Loop 1604 – North Central San Antonio
- Tuesday, September 8 until Thursday, September 10. 9 p.m. to 5 a.m. Ramp closures, in both directions, from Redland Rd. to Green Mountain Rd. for mill and overlay work.
- Tuesday, September 8 until Thursday, September 10. 9 p.m. to 5 a.m. Single eastbound mainlane closure from Redland Rd. to Bulverde Rd. for rail demolition.
- Tuesday, September 8 until Thursday, September 10. 9 p.m. to 5 a.m. Single lane closures, in both directions, from Redland Rd. to Green Mountain Rd. for mill and overlay work.
- Tuesday, September 8 until Friday, September 11. 9 a.m. to 4 p.m. Single eastbound frontage road lane closure from Redland Rd. to Bulverde Rd. for erosion control.
- Tuesday, September 8 until Friday, September 11. Nightly 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from the Stone Oak Parkway entrance ramp to the Gold Canyon Road exit ramp for bridge work.
- Tuesday, September 8 until Friday, September 11. Nightly 9 p.m. until 5 a.m. Alternating westbound mainlane closure from the US 281 north exit ramp to the Stone Oak Parkway exit ramp.
- Tuesday, September 8 until Friday, September 11. Nightly 9 p.m. until 5 a.m. Alternating eastbound frontage road closure from the Stone Oak Parkway entrance ramp to the Gold Canyon Road exit ramp for bridge work.
- Tuesday, September 8 until Friday, September 11. Nightly 9 p.m. until 5 a.m. Alternating westbound frontage road closure from the US 281 north exit ramp to the Stone Oak Parkway exit ramp.
Loop 1604 – North West San Antonio
- Tuesday, September 8 until Thursday, September 10. 9 p.m. to 5 a.m. Eastbound frontage road lane closed from Bandera Rd. to Hausman Rd., including ramps, for installation of illumination poles.
Loop 1604 – Far East San Antonio
- Tuesday, September 8. 9 a.m. to 3 p.m. Northbound to southbound turnaround at Kitty Hawk Rd. closed to move forms.
US 281 – North Central San Antonio/Bexar County
- Tuesday, September 8 until Friday, September 11. Nightly 9 p.m. until 5 a.m. Southbound mainlane closure of the south- to eastbound direct connector ramp to Loop 1604 for bridge work. DETOUR: Take the Redland Road/Sonterra Boulevard exit ramp to the southbound US 281 frontage road, turn left on the eastbound Loop 1604 frontage road and use the Gold Canyon Road entrance ramp.
- Tuesday, September 8 until Friday, September 11. Nightly 9 p.m. until 5 a.m. Southbound frontage road closure from the Evans Road entrance ramp to Encino Rio for soundwall work. DETOUR: Take the southbound US 281 entrance ramp and use the Redland Road exit ramp.
- Tuesday, September 8 until Friday, September 11. Nightly 9 p.m. until 5 a.m. Northbound mainlane closure of the Sonterra Boulevard exit ramp for drainage work. DETOUR: Take the frontage road exit ramp and go through the Loop 1604 intersection.
- Tuesday, September 8 until Friday, September 11. Nightly 9 p.m. until 5 a.m. Northbound mainlane closure from the north- to southbound turnaround at Evans Road for concrete paving. DETOUR: Use the turnaround at Stone Oak/Tournament Players Club (TPC) Parkway. Closure will not happen concurrently with other turnaround closures in the same direction.
- Tuesday, September 8 until Friday, September 11. Nightly 9 p.m. until 5 a.m. Northbound frontage road closure from the north- to southbound turnaround at Encino Rio for concrete paving. DETOUR: Use the turnaround at Stone Oak/Tournament Players Club (TPC) Parkway. Closure will not happen concurrently with other turnaround closures in the same direction.
- Tuesday, September 8 until Friday, September 11. Nightly 9 p.m. until 5 a.m. Southbound frontage road closure from the south- to northbound turnaround at Encino Rio for concrete paving. DETOUR: Use the turnaround at Redland Road. Closure will not happen concurrently with other turnaround closures in the same direction.
- Tuesday, September 8 until Friday, September 11. Nightly 9 p.m. until 5 a.m. Left turn lane northbound mainlane closure at Evans Road both north- to westbound turn lanes for concrete paving. DETOUR: Use the turnaround at Stone Oak/Tournament Players Club (TPC) Parkway. Closure will not happen concurrently with the other turnaround closures in the same direction.
- Tuesday, September 8 until Friday, September 11. Nightly 9 p.m. until 5 a.m. Left lane northbound frontage road closure from Encino Rio to Evans Road for concrete paving.
- Tuesday, September 8 until Friday, September 11. Nightly 9 p.m. until 5 a.m. Left lane southbound frontage road closure from Evans Road to Encino Rio for concrete paving.
- Tuesday, September 8 until Friday, September 11. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from the Donella Drive entrance ramp to Redland Road for bridge work.
- Tuesday, September 8 until Friday, September 11. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from the Sonterra Boulevard entrance ramp to the Donella Drive exit ramp for bridge work.
- Saturday, September 12 until Monday, September 14. Weekend overnight closure 2 a.m. until 5 a.m. Northbound frontage road closure from the north- to southbound turnaround at Encino Rio for concrete paving. DETOUR: Use the turnaround at Evans Road. Closure will not happen concurrently with other turnaround closures in the same direction.
- Saturday, September 12 until Monday, September 14. Weekend overnight closure 2 a.m. until 5 a.m. Southbound frontage road closure from the south- to northbound turnaround at Encino Rio for concrete paving. DETOUR: Use the turnaround at Redland Road. Closure will not happen concurrently with other turnaround closures in the same direction.
- Saturday, September 12 until Monday, September 14. Weekend overnight closure 2 a.m. until 5 a.m. Left lane southbound frontage road closure from Evans Road to Encino Rio for concrete paving.
- Wednesday, September 9 until Friday, September 11. 9 p.m. to 5 a.m. Alternating lane closures from north of Cibolo Creek to south of Marshall Rd. for concrete barrier relocation.
- Wednesday, September 9 until Thursday, September 10. 9 p.m. to 5 a.m. Single southbound lane closure from US 281 and Marshall Rd. to 1,000 feet south of US 281 and Marshall Rd. for barrier placement.
- Thursday, September 10 until Saturday, September 12. 9 p.m. to 5 a.m. Single southbound lane closure from Cibolo Creek bridge to 1,000 feet north of Cibolo Creek bridge for barrier movement.
- Friday, September 11 until Monday, September 14. Continuous closure 9 p.m. to 5 a.m. Full street closure from US 281 and Mountain Lodge to 1,000 feet west of US 281 and Mountain Lodge for pavement markings and curb ramps.
- Friday, September 11 until Monday, September 14. 9 p.m. to 5 a.m. Full closure of Bulverde Road to the west US 281 for traffic switch.
Encino Rio – North Central San Antonio
- Saturday, September 12 until Monday, September 14. Weekend overnight closure 2 a.m. until 5 a.m. Westbound crossing closure of the west- to southbound left turn lane for concrete paving. DETOUR: Use the turnaround at Evans Road.
I-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County
- Tuesday, September 8. 9 a.m. to 4 p.m. Single lane closure on westbound frontage road from Huebner Oaks to 700 feet west of Huebner Oaks for utility work.
- Tuesday, September 8 until Friday, September 11. Nightly 8 p.m. to 6 a.m. Full closure of eastbound mainlanes from Dominion Dr. to Camp Bullis Rd. for asphalt work.
- Friday, September 11 until Saturday, September 12. 10 p.m. to 8 a.m. Full closure of eastbound mainlanes from Camp Bullis Rd. La Cantera Parkway for asphalt work.
- Current until mid-September: Westbound I-10 entrance ramp from Ackerman Road closed. DETOURS:
- Southbound Ackerman traffic can travel south under the I-10
overpass, use the eastbound frontage road to Foster Road, turn left on Foster,
and take the westbound frontage road to the westbound entrance ramp just west
of Foster.
- Northbound Ackerman traffic can use the eastbound frontage
road to Foster Road, turn left on Foster, and take the westbound frontage road
to the westbound entrance ramp just west of Foster.
- Current until further notice. Graytown Road bridge at I-10. DETOURS: Graytown Road traffic will use the frontage roads and the Pfeil Road underpass or Loop 1604 turnaround to cross I-10.
- Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
- Current until further notice. Eastbound entrance ramp from Foster Road. DETOUR: Take next entrance ramp east of Woodlake Parkway.
I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County
- Until further notice, the southbound entrance ramp at Schwab Rd. is closed.
- Current until Saturday, September 5. 9 a.m. to 5:30 p.m. Alternating frontage road lane closures, in both directions, from Huebertus Rd. to Schwab Rd. for landscaping and soil work.
- Monday, September 7 until Friday, September 11. 9 p.m. to 5 a.m. Southbound to northbound turnaround closed from Business 35 bridge to FM 306 bridge for soil nail work.
- Tuesday, September 8 until Wednesday, September 9. 9 a.m. to 3p.m. Single lane closure on northbound frontage road from Business 35 bridge to FM 306 for restriping.
- Tuesday, September 8 until Saturday, September 12. 9 a.m. to 5:30 p.m. Single lane closure on northbound frontage road from Hubertus Rd. to Schwab Rd. for concrete work.
- Tuesday, September 8 until Saturday, September 12. 9 a.m. to 5:30 p.m. Single lane closure on southbound frontage road from Schwab Rd. to Hubertus Rd. for concrete work.
- Tuesday, September 8 until Saturday, September 12. 9 a.m. to 5:30 p.m. Single lane closure on northbound frontage road for improvements to sidewalks, ramps and driveways.
- Wednesday, September 9 until Thursday, September 10. 9 p.m. to 6 a.m. Double northbound mainlane closure from Hubertus Rd. to Schwab Rd. for barrier removal.
- Thursday, September 10 until Friday, September 11. 9 p.m. to 6 a.m. Double southbound mainlane closure from Schwab Rd. to Hubertus Rd. for barrier removal.
- I-410 – West San Antonio
- Current until Monday, September 14. 9 a.m. to 3 p.m. Alternating frontage road closures, in both directions, from Marbach Rd. to Ingram Rd. for work to retaining wall work.
- Current until Wednesday, September 9. Nightly 8 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from Marbach Rd. to Culebra Rd. for barrier installation.
- Current until Monday September 14. Daily 7:00 a.m. to 5:00 p.m. Full closure of southbound frontage road from N.W. Crossroads to Richland Hills for pouring concrete.
- Current until Monday, September 14. Daily 9:00 a.m. to 3:00 p.m. Alternating lane closures, in both directions, from Marbach Rd. to Culebra Rd. for bridge work.
- Current until Monday, September 14. Nightly 8:00 p.m. to 5:00 a.m. Alternating frontage road lane closures, in both directions, from Marbach Rd. to Ingram Rd. for retaining wall work.
- Current until Monday, September 14. Nightly 8 p.m. to 5 a.m. . Alternating frontage road lane closures, in both directions, from Marbach Rd. to Ingram Rd. for retaining wall work.
- Current until Monday, August 31. Nightly 8 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from SH-151 to US-90 for painting operations.
- Current until Monday, August 31. Daily 9 a.m. to 3 p.m. Alternating frontage road lane closures, in both directions, from SH-151 to US-90 for concrete placement.
- Tuesday, September 8 until Friday, September 11. 8 p.m. to 5 a.m. Double left lane closure, in both directions, from Marbach Rd. to Military Dr. for setting of concrete beams
US 90 – West San Antonio
- Current until Monday,
August 31. Daily 9 a.m. to 3 p.m. Alternating lanes, in both directions, from
Loop 410 to Hunt Lane for concrete placement.
- Current until Monday,
August 31. Nightly 8 p.m. to 5 a.m. Alternating lanes, in both directions from
Loop 410 to Hunt Lane for painting operations.
- Saturday, August 22 until Friday, August 28. 9 a.m. to 3 p.m. Alternating frontage road lane closures, in both directions, from Loop 410 to Hunt Lane for sidewalk improvements.
- Current until Monday,
August 31. Daily 9 a.m. to 3 p.m. Eastbound exit ramp to Enrique M. Barrera
Parkway closed for guardrail improvements.
- Current until Friday, September 18. Daily 9 a.m. to 3 p.m. Single frontage road lane closures, in both directions, from W. Military Dr. to S.W. 36th St. for guardrail improvements.
- Current until Friday, September 18. 7:30 p.m. to 6:00 a.m. Single lane closures on frontage roads, in both directions, from W. Military Dr. to S.W. 36th St. for pavement improvements.
SH 151 – West San Antonio
- Current until Monday, September 14. Daily 9:00 a.m. to 3:00 p.m. Alternating frontage road lane closures, in both directions, from Loop 410 to Ingram Rd. for bent work.
- Current until Monday, September 14. Daily 9:00 a.m. to 3:00 p.m. Alternating mainlane closures, in both directions, from Loop 410 to Ingram Rd. for bent work.
- Current until Wednesday, September 9. Nightly 8:00 p.m. to 5:00 a.m. Full closure of eastbound frontage road from Loop 410 to Ingram Rd. for bridge rail demolition.
- Current until Monday, September 14. Nightly 8:00 p.m. to 5:00 a.m. Alternating frontage road lane closures, in both directions, from Loop 410 to Ingram Rd. for bent work.
- Monday, August 24 until Monday, August 31. 8 p.m. to 5 a.m. Full closure of eastbound frontage road from Loop 410 south to Loop 410 north for bridge rail demolition.
SH 16 – Bandera Road
- Tuesday, September 8 until Friday, September 11. 9:30 a.m. to 3:30 p.m. Single lane closures, in both directions, from Bresnahan St. to Braun Rd. for utility work.
PA 1502 – Wurzbach Parkway
- Tuesday, September 8 until Friday, September 11. 9 p.m. to 5 a.m. Single westbound lane closure from east of N.W. Military Dr. to west of Lockhill Selma Rd. for barrier installation.
- Thursday, September 10 until Friday, September 11. 9 p.m. to 5 a.m. Single eastbound lane closure from west of Lockhill Selma Rd. to east of N.W. Military Dr. for barrier installation.
- Saturday, September 12. 7 a.m. to 4 p.m. Single eastbound lane closure from west of Lockhill Selma Rd. to east of N.W. Military Dr. for barrier installation.
FM 1976 – Walzem Road/Gibbs Sprawl Road
- Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes between Woodlake Parkway and Gibbs Sprawl Road for barrier/pavement work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
- Current until further notice. Full-day closure. Southbound lane between Toepperwein Road and Walzem Road for barrier setting work and road rehab work.
FM 78 – Bexar County
- Tuesday, September 8 until Friday, September 11. 9:30 a.m. to 3:30 p.m. Single lane closures, in both directions, from Woodlake Parkway to Firestone Parkway for utility work.
SH 46 – Boerne/Kendall County
- Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
RM/FM 1376 – Kendall County
- Current until Saturday, September 12. Daily 7 a.m. to 7 p.m. Single lane closures, in both directions, from N. School St. to 0.5 miles past Wasp Creek Rd. for culvert work and roadway construction.