes at FM 1516 and all lanes of FM 1516 underneath I-10 as crews install precast concrete panels for the new overpass bridge. DETOUR: Eastbound mainlane traffic will exit at FM 1516 and re-enter the mainlanes just east of Loop 1604. Southbound FM 1516 traffic will take the westbound frontage road and turn around at Foster Road. Northbound FM 1516 traffic will take the eastbound frontage road and turn around at Loop 1604.
- Monday, June 3 until Thursday, June 6. Nightly 9 p.m. until 6 a.m. Full southbound mainlane closure at FM 1103 (Exit 178) including the bridge for work on the new highway overpass/bridge and for barrier removal work.
- Wednesday, June 5 until Saturday, June 8. Nightly 9 p.m. until 6 am. Full northbound mainlane closure at FM 1103 (Exit 178) including the bridge for work on the new highway overpass/bridge and for barrier removal work.
- Current until Friday, June 7. Nightly 8 p.m. to 5 a.m. All southbound main lanes from US 90 to Valley Hi Drive for over sign bridge truss and sign work. The southbound/westbound connector and Valley Hi Drive exit ramp will also be closed. DETOUR: Traffic will be detoured to the frontage road and enter at the next ramp.
- Saturday, June 1. 6 a.m. to 12 noon. Two right southbound main lanes between US 90 exit to the US 90 bridge to remove rip-rap and stage dump trucks.
- Tuesday, June 4. 9 a.m. to 12 noon. Two right southbound main lanes between US 90 exit to the US 90 bridge to stage concrete trucks to pour traffic rail foundation.
- Saturday, June 1. 8 a.m. to 3 p.m. Right eastbound mainlane between east of Loop 1604 and west of I-410 for striping work. DETOUR: Traffic will need to stay on the eastbound frontage road and reenter after I-410.
- Current until Friday, June 7. Nightly 8 p.m. to 5 a.m. All eastbound mainlanes from Ray Ellison Drive to I-410 for over sign bridge truss and sign work. The eastbound/northbound connector will also be closed. DETOUR: Traffic will be detoured to the frontage road and enter at the next ramp.
- Sunday, June 3 until Friday, June 7. Nightly 9 p.m. to 5 a.m. Eastbound right mainlane between Military Drive West and Wiseman Boulevard for mill and inlay work. Ramps will be closed as needed.
- Monday, June 3 until Friday, June 7. Daily 9 a.m. to 4 p.m. Alternating eastbound frontage road lanes between Wiseman Boulevard and I-410 for pouring concrete mow strip work.
- Monday, June 3 until Friday, June 7. Daily 9 a.m. to 4 p.m. Alternating eastbound frontage road lanes between Old Highway 90 and Westover Hills for guardrail work.
- Thursday, June 6 until Friday, June 7. 9 p.m. until 5 a.m. Right northbound mainlane from Old Corpus Road to I-410 westbound exit for light pole installation work.
- City of San Antonio closure for Hardberger Park Landbridge project. Monday, June 3 until Friday, June 7. Daily 9 a.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
- City of San Antonio closure for Hardberger Park Landbridge project. Saturday, June 8. 7 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
Loop 368 – Austin Highway
- Current until Friday, June 14. Daily 9 a.m. to 3 p.m. Alternating lanes in both directions from Montclair Avenue to Old Rittiman Road (including North New Braunfels intersection) for center median work.
- Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes from Woodlake Parkway until Gibbs Sprawl Road for barrier work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
- Monday, June 3 until Saturday, June 8. Daily 9 a.m. until 4 p.m. Westbound right lane from WW White to Grobe Road for sidewalk and driveway work.
- Monday, June 3 until Saturday, June 8. Daily 9 a.m. until 4 p.m. Northbound right lane from Elmi Road to Springfield Road for sidewalk and driveway work.
- Current until Friday, May 31. Full time closure. Alternating lanes in both directions from FM 1332 to Atascosa/McMullen county line for milling and inlay, bridge rail and guard rail work.
- Monday, June 3 until Friday, June 7. Daily 8 a.m. until 5 p.m. Alternating southbound lanes between Tilden and FM 624 for guard fence installation and excavation work.
- Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
- Thursday, June 6 until Friday, June 7. 9 a.m. until 4 p.m. Alternating lanes in both directions from ½-mile east of FM 3351 to 1.5-miles east of FM 3351 (Voss Middle School) for paving work.
- Current until 8 p.m. Friday, May 31. Both directions closed between SH 16 to La Parita Creek for drainage work.
- Monday, June 3 until Saturday, June 8. Daily 9 a.m. until 4 p.m. Northbound right lane of San Pedro Avenue between I-410 and W. Rector for sidewalk and driveway work.