The bridge beams work is discussed in yesterday's post. Today we'll talk about the rest of the road.
We've got electricians and utility crews working on a variety of tasks along the parkway, including the intersections of West Avenue and Wurzbach Parkway and at Jones-Maltsberger and Wurzbach Parkway. We've also got crews building drain inlets along the frontage roads of Hwy. 281.
On the east end of the parkway, Texas Sterling Construction crews are focusing on the Mud Creek area and finishing work at the intersection of Starcrest and Wurzbach. The eastern segment is still on track to finish this fall.