Loop 1604 – North Central San Antonio/Bexar County

  • Sunday, November 28 until Friday, December 3. Nightly 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from IH-10 to Blanco Road for barrier setting and striping.
  • Sunday, November 28 until Friday, December 3. Nightly 9 p.m. until 5 a.m. Alternating westbound mainlane closure from Blanco Road to IH-10 for barrier setting and striping.
  • Sunday, November 28 until Friday, December 3. Nightly 9 p.m. until 5 a.m. westbound mainlane exit ramp to IH-10 / 1604 intersection closure for barrier setting and striping.
  • Sunday, November 28 until Friday, December 3. Nightly 9 p.m. until 5 a.m. Alternating northbound Blanco Road closure from Country Club Lane to Huebner Road for barrier setting and temporary pavement.
  • Sunday, November 28 until Friday, December 3. Nightly 9 p.m. until 5 a.m. Alternating southbound Blanco Road closure from Huebner Road to Country Club Lane for barrier setting and temporary pavement.
  • Monday, November 29 until Friday, December 3. Nightly 11 p.m. until 5 a.m. Periodic short term eastbound frontage road lane closure from the Blanco Road exit ramp to the Blanco Road intersection for RW372 Phase 1.
  • Monday, November 29 until Friday, December 3. Nightly 11 p.m. until 5 a.m. Periodic short term westbound frontage road lane closure from the Blanco Road exit ramp to the Blanco Road intersection for RW372 Phase 1.
  • Monday, November 29 until Friday, December 3. Nightly 11 p.m. until 5 a.m. Periodic short term eastbound mainlane closure from the Blanco Road exit ramp to the Blanco Road intersection for RW372 Phase 1.
  • Monday, November 29 until Friday, December 3. Nightly 11 p.m. until 5 a.m. Periodic short term westbound mainlane closure from the Blanco Road exit ramp to the Blanco Road intersection for RW372 Phase 1.
  • Monday, November 29 until Friday, December 3. Nightly 11 p.m. until 5 a.m. Periodic short term northbound Blanco Road closure at the Loop 1604 intersection for RW372 Phase 1.
  • Monday, November 29 until Friday, December 3. Nightly 11 p.m. until 5 a.m. Periodic short term southbound Blanco Road closure at the Loop 1604 intersection for RW372 Phase 1. 

Loop 1604 – North West San Antonio/Bexar County

  • Sunday, November 21 until Saturday, December 4. Weeknights 9 p.m. until 5 a.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for barrier setting.
  • Sunday, November 21 until Saturday, December 4. Weeknights 9 p.m. until 5 a.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for barrier setting.
  • Sunday, November 21 until Saturday, December 4. Weeknights 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Bandera Road (SH 16) to IH-10 for barrier setting.
  • Sunday, November 21 until Saturday, December 4. Weeknights 9 p.m. until 5 a.m. Alternating westbound mainlane closure from IH-10 to Bandera Road (SH 16) for barrier setting.
  • Monday, October 18 until Tuesday, November 30. Weekdays 9 a.m. until 3 p.m. eastbound to westbound turnaround closure at Loop 1604 and Kyle Seale Parkway for bridge widening.
  • Monday, October 18 until Tuesday, November 30. Weekdays 9 a.m. until 3 p.m. westbound to eastbound turnaround closure at Loop 1604 and Kyle Seale Parkway for bridge widening.
  • Thursday, November 18 until Monday, December 6. Weekdays 9 a.m. until 5 p.m. eastbound to westbound turnaround closure at Loop 1604 and Hausman Road for bridge widening.
  • Thursday, November 18 until Monday, December 6. Weekdays 9 a.m. until 5 p.m. westbound to eastbound turnaround closure at Loop 1604 and Hausman Road for bridge widening. 

Loop 1604 – North East San Antonio/Bexar County

I-10 – East San Antonio/Bexar County/Seguin/Guadalupe County 

  • Current until Friday, December 3. 9 a.m. to 4 p.m. Single lane closure on the westbound frontage road from Foster Rd. to FM 1516 for utility work.
  • Current until further notice. Graytown Road closed at I-10. DETOURS: Graytown Road traffic may use the frontage road and the Pfeil Road underpass or Loop 1604 turnaround to cross I-10. 

I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

  • Monday, November 29 until Friday, December 3. 9 a.m. to 4 p.m. Single lane closure on the southbound frontage road from Forum Parkway to Utopia Boulevard for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 a.m. to 4 p.m. Single lane closure on the southbound frontage road from Forum Parkway to Utopia Boulevard for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 a.m. to 4 p.m. Single lane closure on southbound frontage road from Utopia Boulevard to Retama Parkway for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 a.m. to 4 p.m. Single lane closure on southbound frontage road from Utopia Boulevard to Retama Parkway for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 a.m. to 4 p.m. Single lane closure on southbound frontage road from Retama Parkway to N Evans Road for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 a.m. to 4 p.m. Single median closure of the southbound frontage road and the Loop 1604 westbound frontage road, between Gateway Boulevard and I-35 Junction for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 a.m. to 4 p.m. Single southbound frontage road lane closure from Walzem Road to Crestwind Drive for geotechnical and drilling work. 

I-410 – Northeast San Antonio

  • Monday, November 29 until Friday, December 3. 8 a.m. to 7 p.m. Shoulder closure on the westbound frontage road from the I-410 Loop Interchange to Perrin Beitel Road for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 a.m. to 4 p.m. Shoulder closure eastbound frontage road from Goldstar Drive to Quail Creek Drive for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 a.m. to 4 p.m. Single lane closure eastbound frontage road from Goldstar Drive to Quail Creek Drive for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 a.m. to 4 p.m. Shoulder closure on eastbound frontage road from Perrin Beitel Road to Vicar Drive for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 a.m. to 4 p.m. Shoulder closure on eastbound frontage road from Vicar Drive to the I-410 Loop interchange with Austin Highway for geotechnical and drilling work. 
  • Monday, November 29 until Friday, December 3. 9 a.m. to 4 p.m. Various westbound median closures between the I-410 frontage road and I-410, between the I-410 Loop Interchange and Perrin Beitel Road entrance ramp for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 a.m. to 4 p.m. Single lane closure on the westbound frontage road between the I-410 Interchange and I-410 for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 a.m. to 4 p.m. Shoulder closure on the westbound frontage road from Austin Highway to the I-410 frontage road before joining the I-410 Loop for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 a.m. to 4 p.m. Single westbound frontage road closure from Perrin Creek Road to Perrin Beitel Road for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 a.m. to 4 p.m. Single lane closure on the southbound frontage road from Whirlwind Drive to Walzem Road for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 a.m. to 4 p.m. Single lane closure on the westbound frontage road from Brookhaven Drive to Sage Brush Lane for geotechnical and drilling work.
  • Monday, November 29 until Wednesday, December 3. 9 p.m. to 5 a.m. Single lane closure eastbound from Goldstar Drive to Perrin Beitel Road for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Single lane closure eastbound from Goldstar Drive to Quail Creek Drive for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Various eastbound frontage road closures (including entrance ramp to I-410) from Goldstar Drive to Perrin Beitel Road for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 a.m. to 4 p.m. Westbound shoulder closure from Fratt Road to Ellis Drive for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Single mainlane eastbound closure from N New Braunfels Avenue to Nacogdoches Road for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Entrance ramp closure to I-410 eastbound and single lane closure eastbound from Cripple Creek Street to Ira Lee Road for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Single lane closure eastbound from Ira Lee Road to Silverstar Street for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Single lane closure eastbound from Goldstar Drive to Quail Creek Drive for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Single eastbound lane closure from Fratt Road to Interchange Parkway for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Eastbound entrance ramp closure and frontage road shoulder closure from Quail Creek Drive to Perrin Beitel Road for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Eastbound turnaround closure to westbound frontage road between Quail Creek Drive and Perrin Beitel Road for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Westbound turnaround closure to eastbound frontage road between Perrin Beitel Road and Vicar Drive for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Various eastbound frontage road lane closures (including I-410 entrance ramp) from Perrin Beitel Road to Vicar Drive for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Exit ramp closure connecting eastbound I-410 to southbound Austin Highway, as well as shoulder closures on both sides of the ramp for geotechnical and drilling work. 
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Single lane closure on the entrance ramp that connects Austin Highway to the I-410 westbound frontage road between Cross Creek Drive and Vicar Drive for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Entrance ramp closure connecting Austin Highway to I-410 eastbound between Cross Creek Drive and Fratt Road for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Single northbound lane closure on Austin Highway to I-410 eastbound frontage road from Cross Creek Drive to Fratt Road for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Single closure on the eastbound frontage road from Silverstar Drive to Starcrest Drive for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Single closure on the eastbound frontage road from Goldstar Drive to Quail Creek Drive for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Single lane closure on the westbound from Perrin Beitel Road to Starcrest Drive for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 a.m. to 4 p.m. Various median closures westbound between the I-410 frontage road and the I-410 exit ramp, between the I-410 Loop Interchange and Perrin Beitel Road for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Various median closures westbound between the I-410 frontage road and the I-410 exit ramp, between the I-410 Loop Interchange and Perrin Beitel Road for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Westbound frontage road ramp closure from Perrin Creek Road to Perrin Beitel Road for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Mandatory left turn lane closure on Austin Highway to westbound I-410 frontage road for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Single lane closure on the westbound mainlanes from Brookhaven Drive to Sage Brush Lane for geotechnical and drilling work.
  • Monday, November 29 until Friday, December 3. 9 p.m. to 5 a.m. Single lane closure on the westbound mainlanes from Post Oak Road to Norwich Drive for geotechnical and drilling work. 

I-410 – West San Antonio

  • Current until Monday, November 29. 9 a.m. to 3 p.m. Alternating lane closures on the frontage roads, in both directions, from Marbach Rd. to Bandera Rd. for bridge work.
  • Current until Monday, November 29. 8 p.m. to 5 a.m. Full closure of the northbound frontage road from Meadow Breeze Dr. to SH 151 for bridge work.
  • Current until Monday, November 29. 8 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from Marbach Rd. to Ingram Rd. for bridge work.
  • Current until Monday, November 29. 8 p.m. to 5 a.m. Full closure of mainlanes, in both directions, from W. Military Dr. to Marbach Rd. for bridge work.
  • Current until Monday, December 6. 8 p.m. to 5 a.m. Full closure of the Culebra Rd. intersection at Loop 410 for bridge work.
  • Monday, November 29 until Monday, December 6. 8 p.m. to 5 a.m. Full mainlane closures, in both directions, from W. Military Dr. to Marbach Rd. for bridge work.
  • Monday, November 29 until Monday, December 6. 9 a.m. to 3 p.m. Alternating frontage road closures, in both directions, from Marbach Rd. to Bandera Rd. for bridge work.
  • Monday, November 29 until Monday, December 6. 8 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from Marbach Rd. to Ingram Rd. for bridge work.
  • Monday, November 29 until Monday, December 6. 8 p.m. to 5 a.m. Full closure of the northbound frontage road from Meadow Breeze Dr. to SH 151 for bridge work. 

I-410 – Southwest San Antonio

  • Current until Friday, December 31. Left lane closure on the northbound frontage road from Ray Ellison Blvd. to Medina Base Rd. for roadway rehabilitation.
  • Current until December 2021. Left lane closed on the southbound frontage road at Valley Hi.
  • Current until September 2022. Northbound frontage road turnaround to southbound frontage road closed at Medina Base Rd. 

SH 151 – West San Antonio

  • Monday, November 29 until Monday, December 6. 8 p.m. to 5 a.m. Full closure of the eastbound frontage road from Cable Ranch Rd. to Loop 410 for bridge work.
  • Monday, November 29 until Monday, December 6. 8 p.m. to 5 a.m. Full closure of the westbound frontage road at Loop 410 for bridge work.
  • Monday, November 29 until Monday, December 6. 8 p.m. to 5 a.m. Alternating full closures on the mainlanes, in both directions, at Loop 410 for bridge work. 

PA 1502 – Wurzbach Parkway  

  • Sunday, November 28 9 p.m. until Friday, December 3 4 p.m. Single westbound right lane closure from Elm Creek to Lockhill Selma for barrier shifting. 

I-10 – Kendall County

  • Current until December 2021. Full closure of the eastbound exit 540 ramp to SH 46/Bandera Rd. for roadway construction. DETOUR: Traffic will be diverted to the US-87 exit ramp and use the Scenic Loop Rd. turnaround. 

SH 123 – Guadalupe County

  • Monday, December 6 until Friday, December 10. 8 a.m. to 5:30 p.m. Alternating lane closures, in both directions, near Big Oaks Rd. for striping work.