Friday, March 13

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North Central San Antonio
  • Sunday, March 15 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure from the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Sunday, March 15 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Monday, March 16 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Left lane eastbound frontage road closure at US 281 for concrete work.
  • Monday, March 16 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Alternating westbound frontage road closure from the US 281 north exit ramp to the US 281 northbound frontage road.
  • Saturday, March 21 until Monday, March 23. Weekend full closure 3 a.m. until 5 a.m. Full eastbound mainlane closure of the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Saturday, March 21 until Monday, March 23. Full weekend closure 3 a.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Saturday, March 21 until Monday, March 23. Full Weekend closure 3 a.m. until 5 a.m. Full eastbound frontage road closure of the east- to westbound turnaround at US 281 for direct connector work.
Loop 1604 – Northeast San Antonio
  • Sunday, March 15 until Thursday, March 19. Nightly 9 p.m. until 5 a.m. Eastbound frontage road at O’Connor Road (including intersection) for pavement repair work.
  • Sunday, March 15 until Thursday, March 19. Nightly 9 p.m. until 5 a.m. Frontage road in both directions at Bulverde Road for pavement repair work.
  • Sunday, March 15 until Thursday, March 19. Nightly 9 p.m. until 5 a.m. One mainlane in both directions between Redland Road and Green Mountain Road for guard fence replacement work and mow strip work.
  • Sunday, March 15 until Thursday, March 19. Nightly 9 p.m. until 5 a.m. Westbound frontage road between Bulverde Road and Redland Road for barrier resetting work.
  • Sunday, March 15 until Thursday, March 19. Nightly 9 p.m. until 5 am. One westbound mainlane between Redland Road and Bulverde Road for striping work.
Loop 1604 – Northwest San Antonio
  • Friday, March 13 until Saturday, March 14. 9 p.m. until 5 a.m. Westbound left mainlane between SH 16 (Bandera Road) and FM 1560 (Hausman Road) for barrier setting work.
  • Friday, March 13 until Sunday, March 15. Full weekend closure 9 a.m. until 5 p.m. Eastbound left frontage road lane between Champions Gate and FM 1560 (Hausman Road) for barrier setting work.
  • Friday, March 13 until Monday, March 16. Full weekend closure 9 p.m. until 5 a.m. Eastbound right mainlane and shoulder between SH 16 (Bandera Road) and FM 1560 (Hausman Road) including the Hausman exit ramp (2-month closure) for barrier and traffic rail work.
Loop 1604 – Far East San Antonio
  • None scheduled.
Loop 1604 – South San Antonio
  • Monday, March 9 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Eastbound mainlane at US 281 for barrier removal work.
US 281 – North Central San Antonio/Bexar County
  • Sunday, March 15 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for paving and bridge work.
  • Monday, March 16 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Full northbound mainlane ramp closure of the north- to westbound Loop 1604 direct connector ramp for bridge work. DETOUR: Use the frontage road exit ramp, turn left on the Loop 1604 westbound frontage road, and continue on the US 281 entrance ramp.
  • Monday, March 16 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Full southbound mainlane closure from the south- to northbound turnaround at Stone Oak/Tournament Players Club (TPC) Parkway for bridge work. DETOUR: Use the turnaround south of Stone Oak/Tournament Players Club (TPC) Parkway.
  • Monday, March 16 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Left turn lane northbound mainlane closure at Stone Oak/Tournament Players Club (TPC) Parkway both north- to westbound turn lanes for bridge work. DETOUR: Use the turnaround north of Stone Oak/Tournament Players Club (TPC) Parkway.
  • Monday, March 16 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Left turn lane southbound mainlane closure at Stone Oak/Tournament Players Club (TPC) Parkway both south- to eastbound turn lanes for bridge work. DETOUR: Use the turnaround south of Stone Oak/Tournament Players Club (TPC) Parkway.
  • Monday, March 16 until Friday, March 20. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Marshall Road for soundwall work and safety enhancements.
  • Saturday, March 21 until Monday, March 23. Weekend full closure 3 a.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound frontage road, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Saturday, March 21 until Monday, March 23. Full weekend closure 3 a.m. until 5 a.m. Full northbound mainlane closure from the frontage road exit ramp to the Sonterra Boulevard entrance ramp. DETOUR: Use the frontage road exit ramp, turn right on the Loop 1604 eastbound frontage road, if heading north, take the turnaround at Gold Canyon Road, turn right on the northbound frontage road and use the Stone Oak Parkway exit ramp.
  • Saturday, March 21 until Monday, March 23. Full weekend closure 3 a.m. until 5 a.m. Full southbound frontage road closure at Loop 1604 for direct connector work. DETOUR: Turn right on the westbound frontage road, take the turnaround at Stone Oak Parkway and turn right on the southbound frontage road.
  • Saturday, March 21 until Monday, March 23. Continuous full closure 3 a.m. until 5 a.m. Northbound Redland Road bypass ramp mainlane closure from Sonterra Boulevard to Encino Rio for ramp work.
  • Saturday, March 21 until Monday, March 23. Continuous full closure 3 a.m. until 5 a.m. Left turn lane northbound mainlane closure at Evans Road both north- to westbound turn lanes for bridge work. DETOUR: Use the turnaround north of Evans Road.
  • Saturday, March 21 until Monday, March 23. Continuous full closure 3 a.m. until 5 a.m. Left turn lane southbound mainlane closure at Evans Road both south- to eastbound turn lanes for bridge work. DETOUR: Use the turnaround south of Evans Road.
US 281 – South San Antonio
  • Monday, March 16 until Thursday, March 19. Daily 9 a.m. until 4 p.m. Right mainlane in both directions at FM 1937 for traffic light pole installation work.
I-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County
  • Current until Wednesday, March 18. Daily 9 a.m. until 3 p.m. Eastbound left frontage road lane between Two Creeks and FM 3351 (Ralph Fair Road) for drainage work.
  • Tuesday, March 3 until Thursday, April 9. Daily 7 a.m. until 7 p.m. Westbound right mainlane and shoulder between Kerr/Gillespie county line and Kerr/Kimble county line for paving work.
  • Monday, March 9 until Friday, March 20. Daily 9 a.m. until 3 p.m. Westbound left frontage road lane between FM 3351 (Ralph Fair Road) and Buckskin Drive for drainage work.
  • Tuesday, March 10 until Thursday, April 9. Daily 7 a.m. until 7 p.m. Eastbound right mainlane and shoulder between Kerr/Gillespie county line and Kerr/Kimble county line for paving work.
  • Monday, March 16 until Friday, March 27. Daily 9 a.m. until 3 p.m. Westbound left frontage road lane between Dominion Drive and Boerne Stage Road for retaining wall work.
I-10 – Far East San Antonio/Bexar County/Seguin/Guadalupe County
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Friday, March 13 until Monday, March 16. 8 p.m. to 5 a.m. The left westbound I-10 mainlane from just east of Loop 1604 to just west of Woodlake Parkway will be closed for traffic switch activities. Following the traffic switch, two mainlanes will re-open in the median area and the existing westbound mainlanes and westbound exit ramp to FM 1516 will be closed. DETOUR: Westbound I-10 mainlane drivers needing to access FM 1516 may take either the Loop 1604 exit and travel west on the frontage road to FM 1516 or take the Ackerman Road exit, turn around, and travel back to FM 1516.
  • Monday, March 16 until Wednesday, March 18. Westbound exit ramp to Loop 1604 will be closed to finish drainage and road work. DETOUR: Westbound traffic needing to access Loop 1604 will need to exit Graytown road and continue on the westbound frontage road to Loop 1604.
  • Monday, March 16 until Friday, March 20. Daily 9 a.m. to 3 p.m. One alternating lane in each direction of Ackerman Road under I-10 for bridge construction activities.
I-10 – Central San Antonio
  • None scheduled.
I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County
  • Monday, March 16 until Friday, March 20. Daily 8:30 a.m. until 4 p.m. Right frontage road lane in both directions at Rittiman Road for sidewalk and curb installation work.
  • Monday, March 16 until Saturday, March 21. Daily 8:30 a.m. until 5:30 p.m. Northbound frontage road between FM 1103 and Schwab Road for sidewalk construction work.
  • Wednesday, March 18. 9 a.m. until 4 p.m. Southbound left mainlane and shoulder between Schwab Road and FM 2252 for illumination repair work.
I-37 – Central San Antonio
  • Sunday, March 15 until Tuesday, March 17. Nightly 8 p.m. until 5 a.m. Southbound right mainlane between Cesar Chavez and Boyer for new guard rail installation work.
  • Tuesday, March 17 until Friday, March 20. Nightly 8 p.m. until 5 a.m. Westbound exit ramp to I-10 westbound for new guard rail installation work..
I-410 – West San Antonio
  • Current until Saturday, March 14. Daily 9 a.m. to 3 p.m. One frontage road in both directions between SH 151 to FM 471 (Culebra Road) and the turnarounds at West Military Drive for electrical service work. DETOUR: Traffic will need to use the SH 151 and FM 471 (Culebra Road) turnarounds.
  • Friday, March 13 until Monday, March 16. Weekend 8 p.m. to 5 a.m. All southbound mainlanes between Waters Edge Drive to US 90 for mill and inlay operations. DETOUR: Traffic will take the US 90 eastbound exit to I-410 southbound frontage road.
  • Friday, March 20 until Monday, March 23. Weekend 8 p.m. to 5 a.m. All southbound mainlanes between Waters Edge Drive to US 90 for mill and inlay operations. DETOUR: Traffic will take the US 90 eastbound exit to I-410 southbound frontage road.
  • Current until Monday, March 30. Weekend 8 p.m. to 5 a.m. Two alternating lanes in each direction between SH 151 to Valley Hi Drive for mill and inlay work.
  • Current until Friday, March 27. Daily 9 a.m. to 3 p.m. Alternating frontage road lanes in both directions between US 90 bridge to SH 151 for mill and inlay work.
US 90 – West San Antonio
  • Current until Friday, March 27. Daily 9 a.m. to 3 p.m. Alternating frontage road lanes between Ray Ellison Drive to US 90 bridge (eastbound) and Tomar Drive to Hunt Lane bridge (westbound) for staging equipment and rock placement.
SH 16 – Bandera Road
  • None scheduled.
FM 3351 – Ralph Fair Road
  • None scheduled.
PA 1502 – Wurzbach Parkway
  • City of San Antonio/TCI closure for Hardberger Park Landbridge project. Monday, March 16 until Friday, March 20. 9 a.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
  • City of San Antonio/TCI closure for Hardberger Park Landbridge project. Saturday, March 21. 7 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
FM 2252 – Nacagdoches Road
  • Current until Friday, March 20. Daily 8 a.m. until 5 p.m. Eastbound right lane and shoulder between Loop 1604 and Dolente Road for sidewalk, curb and shoulder work.
FM 1560 – Hausman Road
  • Exit ramp from Loop 1604 eastbound closed for approximately two months starting Monday, March 16.
FM 1516 – South Seguin Road/Converse
  • None scheduled.
SH 218 – Pat Booker Road
  • None scheduled.
Spur 371 – General Hudnell Drive
  • None scheduled.
US 87 – Roland Avenue
  • Current until Sunday, March 15. Daily 9 a.m. until 4 p.m. One lane in both directions between I-10 and Rigsby Avenue for placing sod, manhole and electrical work.
Spur 421 – Bandera Road
  • None scheduled.
FM 1976 – Walzem Road/Gibbs Sprawl Road
  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes between Woodlake Parkway and Gibbs Sprawl Road for barrier/pavement work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
  • Current until further notice. Full-day closure. Southbound lane between Toepperwein Road and Walzem Road for barrier setting work and road rehab work.
Loop 353 – New Laredo Highway
  • None scheduled.
Other Roads – Bexar County
  • None scheduled.
Loop 337 – New Braunfels/Comal County
  • Current until Tuesday, April 7. Full-time closure. Northbound access road to Landa Street for road widening, traffic island removal, sidewalk and curb work.
FM 2673 – Canyon Lake/Comal County
  • None scheduled.
FM 2252 – Comal County
  • None scheduled.
SH 46 – Guadalupe County
  • None scheduled.
FM 78 – Guadalupe County
  • None scheduled.
FM 1518 – Schertz/Cibolo Guadalupe County
  • None scheduled.
US 90A – Seguin/Guadalupe County
  • None scheduled.
SH 123 – Seguin/Guadalupe County
  • None scheduled.
Business 123 – South Austin Street/Seguin/Guadalupe County
  • None scheduled.
I-35 – Atascosa County/Frio County
  • Friday, March 13. 8 a.m. until 5 p.m. One northbound mainlane between FM 3175 and FM 2790 for barrier resetting work.
US 181 – Floresville/Wilson County
  • None scheduled.
US 87 – Wilson County
  • None scheduled.
SH 46 – Boerne/Kendall County
  • Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
RM/FM 1376 – Kendall County
  • Current until 7 p.m. Saturday, March 14. One lane at various locations between North School Street and Wasp Creek Road for culvert work.
  • Current until Sunday, March 15. Full time all-day closure. All lanes in both directions at Wasp Creek Road for road reconstruction work. DETOUR: Roadway open to local traffic but drivers wishing to travel between Boerne and Sisterdale will be diverted to FM 474 and FM 473.
  • Monday, March 16 until Saturday, March 21. Daily 7 a.m. until 7 p.m. One lane at various locations between North School Street and Wasp Creek Road for culvert work.
FM 1333 – Atascosa County
  • Current until Friday, May 1. Full closure (all day) in both directions at Atascosa River (between FM 476 and SH 173) for culvert removal and replacement work.
FM 140 – Atascosa County
  • Current until Saturday, March 21. Daily 7 a.m. until 7 p.m. Alternating lanes in both directions (flagging operations) between SH 16 and La Parita Creek for paving work.
SH 16 – McMullen County
  • Monday, March 16 until Friday, March 20. Daily 7 a.m. until 6 p.m. Alternating lanes in both directions between Ben Franklin Road and McMullen/Duval County line for paving work.