Friday, August 19

UPCOMING SCHEUDLED CONSTRUCTION CLOSURES

Loop 1604 – North West San Antonio/Bexar County

Loop 1604 – North Central San Antonio/Bexar County

  • Sunday, August 21 until Friday, August 26. Nightly 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Tradesman Road to US 281 exit ramp for barrier setting and striping.
  • Sunday, August 21 until Friday, August 26. Nightly 9 p.m. until 5 a.m. Alternating westbound mainlane closure from US 281 exit ramp to Tradesman Road for barrier setting and striping.
  • Sunday, August 21 until Friday, August 26. Nightly 9 p.m. until 5 a.m. Alternating eastbound frontage road closure from IH-10 to US 281 for barrier setting and striping.
  • Sunday, August 21 until Friday, August 26. Nightly 9 p.m. until 5 a.m. Alternating westbound frontage road closure from US 281 to IH-10 for barrier setting and striping.
  • Sunday, August 21 until Friday, August 26. Nightly 9 p.m. until 5 a.m. Westbound to eastbound turnaround full closure at Loop 1604 and NW Military Highway for drilling shafts.
  • Monday, August 22 until Friday, August 26. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround full closure at Loop 1604 and Lockhill Selma Road for concrete island demo and temporary traffic signal work.
  • Monday, August 22 until Friday, August 26. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround short term full closure at Loop 1604 and NW Military Highway for concrete placement for drill shafts.
  • Monday, August 22 until Friday, August 26. Weekdays 9 a.m. until 3 p.m. Northbound Lockhill Selma Road right turn lane closure to eastbound Loop 1604 frontage road for traffic signal work.
  • Sunday, August 21 until Sunday, August 28. Weekdays/Weeknights 12 a.m. until 12 a.m. Eastbound to westbound turnaround full closure at Loop 1604 and NW Military Highway for bridge widening construction. 

Loop 1604 – North East San Antonio/Bexar County

  • Sunday, August 21 until Tuesday, August 23. 9 p.m. to 5 a.m. Single northbound mainlane closure from Palisades Dr. to Pat Booker Rd. for roadwork.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Westbound Loop 1604 frontage road exit ramp closure from Gateway Boulevard to Lookout Road for barrier work. Traffic must use Lookout Road exit.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Westbound Lookout Road exit ramp closure between Gateway Boulevard and Lookout Road for barrier work. Traffic must use the Nacogdoches Road turnaround to access Lookout Road.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m.  Alternating lane closures on westbound Loop 1604 bypass from Lookout Road to Union Pacific Railroad for barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Westbound Loop 1604 exit ramp closure and left lane ramp closure from Union Pacific Railroad to Nacogdoches Road for barrier work. Traffic must continue westbound on Loop 1604 and use the Green Mountain Road exit to access Nacogdoches Road.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound Loop 1604 frontage road between Gateway Boulevard and Lookout Road for barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound Loop 1604 frontage road between Union Pacific Railroad and Nacogdoches for barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Westbound Loop 1604 entrance ramp closure from Union Pacific Railroad to Nacogdoches Road for barrier work. Traffic must continue westbound on frontage road and use the next entrance ramp to access Loop 1604.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Full lane closure on Loop 1604 eastbound-to-westbound turnaround between Nacogdoches Road and Union Pacific Railroad for barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Alternating lane closures on Loop 1604 frontage road westbound-to-eastbound turnaround between Lookout Road and Union Pacific Railroad for barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound Loop 1604 between Nacogdoches Road and I-35 for striping and barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound Loop 1604 between I-35 and Nacogdoches Road for barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Lookout Road exit ramp closure on eastbound Loop 1604 between Nacogdoches Road and Union Pacific Railroad for striping and barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Alternating lane closures on Loop 1604 entrance ramp and Loop 1604 frontage road bypass from Nacogdoches Road to Union Pacific Railroad for striping and barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound frontage road bypass of Loop 1604 from Union Pacific Railroad to Lookout Road for barrier and striping work. 

US 281 – North San Antonio/Bexar County

  • Friday, August 26. 8 p.m. to 5 a.m. Full closure of the intersection at Overlook Parkway for bridge work.
  • Friday, September 9. 8 p.m. to 5 a.m. Full closure of the intersection at Wilderness Oak for bridge work.
  • Tuesday, September 23. 8 p.m. to 5 a.m. Full closure of the intersection at Overlook Parkway for bridge work. 

I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

  • Sunday, August 21 until Friday, August 26. 9:00 p.m. to 5:00 a.m. Left lane closure on northbound frontage road of I-35 from Agora Parkway to Pasatiempo for geotechnical and drilling work.
  • Sunday, August 21 until Friday, August 26. 9:00 p.m. to 5:00 a.m. FM 1518 exit ramp (exit 174A) closure on northbound I-35 and left lane closure on northbound frontage road of I-35 from exit 174A to Pasatiempo for geotechnical and drilling work. Traffic must exit Olympia Parkway (exit 173).
  • Sunday, August 21 until Friday, August 26. 9:00 p.m. to 5:00 a.m. Right lane closure on northbound I-35 mainlane from Olympia Parkway to Pasatiempo for geotechnical and drilling work.
  • Sunday, August 21 until Friday, August 26. 9:00 p.m. to 5:00 a.m. Right lane closure on northbound I-35, Pat Booker Road exit ramp closure, and left lane closure on northbound frontage road of I-35 from Judson Road to Sandpiper Drive for geotechnical and drilling work. All traffic must exit Toepperwein Road (exit 170B).
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) and entrance ramp on southbound I-35 between Judson Road and O’Connor Road for striping and barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35, left lane closure on southbound frontage road and closure of southbound I-35 entrance ramp from Pat Booker Road to Ferrell Road for barrier work. Traffic must continue straight to Judson Road entrance ramp.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35, left lane closure on southbound frontage road and entrance ramp closure of I-35 between Judson Road and O’Connor Road for barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35 and exit ramp closure between Toepperwein Road and Judson Road for barrier work.
  • Sunday, August 21 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Left lane closure on southbound I-35 frontage road and Toepperwein Road and exit ramp closure to Judson Road for barrier work.
  • Monday, August 22 until Friday, August 26. 9:00 p.m. to 5:00 p.m. Right shoulder closure on northbound I-35 frontage road from Pat Booker Road to Loop 1604 for construction exit/entrance work.
  • Tuesday, August 23 until Friday, August 26. 9:00 p.m. to 5:00 a.m. Right lane closure of northbound I-35 frontage road from O’Connor Road to Judson Road for subsurface utility work.
  • Tuesday, August 23 until Friday, August 26. 9:00 p.m. to 5:00 p.m. Left lane closure of northbound I-35 frontage road from Chelsea Place to Schertz Parkway for subsurface utility work.
  • Wednesday, August 24 until Saturday, August 27. 9:00 p.m. to 5:00 a.m. Right lane closure on eastbound and westbound of Pat Booker Road between I-35 frontage roads for riprap removal work. 

I-10 – East San Antonio/Bexar County

  • Continuing through Tuesday, September 16. I-10 EB exit to Ackerman closed continuously for overpass work. Detour: Eastbound I-10 traffic can exit at Foster Road, turnaround at intersection, and use westbound frontage road back to Ackerman.
  • Sunday, August 21 until Monday, August 22. 9 p.m. to 5 a.m. Full closure of the westbound mainlanes at FM 1538 for bridge work.
  • Sunday, August 21 until Friday, August 26. 8 p.m. to 6 a.m. Single eastbound mainlane closure from Zuehl Rd. to FM 465 for barrier work.
  • Monday, August 22 until Tuesday, August 23. 9 p.m. to 5 a.m. Full closure of the westbound mainlanes at FM 2538 to FM 1538 for bridge work.
  • Monday, August 22. 9 a.m. to 4 p.m. Eastbound ramp closures at Zuehl Rd. for barrier work.
  • Tuesday, August 23 until Wednesday, August 24. 9 p.m. to 5 a.m. Full closure of the eastbound mainlanes at FM 1538 for bridge work.
  • Wednesday, August 24 until Thursday, August 25. 9 p.m. to 5 a.m. Full closure of the westbound mainlanes at FM 2538 for bridge work.
  • Thursday, August 25 until Friday, August 26. 9 p.m. to 5 a.m. Full closure of the eastbound mainlanes at FM 2538 for bridge work.
  • Monday, August 22 until Tuesday, August 23. 9 p.m. to 5 a.m. Full closure of the westbound mainlanes from FM 2538 to FM 1518 for bridge work.
  • Friday, September 9 9 p.m. to Monday, September 12 5 a.m. Full closure of the westbound mainlanes from Pfeil Rd. to Loop 1604. 

I-410 – North East San Antonio

  • Monday, August 22 until Friday, August 26. 9:00 p.m. to 5:00 p.m. Alternating lane closures on westbound Loop 410 frontage road from Perrin Creek to Perrin Beitel Road for construction exit/entrance work. 

I-410 – East San Antonio

  • Saturday, August 20. Northbound I-410 exit to eastbound I-10 closure from 8 p.m. to 5 p.m. for barrier repair. DETOURS:
  • Northbound I-410 traffic to eastbound I-10 will exit at East Houston Street, take the northbound I-410 frontage road, and enter after Ackerman Road.
  • Northbound I-410 traffic to westbound I-10 will exit at East Houston Street, take the northbound I-410 frontage road, turn around at Ackerman Road, and enter after Ackerman.
  • Saturday, August 20 through Sunday, August 28. DAYTIME Northbound I-410 frontage road left lane closures between East Houston Street and I-10 from 8 a.m. to 5 p.m. for wall work.   
  • Saturday, August 20 through Sunday, August 28. DAYTIME Southbound I-410 frontage road alternating lane closures between I-10 and East Houston Street from 8 a.m. to 5 p.m. for roadwork.   
  • Monday, August 22 through Friday, August 26. DAYTIME I-10 eastbound and westbound rolling lane closures between 1516 and Pfeil Road from 9 a.m. to 3 p.m. for litter cleanup and barrier work.

I-410 – West San Antonio

  • Current until Saturday, August 20. 8 p.m. to 11 a.m. Full closure of the northbound frontage road from Culebra Rd. to Ingram Rd. for utility work.
  • Current until Saturday, August 20. 9 a.m. to 3 p.m. Alternating lane closures on the frontage roads, in both directions, from Marbach Rd. to Ingram Rd. for road work.
  • Current until Friday, August 26. 8 p.m. to 5 a.m. Full closure of the northbound frontage road from Marbach Rd. to SH 151 for barrier work.
  • Current until Saturday, August 20. 7 a.m. to 5 p.m. Full closure of the northbound entrance ramp from Marbach Rd. for barrier work.
  • Current until Monday, August 22. 8 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from Marbach Rd. to Ingram Rd. for road work.
  • Current until Sunday, August 27. 9 a.m. to 3 p.m. Single northbound mainlane closure from Marbach Rd. to SH 151 for barrier removal.
  • Current until Sunday, August 27. 9 a.m. to 3 p.m. Single lane closure on the northbound frontage road from Marbach Rd. to SH 151 for concrete work. 

SH 151 – Bexar County

  • Current until Sunday, August 20. 9 a.m. to 3 p.m. Alternating lane closures on the frontage roads, in both directions, from Marbach Rd. to Ingram Rd. for road work.
  • Sunday, August 21. 7 a.m. to 4 p.m. Full closure of the mainlanes, in both directions, at Wiseman Blvd. for utility work. Traffic will be stopped in 15-minute intervals throughout the day. 

PA 1502 – Wurzbach Parkway

  • Current until Wednesday, August 31. 9 a.m. to 3 p.m. Various lane closures, in both directions, from Blanco Rd. to Wetmore Rd. for road work.
  • Monday, August 22 until Friday, September 2. 9 a.m. to 4 p.m. Right turn lane closures, in all directions, at N.W. Military Highway intersection for median work. 

FM 1535 – N.W. Military Highway

  • Monday, August 22 until Friday, September 2. 9 a.m. to 4 p.m. Single lane closure, in both directions, at the Wurzbach Parkway intersection for median work. 

SH 181 – Bexar County

  • Current until Friday, August 26. 9 a.m. to 4 p.m. Alternating lane closures, in both directions, from I-37 to Wilson County Line for road repairs. 

US 87 – Rigsby Road

  • Friday, August 19 until Monday, September 19. 9 a.m. to 4 p.m. Alternating lane closures, in both directions, from Roland Ave. to Loop 410 for striping operations. 

SH 16 – Bexar County

  • Monday, August 29 until Friday, September 2. Nightly 9 p.m. to 5 a.m. Alternating lane closures, in both directions, from Loop 1604 to Circle A Trail for striping operations. 

US 181 – Bexar County

  • Friday, August 19 until Monday, September 19. 9 p.m. to 5 a.m. Alternating lane closures, in both directions, from Wilson County Line to I-37 for bridge work and striping operations. 

FM 725 – Comal County

  • Current until Thursday, September 1. Full closure of the northbound to southbound turnaround at I-35 for operational improvements. 

I-10 – Kendall County

  • Friday, August 19 – 9 p.m. until Monday, August 22 – 5 a.m. Full closure of the mainlanes, in both directions, from SH 46 to US 87 for traffic switch. Traffic will be directed to frontage roads.