Loop 1604 – North Central San
Antonio
- Saturday, June 13 until Monday, June 15. Weekend closure 7 a.m. until 5 a.m. Alternating eastbound mainlane closure of the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work.
- Sunday, June 14 until Thursday, June 18. 8 a.m. to 5 p.m. Eastbound frontage road lane closure from Redland Rd. to Bulverde Rd. for curb pouring.
- Sunday, June 14 until Thursday, June 18. 7 p.m. to 6 a.m. Westbound frontage road lane closure from Bulverde Rd. to Redland Rd.
- Sunday, June 14 until Thursday, June 18. 7 p.m. to 6 a.m. Alternating mainlane closures, in both directions, from Redland Rd. to Green Mountain Rd. for multibeam guard fence replacement.
- Sunday, June 14 until Friday, June 19. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure of the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
- Monday, June 15. 9 a.m. to 4 p.m. Westbound frontage road single lane closure from 1,600 feet east of Lockhill Selma Rd. and Lou Mel Rd for communication line placement.
- Monday, June 15 until Friday, June 19. Nightly 9 p.m. until 5 a.m. Left lane westbound frontage road closure from the US 281 north exit ramp to the northbound US 281 frontage road.
- Saturday, June 20 until Monday, June 22. Full weekend closure 3 a.m. until 5 a.m. Full eastbound mainlane closure of the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
- Saturday, June 20 until Monday, June 22. Full weekend closure 3 a.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
Loop 1604 – Northeast San Antonio
- Sunday, June 14 until Friday, June 19. 8 p.m. to 5 a.m. Single mainlane closures, in both directions, from Green Mountain Rd. to I-35 Cloverleaf ramp for pavement work.
- Sunday, June 14 until Friday, June 19. 8 p.m. to 5 a.m. Single mainlane closures, in both directions, from Green Mountain Rd. to I-35 Cloverleaf ramp for guardrail and sign improvements.
- Monday, June 15. 9 a.m. to 3 p.m. Single westbound mainlane closure from Judson Rd. to O’Connor Rd. for bridge rail replacement.
- Thursday, June 18 until Friday, June 19. 9 a.m. to 4 p.m. Single eastbound frontage road lane closure from Bandera Rd. to Hausman Rd. to lay hot mix
- None scheduled.
Loop 1604 – Far East San Antonio
- Friday, June 12 until Monday, June 15. 7 p.m.
to 6 a.m. Closure of southbound to northbound turnaround lane at Kitty
Hawk Rd. for construction and traffic switch.
Loop 1604 – South San Antonio
- None scheduled.
- Friday, June 12 until Monday, June 15. Full weekend closure 9 p.m. until 5 a.m. Full northbound frontage road closure from Loop 1604 to Sonterra Boulevard for drainage work. DETOUR: Turn left on the southbound frontage road, take the turnaround at Donella Drive and use the Donella Drive entrance ramp.
- Saturday, June 13 until Monday, June 15. Weekend closure 7 a.m. until 5 a.m. Northbound mainlane closure from the north- to southbound turnaround at Stone Oak/Tournament Players Club (TPC) Parkway for concrete paving. DETOUR: Use the turnaround north of Stone Oak/Tournament Players Club (TPC) Parkway.
- Saturday, June 13 until Monday, June 15. Weekend closure 7 a.m. until 5 a.m. Left turn lane northbound mainlane closure at Stone Oak/Tournament Players Club (TPC) Parkway both north- to westbound turn lanes for bridge work. DETOUR: Use the turnaround north of Stone Oak/Tournament Players Club (TPC) Parkway.
- Saturday, June 13 until Monday, June 15. Weekend closure 7 a.m. until 5 a.m. Left turn lane southbound mainlane closure at Stone Oak/Tournament Players Club (TPC) Parkway both south- to eastbound turn lanes for concrete paving. DETOUR: Use the turnaround at Evans Road.
- Saturday, June 13 until Monday, June 15. Weekend closure 7 a.m. until 5 a.m. Right/center mainlane closure from Evans Road to Encino Rio.
- Monday, June 15 until Friday, June 19. Nightly 9 p.m. until 5 a.m. Full southbound frontage road closure at Loop 1604 for direct connector work. DETOUR: Turn right on the westbound frontage road, take the turnaround at Stone Oak Parkway and turn right on the southbound frontage road.
- Monday, June 15 until Friday, June 19. Nightly 9 p.m. until 5 a.m. Northbound mainlane closure from the north- to southbound turnaround at Encino Rio for bridge work. DETOUR: Use the turnaround at Evans Road. Closure will not happen concurrently with other turnaround closures in the same direction.
- Monday, June 15 until Friday, June 19. Nightly 9 p.m. until 5 a.m. Northbound mainlane closure from the north- to southbound turnaround at Evans Road for bridge work. DETOUR: Use the turnaround at Stone Oak/Tournament Players Club (TPC) Parkway. Closure will not happen concurrently with other turnaround closures in the same direction.
- Monday, June 15 until Friday, June 19. Nightly 9 p.m. until 5 a.m. Northbound mainlane closure from the north- to southbound turnaround at Stone Oak/Tournament Players Club (TPC) Parkway for bridge work. DETOUR: Use the turnaround north of Stone Oak/Tournament Players Club (TPC) Parkway. Closure will not happen concurrently with other turnaround closures in the same direction.
- Monday, June 15 until Friday, June 19. Nightly 9 p.m. until 5 a.m. Southbound mainlane closure from the south- to northbound turnaround at Stone Oak/Tournament Players Club (TPC) Parkway for bridge work. DETOUR: Use the turnaround at Evans Road. Closure will not happen concurrently with other turnaround closures in the same direction.
- Monday, June 15 until Friday, June 19. Nightly 9 p.m. until 5 a.m. Southbound mainlane closure from the south- to northbound turnaround at Evans Road for bridge work. DETOUR: Use the turnaround at Encino Rio. Closure will not happen concurrently with other turnaround closures in the same direction.
- Monday, June 15 until Friday, June 19. Nightly 9 p.m. until 5 a.m. Left turn lane northbound mainlane closure at Evans Road both north- to westbound turn lanes for bridge work. DETOUR: Use the turnaround at Stone Oak/Tournament Players Club (TPC) Parkway. Closure will not happen concurrently with other turnaround closures in the same direction.
- Monday, June 15 until Friday, June 19. Nightly 9 p.m. until 5 a.m. Left turn lane southbound mainlane closure at Evans Road both south- to eastbound turn lanes for bridge work. DETOUR: Use the turnaround at Encino Rio. Closure will not happen concurrently with other turnaround closures in the same direction.
- Monday, June 15 until Friday, June 19. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Marshall Road for bridge work and safety enhancements.
- Monday, June 15 until Friday, June 19. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for bridge work and safety enhancements.
- Monday, June 15 until Friday, June 19. Nightly 9 p.m. until 5 a.m. Alternating southbound frontage road closure from Sonterra Boulevard to Loop 1604 for concrete paving.
- Saturday, June 20 until Monday, June 22. Full weekend closure 3 a.m. until 5 a.m. Full northbound mainlane closure from the frontage road exit ramp to the Sonterra Boulevard entrance ramp. DETOUR: Take the frontage road exit ramp and use the Sonterra Boulevard entrance ramp.
- Saturday, June 20 until Monday, June 22. Weekend closure 3 a.m. until 5 a.m. Full southbound frontage road closure at Loop 1604 for direct connector work. DETOUR: Turn right on the westbound frontage road, take the turnaround at Stone Oak Parkway and turn right on the southbound frontage road.
- Saturday, June 20 until Monday, June 22. Weekend closure 3 a.m. until 5 a.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for bridge work and safety enhancements.
- Saturday, June 13 until Monday June 15. Weekend closure 7 a.m. until 5 a.m. Right lane westbound crossing closure at US 281 for bridge work.
- None scheduled.
I-10 – Northwest San Antonio/Bexar County/Kendall
County/Kerr County
- Current until Friday, June
26. Nightly 9 p.m. to 5 a.m. Full southbound mainlane closure from Ralph
Fair Rd. to La Cantera Parkway for outside shoulder repair. DETOUR:
Traffic take Exit 550 Ralph Fair Rd./Boerne Stage Rd. onto the eastbound
frontage road through Ralph Fair Rd. intersection, pass Boerne Stage Rd.
intersection, and re-enter the eastbound mainlanes one mile east of Camp
Bullis Rd.
- Monday, June 15 until
Tuesday, June 16. 9 p.m. to 5 a.m. Frontage road closure, in both
directions, at the Balcones Creek Turnaround for bridge deck pour.
- Sunday,
June 28. 7 a.m. to 12 p.m. Full mainlane and frontage road closure at
Heuremann Rd. to allow for CPS to transfer overhead lines to new poles.
- Sunday,
June 28. 7 a.m. to 12 p.m. Westbound mainlane frontage road lane closure
from 0.5 miles west of Camp Bullis Rd. to 0.8 miles west of Camp Bullis
Rd. for pole placement.
- Sunday,
June 28 until Friday, June 3. 9 p.m. to 5 a.m. Westbound mainlane closure
from La Cantera Parkway to Ralph Fair Rd (FM 3351) for the removal of
portable concrete traffic barrier.
- Monday,
July 5 until Friday, July 17. 9 a.m. to 5 p.m. Eastbound mainlane closure
from Ralph Fair Rd. (FM 3351) to La Cantera Parkway for the removal of
portable concrete traffic barrier.
- Friday, June 12 until Monday, June 14. Weekend closure from 9 p.m. Friday to 5 a.m. Monday. Alternating eastbound I-10 mainlane closures between Ackerman and Foster for eastbound traffic switch.
- Saturday, June 13. East and westbound lane closures from 5 a.m. to 9 p.m. Alternating lane closures between Loop 1604 and Pfeil Road for east and westbound traffic switch.
- Sunday, June 14. FM 1516 intersection closed from 8 p.m. to 5 a.m. for bridge concrete pour. DETOUR: Northbound FM 1516 traffic can use Loop 1604 turnaround. Southbound FM 1516 traffic can use Woodlake Parkway turnaround.
- Sunday, June 14 thru Friday, June 19. Nighttime closures from 7 p.m. to 5 a.m. each night. Left lane closed between Loop 1604 and Pfeil Rd. to move construction barrier.
- Current until further notice. Graytown Road bridge at I-10. DETOURS: Graytown Road traffic will use the frontage roads and the Pfeil Road underpass or Loop 1604 turnaround to cross I-10.
- Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
- Current until further notice. Eastbound entrance ramp from Foster Road. DETOUR: Take next entrance ramp east of Woodlake Parkway.
- None
scheduled.
I-35 – Central San Antonio/Northeast San
Antonio/New Braunfels/Comal County
- Current until Saturday, June 27. 9 a.m. to 5
p.m. Single lane closure of northbound frontage road from Schwab Rd. to FM
2252 (Hubertus Rd.) for barrier work.
- Monday, June 15 until Saturday, June 20. 7:30 a.m. to 5:30 p.m. Single northbound frontage road lane closure from Schwab Rd. to Hubertus Rd. for removal of top soil and concrete work.
- Monday, June 15 until Tuesday, June 16. 8 p.m. to 5 a.m. I-35S exit ramp closure from I-10 eastbound for underpass lighting.
I-37 – Central/South San Antonio
- Wednesday, June 17 until Thursday, June 18. 8 p.m. to 5 a.m. Westbound exit ramp closure at I-10W and I-37S for under pass lighting.
I-410 – West San Antonio
- Friday, June 12 until Saturday June 13. 8 p.m.
to 5 a.m. Alternating mainlane closures, in both directions, from
northbound mainlane Marbach Rd. exit to Marbach Rd. for equipment staging.
- Current until Monday, June 15. Nightly 8 p.m.
to 5 a.m. Alternating mainlane closures, in both directions, from Marbach
Rd. to Culebra Rd. for barrier installation.
- Current until Monday, June 15. Daily 9 a.m. to
3 p.m. Alternating frontage road closures, in both directions, from
Marbach Rd. to Ingram Rd., including the Military Dr. turnarounds, for
wall and pipe work.
- Current until Monday, June 15. Daily 9 a.m. to
3 p.m. Single lane closure on southbound frontage road from NW Crossroads
to Military Dr. to remove concrete riprap.
- Wednesday, June 17 until Monday, June 22. 9
a.m. to 4 p.m. Northbound frontage road single lane closure from Meadow
Bend Dr. to Tom Slick Park for transfer of communication lines on existing
poles.
- Current until Friday, June 26. Nightly, 8 p.m.
to 5 a.m. Multiple closures from US-90 to SH 151 to stage equipment:
southbound frontage road from US-90 to Marbach Rd.; southbound mainlane
off-ramp to Marbach Rd.; and southbound frontage road on-ramp from US-90.
DETOUR: Traffic heading to SH 151 coming from Loop 410 northbound
mainlanes will detour to exit 7 (Marbach Rd.) and continue on Loop 410
northbound frontage road to SH 151.
- Current until Friday, June 26. Nightly 8 p.m.
to 5 a.m. Multiple closures from US-90 to Marbach Rd. for equipment
staging: southbound frontage road from Marbach Rd. to US-90; southbound
mainlane off-ramp to east US-90; and southbound frontage road on-ramp from
Marbach Rd. DETOUR: Traffic coming from Loop 410 southbound mainlanes will
detour to Valley-Hi off-ramp and continue on Loop 410 southbount frontage
road to take the turnaround to Loop 410 northbound frontage road and
continue on Loop 410 frontage road to US-90 or Marbach Rd.
- Current until Friday, June 26. Nightly 8 p.m.
to 5 a.m. Multiple closures from SH 151 to Marbach Rd. for equipment
staging: southbound frontage road from SH 151 to Marbach Rd.; southbound
mainlane off-ramp to Marbach Rd.; and southbound frontage road on-ramp
from SH 151. DETOUR: Traffic coming from Loop 410 southbound mainlanes
will detour to US-90 off-ramp, continue to Loop 410 southbound frontage
roads and take the SB/EB cloverleaf and continue on Loop 410 northbound
frontage road to Marbach Rd.
- Current until Friday, June 26. Nightly 8 p.m.
to 5 a.m. Multiple lane closures from SH 151 to Marbach Rd. for equipment
staging: southbound frontage road from US-90 to Marbach Rd.; southbound
mainlane off-ramp to Marbach Rd.; southbound frontage road on-ramp from
US-90. DETOUR: Traffic traveling to SH 151 coming from Loop 410 northbound
mainlanes will detour to exit 7 (Marbach Rd.) and continue to Loop 410
northbound frontage road to SH 151.
- Monday, June 15 until Thursday, July 2. 8 p.m.
to 5 a.m. Alternating mainlane closures at Marbach Rd. bridge for
equipment staging and the removal of concrete islands.
US 90 – West San Antonio
- Monday, June 15 until Friday, June 19. 9 a.m.
to 3 p.m. Single frontage road lane closure, in both directions, from West
Military Dr. to SW 36th St. for guardrail improvements.
SH 151 – West San Antonio
- Current
until Monday, June 15. Nightly, 8 p.m. to 5 a.m. Full westbound mainlane
closure from Loop 410 exit to Ingram Rd for bent work. DETOUR: Traffic
will be detoured to the frontage road through the 410/151 intersection to
take the next entrance ramp to SH 151 westbound.
- Current until Monday, June 15. Daily, 9 a.m. to 3 p.m. Alternating
mainlane closures, in both directions, from Loop 410 to Ingram Rd for bent
work.
- Current until Monday, June 15. Daily 9 a.m. to 3 p.m. Alternating
frontage road closures, in both directions, from Loop 410 to Ingram Rd.
Eastbound and westbound turnarounds will be closed 24-hours. DETOUR:
Eastbound and westbound turnaround will detour to the 410/151 intersection
to take two left turns.
- Current until Monday, June 15. Nightly 8 p.m. to 5 a.m. Alternating
lane closures on frontage road, in both directions, from Loop 410 to
Ingram Rd. for bent work. Eastbound and westbound turnarounds will be
closed 24-hours. DETOUR: Eastbound and westbound traffic will detour to
the 410/151 intersection to take two left turns.
SH 16 – Bandera Road
- None scheduled.
FM 3351 –
Ralph Fair Road
- None scheduled.
PA 1502 – Wurzbach Parkway
- City of San Antonio/PWD closure for Hardberger
Park Land Bridge project. Saturday, June 13 until Sunday, June 14. Daily 9 a.m. to 4 p.m. Single
mainlane closure, in both directions, from 0.5 miles from NW Military Dr.
(FM 1535) to 0.25 miles from Blanco Rd. (FM 2696) to allow for
construction haul trucks to enter roadway.
- City of San Antonio/PWD closure for Hardberger
Park Land Bridge project. Monday, June 15 until Friday, June 19. Nightly 9 p.m. to 5 a.m.
Full mainlane closure, in both directions, from NW Military Dr. (FM 1535)
to Blanco Rd. (FM 2696) for bridge decking. DETOUR: Traffic will utilize
West Ave. and Lockhill Selma Rd.
- City of San Antonio/PWD closure for Hardberger
Park Land Bridge project. Monday, June 15 until Friday, June 19. Daily 9 a.m. to 4 p.m.
Single mainlane closure, in both directions, from 0.5 miles from NW
Military Dr. (FM 1535) to 0.25 miles from Blanco Rd. (FM 2696) to allow
for construction haul trucks to enter roadway.
- City of San Antonio/PWD closure for Hardberger
Park Land Bridge project. Friday, June 19 until Sunday, June 21. Nightly 9 p.m. to 5 a.m. Full
mainlane closure, in both directions, from NW Military Dr. (FM 1535) to
Blanco Rd. (FM 2696) for bridge decking. DETOUR: Traffic will utilize West
Ave. and Lockhill Selma Rd.
- Monday, June 15 until Friday, June 19. 9 a.m.
to 5 p.m. Single lane closure, in both directions, from Old Pearsall Rd.
to Rockgate Dr. for concrete mowstrip and sidewalk improvements.
FM 2252 – Nacogdoches Road
- None scheduled.
- Exit ramp from Loop 1604 eastbound closed until
further notice starting Monday, March 16.
SH 218 – Pat Booker Road
- None scheduled.
- None
scheduled.
- None scheduled.
- None scheduled.
Spur 421 –
Bandera Road
- None scheduled.
FM 1976 – Walzem Road/Gibbs Sprawl Road
- Current until further notice. Daily 7 a.m.
until 7 p.m. Alternating southbound lanes between Woodlake Parkway and
Gibbs Sprawl Road for barrier/pavement work (existing seven total lanes
narrowed to three, with one in each direction and a two-way turn lane in
the middle).
- Current until further notice. Full-day
closure. Southbound lane between Toepperwein Road and Walzem Road for
barrier setting work and road rehab work.
- None scheduled.
- Monday, June 15 until Friday, June 19. Single lane closures, in both directions, from Billy Mitchell Blvd. to US Highway 90 for concrete construction and barrier installation.
- None
scheduled.
FM 306 –
New Braunfels/Comal County
- None scheduled.
Loop 337 –
New Braunfels/Comal County
- None
scheduled.
- Sunday,
June 14 until Friday, June 19. 7 p.m. to 5 a.m. Alternating mainlane
closures, in both directions, from Independence Dr. to Woodland Ave. for the
placement of reinforced concrete pipe.
- Sunday, June
14 until Friday, June 19. 7 p.m. to 5 a.m. Alternating mainlane closures,
in both directions, from Independence Dr. to Woodland Ave. for the
placement of reinforced concrete pipe
FM 1863 – Comal County
- None
scheduled.
FM 2673 –
Canyon Lake/Comal County
- None scheduled.
FM 1516 – South Seguin Road/Converse
- None scheduled.
FM 2252 –
Comal County
- None scheduled.
SH 46 – Guadalupe County
- None
scheduled.
FM 78 – Guadalupe County
- None
scheduled.
FM 1518 – Schertz/Cibolo Guadalupe County
- None scheduled.
US 90A – Seguin/Guadalupe County
- None scheduled.
- None scheduled.
Business 123 – South Austin Street/Seguin/Guadalupe
County
- None scheduled.
I-35 – Atascosa County/Frio County
- None scheduled.
US 181 – Floresville/Wilson County
- None scheduled.
US 87 – Wilson County
- None scheduled.
SH 46 – Boerne/Kendall County
- Current until further notice. 9 p.m. until 5
a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for
traffic switch (drivers diverted to the right side for construction access
on the right side; left turn lane remains open).
RM/FM 1376 – Kendall County
- Monday, June 15 until Saturday, June 20. 7
a.m. to 7 p.m. Single lane closure, in both directions, from N. School St.
to 0.5 miles past Wasp Creek Rd. for culvert work and roadway
reconstruction.
- Monday, June 15 until Wednesday, June 17. 7 a.m. to 5 p.m. Single eastbound mainlane closure from Park Place to Chaparral Creek Dr. for sidewalk repairs.
FM 1333 – Atascosa County
- None scheduled.
FM 140 – Atascosa County
- None scheduled.
SH 16 – McMullen County
- None scheduled.
- Monday, June 15 until Friday, June 19. 8 a.m. to 5 p.m. Westbound right lane closure from FM 78 to I-35 for pavement work.
- Current until Tuesday, June 16. Daylight work.
Alternating mainlane and shoulder closures, in both directions, from 1.2
miles east of Kerr/Kimble County Line to 0.5 miles east of Kerr/Kimble
County Line for metal beam guard fence work.
- None scheduled.