Friday, September 8

UPCOMING SCHEUDLED CONSTRUCTION CLOSURES

Loop 1604 – North West San Antonio/Bexar County

  • Sunday, Sept. 10 until Monday, Sept. 25. Weeknights 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Bandera Road (SH 16) to IH-10 for portable concrete traffic barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, Sept. 10 until Monday, Sept. 25. Weeknights 9 p.m. until 5 a.m. Alternating westbound mainlane closure from IH-10 to Bandera Road (SH 16) for portable concrete barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, Sept. 10 until Monday, Sept. 25. Weeknights 9 p.m. until 5 a.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for portable concrete traffic barrier installation. Nightly alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, Sept. 10 until Monday, Sept. 25. Weeknights 9 p.m. until 5 a.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for portable concrete traffic barrier installation. Nightly alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, Sept. 10 until Monday, Sept. 25. Weeknights 8 p.m. until 5 a.m. Eastbound frontage road lane full closure from John Peace Boulevard/La Cantera Parkway to IH-10 for eastbound direct connector bridge construction. Nightly frontage road full closure. Only one full frontage lane closure to occur per direction. Excluding weekends.
  • Sunday, Sept. 10 until Monday, Sept. 25. Weeknights 8 p.m. until 5 a.m. Westbound frontage road lane full closure from IH-10 to John Peace Boulevard/La Cantera Parkway for westbound collector distributor bridge construction. Nightly frontage road full closure. Only one full frontage lane closure to occur per direction. Excluding weekends.
  • Sunday, Sept. 10 until Monday, Sept. 25. Weeknights 9 p.m. until 5 a.m. IH-10 eastbound mainlane exit ramp closure to Loop 1604 westbound for westbound collector distributor bridge construction on the bridge at Leon Creek. Nightly closure. Excluding weekends.
  • Sunday, Sept. 10 until Monday, Sept. 25. Weeknights 9 p.m. until 5 a.m. Ramp/cloverleaf closure from IH-10 westbound to Loop 1604 westbound for westbound collector distributor bridge construction on the bridge at Leon Creek. Nightly closure. Excluding weekends.
  • Sunday, Sept. 10 until Monday, Sept. 25. Weeknights 9 p.m. until 5 a.m. Loop 1604 westbound exit ramp to La Cantera Parkway closure for westbound direct connector bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Sept. 10 until Monday, Sept. 25. Weeknights 9 p.m. until 5 a.m. Loop 1604 westbound entrance ramp from IH-10 closure for westbound direct connector bridge construction. Nightly closure. Excluding weekends.
  • Monday, Sept. 11 until Monday, Sept. 25. Weekdays 9 a.m. until 3 p.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for traffic barrier, sidewalk construction and beam placement/bridge construction. Daily alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Monday, Sept. 11 until Monday, Sept. 25. Weekdays 9 a.m. until 3 p.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for traffic barrier, sidewalk construction and beam placement/bridge construction. Daily alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Monday, Sept. 11 until Monday, Sept. 25. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Hausman Road for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, Sept. 11 until Monday, Sept. 25. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Hausman Road for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, Sept. 11 until Monday, Sept. 25. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, Sept. 11 until Monday, Sept. 25. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, Sept. 11 until Monday, Sept. 25. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, Sept. 11 until Monday, Sept. 25. Weekdays 9 a.m. until 3 p.m. Eastbound to Westbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, Sept. 11 until Monday, Sept. 25. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and La Cantera Parkway/John Peace Boulevard for bridge construction. Only one turnaround to be closed at a time on each direction. Excluding weekends.
  • Monday, Sept. 11 until Monday, Sept. 25. 12 a.m. until 12 a.m. Eastbound to westbound turnaround closure at Loop 1604 and Kyle Seale Parkway for bridge widening/retaining walls. Only one turnaround to be closed at a time.
  • Monday, Sept. 11 until Monday, Sept. 25. 12 a.m. until 12 a.m. Westbound to eastbound turnaround closure at Loop 1604 and Kyle Seale Parkway for bridge widening/retaining walls. Only one turnaround to be closed at a time.
  • Monday, Sept. 11 until Monday, Sept. 25. 12 a.m. until 12 a.m. Westbound to eastbound turnaround closure at Loop 1604 and La Cantera Parkway/John Peace Boulevard for bridge construction. Only one turnaround to be closed at a time on each direction. 

Loop 1604 – North Central San Antonio/Bexar County

  • Sunday, September 10 until Friday, September 15. Nightly 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Tradesman Road to Stone Oak Parkway exit ramp for barrier setting and striping.
  • Sunday, September 10 until Friday, September 15. Nightly 9 p.m. until 5 a.m. Alternating westbound mainlane closure from Stone Oak Parkway exit ramp to Tradesman Road for barrier setting and striping.
  • Sunday, September 10 until Friday, September 15. Nightly 9 p.m. until 5 a.m. Alternating eastbound frontage road closure from IH-10 to Stone Oak Parkway exit ramp for barrier setting and striping.
  • Sunday, September 10 until Friday, September 15. Nightly 9 p.m. until 5 a.m. Alternating westbound frontage road closure from Stone Oak Parkway exit ramp to IH-10 for barrier setting and striping.
  • Thursday, September 14 until Saturday, September 16. Nightly 9 p.m. until 5 a.m. Westbound mainlane right lane from Lockhill Selma Road entrance ramp to the IH-10 interchange exit ramps will be closed to set deck panels on the westbound direct connector.
  • Thursday, September 14 until Saturday, September 16. Nightly 9 p.m. until 5 a.m. Loop 1604 westbound exit ramp to frontage road/ IH-10 intersection will be closed set deck panels on the westbound direct connector.
  • Thursday, September 14 until Saturday, September 16. Nightly 9 p.m. until 5 a.m. Loop 1604 westbound entrance ramp from Lockhill Selma Road. The auxiliary lane will also be closed to set deck panels on the westbound direct connector.
  • Sunday, September 10 until Sunday, September 17. Daily/Nightly 12 a.m. until 12 p.m. Westbound to Eastbound turnaround long term closure at Loop 1604 and NW Military Highway for bridge substructure. This closure will remain in place for approximately 4 weeks.
  • Sunday, September 10 until Sunday, September 17. Daily/Nightly 12 a.m. until 12 p.m. Westbound to Eastbound turnaround long term closure at Loop 1604 and Lockhill Selma Road for wall construction under bridge. This closure will remain in place for approximately 4 weeks. 

Loop 1604 – North East San Antonio/Bexar County

  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Full closure on eastbound mainlanes of Loop 1604 from Lookout Road to I-35 for striping work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Eastbound to westbound Loop 1604 turnaround closure from Nacogdoches Road to Union Pacific Railroad for retaining wall demolition work. Traffic should use Lookout Road intersection.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound frontage road of Loop 1604, right lane entrance ramp closure, and turnaround closure from Nacogdoches Road to Union Pacific Railroad for striping work. Traffic should use Lookout Road intersection.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound frontage road of Loop 1604 from Lookout Road to I-35 for striping and barrier work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Eastbound to westbound Loop 1604 turnaround closure at Lookout Road for construction work. Traffic should use Lookout Road intersection.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating mainlane closures on eastbound Loop 1604 from Nacogdoches Road to I-35 and exit ramp closure to Nacogdoches Road for barrier work. Traffic should use next exit ramp.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Exit ramp closure on eastbound mainlanes of Loop 1604 to Lookout Road for striping work. Traffic should use prior exit ramp.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound bypass ramp and entrance ramp closure of Loop 1604 from Nacogdoches Road to Lookout Road for striping work. Traffic should use next entrance ramp.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating mainlane closures on eastbound Loop 1604, entrance ramp closure, and exit ramp closure on eastbound Loop 1604 from Nacogdoches Road to I-35 for striping work. Traffic should use prior exit and next entrance ramps.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Exit ramp closure on eastbound mainlanes of Loop 1604 from Lookout Road to IKEA-RBFCU Parkway for striping work. Traffic should use prior exit ramp.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on the eastbound Loop 1604 collector ramp at the I-35 interchange for striping work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Full closure on westbound mainlanes of Loop 1604 from Pat Booker Road to Lookout Road for striping work. Traffic should use next entrance ramp.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Westbound to eastbound Loop 1604 turnaround closure at Lookout Road for demolition work. Traffic should use Lookout Road intersection.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating mainlane closures, exit ramp closure, and entrance ramp closure on westbound Loop 1604 from I-35 to Nacogdoches Road for barrier work. Traffic should use prior exit and next entrance ramps.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound frontage road, exit ramp closure, and entrance ramp closure of Loop 1604 from Union Pacific Railroad and Nacogdoches Road for barrier work. Traffic should use next available ramps.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound frontage road and westbound bypass ramp of Loop 1604 from I-35 to Nacogdoches Road for construction entrance and temporary pavement work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Exit ramp closure on westbound mainlanes of Loop 1604 to Lookout Road for pavement and striping work. Traffic should use next exit ramp.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Exit ramp closure on westbound Loop 1604 connector ramp from southbound I-35 to Lookout Road for striping work. Traffic should use next exit ramp.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Westbound to eastbound Loop 1604 turnaround closure from Lookout Road to Union Pacific Railroad for retaining wall demolition work. Traffic must use Nacogdoches Road turnaround.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Full closure of Lookout Road intersection and turnarounds for striping work. Traffic should follow detour signs.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Full closure on westbound frontage road of Loop 1604 from Gateway Boulevard to Gateway Place for setting caps. Traffic should follow detour signs. 

US 281 – North San Antonio/Bexar County

  • Monday, September 11 until Saturday, September 16. 9 a.m. to 3 p.m. Alternating lane closures on the frontage roads, in both directions, from Marshall Rd. to Borgfeld Rd. for concrete work.
  • Monday, September 11 until Saturday, September 16. 8 p.m. to 5 a.m. Alternating lane closures on the frontage roads, in both directions, from Marshall Rd. to Borgfeld Rd. for concrete work.
  • Monday, September 11 until Saturday, September 16. 9 a.m. to 4 p.m. Northbound exit ramp to Bulverde Rd. closed for concrete work.
  • Monday, September 11 util Saturday, September 16. 9 a.m. to 3 p.m. Alternating mainlane closures, in both directions, from Marshall Rd. to Borgfeld Rd. for painting operations.
  • Monday, September 11 util Saturday, September 16. 8 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from Marshall Rd. to Borgfeld Rd. for painting operations. 

I-10 – North West San Antonio/Bexar County

  • Sunday, September 10. 7 a.m. to 4 p.m. Full closure of mainlanes, in both directions, at Loop 1604 for utility work. Traffic will be stopped intermittently throughout the day in 15-minute intervals.
  • Sunday, Sept. 10 until Friday, Sept. 22. Weeknights 9 p.m. until 5 a.m. Alternating IH-10 westbound frontage road closure from De Zavala Road to Camp Bullis Road for portable concrete traffic barrier installation. Nightly alternating frontage closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, Sept. 10 until Friday, Sept. 22. Weeknights 9 p.m. until 5 a.m. Alternating IH-10 eastbound frontage road closure from Camp Bullis Road to De Zavala Road for portable concrete traffic barrier installation. Nightly alternating frontage closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, Sept. 10 until Friday, Sept. 22. Weeknights 9 p.m. until 5 a.m. Alternating IH-10 westbound mainlane closure from De Zavala Road to Camp Bullis Road for portable concrete traffic barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, Sept. 10 until Friday, Sept. 22. Weeknights 9 p.m. until 5 a.m. Alternating IH-10 eastbound mainlane closure from Camp Bullis Road to De Zavala Road for portable concrete traffic barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, Sept. 10 until Friday, Sept. 22. Weeknights 9 p.m. until 5 a.m. Exit ramp full closure from Loop 1604 eastbound to IH-10 eastbound for portable concrete traffic barrier installation. Nightly closures. Excluding weekends.
  • Sunday, Sept. 10 until Friday, Sept. 22. Weeknights 9 p.m. until 5 a.m. IH‑10 westbound mainlane exit ramp to La Cantera Parkway (braided ramp) full closure for portable concrete traffic barrier installation. Nightly closures. Excluding weekends.
  • Sunday, Sept. 10 until Friday, Sept. 22. Weeknights 9 p.m. until 5 a.m. IH‑10 westbound frontage road entrance ramp to IH-10 mainlanes before La Cantera Parkway (braided ramp) full closure for portable concrete traffic barrier installation. Nightly closures. Excluding weekends.
  • Sunday, Sept. 10 until Friday, Sept. 22. Weeknights 9 p.m. until 5 a.m. IH‑10 westbound mainlane exit ramp to Camp Bullis Road closure for portable concrete traffic barrier installation. Nightly closures. Excluding weekends.
  • Sunday, Sept. 10 until Friday, Sept. 22. Weeknights 9 p.m. until 5 a.m. IH‑10 eastbound frontage road entrance ramp to IH-10 mainlanes after Loop 1604 interchange full closure for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, Sept. 10 until Friday, Sept. 22. Weeknights 9 p.m. until 5 a.m. Exit ramp full closure from IH-10 westbound to Loop 1604 eastbound for portable concrete traffic barrier installation. Nightly closures. Excluding weekends.
  • Sunday, Sept. 10 until Friday, Sept. 22. Weeknights 9 p.m. until 5 a.m. Ramp/cloverleaf full closure from IH-10 eastbound to Loop 1604 eastbound for portable concrete traffic barrier installation. Nightly closures. Excluding weekends.
  • Sunday, Sept. 10 until Friday, Sept. 22. Weeknights 9 p.m. until 5 a.m. Ramp/cloverleaf full closure from Loop 1604 westbound to IH-10 eastbound for portable concrete traffic barrier installation. Nightly closures. Excluding weekends.
  • Sunday, Sept. 10 until Friday, Sept. 22. Weeknights 9 p.m. until 5 a.m. Ramp/cloverleaf full closure from IH-10 westbound to Loop 1604 westbound for portable concrete traffic barrier installation. Nightly closures. Excluding weekends.
  • Sunday, Sept. 10 until Friday, Sept. 22. Weeknights 9 p.m. until 5 a.m. Alternating Loop 1604 westbound mainlane closure from the exit ramp at Lockhill Selma Road to Valero Way overhead sign bridge removal. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, Sept. 10 until Friday, Sept. 22. Weeknights 9 p.m. until 5 a.m. Alternating Loop 1604 eastbound mainlane closure from the Valero Way exit ramp to the Lockhill Selma Road entrance ramp for overhead sign bridge removal. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, Sept. 10 until Friday, Sept. 22. Weeknights 9 p.m. until 5 a.m. IH-10 westbound frontage road full closure from UTSA Boulevard to the Loop 1604 interchange for bridge construction. Nightly frontage road closure. Excluding weekends.
  • Sunday, Sept. 10 until Friday, Sept. 22. Weeknights 9 p.m. until 5 a.m. Loop 1604 westbound collector distributor from Vance Jackson Road to Valero Way and the Loop 1604 westbound to IH-10 eastbound cloverleaf closure for micropile construction under the IH-10 and Loop 1605 interchange. Nightly closures. Excluding weekends.
  • Sunday, Sept. 10 until Friday, Sept. 22. Weeknights 9 p.m. until 5 a.m. Loop 1604 eastbound collector distributor from Valero Way to Vance Jackson Road closure for micropile construction under the IH-10 and Loop 1605 interchange. Nightly closures. Excluding weekends.
  • Sunday, Sept. 10 until Friday, Sept. 22. Weeknights 9 p.m. until 5 a.m. IH-10 westbound entrance ramp between De Zavala Road and UTSA Boulevard full closure for concrete barrier relocation. Nightly closures. Excluding weekends.
  • Sunday, Sept. 10 until Friday, Sept. 22. Weeknights 11 p.m. until 5 a.m. IH-10 eastbound entrance ramp just after La Cantera Parkway full closure for pedestrian bridge installation. Nightly closures. Excluding weekends.
  • Sunday, Sept. 10 until Friday, Sept. 22. Weeknights 11 p.m. until 5 a.m. IH-10 eastbound frontage road from the La Cantera Parkway intersection to the entrance ramp just after La Cantera Parkway full closure for pedestrian bridge installation. Nightly closures. Excluding weekends.
  • Sunday, Sept. 10 until Friday, Sept. 22. Weeknights 9 p.m. until 5 a.m. IH-10 eastbound frontage road, directly under the Loop 1604 interchange full closure for bridge foundation construction. Nightly closures. Excluding weekends.
  • Monday, Sept. 11 until Friday, Sept. 22. Weekdays 9 a.m. until 3 p.m. Alternating IH-10 westbound frontage road lane closure from De Zavala Road to Camp Bullis Road to set portable concrete barrier. Daily alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Monday, Sept. 11 until Friday, Sept. 22. Weekdays 9 a.m. until 3 p.m. Alternating IH-10 eastbound frontage road lane closure from Camp Bullis Road to De Zavala Road to set portable concrete barrier. Daily alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Friday, Sept. 8 at 9 p.m. until Monday, Sept. 11 at 5 a.m. IH-10 westbound exit ramp to La Cantera Parkway full closure for braided ramp demolition.
  • Friday, Sept. 8 at 9 p.m. until Monday, Sept. 11 at 5 a.m. IH-10 westbound mainlane right travel lane between the Loop 1604 interchange and the exit ramp to Camp Bullis Road full closure for braided ramp demolition.
  • Friday, Sept. 8 at 9 p.m. until Monday, Sept. 11 at 5 a.m. IH-10 westbound frontage road left lane between the Loop 1604 interchange and La Cantera Parkway full closure for braided ramp demolition. 

I-10 – East San Antonio/Bexar County

  • Friday, September 8 until Saturday, September 9. 8 p.m. to 5 a.m. Single eastbound mainlane closure from FM 2538 to Zuehl Rd. for traffic switch.
  • Friday, September 8 until Monday, September 11. 9 p.m. to 5 a.m. Full closure of the westbound mainlanes from FM 465 to FM 1518 for traffic switch. 

I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

  • Current until Saturday September 9, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from McMorris Boulevard to Pat Booker Road for construction.
  • Current until Wednesday, October 4, long-term closure (24/7). Left lane closure on southbound I-35 frontage road between Toepperwein Road and Judson Road for retaining wall, drilled shaft, column, and cap work.
  • Current until Sunday, December 10, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 at Fratt Road for construction work.
  • Current until Saturday, December 23 long-term closure (24/7). Alternating lane closures on southbound I-35 frontage road between Thousand Oaks Drive and Whirlwind Drive for roadway reconstruction and structural work.
  • Current until Saturday, December 30, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from Retama Parkway to Old Austin Road for temporary pavement, striping, barrier, column, and cap work.
  • Current until Monday, September 9, 2024, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from McMorris Boulevard for construction.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Rolling closure project-wide for sweeping operation.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on northbound mainlanes and entrance ramp closure of I-35 from Evans Road to Roy Richard Drive for barrier work. Traffic should use next entrance ramp.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on northbound frontage road, exit ramp closure, and entrance ramp closure of I-35 from Schertz Parkway to Roy Richard Drive for barrier work. Traffic should use next exit and entrance ramps.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on southbound I-35 mainlanes from Schertz Parkway to Forum Parkway for bridge structure work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, entrance ramp closure, and exit ramp closure from Roy Richard Drive to Schertz Parkway for bridge structure work. Traffic should use next entrance and exit ramps.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road, exit ramp closure, and entrance ramp closure of I-35 from Roy Richard Drive to Schertz Parkway for striping, barrier, and temporary pavement work. Traffic should use next exit and entrance ramps.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on northbound mainlanes and exit ramp closure of I-35 from Forum Parkway to Evans Road for drainage work. Traffic should use next exit ramp.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on northbound frontage road, exit ramp closure, and entrance ramp closure of I-35 from Forum Parkway to Evans Road for drainage work. Traffic should use next exit and entrance ramps.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on northbound frontage road, exit ramp closure, and entrance ramp closure of I-35 from Forum Parkway to Evans Road for drainage and barrier work. Traffic should use next exit and entrance ramps.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Northbound to southbound I-35 turnaround closure at Evans Road for striping, barrier, and temporary pavement work. Traffic should use Evans Road intersection.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Full closure on southbound frontage road of I-35 from Old Austin Road to Forum Parkway for bridge work. Traffic should follow detour signs.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road of I-35 from Olympia Parkway to Gateway Boulevard for bridge foundation, temporary pavement, striping and barrier work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road of I-35 from Evans Road to Olympia Parkway for bridge foundation, striping, barrier work, and temporary pavement work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on southbound I-35 mainlanes from Forum Parkway to Ferrell Road for bridge structure work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Full closure on southbound frontage road of I-35 from Retama Parkway to Olympia Parkway for bridge substructure work. Traffic should follow detour signs.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road, exit ramp closure, and entrance ramp closure of I-35 from Schertz Parkway to Evans Road for striping, barrier, and temporary pavement work. Traffic should use next exit and entrance ramps.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Southbound I-35 entrance ramp closure from Old Austin Road to Forum Parkway for construction work. Traffic must use the Forum Parkway turnaround and follow detour signs to access southbound I-35.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on southbound mainlanes and entrance ramp closure of I-35 from Retama Parkway to Forum Parkway for striping work. Traffic should use next entrance ramp.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Full closure on northbound I-35 collector ramp at the Loop 1604 interchange for striping, barrier, and construction entrance work. Traffic should follow detour signs.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Eastbound Loop 1604 to northbound I-35 connector ramp closure for striping and barrier work. Traffic should follow detour signs.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Full closure of southbound frontage road from IKEA-RBFCU Parkway to Pat Booker Road, eastbound Loop 1604 to southbound I-35 connector ramp closure, and southbound I-35 collector ramp closure at the Loop 1604 interchange for striping and barrier work. Traffic should follow detour signs.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating ramp closures on southbound I-35 connector ramp to Pat Booker Road for striping, barrier, and bridge substructure work. Traffic must exit Loop 1604 (exit 172) and follow the detour signs to Pat Booker Road.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Eastbound Loop 1604 to southbound I-35 connector ramp closure for striping and barrier work. Traffic must exit at IKEA-RBFCU Parkway and follow the detour signs to southbound I-35.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Westbound Loop 1604 to southbound I-35 connector ramp closure for earthwork. Traffic must exit at Lookout Road and follow the detour signs to southbound I-35.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Southbound I-35 collector ramp closure at the Loop 1604 interchange for striping and barrier work. Traffic must use west Loop 1604 (exit 172) to access southbound I-35 and follow detour signs.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Southbound I-35 to westbound Loop 1604 connector ramp closure and alternating lane closures on southbound mainlanes of I-35 at the exit to Loop 1604 for bridge substructure work. Southbound I-35 to Loop 1604 traffic should exit at Retama Parkway and follow the detour signs to Loop 1604.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Westbound Loop 1604 collector ramp closure at I-35 interchange for geotechnical work. Traffic should follow the detour signs.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (2) on northbound mainlanes of I-35, alternating exit ramp closures, and entrance ramp closure from Toepperwein Road to Loop 1604 for barrier setting and structures work. Traffic should follow the detour signs to the available ramps.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Full closure on northbound frontage road of I-35 and entrance ramp closure from Shin Oak Road to Pat Booker Road for striping, barrier, and temporary pavement work. Traffic should follow detour signs.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Full closure of northbound frontage road, exit ramp closure, and entrance ramp closure of I-35 from Pat Booker Road to Loop 1604 interchange for striping, barrier, and temporary pavement work. Traffic should follow detour signs.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Full closure on southbound frontage road and entrance ramp of I-35 from Shin Oak Drive to Toepperwein Road for cap form erection work. Accommodations will be made for local traffic. Southbound frontage road of I-35 traffic must follow detour.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, entrance ramp closure, and exit ramp closure from Pat Booker Road to Judson Road for structures work. Traffic should use next entrance and exit ramps.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on northbound mainlanes of I-35 from I-35 Access Road near Shin Oak Drive to Forum Parkway for striping, barrier, and temporary pavement work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Full closure of eastbound and westbound lanes of Pat Booker Road at I-35 for construction work. Traffic should follow detour signs.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Full closure of I-35 Access Road bridge from I-35 northbound frontage road to I-35 southbound frontage road, near Shin Oak Drive for construction work. Traffic should follow detour signs.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on northbound frontage road, entrance ramp closure, and alternating exit ramp closures of I-35 from Judson Road to Shin Oak Drive for barrier work. Traffic should follow the detour sign to the available ramps.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on northbound frontage road, right lane closure on northbound mainlanes, and exit ramp closure of I-35 from Bludau-Bishop Road to Gunn Road, right lane closure on the eastbound and westbound at the intersection of Judson Road and Randolph Boulevard and left lane closure on Randolph Boulevard at Judson Road for temporary pavement and signal works. Traffic should use the next exit ramp.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on northbound mainlanes of I-35 from Weidner Road to Bludau-Bishop Road for striping and barrier work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (2) on northbound frontage road, alternating entrance ramp closures, and exit ramp closure of I-35 from Weidner Road to Bludau-Bishop Road for earthwork and striping. Traffic should follow the detour signs to the available ramps.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple right lane closures (2) on northbound mainlanes of I-35, entrance ramp closure, and alternating exit ramp closures from O’Connor Road to Toepperwein Road for barrier setting and structures work. Traffic should follow the detour signs to the available ramps.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Full closure on southbound mainlanes of I-35 at O’Connor Road for overhead sign removal.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road of I-35 from Judson Road to O’Connor Road for earthwork, paving, striping, and barrier work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound mainlanes of I-35, exit ramp closure, and left lane closure on southbound frontage road of I-35 at O’Connor Road for barrier work. Traffic should use next exit.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple right lane closures (3) on southbound I-35 mainlanes, entrance ramp closure, exit ramp closure, and left lane closures (2) on southbound frontage road of I-35 from Judson Road to O’Connor Road for striping, barrier, and paving work. Traffic should use next entrance and exit ramps.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on southbound I-35 mainlanes from Judson Road to O’Connor Road for striping work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Right lane closure on westbound and eastbound of Toepperwein Road at I-35 for barrier work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on southbound mainlanes of I-35, exit ramp closure, and left lane closure on southbound frontage road of I-35 from Toepperwein Road to Judson Road for earthwork and barrier work. Traffic should use next exit ramp.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on northbound mainlanes of I-35 from Thousand Oaks Drive to Weidner Road for striping and barrier work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (2) on northbound frontage road, entrance ramp closure, exit ramp closures, and northbound to southbound turnaround at I-35 from Thousand Oaks Drive to Weidner Road for earthwork and striping. Traffic should follow the detour signs to the available ramps.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Left lane closure on northbound and southbound mainlanes of I-35 from Weidner Road to Loop 1604 for utility work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road of I-35, entrance ramp closure, and exit ramp closure from O’Connor Road to Weidner Road for drainage and barrier work. Traffic should use next entrance and exit ramps.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road of I-35 and entrance ramp closure from Weidner Road to Thousand Oaks Drive for earthwork, drainage and barrier work. Traffic should use prior entrance ramp.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on southbound mainlanes, alternating entrance and exit ramp closures, and alternating lane closures on southbound frontage road of I-35 from O’Connor Road to Weidner Road for striping work. Traffic should use the next exit and entrance ramps.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (2) on southbound mainlanes, entrance ramp closure, exit ramp closure, and alternating lane closures on southbound frontage road of I-35 from Weidner Road to Thousand Oaks Drive for striping work. Traffic should use the next exit and entrance ramps.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (2) on northbound mainlanes of I-35 from Randolph Boulevard to Thousand Oaks for barrier setting.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on northbound frontage road of I-35 from Crestway Drive to Starlight Terrace for barrier work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Full closure on southbound frontage road and northbound to southbound turnaround closure of I-35 from Thousand Oaks Drive to Whirlwind Drive for drilling work. Traffic should follow detour signs. Accommodations will be made for local traffic.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road of I-35 and exit ramp closure from Thousand Oaks Drive to Randolph Boulevard for permanent widening work. Traffic should use prior exit ramp.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Southbound to northbound turnaround closure at Walzem Road, alternating lane closures on northbound frontage road, and alternating entrance and exit ramp closures of I-35 from Walzem Road to Crestway Drive for striping and barrier work. Traffic should follow detour signs for available ramps.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Left lane closure on northbound and southbound mainlanes of I-35 from Walzem Road to Weidner Road for utility work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (2) on northbound mainlanes of I-35 and alternating lane closure on exit ramp from Walzem Road to Randolph Boulevard for barrier setting.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (2) on northbound and southbound of Interchange Parkway from Austin Highway (Loop 368) to Walzem Road and multiple lane closures (2) on eastbound and westbound of Fratt Road from I-35 southbound frontage road to Austin Highway (Loop 368) for barrier work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound mainlanes of I-35 from Randolph Boulevard to Walzem Road for cap work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Entrance ramp closure on southbound frontage road of I-35 from Fratt Drive to Walzem Road for drilled shaft and column work. Traffic to use next entrance ramp.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Full closure on southbound frontage road, exit ramp, and entrance ramp of I-35 from Randolph Boulevard to Fratt Road for drilled shaft work. Traffic should follow detour signs.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Exit ramp closure on southbound mainlanes and alternating lane closures on southbound frontage road of I-35 from Randolph Boulevard to Walzem Road for geotechnical, drilled shaft, and column work. Traffic to use next exit ramp.
  • Monday, September 11 until Friday, September 15. 12:00 p.m. to 5:00 a.m. Right lane closure on southbound frontage road of I-35 from FM 2252 to Cibolo Valley Drive and rolling closures on southbound mainlanes of I-35 from Cibolo Valley Drive to Pat Booker Road for beam staging. 

I-410 – North East San Antonio

  • Current until Saturday September 23, long-term closure (24/7). Left lane closure on westbound frontage road of I-410 from Perrin Creek to Austin Highway (Loop 368) for construction.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Entrance ramp closure on northbound Austin Highway (Loop 368) to eastbound I-410 for barrier work. Traffic should use next entrance ramp.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on northbound Austin Highway (Loop 368) from Walzem Road to Interchange Parkway for barrier work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on northbound Austin Highway (Loop 368) connector ramp to westbound I-410 for barrier work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound frontage road of I-410, entrance ramp closure, and eastbound to westbound turnaround closure between Starcrest Drive and Perrin Beitel for striping and barrier work. Traffic should use next entrance ramp.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound frontage road of I-410, entrance ramp closure, and right mainlane closure from Perrin Beitel to Austin Highway (Loop 368) for striping and barrier work. Traffic should follow detour signs.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (2) on eastbound mainlane of I-410 from Austin Highway (Loop 368) to Randolph Boulevard for barrier work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (2) on eastbound mainlanes of I-410 from Starcrest Drive to Austin Highway (Loop 368) for barrier setting.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound frontage road and exit ramp closure of I-410 from Randolph Boulevard to Perrin Beitel for drilled shaft work. Traffic to use next exit ramp.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (2) on westbound I-410 mainlanes from I-35 to Austin Highway (Loop 368) for cap and barrier work.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple lane closures (3) on westbound mainlanes and exit ramp closure of I-410 from I-35 to Perrin Beitel for striping and barrier work. Traffic should use next exit ramp.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Entrance ramp closure on westbound frontage road and exit ramp closure of I-410 to Austin Highway (Loop 368) for barrier work. Traffic should follow detour signs.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Multiple left lane closures (2) and entrance ramp closure on eastbound frontage road of I-410 from Nacogdoches Road to Harry Wurzbach Road for striping and barrier work. Traffic should use next entrance ramp.
  • Sunday, September 10 until Saturday, September 16. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound frontage road of I-410, entrance ramp closure, and exit ramp closure from Harry Wurzbach Road to Starcrest Drive for striping and barrier work. Traffic should use prior entrance and exit ramps. 

FM 1535 – N.W. Military Highway

  • Monday, September 11 until Friday, September 15. 7 a.m. to 6 p.m. Alternating lane closures, in both directions, from Loop 1604 to Huebner Rd. for curb and sidewalk installation. 

PA 1502 – Wurzbach Parkway

  • Current until Friday, September 22. 8 p.m. to 5 a.m. Alternating lane closures, in both directions, from N.W. Military Highway to Wetmore Rd. for milling and paving operations.
  • Sunday, September 10. 6 a.m. to 5 p.m. Full closure of the intersection at Nacogdoches Rd. for utility work. 

SH 151 – West San Antonio/Bexar County

  • Monday, September 11 until Friday, September 22. 9 a.m. to 3 p.m. Alternating lane closures on the westbound frontage road from Ingram Rd. to Loop 410 for excavation.
  • Current until Wednesday, September 13. 9 a.m. to 3 p.m. Alternating lane closures on the westbound frontage road from Potranco Rd. to Ingram Rd. for excavation.
  • Sunday, September 10 until Tuesday, September 12. 9 p.m. to 5 a.m. Westbound turnaround to Ingram Rd. closed for bore installation.
  • Tuesday, September 12 until Friday, September 15. 9 a.m. to 3 p.m. Turnarounds closed in both directions at Hunt Ln. for drilling operations.
  • Wednesday, September 13 until Friday, September 22. 9 a.m. to 3 p.m. Single lane closure on the westbound frontage road from Ingram Rd. to Potranco Rd. for conduit installation.
  • Monday, September 11 until Friday, September 22. 9 a.m. to 3 p.m. Single lane closure on the westbound frontage road from Loop 410 to Ingram Rd. for conduit work.