As part of the ongoing IH-10 frontage road construction the contractor is progressing into the next stage of construction which will open the new Eastbound Exit 540 to SH 46/Bandera Rd. and the new Eastbound Frontage Road approaching SH 46.
Exiting traffic will be able to turn in either direction onto SH 46. There will not be any additional changes to the intersection traffic configuration at this time.
Work is scheduled to start on Monday December 20, 2021 at 9:00 AM, weather
permitting.
This will allow TxDOT’s contractor to shift traffic onto the portion of the new bridge and new pavement that has been built so that the old SH 46 bridge can be demolished and the remainder of the new 6 lane bridge and approach work can be completed. Estimated completion Spring 2022.