Friday, February 25

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

 

Loop 1604 – North East San Antonio/Bexar County

  • Monday, February 28. 9 a.m. to 3 p.m. Westbound exit ramp to I-35 closed for bridge repairs.
  • Monday, February 28. 9 a.m. to 3 p.m. Full closure of the eastbound exit ramp to I-35 for bridge deck repairs.
  • Tuesday, March 1. 9 a.m. to 3 p.m. Full closure of the eastbound exit ramp to I-35 for asphalt work. 

Loop 1604 – North West San Antonio/Bexar County

  • Sunday, February 27 until Friday, March 11. Weeknights 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Bandera Road (SH 16) to IH-10 for barrier setting.
  • Sunday, February 27 until Friday, March 11. Weeknights 9 p.m. until 5 a.m. Alternating westbound mainlane closure from IH-10 to Bandera Road (SH 16) for barrier setting.
  • Sunday, February 27 until Friday, March 11. Weeknights 9 p.m. until 5 a.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for barrier setting.
  • Sunday, February 27 until Friday, March 11. Weeknights 9 p.m. until 5 a.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for barrier setting.
  • Sunday, February 27 until Friday, March 11. Weeknights 9 p.m. until 5 a.m. Eastbound mainlane full closure from Bandera Road (SH 16) to Kyle Seale Parkway for bridge construction: caps, beams and rail demo.
  • Sunday, February 27 until Friday, March 11. Weeknights 9 p.m. until 5 a.m. Westbound mainlane full closure from Kyle Seale Parkway to Bandera Road (SH 16) for bridge construction: caps, beams and rail demo.
  • Sunday, February 27 until Friday, March 11. Weeknights 9 p.m. until 5 a.m. Northbound Hausman Road full closure at the Loop 1604 intersection for bridge construction: caps, beams and rail demo.
  • Sunday, February 27 until Friday, March 11. Weeknights 9 p.m. until 5 a.m. Southbound Hausman Road full closure at the Loop 1604 intersection for bridge construction: caps & beams.
  • Sunday, February 27 until Friday, March 11. Weeknights 9 p.m. until 5 a.m. Eastbound to westbound turnaround full closure at Loop 1604 and Hausman Road for bridge construction: caps & beams.
  • Sunday, February 27 until Friday, March 11. Weeknights 9 p.m. until 5 a.m. Westbound to eastbound turnaround full closure at Loop 1604 and Hausman Road for bridge construction: caps & beams.
  • Monday, February 28 until Monday, March 14. Weekdays 9 a.m. until 3 p.m. Eastbound frontage road outside lane closure from Hausman Road to John Peace Boulevard /La Cantera Parkway for sidewalk construction.
  • Monday, February 28 until Monday, March 14. Weekdays 9 a.m. until 5 p.m. eastbound to westbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, February 28 until Monday, March 14. Weekdays 9 a.m. until 5 p.m. westbound to eastbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, February 28 until Monday, March 14. Weekdays 9 a.m. until 5 p.m. eastbound to westbound turnaround closure at Loop 1604 and Hausman Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, February 28 until Monday, March 14. Weekdays 9 a.m. until 5 p.m. westbound to eastbound turnaround closure at Loop 1604 and Hausman Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, February 28 until Monday, March 14. Weekdays 9 a.m. until 5 p.m. eastbound to westbound turnaround closure at Loop 1604 and Kyle Seale Parkway for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, February 28 until Monday, March 14. Weekdays 9 a.m. until 5 p.m. westbound to eastbound turnaround closure at Loop 1604 and Kyle Seale Parkway for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, February 28 until Monday, March 14. Weekdays 9 a.m. until 5 p.m. eastbound to westbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, February 28 until Monday, March 14. Weekdays 9 a.m. until 5 p.m. westbound to eastbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time. 

Loop 1604 – North Central San Antonio/Bexar County

US 281 – North San Antonio/Bexar County

  • Saturday, February 26 until Monday, February 28. Nightly 9 p.m. until 5 a.m. Alternating northbound frontage road closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for signage installation and lane striping.
  • Saturday, February 26 until Monday, February 28. Nightly 9 p.m. until 5 a.m. Alternating southbound frontage road closure from Stone Oak Parkway to Loop 1604 for signage installation and lane striping.
  • Sunday, February 27 until Monday, February 28. Overnight 9 p.m. until 5 a.m. Alternating northbound frontage road closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for signage installation and lane striping.
  • Sunday, February 27 until Monday, February 28. Overnight 9 p.m. until 5 a.m. Alternating southbound frontage road closure from Stone Oak Parkway to Loop 1604 for signage installation and lane striping.
  • Monday, February 28 until Thursday, March 3. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for signage installation and lane striping.
  • Monday, February 28 until Thursday, March 3. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Stone Oak Parkway to Loop 1604 for signage installation and lane striping.
  • Monday, February 28 until Friday, March 4. Continuous 9 p.m. until 3 p.m. Alternating northbound frontage road closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for signage installation and lane striping.
  • Monday, February 28 until Friday, March 4. Continuous 9 p.m. until 3 p.m. Alternating southbound frontage road closure from Stone Oak Parkway to Loop 1604 for signage installation and lane striping.
  • Saturday, March 5 until Monday, March 7. Nightly 9 p.m. until 5 a.m. Alternating northbound frontage road closure from Loop 1604 to Stone Oak/Tournament Players Club (TPC) Parkway for signage installation and lane striping.
  • Saturday, March 5 until Monday, March 7. Nightly 9 p.m. until 5 a.m. Alternating southbound frontage road closure from Stone Oak Parkway to Loop 1604 signage installation and lane striping. 

US 90 – Central San Antonio/Bexar County

  • Wednesday, March 2 until Friday, March 4. 8 p.m. to 5 a.m. Full closure of the westbound exit ramp to southbound I-35 for installation of metal beam guard fence. 

I-10 – East San Antonio/Bexar County/Seguin/Guadalupe County 

  • Sunday, February 27. 7 a.m. to 5 p.m. Full closure of mainlanes, in both directions, at FM 1518 for utility work. Closures will be in 15 minute intervals.
  • Current until further notice. Graytown Road closed at I-10. DETOURS: Graytown Road traffic may use the frontage road and the Pfeil Road underpass or Loop 1604 turnaround to cross I-10. 

I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

  • Sunday, February 27 until Friday, March 4. 9 p.m. to 5 a.m. Northbound exit ramp (168) closure from Joe Lee Street to North Weidner Road for geotechnical and drilling work. Traffic should use the O’Connor Road exit ramp (169). Follow the detour signs.
  • Sunday, February 27 until Friday, March 4. 9 p.m. to 5 a.m. Turnaround closure from north to southbound frontage road from Joe Lee Street to North Weidner Road for geotechnical and drilling work.
  • Sunday, February 27 until Friday, March 4. 9 p.m. to 5 a.m. Turnaround closure from south to northbound frontage road from North Weidner Road to Bomar Lane for geotechnical and drilling work.
  • Sunday, February 27 until Friday, March 4. 9 p.m. to 5 a.m.  O’Connor Road exit ramp (169) closure on northbound I-35 and single lane closure on the I-35 northbound frontage road from Wayland Way to O’Connor Road for geotechnical and drilling work. Drivers must use the Weidner Road exit (168). Follow the detour signs.
  • Sunday, February 27 until Friday, March 4. 9 p.m. to 5 a.m. Northbound entrance ramp closure and single frontage road lane closure from O’Connor Road to Bladau Bishop for geotechnical and drilling work. Traffic should use the Toepperwein Road entrance ramp. Follow the detour signs.
  • Sunday, February 27 until Friday, March 4. 9 p.m. to 5 a.m.  Northbound exit ramp (170B) and single lane frontage road lane closure from Judson Road to Toepperwein Road for geotechnical and drilling work. Drivers must use Judson Road (170A) exit ramp. Follow the detour signs.
  • Sunday, February 27 until Friday, March 4. 9 p.m. to 5 a.m.  Northbound exit ramp (171) to Pat Booker Road and single lane closure on the I-35 northbound frontage road from Toepperwein Road to Shin Oak Drive for geotechnical and drilling work. Drivers must use the Toepperwein Road exit (170B). Follow the detour signs.
  • Sunday, February 27 until Friday, March 4. 9 p.m. to 5 a.m. Single lane closure on southbound frontage road from Toepperwein Road to Judson Road for geotechnical and drilling work.
  • Monday, February 28 until Wednesday, March 2. 9 a.m. to 4 p.m. Single lane closure on southbound frontage road from Judson Road exit to Judson Road intersection for wall investigation work.
  • Monday, February 28 until Friday, March 4. 9 a.m. to 4 p.m. Single lane closure on the northbound frontage road from North Weidner Road to O’Connor Road for geotechnical and drilling work.
  • Monday, February 28 until Friday, March 4. 9 a.m. to 4 p.m. Single lane closure on the northbound frontage road of from O’Connor Road to Bladau Bishop for geotechnical and drilling work.
  • Monday, February 28 until Friday, March 4. 9 a.m. to 4 p.m. Single lane closure on the northbound I-35 frontage road from O’Connor Road to Judson Road for geotechnical and drilling work.
  • Monday, February 28 until Friday, March 4. 9 a.m. to 4 p.m. Single lane closure on the northbound frontage road from Pasatiempo Road to Valhalla Road for geotechnical and drilling work.
  • Monday, February 28 until Friday, March 4. 9 a.m. to 4 p.m. Single lane closure on northbound frontage road from Judson Road to Toepperwein Road for geotechnical and drilling work.
  • Monday, February 28 until Friday, March 4. 9 a.m. to 4 p.m. Double lane closure on northbound frontage road from Sandpiper Drive to Shin Oak Drive for geotechnical and drilling work.
  • Monday, February 28 until Friday, March 4. 9 a.m. to 4 p.m. Double lane closure on northbound frontage road from Shin Oak Drive to Pat Booker Road for geotechnical and drilling work.
  • Monday, February 28 until Friday, March 4. 9 a.m. to 4 p.m. Single lane closure on northbound frontage road at Pat Booker Road for geotechnical and drilling work.
  • Monday, February 28 until Friday, March 4. 9 a.m. to 4 p.m. Single lane closure on westbound Pat Booker Road at northbound frontage road for geotechnical and drilling work.
  • Wednesday, March 2 until Friday, March 4. 9 a.m. to 4 p.m. Single lane closure on northbound frontage road from O’Conner Road exit to Bladau Bishop for wall investigation work.
  • Monday, February 28 until Friday, March 4. 9 a.m. to 4 p.m. Single lane closure on northbound frontage road from I-35 Access Road to Converse Road for geotechnical and drilling work.
  • Monday, February 28 until Friday, March 4. 9 a.m. to 4 p.m. Mobile operations on northbound and southbound mainlanes and frontage roads from Walzem Road to FM 3009 for edge drop off measurements.
  • Monday, February 28 until Saturday, March 5. 9 a.m. to 5:30 p.m. Single northbound frontage road lane from FM 2252 to Schwab Rd. for sidewalk, headwall and rail work. 

I-410 – North East San Antonio

  • Sunday, February 27 until Friday, March 4. 9 p.m. to 5 a.m. Turnaround closure from east to westbound frontage road between Quail Creek Drive and Perrin Beitel Road for geotechnical and drilling work.
  • Sunday, February 27 until Friday, March 4. 9 p.m. to 5 a.m. Turnaround closure from west to eastbound frontage road between Perrin Beitel Road and Vicar Drive for geotechnical and drilling work.
  • Sunday, February 27 until Friday, March 4. 9 p.m. to 5 a.m. Mandatory left turn lane closure on Austin Highway to westbound I-410 frontage road between I-35 Frontage Road Loop and NE Interstate 410 Loop for geotechnical and drilling work. Traffic should detour south on Austin Highway to Perrin Creek Road.
  • Sunday, February 27 until Friday, March 4. 9 p.m. to 5 a.m. Single lane closure westbound from Ira Lee Road to Starcrest Drive for geotechnical and drilling work. 
  • Monday, February 28 until Friday, March 4. 9 a.m. to 4 p.m. Mobile operations on eastbound and westbound main lanes and frontage roads from Nacogdoches Road and I-35 for edge drop off measurements.
  • Monday, February 28 until Friday, March 4. 9 a.m. to 4 p.m. Shoulder closure of the eastbound turnaround lane to westbound frontage road between Quail Creek Drive and Perrin Beitel Road for geotechnical and drilling work. 

I-410 – East San Antonio

  • Continuing through Monday, February 21. DAYTIME alternating Northbound I-410 lane closures between Houston Street and I-10 as well as I-10 EB between I-410 and Ackerman Road from 9 a.m. to 5 p.m. each day for pavement repair. 
  • Monday, February 28 through Monday, March 14. Southbound I-410 alternating lane closures between I-10 and Rigsby Avenue from 9 p.m. to 5 a.m. nightly for stripping. Ramps closed as needed when right lane closed. Detour: Southbound I-410 traffic may exit at East Southcross Boulevard, turn around at intersection and return on northbound I-410 frontage road.
  • Current until Monday, March 7. 9 a.m. to 5 p.m. Alternating lane closures on the northbound frontage road from E. Houston St. to Ackerman Rd.  

I-410 – West San Antonio

  • Current until Monday, February 28. 8 p.m. to 5 a.m. Full closure of the northbound frontage road from Meadow Breeze Dr. to SH 151 for bridge work.
  • Current until Monday, February 28. 9 p.m. to 5 a.m. Southbound exit ramp to Marbach Rd. closed for bridge work.
  • Current until Monday, February 28. 8 p.m. to 5 a.m. Full closure of the mainlanes, in both directions, from W. Military Dr. to Marbach Rd. for bridge work.
  • Current until Monday, February 28. 9 a.m. to 3 p.m. Alternating lane closures on the frontage roads, in both directions, from Marbach Rd. to Bandera Rd. for bridge work.
  • Current until Monday, February 28. 8 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from Marbach Rd. to Ingram Rd. for bridge work.
  • Current until Monday, February 28. 8 a.m. to 5 p.m. Alternating closures of the turnarounds at Culebra Rd. for concrete work.
  • Current until Monday, February 28. 8 p.m. to 5 a.m. Southbound exit ramp to Ingram Rd. closed for traffic switch.
  • Current until Monday, February 28. 9 a.m. to 3 p.m. Single southbound mainlane closure from W. Military Dr. to SH 151 for concrete work.
  • Current until Monday, February 28. 8 p.m. to 5 a.m. Full closure of the turnarounds at Ingram Rd. for traffic switch.
  • Current until Monday, February 28. 9 a.m. to 5 p.m. Southbound W. Military Dr. bypass ramp closed for concrete work.
  • Current until Monday, February 28. 8 p.m. to 5 a.m. Double northbound mainlane closure from Ingram Rd. to Culebra Rd. for column work.
  • Monday, February 28 until Wednesday, March 2. 8 p.m. to 5 a.m. Full closure of the southbound frontage road at Ingram Rd. for high mast work.
  • Monday, February 28 until Wednesday, March 2. 8 p.m. to 5 a.m. Full closure of the southbound frontage road from SH 151 to Marbach Rd. for high mast work.
  • Monday, February 28 until Monday, March 7. 8 p.m. to 5 a.m. Southbound exit ramp to Ingram Rd. closed for traffic switch.
  • Monday, February 28 until Monday, March 7. 9 a.m. to 5 p.m. Full closure of the southbound bypass ramp to W. Military Dr. for concrete work.
  • Monday, February 28 until Monday, March 7. 8 p.m. to 5 a.m. Double northbound mainlane closures from Ingram Rd. to Culebra Rd. for column work.
  • Monday, February 28 until Monday, March 7. 9 p.m. to 5 a.m. Full closure of the southbound exit ramp to Marbach Rd. for bridge work.
  • Monday, February 28 until Monday, March 7. 9 a.m. to 3 p.m. Single southbound mainlane closure from W. Military Dr. to SH 151 for concrete work.
  • Monday, February 28 until Monday, March 7. 8 p.m. to 5 a.m. Full closure of the Ingram Rd. intersection at Loop 410 for traffic switch.
  • Monday, February 28 until Monday, March 7. 8 p.m. to 5 a.m. Full closure of the mainlanes, in both directions, from W. Military Dr. to Marbach Rd. for bridge work.
  • Monday, February 28 until Monday, March 7. 9 a.m. to 3 p.m. Alternating frontage road lane closures from Marbach Rd. to Bandera Rd. for bridge work.
  • Monday, February 28 until Monday, March 7. 8 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from Marbach Rd. to Ingram Rd. for bridge work.
  • Monday, February 28 until Monday, March 7. 8 p.m. to 5 a.m. Full closure of the northbound frontage road from Meadow Breeze Dr. to SH 151 for bridge work.
  • Monday, February 28 until Monday, March 7. 8 a.m. to 5 p.m. Alternating full closure of the turnarounds at Culebra Rd. for concrete work. 

I-410 – Southwest San Antonio

  • Current until September 2022. Northbound frontage road turnaround to southbound frontage road closed at Medina Base Rd. 

SH 151 – West San Antonio

  • Current until Monday, February 28. 9 a.m. to 3 p.m. Alternating westbound mainlane closures from W. Military Dr. to Ingram Rd. for pipe installation.
  • Current until Monday February 28. 8 p.m. to 5 a.m. Full closure of the eastbound frontage road from Cable Ranch Rd. to Loop 410 for bridge work.
  • Current until Monday, February 28. 8 p.m. to 5 a.m. Alternating full closures of the mainlanes, in both directions, at Loop 410 for bridge work.
  • Monday, February 28 until Monday, March 7. 8 p.m. to 5 a.m. Full closure of the eastbound frontage road from Cable Ranch Rd. to Loop 410 for bridge work.
  • Monday, February 28 until Monday, March 7. 8 p.m. to 5 a.m. Full alternating closures of the mainlanes, in both directions, at Loop 410 for bridge work.  
  • Monday, February 28 until Monday, March 7. 9 a.m. Single lane closure on the westbound frontage road at Loop 410 for pipe laying. 

I-37 – South East San Antonio/Bexar County

  • Current until Monday, February 28. Full closure of the southbound exit ramp to Fair Ave. for metal beam guard fence repairs.
  • Wednesday, March 2 until Friday, March 4. 8 p.m. to 5 a.m. Southbound exit ramp to Fair Ave. closed for metal beam guard fence installation. 

PA 1502 – Wurzbach Parkway

  • Monday, February 28 until Friday, March 4. 9 a.m. to 3 p.m. Single lane closures, in both directions, at Thousand Oaks Dr. for electrical work.
  • Monday, February 28 until Friday, March 4. 9 a.m. to 3 p.m. Single eastbound mainlane closure from N.W. Military Highway to Blanco Rd. for electrical work. 

I-10 – Kendall County

  • Current until Spring 2022. Full closure of the eastbound frontage road from Menger Springs to US 87 (Main St.) for road construction. 

Loop 337 – Comal County

  • Monday, February 28 until Friday, March 4. 8 a.m. to 5 p.m. Single northbound lane closure at River Rd. for bridge work. 

FM 725 – Guadalupe County

  • Current until Wednesday, March 2. 8 a.m. to 3:30 p.m. Single lane closures, in both directions, from Ski Lodge Rd. to Terminal Loop Rd. for striping operations.