Friday, August 26

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North West San Antonio/Bexar County

  • Sunday, August 28 until Friday, September 9. Weeknights 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Bandera Road (SH 16) to IH-10 for portable concrete traffic barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding Weekends.
  • Sunday, August 28 until Friday, September 9. Weeknights 9 p.m. until 5 a.m. Alternating westbound mainlane closure from IH-10 to Bandera Road (SH 16) for portable concrete barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding Weekends.
  • Sunday, August 28 until Friday, September 9. Weeknights 9 p.m. until 5 a.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for portable concrete traffic barrier installation. Nightly alternating frontage road closures. One lane to Sunday, August 28 until Friday, September 9. Weeknights 9 p.m. until 5 a.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for portable concrete traffic barrier installation. Nightly alternating frontage road closures. One lane to remain open at all times. Excluding Weekends.
  • Sunday, August 28 until Friday, September 9. Weeknights 9 p.m. until 5 a.m. Eastbound mainlane full closure from Babcock Road to La Cantera Parkway for bridge construction – rail demo. Only one full mainlane closure to occur per direction, per night.
  • Sunday, August 28 until Friday, September 9. Weeknights 9 p.m. until 5 a.m. Westbound mainlane full closure from La Cantera Parkway to Babcock Road for bridge construction – rail demo. Excluding Weekends. Only one full mainlane closure to occur per direction, per night.
  • Sunday, August 28 until Friday, September 9. Weeknights 9 p.m. until 5 a.m. Full intersection closure at Loop 1604 and Bandera Road (SH 16) in both directions, including turnarounds, for bridge construction – formwork removal.
  • Sunday, August 28 until Friday, September 9. Weeknights 9 p.m. until 5 a.m. Full intersection closure at Loop 1604 and La Cantera Parkway/John Peace Boulevard in both directions, including turnarounds, for bridge construction – rail demo.
  • Thursday, September 1 until Thursday, September 8. Weeknights 9 p.m. until 5 a.m. Westbound mainlaine exit ramp full closure to the westbound frontage road approaching La Cantera Parkway to relocate barriers.
  • Thursday, September 8 until Thursday, September 15. Weeknights 9 p.m. until 5 a.m. Eastbound mainlane entrance ramp full closures from La Cantera Parkway to relocate barriers.
  • Thursday, September 8 until Thursday, September 15. Weeknights 9 p.m. until 5 a.m. Eastbound mainlane exit ramp full closure to Vance Jackson Road to relocate barriers.
  • Monday, August 29 until Monday, September 12. Weekdays 9 a.m. until 3 p.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for sidewalk construction. Daily alternating frontage road closures. One lane to remain open at all times. Excluding Weekends.
  • Monday, August 29 until Monday, September 12. Weekdays 9 a.m. until 3 p.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for sidewalk construction. Daily alternating frontage road closures. One lane to remain open at all times. Excluding Weekends.
  • Monday, August 29 until Monday, September 12. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Alternating. Only one turnaround to be closed at a time. Excluding Weekends.
  • Monday, August 29 until Monday, September 12. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Alternating. Only one turnaround to be closed at a time. Excluding Weekends.
  • Monday, August 29 until Monday, September 12. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Alternating. Only one turnaround to be closed at a time. Excluding Weekends.
  • Monday, August 29 until Monday, September 12. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Alternating. Only one turnaround to be closed at a time. Excluding Weekends.
  • Monday, August 29 until Monday, September 12. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and La Cantera Parkway for bridge widening. Alternating. Only one turnaround to be closed at a time. Excluding Weekends.
  • Monday, August 29 until Monday, September 12. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and La Cantera Parkway for bridge widening. Alternating. Only one turnaround to be closed at a time. Excluding Weekends. 

Loop 1604 – North Central San Antonio/Bexar County

  • Sunday, August 28 until Friday, September 2. Nightly 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Tradesman Road to US 281 exit ramp for barrier setting and striping.
  • Sunday, August 28 until Friday, September 2. Nightly 9 p.m. until 5 a.m. Alternating westbound mainlane closure from US 281 exit ramp to Tradesman Road for barrier setting and striping.
  • Sunday, August 28 until Friday, September 2. Nightly 9 p.m. until 5 a.m. Alternating eastbound frontage road closure from IH-10 to US 281 for barrier setting and striping.
  • Sunday, August 28 until Friday, September 2. Nightly 9 p.m. until 5 a.m. Alternating westbound frontage road closure from US 281 to IH-10 for barrier setting and striping.
  • Sunday, August 28 until Friday, September 2. Nightly 9 p.m. until 5 a.m. Westbound to eastbound turnaround full closure at Loop 1604 and NW Military Highway for drilling shafts.
  • Sunday, August 28 until Friday, September 2. Nightly 9 p.m. until 5 a.m. Eastbound to westbound turnaround full closure at Loop 1604 and Huebner Road for wall excavation.
  • Monday, August 29 until Friday, September 2. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround full closure at Loop 1604 and Lockhill Selma Road for concrete island demo and temporary traffic signal work.
  • Monday, August 29 until Friday, September 2. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround short term full closure at Loop 1604 and NW Military Highway for concrete placement for drill shafts.
  • Monday, August 29 until Friday, September 2. Weekdays 9 a.m. until 3 p.m. Northbound Lockhill Selma Road right turn lane closure to eastbound Loop 1604 frontage road for traffic signal work.
  • Sunday, August 28 until Sunday, September 4. Weekdays/Weeknights 12 a.m. until 12 a.m. Eastbound to westbound turnaround full closure at Loop 1604 and NW Military Highway for bridge widening construction. 

Loop 1604 – North East San Antonio/Bexar County

  • Monday, August 29 until Wednesday, August 31. 9 p.m. to 5 a.m. Alternating mainlane closures from Palisades Dr. to Pat Booker Rd. for overhead structure work. 

US 281 – North San Antonio/Bexar County

  • Friday, September 9. 8 p.m. to 5 a.m. Full closure of the intersection at Wilderness Oak for bridge work.
  • Tuesday, September 23. 8 p.m. to 5 a.m. Full closure of the intersection at Overlook Parkway for bridge work.  

I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

I-35 – South San Antonio/Bexar County

  • Sunday, August 28. 7 a.m. to 4 p.m. Full closure of the mainlanes, in both directions, at Shepard Rd. for utility work. Traffic will be stopped in 15-minute intervals throughout the day. 

I-10 – East San Antonio/Bexar County

  • Continuing through Tuesday, September 16. I-10 EB exit to Ackerman closed continuously for overpass work. Detour: Eastbound I-10 traffic can exit at Foster Road, turn around at intersection, and use westbound frontage road back to Ackerman. Click here for detour map.
  • Continuing through Friday, September 2. DAYTIME I-10 eastbound and westbound alternating lane closures between FM 1516 and Pfeil Road from 9 a.m. to 3 p.m. for litter cleanup and barrier work.
  • Friday, September 9 9 p.m. to Monday, September 12 5 a.m. Full closure of the westbound mainlanes from Pfeil Rd. to Loop 1604. 

I-410 – East San Antonio

  • Sunday, October 9. 7 p.m. to 4 p.m. Full closure of mainlanes at W.W. White Rd. for utility work. Traffic will be stopped in 15-minute intervals throughout the day.
  • Continuing through Sunday, September 11. DAYTIME Northbound I-410 frontage road left lane closures between East Houston Street and I-10 from 8 a.m. to 5 p.m. for wall work.   
  • Continuing through Sunday, September 11. DAYTIME Southbound I-410 frontage road alternating lane closures between I-10 and East Houston Street from 8 a.m. to 5 p.m. for roadwork.   
  • Friday, August 26 through Monday, August 29, NIGHTTIME Northbound I-410 frontage road closure from East Houston Street on-ramp to eastbound I-10 from 7 p.m. to 7 a.m. Detour: Northbound I-410 traffic to Ackerman Road may take northbound I-410 to I-10 EB exit ramp, turn around at Foster Road, and take I-10 Westbound frontage road to Ackerman.
  • Monday, August 29 through Monday, September 12. DAYTIME intersection closure at  Cornerway Boulevard at I-10 Westbound frontage road from 9 a.m. to 4 p.m. to install manholes. Cornerway detour
  • Use Dietrich Road as detour to access Cornerway Blvd.
  • Sunday, August 28 through Wednesday, September 7. NIGHTTIME Northbound I-410 exit to eastbound I-10 closure from 8 p.m. to 5 a.m. for barrier repair. Click here for detour map. 

I-410 – South San Antonio

  • Tuesday, August 30 until Thursday, September 1. 9 a.m. to 3 p.m. Single mainlane closure, in both directions, from Old Pearsall Rd. to I-37 for utility work. 

PA 1502 – Wurzbach Parkway

  • Current until Wednesday, August 31. 9 a.m. to 3 p.m. Various lane closures, in both directions, from Blanco Rd. to Wetmore Rd. for road work.
  • Current until Friday, September 2. 9 a.m. to 4 p.m. Right turn lane closures, in all directions, at N.W. Military Highway intersection for median work. 

FM 1535 – N.W. Military Highway

  • Current until Friday, September 2. 9 a.m. to 4 p.m. Single lane closure, in both directions, at the Wurzbach Parkway intersection for median work. 

US 90 – West San Antonio/Bexar County

  • Tuesday, August 30 until Thursday, September 1. 9 a.m. to 3 p.m. Single left mainlane closures, in both directions, from Nogalitos to Callaghan Rd. for utility work. 

US 87 – Rigsby Road

  • Current until Monday, September 19. 9 a.m. to 4 p.m. Alternating lane closures, in both directions, from Roland Ave. to Loop 410 for striping operations. 

SH 16 – Bexar County

  • Monday, August 29 until Friday, September 2. Nightly 9 p.m. to 5 a.m. Alternating lane closures, in both directions, from Loop 1604 to Circle A Trail for striping operations. 

US 181 – Bexar County

  • Current until Monday, September 19. 9 p.m. to 5 a.m. Alternating lane closures, in both directions, from Wilson County Line to I-37 for bridge work and striping operations. 

FM 725 – Comal County

  • Current until Thursday, September 1. Full closure of the northbound to southbound turnaround at I-35 for operational improvements. 

I-10 – Kendall County

  • Sunday, August 28 until Friday, October 28. 9 p.m. to 5 a.m. Single mainlane closures, in both directions, from US 87 to FM 473 for pavement operations.  
  • Thursday, September 1. 9 a.m. to 3 p.m. Single westbound mainlane closure from Scenic Loop Rd. to Ramp 542 for utility work.

Friday, August 19

UPCOMING SCHEUDLED CONSTRUCTION CLOSURES

Loop 1604 – North West San Antonio/Bexar County

Loop 1604 – North Central San Antonio/Bexar County

  • Sunday, August 21 until Friday, August 26. Nightly 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Tradesman Road to US 281 exit ramp for barrier setting and striping.
  • Sunday, August 21 until Friday, August 26. Nightly 9 p.m. until 5 a.m. Alternating westbound mainlane closure from US 281 exit ramp to Tradesman Road for barrier setting and striping.
  • Sunday, August 21 until Friday, August 26. Nightly 9 p.m. until 5 a.m. Alternating eastbound frontage road closure from IH-10 to US 281 for barrier setting and striping.
  • Sunday, August 21 until Friday, August 26. Nightly 9 p.m. until 5 a.m. Alternating westbound frontage road closure from US 281 to IH-10 for barrier setting and striping.
  • Sunday, August 21 until Friday, August 26. Nightly 9 p.m. until 5 a.m. Westbound to eastbound turnaround full closure at Loop 1604 and NW Military Highway for drilling shafts.
  • Monday, August 22 until Friday, August 26. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround full closure at Loop 1604 and Lockhill Selma Road for concrete island demo and temporary traffic signal work.
  • Monday, August 22 until Friday, August 26. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround short term full closure at Loop 1604 and NW Military Highway for concrete placement for drill shafts.
  • Monday, August 22 until Friday, August 26. Weekdays 9 a.m. until 3 p.m. Northbound Lockhill Selma Road right turn lane closure to eastbound Loop 1604 frontage road for traffic signal work.
  • Sunday, August 21 until Sunday, August 28. Weekdays/Weeknights 12 a.m. until 12 a.m. Eastbound to westbound turnaround full closure at Loop 1604 and NW Military Highway for bridge widening construction. 

Loop 1604 – North East San Antonio/Bexar County

  • Sunday, August 21 until Tuesday, August 23. 9 p.m. to 5 a.m. Single northbound mainlane closure from Palisades Dr. to Pat Booker Rd. for roadwork.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Westbound Loop 1604 frontage road exit ramp closure from Gateway Boulevard to Lookout Road for barrier work. Traffic must use Lookout Road exit.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Westbound Lookout Road exit ramp closure between Gateway Boulevard and Lookout Road for barrier work. Traffic must use the Nacogdoches Road turnaround to access Lookout Road.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m.  Alternating lane closures on westbound Loop 1604 bypass from Lookout Road to Union Pacific Railroad for barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Westbound Loop 1604 exit ramp closure and left lane ramp closure from Union Pacific Railroad to Nacogdoches Road for barrier work. Traffic must continue westbound on Loop 1604 and use the Green Mountain Road exit to access Nacogdoches Road.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound Loop 1604 frontage road between Gateway Boulevard and Lookout Road for barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound Loop 1604 frontage road between Union Pacific Railroad and Nacogdoches for barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Westbound Loop 1604 entrance ramp closure from Union Pacific Railroad to Nacogdoches Road for barrier work. Traffic must continue westbound on frontage road and use the next entrance ramp to access Loop 1604.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Full lane closure on Loop 1604 eastbound-to-westbound turnaround between Nacogdoches Road and Union Pacific Railroad for barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Alternating lane closures on Loop 1604 frontage road westbound-to-eastbound turnaround between Lookout Road and Union Pacific Railroad for barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound Loop 1604 between Nacogdoches Road and I-35 for striping and barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound Loop 1604 between I-35 and Nacogdoches Road for barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Lookout Road exit ramp closure on eastbound Loop 1604 between Nacogdoches Road and Union Pacific Railroad for striping and barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Alternating lane closures on Loop 1604 entrance ramp and Loop 1604 frontage road bypass from Nacogdoches Road to Union Pacific Railroad for striping and barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound frontage road bypass of Loop 1604 from Union Pacific Railroad to Lookout Road for barrier and striping work. 

US 281 – North San Antonio/Bexar County

  • Friday, August 26. 8 p.m. to 5 a.m. Full closure of the intersection at Overlook Parkway for bridge work.
  • Friday, September 9. 8 p.m. to 5 a.m. Full closure of the intersection at Wilderness Oak for bridge work.
  • Tuesday, September 23. 8 p.m. to 5 a.m. Full closure of the intersection at Overlook Parkway for bridge work. 

I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

  • Sunday, August 21 until Friday, August 26. 9:00 p.m. to 5:00 a.m. Left lane closure on northbound frontage road of I-35 from Agora Parkway to Pasatiempo for geotechnical and drilling work.
  • Sunday, August 21 until Friday, August 26. 9:00 p.m. to 5:00 a.m. FM 1518 exit ramp (exit 174A) closure on northbound I-35 and left lane closure on northbound frontage road of I-35 from exit 174A to Pasatiempo for geotechnical and drilling work. Traffic must exit Olympia Parkway (exit 173).
  • Sunday, August 21 until Friday, August 26. 9:00 p.m. to 5:00 a.m. Right lane closure on northbound I-35 mainlane from Olympia Parkway to Pasatiempo for geotechnical and drilling work.
  • Sunday, August 21 until Friday, August 26. 9:00 p.m. to 5:00 a.m. Right lane closure on northbound I-35, Pat Booker Road exit ramp closure, and left lane closure on northbound frontage road of I-35 from Judson Road to Sandpiper Drive for geotechnical and drilling work. All traffic must exit Toepperwein Road (exit 170B).
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) and entrance ramp on southbound I-35 between Judson Road and O’Connor Road for striping and barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35, left lane closure on southbound frontage road and closure of southbound I-35 entrance ramp from Pat Booker Road to Ferrell Road for barrier work. Traffic must continue straight to Judson Road entrance ramp.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35, left lane closure on southbound frontage road and entrance ramp closure of I-35 between Judson Road and O’Connor Road for barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35 and exit ramp closure between Toepperwein Road and Judson Road for barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Left lane closure on southbound I-35 frontage road and Toepperwein Road and exit ramp closure to Judson Road for barrier work.
  • Monday, August 22 until Friday, August 26. 9:00 p.m. to 5:00 p.m. Right shoulder closure on northbound I-35 frontage road from Pat Booker Road to Loop 1604 for construction exit/entrance work.
  • Tuesday, August 23 until Friday, August 26. 9:00 p.m. to 5:00 a.m. Right lane closure of northbound I-35 frontage road from O’Connor Road to Judson Road for subsurface utility work.
  • Tuesday, August 23 until Friday, August 26. 9:00 p.m. to 5:00 p.m. Left lane closure of northbound I-35 frontage road from Chelsea Place to Schertz Parkway for subsurface utility work.
  • Wednesday, August 24 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Right lane closure on eastbound and westbound of Pat Booker Road between I-35 frontage roads for riprap removal work. 

I-10 – East San Antonio/Bexar County

  • Continuing through Tuesday, September 16. I-10 EB exit to Ackerman closed continuously for overpass work. Detour: Eastbound I-10 traffic can exit at Foster Road, turnaround at intersection, and use westbound frontage road back to Ackerman.
  • Sunday, August 21 until Monday, August 22. 9 p.m. to 5 a.m. Full closure of the westbound mainlanes at FM 1538 for bridge work.
  • Sunday, August 21 until Friday, August 26. 8 p.m. to 6 a.m. Single eastbound mainlane closure from Zuehl Rd. to FM 465 for barrier work.
  • Monday, August 22 until Tuesday, August 23. 9 p.m. to 5 a.m. Full closure of the westbound mainlanes at FM 2538 to FM 1538 for bridge work.
  • Monday, August 22. 9 a.m. to 4 p.m. Eastbound ramp closures at Zuehl Rd. for barrier work.
  • Tuesday, August 23 until Wednesday, August 24. 9 p.m. to 5 a.m. Full closure of the eastbound mainlanes at FM 1538 for bridge work.
  • Wednesday, August 24 until Thursday, August 25. 9 p.m. to 5 a.m. Full closure of the westbound mainlanes at FM 2538 for bridge work.
  • Thursday, August 25 until Friday, August 26. 9 p.m. to 5 a.m. Full closure of the eastbound mainlanes at FM 2538 for bridge work.
  • Monday, August 22 until Tuesday, August 23. 9 p.m. to 5 a.m. Full closure of the westbound mainlanes from FM 2538 to FM 1518 for bridge work.
  • Friday, September 9 9 p.m. to Monday, September 12 5 a.m. Full closure of the westbound mainlanes from Pfeil Rd. to Loop 1604. 

I-410 – North East San Antonio

  • Monday, August 22 until Friday, August 26. 9:00 p.m. to 5:00 p.m. Alternating lane closures on westbound Loop 410 frontage road from Perrin Creek to Perrin Beitel Road for construction exit/entrance work. 

I-410 – East San Antonio

  • Saturday, August 20. Northbound I-410 exit to eastbound I-10 closure from 8 p.m. to 5 p.m. for barrier repair. DETOURS:
  • Northbound I-410 traffic to eastbound I-10 will exit at East Houston Street, take the northbound I-410 frontage road, and enter after Ackerman Road.
  • Northbound I-410 traffic to westbound I-10 will exit at East Houston Street, take the northbound I-410 frontage road, turn around at Ackerman Road, and enter after Ackerman.
  • Saturday, August 20 through Sunday, August 28. DAYTIME Northbound I-410 frontage road left lane closures between East Houston Street and I-10 from 8 a.m. to 5 p.m. for wall work.   
  • Saturday, August 20 through Sunday, August 28. DAYTIME Southbound I-410 frontage road alternating lane closures between I-10 and East Houston Street from 8 a.m. to 5 p.m. for roadwork.   
  • Monday, August 22 through Friday, August 26. DAYTIME I-10 eastbound and westbound rolling lane closures between 1516 and Pfeil Road from 9 a.m. to 3 p.m. for litter cleanup and barrier work.

I-410 – West San Antonio

  • Current until Saturday, August 20. 8 p.m. to 11 a.m. Full closure of the northbound frontage road from Culebra Rd. to Ingram Rd. for utility work.
  • Current until Saturday, August 20. 9 a.m. to 3 p.m. Alternating lane closures on the frontage roads, in both directions, from Marbach Rd. to Ingram Rd. for road work.
  • Current until Friday, August 26. 8 p.m. to 5 a.m. Full closure of the northbound frontage road from Marbach Rd. to SH 151 for barrier work.
  • Current until Saturday, August 20. 7 a.m. to 5 p.m. Full closure of the northbound entrance ramp from Marbach Rd. for barrier work.
  • Current until Monday, August 22. 8 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from Marbach Rd. to Ingram Rd. for road work.
  • Current until Sunday, August 27. 9 a.m. to 3 p.m. Single northbound mainlane closure from Marbach Rd. to SH 151 for barrier removal.
  • Current until Sunday, August 27. 9 a.m. to 3 p.m. Single lane closure on the northbound frontage road from Marbach Rd. to SH 151 for concrete work. 

SH 151 – Bexar County

  • Current until Sunday, August 20. 9 a.m. to 3 p.m. Alternating lane closures on the frontage roads, in both directions, from Marbach Rd. to Ingram Rd. for road work.
  • Sunday, August 21. 7 a.m. to 4 p.m. Full closure of the mainlanes, in both directions, at Wiseman Blvd. for utility work. Traffic will be stopped in 15-minute intervals throughout the day. 

PA 1502 – Wurzbach Parkway

  • Current until Wednesday, August 31. 9 a.m. to 3 p.m. Various lane closures, in both directions, from Blanco Rd. to Wetmore Rd. for road work.
  • Monday, August 22 until Friday, September 2. 9 a.m. to 4 p.m. Right turn lane closures, in all directions, at N.W. Military Highway intersection for median work. 

FM 1535 – N.W. Military Highway

  • Monday, August 22 until Friday, September 2. 9 a.m. to 4 p.m. Single lane closure, in both directions, at the Wurzbach Parkway intersection for median work. 

SH 181 – Bexar County

  • Current until Friday, August 26. 9 a.m. to 4 p.m. Alternating lane closures, in both directions, from I-37 to Wilson County Line for road repairs. 

US 87 – Rigsby Road

  • Friday, August 19 until Monday, September 19. 9 a.m. to 4 p.m. Alternating lane closures, in both directions, from Roland Ave. to Loop 410 for striping operations. 

SH 16 – Bexar County

  • Monday, August 29 until Friday, September 2. Nightly 9 p.m. to 5 a.m. Alternating lane closures, in both directions, from Loop 1604 to Circle A Trail for striping operations. 

US 181 – Bexar County

  • Friday, August 19 until Monday, September 19. 9 p.m. to 5 a.m. Alternating lane closures, in both directions, from Wilson County Line to I-37 for bridge work and striping operations. 

FM 725 – Comal County

  • Current until Thursday, September 1. Full closure of the northbound to southbound turnaround at I-35 for operational improvements. 

I-10 – Kendall County

  • Friday, August 19 – 9 p.m. until Monday, August 22 – 5 a.m. Full closure of the mainlanes, in both directions, from SH 46 to US 87 for traffic switch. Traffic will be directed to frontage roads.

I-10 CLOSED AT SH 46 IN KENDALL COUNTY THIS WEEKEND

 


As part of the ongoing IH-10 frontage road construction the contractor is progressing into the next stage of construction which will require the realigning the I-10 mainlanes under SH-46 (Bandera Rd.) bridge.

The last stage of construction for the new SH-46 bridge will necessitate transitioning the I-10 mainlane traffic from their current location to the segment that is currently a work area closed to traffic.  The mainlane transition will place the eastbound mainlanes back in their natural configuration and the westbound mainlanes will be south of their existing orientation. 

The transition is necessary to construct the second half of the SH-46 bridge while maintaining a safe passage for motorists and all construction personnel.

Work is scheduled to start on Friday AUGUST 19, 2022 at 9:00 pm and is expected to complete by 5:00 am on Monday AUGUST 22, 2022, weather permitting.

The westbound mainlanes will be reduced to one-lane then forced to use Exit 540 (SH-46/Bandera Rd). Westbound frontage road traffic will continue through the SH-46 intersection then back onto the mainlanes at the next available entrance ramp located near Fredricks Creek. Off-duty uniformed officers will control the traffic movement at the SH 46 intersection.

The eastbound mainlanes will be reduced to one-lane then forced to use Exit 540 (SH-46/Bandera Rd).  Eastbound frontage road traffic will continue through the SH 46 intersection than back onto the mainlanes at the next available entrance ramp located ¼ west of the US 87 interchange. Off-duty uniformed officers will control the traffic movement at the SH 46 intersection.

For safety reasons, the active bridge on SH 46 at IH 10 will be closed requiring all traffic to turn right onto the frontage roads.

  • Westbound SH-46 traffic will be detoured to westbound I-10, to the Johns Road intersection, and back to Exit 540 SH-46 (see westbound detour route exhibit).
  • Eastbound SH-46 traffic will be detoured the eastbound frontage road, onto the eastbound I-10 mainlanes, to Exit 543 Scenic Loop, where traffic will use the turnaround to reach the westbound frontage road into Boerne/Main St. (see eastbound detour route exhibit).

Friday, August 12

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North West San Antonio/Bexar County

  • Sunday, August 14 until Friday, August 26. Weeknights 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Bandera Road (SH 16) to IH-10 for barrier setting.
  • Sunday, August 14 until Friday, August 26Weeknights 9 p.m. until 5 a.m. Alternating westbound mainlane closure from IH-10 to Bandera Road (SH 16) for barrier setting.
  • Sunday, August 14 until Friday, August 26. Weeknights 9 p.m. until 5 a.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for barrier setting.
  • Sunday, August 14 until Friday, August 26. Weeknights 9 p.m. until 5 a.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for barrier setting.
  • Sunday, August 14 until Friday, August 26. Weeknights 9 p.m. until 5 a.m. Eastbound mainlane full closure from Babcock Road to La Cantera Parkway for bridge construction.
  • Sunday, August 14 until Friday, August 26. Weeknights 9 p.m. until 5 a.m. Westbound mainlane full closure from La Cantera Parkway to Babcock Road for bridge construction: caps, beams & rail demo.
  • Sunday, August 14 until Friday, August 26. Weeknights 9 p.m. until 5 a.m. Full intersection closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue in both directions, including turnarounds, for bridge construction.
  • Sunday, August 14 until Friday, August 26. Weeknights 9 p.m. until 5 a.m. Full intersection closure at Loop 1604 and La Cantera Parkway/John Peace Boulevard in both directions, including turnarounds, for bridge construction.
  • Monday, August 15 until Monday, August 29. Weekdays 9 a.m. until 3 p.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for barrier setting.
  • Monday, August 15 until Monday, August 29. Weekdays 9 a.m. until 3 p.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for barrier setting.
  • Monday, August 15 until Monday, August 29. Weekdays 9 a.m. until 3 p.m. Eastbound frontage road right outside lane closure from Babcock Road to Chase Hill Boulevard/Brennan Avenue for gas utility work.
  • Monday, August 15 until Monday, August 29. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, August 15 until Monday, August 29. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, August 15 until Monday, August 29. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, August 15 until Monday, August 29. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, August 15 until Monday, August 29. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and La Cantera Parkway for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, August 15 until Monday, August 29. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and La Cantera Parkway for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Sunday, August 14 at 8 p.m. until Monday, August 15 at 5 a.m. Overnight. Westbound mainlane full closure at Bandera Road (SH 16) for bridge construction: bridge deck pour.
  • Sunday, August 14 at 8 p.m. until Monday, August 15 at 5 a.m. Overnight. Full intersection closure at Loop 1604 and Bandera Road (SH 16), both directions, including turnarounds, for bridge construction. 

Loop 1604 – North Central San Antonio/Bexar County

  • Sunday, August 14 until Friday, August 19. Nightly 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Tradesman Road to US 281 exit ramp for barrier setting and striping.
  • Sunday, August 14 until Friday, August 19. Nightly 9 p.m. until 5 a.m. Alternating westbound mainlane closure from US 281 exit ramp to Tradesman Road for barrier setting and striping.
  • Sunday, August 14 until Friday, August 19. Nightly 9 p.m. until 5 a.m. Alternating eastbound frontage road closure from IH-10 to US 281 for barrier setting and striping.
  • Sunday, August 14 until Friday, August 19. Nightly 9 p.m. until 5 a.m. Alternating westbound frontage road closure from US 281 to IH-10 for barrier setting and striping.
  • Sunday, August 14 until Friday, August 19. Nightly 9 p.m. until 5 a.m. Westbound to eastbound turnaround full closure at Loop 1604 and NW Military Highway for drilling shafts.
  • Monday, August 15 until Friday, August 19. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround full closure at Loop 1604 and Lockhill Selma Road for concrete island demo and temporary traffic signal work.
  • Monday, August 15 until Friday, August 19. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround short term full closure at Loop 1604 and NW Military Highway for concrete placement for drill shafts.
  • Monday, August 15 until Friday, August 19. Weekdays 9 a.m. until 3 p.m. Northbound Lockhill Selma Road right turn lane closure to eastbound Loop 1604 frontage road for traffic signal work.
  • Sunday, August 14 until Sunday, August 21. Weekdays/Weeknights 12 a.m. until 12 a.m. Eastbound to westbound turnaround full closure at Loop 1604 and NW Military Highway for bridge widening construction. 

Loop 1604  - North East San Antonio/Bexar County

  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Alternating lane closure on westbound Loop 1604 frontage road from Union Pacific Railroad to Nacogdoches Road for geotechnical and drilling work.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Right shoulder closure on Loop 1604 frontage road eastbound-to-westbound turnaround from Nacogdoches Road to Union Pacific Railroad for geotechnical and drilling work.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Left lane closure on Loop 1604 frontage road westbound-to-eastbound turnaround from Lookout Road to Union Pacific Railroad for geotechnical and drilling work.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Westbound Loop 1604 frontage road exit ramp closure from Gateway Boulevard to Lookout Road for striping and barrier work. Traffic must use Lookout Road exit.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Westbound Lookout Road exit ramp closure between Gateway Boulevard and Lookout Road for striping and barrier work. Traffic must use the Nacogdoches Road turnaround to access Lookout Road.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound Loop 1604 bypass from Lookout Road to Union Pacific Railroad for striping and barrier work.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Westbound Loop 1604 exit ramp closure from Union Pacific Railroad to Nacogdoches Road for striping and barrier work. Traffic must continue westbound on Loop 1604 and use the Green Mountain Road exit to access Nacogdoches Road.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Westbound Loop 1604 entrance ramp closure from Union Pacific Railroad to Nacogdoches Road for striping and barrier work. Traffic must continue westbound on frontage road and use the next entrance ramp to access Loop 1604.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound Loop 1604 frontage road between Gateway Boulevard and Lookout Road for striping and barrier work.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound Loop 1604 frontage road between Union Pacific Railroad and Nacogdoches for striping and barrier work.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Alternating lane closures on Loop 1604 frontage road eastbound-to-westbound turnaround between Nacogdoches Road and Union Pacific Railroad for striping and barrier work.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Alternating lane closures on Loop 1604 frontage road westbound to eastbound turnaround between Lookout Road and Union Pacific Railroad for striping and barrier work.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound Loop 1604 between Nacogdoches Road and I-35 for striping and barrier work.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound Loop 1604 between I-35 and Nacogdoches Road for striping and barrier work. 

I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Northbound-to-southbound turnaround closure at Thousand Oaks Drive and I-35 for geotechnical and drilling work. Traffic will use the traffic signals at Thousand Oaks intersection to access southbound I-35 frontage road.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35 frontage road from Randolph Boulevard to Fratt Road for geotechnical and drilling work.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Left lane closure on northbound I-35 frontage road from Crestway Road to Starlight Terrace for geotechnical and drilling work.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Left lane closure on northbound frontage road of I-35 from Starlight Terrace to Weidner Road for geotechnical drilling work.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m.  Left lane closure on northbound frontage road of I-35 from Agora Parkway to Pasatiempo for geotechnical and drilling work.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. FM 1518 exit ramp (exit 174A) closure on northbound I-35 and left lane closure on northbound frontage road of I-35 from exit 174A to Pasatiempo for geotechnical and drilling work. Traffic must exit Olympia Parkway (exit 173).
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Right shoulder closure on northbound I-35 mainlane from Olympia Parkway to Pasatiempo for geotechnical and drilling work.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m.  Right lane closure on northbound I-35, Pat Booker Road exit ramp closure, and left lane closure on northbound frontage road of I-35 from Judson Road to Sandpiper Drive for geotechnical and drilling work. All traffic must exit Toepperwein Road (exit 170B).
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Left lane closure of northbound I-35 frontage road from Chelsea Place to Schertz Parkway for subsurface utility work.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on southbound I-35 between Thousand Oaks and Walzem Road for striping and barrier work.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Alternating lane closure on southbound I-35 frontage road between Thousand Oaks and Walzem Road for striping and barrier work.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) and entrance ramp on southbound I-35 between Judson Road to O’Connor Road for striping and barrier work. Traffic must continue southbound on frontage road to access I-35.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35, left lane closure on southbound frontage road and closure on southbound I-35 entrance ramp from Pat Booker Road to Ferrell Road for barrier work. Traffic must continue southbound on frontage road to access I-35.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35, left lane closure on southbound frontage road and entrance ramp closure of I-35 between Judson Road and O’Connor Road for barrier work. Traffic must continue on southbound frontage road to access I-35.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35 and exit ramp closure between Toepperwein Road and Judson Road for barrier work. Traffic must continue on southbound I-35 and use the O’Connor Road exit to access Judson Road.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Left lane closure on southbound I-35 frontage road and Toepperwein Road and exit ramp closure to Judson Road for striping and barrier work. Traffic must continue on southbound I-35 and use the O’Connor Road exit to access Judson Road.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Left lane closure of northbound I35 frontage road from Crestway Drive to Starlight Terrace for subsurface utility work.
  • Sunday, August 14 until Saturday, August 20. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35 frontage road from Evans Road to Retama Parkway for subsurface utility work. 

I-10 – East San Antonio/Bexar County

  • Continuing through Saturday, August 20. I-10 EB exit to Ackerman closed continuously for overpass work. Detour: Eastbound I-10 traffic can exit at Foster Road, turnaround at intersection, and use westbound frontage road back to Ackerman.
  • Sunday, August 14 until Monday, August 15. 9 p.m. to 5 a.m. Full closure of the westbound mainlanes from Zuehl Rd. to FM 1518 for striping operations.
  • Monday, August 15 until Friday, August 19. 9 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from Zuehl Rd. to FM 1518 for barrier movement.
  • Monday, August 15 until Friday, August 19. 9 a.m. to 4 p.m. Eastbound exit and entrance ramps for Santa Clara closed for detour work.
  • Monday, August 22 until Tuesday, August 23. 9 p.m. to 5 a.m. Full closure of the westbound mainlanes from FM 2538 to FM 1518 for bridge work.
  • Friday, September 9 9 p.m. to Monday, September 12 5 a.m. Full closure of the westbound mainlanes from Pfeil Rd. to Loop 1604. 

I-410 – East San Antonio

  • Continuing through Wednesday, August 17. NIGHTTIME northbound I-410 exit to eastbound I-10 closure from 9 p.m. to 5 a.m. except for Friday and Saturday night for overpass work. 

I-410 – West San Antonio

  • Monday, August 8 until Saturday, August 20. 9 a.m. to 3 p.m. Alternating lane closures on the frontage roads, in both directions, from Marbach Rd. to Ingram Rd. for road work.
  • Tuesday, August 9 until Friday, August 26. 8 p.m. to 5 a.m. Full closure of the northbound frontage road from Marbach Rd. to SH 151 for barrier work.
  • Saturday, August 13 until Saturday, August 20. 7 a.m. to 5 p.m. Full closure of the northbound entrance ramp from Marbach Rd. for barrier work.
  • Sunday, August 7 until Monday, August 22. 8 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from Marbach Rd. to Ingram Rd. for road work.
  • Monday, August 15 until Sunday, August 27. 9 a.m. to 3 p.m. Single northbound mainlane closure from Marbach Rd. to SH 151 for barrier removal.
  • Monday, August 15 until Sunday, August 27. 9 a.m. to 3 p.m. Single lane closure on the northbound frontage road from Marbach Rd. to SH 151 for concrete work. 

SH 151 – Bexar County

  • Monday, August 8 until Sunday, August 20. 9 a.m. to 3 p.m. Alternating lane closures on the frontage roads, in both directions, from Marbach Rd. to Ingram Rd. for road work. 

PA 1502 – Wurzbach Parkway

  • Monday, August 1 until Wednesday, August 31. 9 a.m. to 3 p.m. Various lane closures, in both directions, from Blanco Rd. to Wetmore Rd. for road work. 

SH 181 – Bexar County

  • Current until Friday, August 26. 9 a.m. to 4 p.m. Alternating lane closures, in both directions, from I-37 to Wilson County Line for road repairs. 

US 87 – Rigsby Road

  • Current until Friday, August 19. 9 a.m. to 4 p.m. Alternating lane closures, in both directions, from Loop 410 to Roland Ave. for manhole repairs. 

SP 122 – Presa Street

  • Friday, August 12 until Saturday, August 13. 7 p.m. to 6 a.m. Alternating lane closures, in both directions, from Loop 13 to Loop 410 for pavement operations. 

Camp Bullis Road – Bexar County

  • Monday, August 15 until Friday, August 19. 9 p.m. to 5 a.m. Full closure of Camp Bullis Rd. east of I-10 to Shady Lane Dr. for utility work. 

FM 725 – Comal County

  • Current until Thursday, September 1. Full closure of the northbound to southbound turnaround at I-35 for operational improvements. 

I-10 – Kendall County

  • Monday, August 15 until Friday, August 19. 9 a.m. to 4 p.m. Single lane closure on the westbound frontage road from Scenic Loop Rd. to US 87 for milling operations.