Friday, October 21

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North West San Antonio/Bexar County

  • Sunday, October 23 until Friday, November 4. Weeknights 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Bandera Road (SH 16) to IH-10 for portable concrete traffic barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding Weekends.
  • Sunday, October 23 until Friday, November 4. Weeknights 9 p.m. until 5 a.m. Alternating westbound mainlane closure from IH-10 to Bandera Road (SH 16) for portable concrete barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding Weekends.
  • Sunday, October 23 until Friday, November 4. Weeknights 9 p.m. until 5 a.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for portable concrete traffic barrier installation. Nightly alternating frontage road closures. One lane to remain open at all times. Excluding Weekends.
  • Sunday, October 23 until Friday, November 4. Weeknights 9 p.m. until 5 a.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for portable concrete traffic barrier installation. Nightly alternating frontage road closures. One lane to remain open at all times. Excluding Weekends.
  • Sunday, October 23 until Friday, November 4. Weeknights 9 p.m. until 5 a.m. Eastbound mainlane full closure from Babcock Road to La Cantera Parkway for bridge construction. Only one full mainlane closure to occur per direction, per night.
  • Sunday, October 23 until Friday, November 4. Weeknights 9 p.m. until 5 a.m. Westbound mainlane full closure from La Cantera Parkway to Babcock Road for bridge construction. Excluding Weekends. Only one full mainlane closure to occur per direction, per night.
  • Sunday, October 23 until Friday, October 28. Weeknights 9 p.m. until 5 a.m. Westbound mainlane full closure from Kyle Seale Parkway to Bandera Road for overhead sign bridge removal. Excluding Weekends. Only one full mainlane closure to occur per direction, per night.
  • Sunday, October 23 until Friday, October 28. Weeknights 9 p.m. until 5 a.m. Eastbound mainlane full closure at Bandera Road for overhead sign bridge removal. Excluding Weekends. Only one full mainlane closure to occur per direction, per night.
  • Sunday, October 23 until Friday, October 28. Weeknights 9 p.m. until 5 a.m. Full ramp closure at eastbound Loop 1604, Vance Jackson Road exit ramp. Traffic will utilize the eastbound exit ramp at La Cantera Parkway and continue on the eastbound frontage road. Excluding weekends. Two consecutive ramps will not be closed at the same time at any point.
  • Monday, October 24 until Monday, November 7. Weekdays 9 a.m. until 3 p.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 to set portable concrete barrier, sidewalk construction and beam placement. Daily alternating frontage road closures. One lane to remain open at all times. Excluding Weekends.
  • Monday, October 24 until Monday, November 7. Weekdays 9 a.m. until 3 p.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) to set portable concrete barrier, sidewalk construction and beam placement. Daily alternating frontage road closures. One lane to remain open at all times. Excluding Weekends.
  • Monday, October 24 until Monday, November 7. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Alternating. Only one turnaround to be closed at a time. Excluding Weekends.
  • Monday, October 24 until Monday, November 7. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Alternating. Only one turnaround to be closed at a time. Excluding Weekends.
  • Monday, October 24 until Monday, November 7. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Alternating. Only one turnaround to be closed at a time. Excluding Weekends.
  • Monday, October 24 until Monday, November 7. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Alternating. Only one turnaround to be closed at a time. Excluding Weekends.
  • Monday, October 24 until Monday, November 7. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and La Cantera Parkway for bridge widening. Alternating. Only one turnaround to be closed at a time. Excluding Weekends.
  • Monday, October 24 until Monday, November 7. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and La Cantera Parkway for bridge widening. Alternating. Only one turnaround to be closed at a time. Excluding Weekends.
  • Friday, October 28 at 9 p.m. until Monday, October 31 at 5 p.m. Weekend Only. Eastbound mainlane closure between Bandera Road and Kyle Seale Parkway for traffic switch, relocation of concrete traffic barrier. Only one full mainlane closure to occur per direction, per night. 

Loop 1604 – North Central San Antonio/Bexar County

  • Sunday, October 23 until Thursday, October 27. 9 p.m. to 5 a.m. Westbound entrance ramp from Redland Rd. and flyover ramps to US 281 closed for bridge repairs.
  • Sunday, October 23 until Friday, October 28. Nightly 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Tradesman Road to US 281 exit ramp for barrier setting and striping.
  • Sunday, October 23 until Friday, October 28. Nightly 9 p.m. until 5 a.m. Alternating westbound mainlane closure from US 281 exit ramp to Tradesman Road for barrier setting and striping.
  • Sunday, October 23 until Friday, October 28. Nightly 9 p.m. until 5 a.m. Alternating eastbound frontage road closure from IH-10 to US 281 for barrier setting and striping.
  • Sunday, October 23 until Friday, October 28. Nightly 9 p.m. until 5 a.m. Alternating westbound frontage road closure from US 281 to IH-10 for barrier setting and striping.
  • Sunday, October 23 until Friday, October 28. Nightly 9 p.m. until 5 a.m. Westbound to eastbound turnaround full closure at Loop 1604 and NW Military Highway for drilling shafts.
  • Sunday, October 23 until Friday, October 28. Nightly 11 p.m. until 5 a.m. Westbound mainlanes full closure from Blanco Road exit ramp to Bitters Road entrance ramp for retaining wall excavation work and temporary illumination.
  • Sunday, October 23 until Friday, October 28. Nightly 11 p.m. until 5 a.m. Eastbound frontage road periodic short term, full closure from Salado Creek to Huebner Road for retaining wall excavation work and temporary illumination.
  • Sunday, October 23 until Friday, October 28. Nightly 11 p.m. until 5 a.m. Westbound frontage road periodic short term, full closure from Huebner Road to Salado Creek for retaining wall excavation work and temporary illumination.
  • Sunday, October 23 until Friday, October 28. Nightly 11 p.m. until 5 a.m. Eastbound mainlane periodic short term, full closure from Bitters Road exit ramp to Blanco Road entrance ramp for retaining wall excavation work and temporary illumination.
  • Sunday, October 23 until Friday, October 28. Nightly 11 p.m. until 5 a.m. Northbound Bitters Road periodic short term, full closure at Loop 1604 intersection for retaining wall excavation work and temporary illumination.
  • Sunday, October 23 until Friday, October 28. Nightly 11 p.m. until 5 a.m. Southbound Bitters Road periodic short term, full closure at Loop 1604 intersection for retaining wall excavation work and temporary illumination.
  • Sunday, October 23 until Friday, October 28. Nightly 9 p.m. until 5 a.m. Right lane closure on southbound Blanco Road from W. Blanco Road to Talavera Parkway for barrier setting.
  • Monday, October 24 until Friday, October 28. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround full closure at Loop 1604 and Lockhill Selma Road for bridge widening construction.
  • Monday, October 24 until Friday, October 28. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround short term full closure at Loop 1604 and NW Military Highway for concrete placement for drilling shafts.
  • Sunday, October 23 until Sunday, October 30. Weekdays/Weeknights 12 a.m. until 12 a.m. Eastbound to westbound turnaround full closure at Loop 1604 and Lockhill Selma for bridge widening construction.

Loop 1604 – North East San Antonio/Bexar County

  • Sunday, October 23 until Saturday, October 29. 9:00 p.m. to 5:00 a.m. Eastbound Loop 1604 Lookout Road exit ramp closure from Nacogdoches Road to Union Pacific Railroad for overhead sign removal. Traffic must use the Nacogdoches exit to access Lookout Road.
  • Sunday, October 23 until Saturday, October 29. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound Loop 1604 from Nacogdoches Road to I-35 for barrier work.
  • Sunday, October 23 until Saturday, October 29. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound frontage road of Loop 1604 from Nacogdoches Road to Union Pacific Railroad for excavation work.
  • Sunday, October 23 until Saturday, October 29. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound Loop 1604 from I-35 to Nacogdoches Road for barrier work. 

I-10 – North West San Antonio/Bexar County

  • Sunday, October 23 until Friday, November 4. Weeknights 9 p.m. until 5 a.m. Alternating westbound frontage road closure from De Zavala Road to Camp Bullis Road for portable concrete traffic barrier installation. Nightly alternating frontage closures. One lane to remain open at all times. Excluding Weekends.
  • Sunday, October 23 until Friday, November 4. Weeknights 9 p.m. until 5 a.m. Alternating eastbound frontage road closure from Camp Bullis Road to De Zavala Road for portable concrete traffic barrier installation. Nightly alternating frontage closures. One lane to remain open at all times. Excluding Weekends.
  • Sunday, October 23 until Friday, November 4. Weeknights 9 p.m. until 5 a.m. Alternating westbound mainlane closure from De Zavala Road to Camp Bullis Road for portable concrete traffic barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding Weekends.
  • Sunday, October 23 until Friday, November 4. Weeknights 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Camp Bullis Road to De Zavala Road for portable concrete traffic barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding Weekends.
  • Monday, October 24 until Monday, November 7. Weekdays 9 a.m. until 3 p.m. Alternating westbound frontage road closure from De Zavala Road to Camp Bullis Road for portable concrete traffic barrier installation. Daily alternating frontage closures. One lane to remain open at all times. Excluding Weekends.
  • Monday, October 24 until Monday, November 7. Weekdays 9 1.m. until 3 p.m. Alternating eastbound frontage road closure from Camp Bullis Road to De Zavala Road for portable concrete traffic barrier installation. Daily alternating frontage closures. One lane to remain open at all times. Excluding Weekends. 

I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

  • Sunday, October 23. 9:00 p.m. to 5:00 a.m. Right lane closure on northbound I-35 frontage road from Olympia Parkway to Pasatiempo for geotechnical work.
  • Sunday, October 23. 9:00 p.m. to 5:00 a.m. Right lane closure on northbound I-35 frontage road from Olympia Parkway to Pasatiempo for geotechnical work.
  • Sunday, October 23. 9:00 p.m. to 5:00 a.m. Left lane closure on northbound I-35 frontage road from Joe Lee Street to Weidner Road for geotechnical drilling work.
  • Sunday, October 23 until Tuesday, October 25. 9:00 p.m. to 5:00 a.m. Right shoulder closure on northbound I-35 mainlane and left lane closure on frontage road from Schertz Parkway to Roy Richard Drive for utility pothole work.
  • Sunday, October 23 until Tuesday, October 25. 9:00 p.m. to 5:00 a.m. Right shoulder closure on northbound I-35 mainlane and left lane closure on frontage road from Schertz Parkway to Roy Richard Drive for utility pothole work.
  • Sunday, October 23 until Saturday, October 29. 9:00 p.m. to 5:00 a.m. Multiple right lane (2) and alternating ramp closures on southbound I-35 connector from Loop 1604 to Toepperwein Road for striping and barrier work. Traffic must use next ramp to access I-35.
  • Sunday, October 23 until Saturday, October 29. 9:00 p.m. to 5:00 a.m. Multiple left lane (3) closures on southbound I-35 from Forum Parkway to Ferrell Road. for striping and barrier work.
  • Sunday, October 23 until Saturday, October 29. 9:00 p.m. to 5:00 a.m. Right mainlane closure on southbound I-35 and southbound I-35 entrance ramp closure from Pat Booker Road to Toepperwein Road for drill shaft work. Traffic must use next entrance ramp to access I-35.
  • Sunday, October 23 until Saturday, October 29. 9:00 p.m. to 5:00 a.m. Left lane closure on southbound I-35 frontage road and exit ramp from Pat Booker Road to Judson Road for drill shaft work.
  • Sunday, October 23 until Saturday, October 29. 9:00 p.m. to 5:00 a.m. Multiple left lane closure (3) on southbound I-35 mainlane from Pat Booker Road to O’Connor Road for striping work.
  • Sunday, October 23 until Saturday, October 29. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35, alternating lane closures on southbound frontage road of I-35 and exit ramp closure on southbound I-35 from Toepperwein Road to Judson Road for drill shaft operations and safety fall protection work. Traffic must use O’Connor Road exit to access Judson Road.
  • Sunday, October 23 until Saturday, October 29. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound and westbound Toepperwein Road from southbound frontage road of I-35 to northbound frontage road of I-35. for drill shaft work.
  • Sunday, October 23 until Saturday, October 29. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road of I-35 from Judson Road to O’Connor Road for earth work.
  • Sunday, October 23 until Saturday, October 29. 9:00 p.m. to 5:00 a.m. Multiple right lane closure (3) and ramps on southbound I-35 mainlane from Pat Booker Road to O’Connor Road for striping work. Traffic must use next ramp.
  • Sunday, October 23 until Saturday, October 29. 9:00 p.m. to 5:00 a.m. Multiple left lane (2) closures on southbound frontage road of I-35 from Thousand Oaks Drive to Randolph Boulevard for drill shaft work.
  • Sunday, October 23 until Saturday, October 29. 9:00 p.m. to 5:00 a.m. Left lane closure on southbound frontage road of I-35 from Randolph Boulevard to Walzem Road for drill shaft work.
  • Monday, October 24. 9:00 p.m. to 5:00 a.m. Mobile operations on westbound Pat Booker Road at southbound I-35 frontage road for equipment movement work.
  • Monday, October 24. 9:00 p.m. to 5:00 a.m. Right lane closure on northbound I-35 frontage road from Olympia Parkway to Pasatiempo for geotechnical drilling work.
  • Monday, October 24. 9:00 p.m. to 5:00 a.m. Right lane closure on northbound I-35 frontage road from Olympia Parkway to Pasatiempo for geotechnical drilling work.
  • Monday, October 24. 9:00 p.m. to 5:00 a.m. Northbound-to-southbound turnaround closure at Weidner Road intersection for geotechnical drilling work. Traffic must use traffic signals to access southbound I-35.
  • Tuesday, October 25. 9:00 p.m. to 5:00 a.m. Entrance ramp closure on northbound I-35 frontage road from Weidner Road to Bomar Lane for subsurface drilling work.
  • Wednesday, October 26 until Friday, October 28. 9:00 p.m. to 5:00 a.m. Left lane closure on northbound I-35 frontage road from Weidner Road to Bladau Bishop for subsurface exploration work.
  • Thursday, October 27. 9:00 p.m. to 5:00 a.m. Left lane closure on northbound frontage road of I-35 from Crestway Drive to Thousand Oaks Drive for geotechnical drilling work. 

I-10 – East San Antonio/Bexar County

  • Saturday, October 22. 5 a.m. to 9 p.m. Alternating eastbound mainlane closures from FM 2538 to Zuehl Rd. for traffic switch.
  • Sunday, October 23. 8 p.m. to 6 a.m. Single eastbound mainlane closure from FM 2538 to Zuehl Rd. for traffic switch.
  • Continuing through Tuesday, November 8. NIGHTTIME I-10 eastbound exit to Ackerman closed from 9 p.m. to 5 a.m. for ramp work. Detour: Eastbound I-10 traffic can exit at Foster Road, turn around at intersection, and use westbound frontage road back to Ackerman. 
  • Continuing through Friday, October 28. DAYTIME I-10 westbound alternating single lane closures between Ackerman Road and I-10 for overpass work. 
  • Saturday, October 22. I-10 eastbound full mainlane closure between Loop 1604 and Graytown Road from 4 a.m. to 7 p.m. for pavement repair. Loop 1604 and Graytown Road onramps to eastbound I-10 also closed. Loop 1404 and Detour: Eastbound I-10 traffic will exit at Loop 1604, continue on I-10 eastbound frontage road, and take temporary on-ramp west of Pfeil Road. (Additional I-10 eastbound alternating lane closure  between Cibolo Creek and Zuehl Road to shift traffic towards the median and move barrier)
  • Monday, October 24. Westbound I-10 right lane closure between Graytown Road and Scenic Lake Drive from 9 a.m. to 3 p.m. for barrier work.
  • Thursday, October 27 until Friday, October 28. 9 p.m. to 5 a.m. Full closure of the eastbound mainlanes at FM 1518 for barrier work.
  • Saturday, October 29. 6 a.m. to 5 p.m. Single eastbound mainlane closure at FM 1518 for shoulder repairs.
  • Sunday, October 30 until Monday, October 31. 9 p.m. to 5 a.m. Alternating eastbound mainlane closures from Pfeil Rd. to FM 1518 for striping operations. 

I-410 – North East San Antonio

  • Sunday, October 23. 9:00 p.m. to 5:00 a.m. Right shoulder closure on eastbound Loop 410 mainlane from Quail Creek Drive to Perrin Beitel for subsurface drilling work.
  • Sunday, October 23. 9:00 p.m. to 5:00 a.m. Northbound to southbound turnaround and entrance ramp on westbound Loop 410 from Perrin Beitel Road to Starcrest Road for crash cushion work. (Maintenance)
  • Sunday, October 23. 9:00 p.m. to 5:00 a.m. Right shoulder closure on westbound Loop 410 mainlane from Austin Highway to Perrin Beitel Road for guardrail repair work. (Maintenance)
  • Sunday, October 23. 9:00 p.m. to 5:00 a.m. Exit ramp closure on eastbound Loop 410 between Nacogdoches Road to Harry Wurzbach Road for crash cushion repair work. 

I-410 – East San Antonio

  • Friday, October 21 through Friday, November 4, (except for Friday and Saturday nights). NIGHTTIME northbound I-410 mainlanes closed between E. Houston Street and I-10 on-ramp from 9 p.m. to 5 a.m. for overpass work. E. Houston Street entrance ramp to northbound I-410 also closed. Detour
  • Exit at E. Houston street, take I-10 northbound frontage to Ackerman, turn around, and take westbound I-10 back to northbound I-410.
  • Saturday, October 22 through Saturday, November 5. NIGHTTIME northbound I-410 frontage road closure from East Houston Street on-ramp to eastbound I-10 from 9 p.m. to 5 a.m. (No closures Friday or Saturday Night.)  Detour: Northbound I-410 traffic to Ackerman Road may take northbound I-410 to I-10 EB exit ramp, turn around at Foster Road, and take I-10 westbound frontage road to Ackerman.
  • Friday, October 21 through Friday, November 4. NIGHTTIME northbound I-410 ramp to eastbound I-10 closed from 9 p.m. to 5 a.m. for overpass work. Detour:
  • Northbound I-410 traffic to eastbound I-10 will take the I-410 northbound to I-10 westbound cloverleaf ramp, then the I-10 WB to I-10 Southbound cloverleaf ramp, and finally the I-410 southbound to I-10 eastbound cloverleaf ramp.
  • Continuing through Thursday, November 3. DAYTIME northbound and southbound I-410 frontage road alternating lane closures between I-10 and East Houston Street from 9 a.m. to 4 p.m. for bridge and road work.  
  • Continuing through Friday, October 28. Loop 1604 and I-10 intersection, all left turn lanes closed continuously until 5 a.m. October 28 for bridge work.
  • Continuing through Friday, November 18. DAYTIME eastbound I-10 exit to southbound I-410 closed from 9 a.m. to 4 p.m. daily. Detour:
  • Eastbound I-10 traffic to Southbound I-410 will exit at W.W. White Road, continue on the eastbound I-10 frontage road, and take entrance ramp at E. Houston Street. 

I-410 – West San Antonio

  • Current until Monday, October 30. 9 p.m. to 5 a.m. Exit ramp to Valley Hi Dr. closed for repairs.
  • Current until Monday, October 31. 8 p.m. to 5 a.m. Alternating lane closures on the frontage roads, in both directions, from Bandera Rd. to Marbach Rd. for asphalt operations.
  • Current until Monday, October 31. 9 a.m. to 5 p.m. Full closure of the northbound exit ramp to eastbound SH 151 for bridge work.
  • Current until Monday, October 31. 8 p.m. to 5 a.m. Southbound exit ramp to Ingram Rd. closed for traffic rail installation.
  • Monday, October 24 until Friday, October 28. 9 p.m. to 5 a.m. Single northbound mainlane closure from Old Pearsall Rd. to Ray Ellison Blvd. for barrier work. 

SH 151 – West San Antonio

  • Current until Monday, October 31. 8 a.m. to 5 p.m. Single eastbound mainlane closure at Cable Ranch Rd. for sign work.
  • Current until Tuesday, November 1. 9 a.m. to 4 p.m. Single lane closure on the southbound frontage road at Old Highway 90 for curb and sidewalk replacement. 

SH 16 – Bandera Road

  • Monday, October 24 until Friday, October 28. 9 a.m. to 3 p.m. Single lane closures, in both directions, from Loop 1604 to Diamond K Trail for utility work.
  • Monday, October 24 until Friday, October 28. 9 p.m. to 5 a.m. Alternating lane closures, in both directions, from Loop 1604 to Diamond K Trail for utility work. 

FM 1535 – N.W. Military Highway

  • Monday, October 24 until Friday, October 28. 7 a.m. to 6 p.m. Single lane closures, in both directions, from Loop 1604 to Huebner Rd. for utility work. 

PA 1502 – Wurzbach Parkway

  • Current until Monday, October 31. 9 a.m. to 3 p.m. Various lane closures, in both directions, at the Wurzbach Parkway intersection for utility work. 

FM 471 – Bexar County

  • Monday, October 24 until Wednesday, November 9. Single northbound lane closure from Old FM 471 S to Old FM 471 N for construction of drainage crossing. Traffic will be detoured to Old FM 471. 

US 181 – Bexar County

  • Current until Monday, October 31. 9 a.m. to 4 p.m. Alternating lane closures, in both directions, from Wilson County Line to I-37 for striping operations. 

US 90 – Bexar County

  • Sunday, October 23. 9 a.m. to 4 p.m. Full closure of the mainlanes, in both directions, at Cagnon Rd. for utility work. Traffic will be stopped intermittently throughout the day in 15-minute intervals. 

SH 46 – Comal County

  • Monday, October 24 until Friday, November 4. 9 p.m. to 5 a.m. Single lane closures, in both directions, from Old Boerne Rd. to Bentwood Dr. for striping operations.