** WEATHER PERMITTING/SUBJECT TO CHANGE**
Loop 1604 – North Central San Antonio
- Friday, September 6 until Monday, September 9. Full weekend closure 9 p.m. until 5 a.m. Full westbound frontage road closure from Gold Canyon Road to the US 281 northbound frontage road for utility work. DETOUR: Take a double left at Gold Canyon Road, take a double left at Redland Road, use the Redland Road entrance ramp, take the Stone Oak Parkway exit ramp and use the turnaround at Stone Oak Parkway.
- Monday, September 9 until Friday, September 13. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure of the US 281 north exit ramp to the Redland Road entrance ramp for bridge span work. DETOUR: Use the US 281 north exit ramp through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
- Monday, September 9 until Friday, September 13. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for bridge span work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
- Saturday, September 14 until Monday, September 16. Full weekend closure 3 a.m. until 5 a.m. Full eastbound mainlane closure of the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
- Saturday, September 14 until Monday, September 16. Full weekend closure 3 a.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
- Current until Saturday, September 14 (excluding Sundays). Daily 8 a.m. until 4 p.m. Westbound left frontage road lane between Redland Road and Bulverde Road for truck/material access.
- Sunday, September 8 until Friday, September 13. Nightly 9 p.m. until 5 a.m. One frontage road lane in both directions between SH 16 (Bandera Road) and Roger’s Ranch Road/Bitters Road for pavement marking installation work.
- Current until 3 p.m. Saturday, September 7. Alternating northbound frontage road between south of US 90 to just south of FM 1957 (Potranco Road) for closeout item work.
- Current until 3 p.m. Saturday, September 7. Alternating northbound mainlanes between south of US 90 to just south of FM 1957 (Potranco Road) for closeout item work.
- Current until 3 p.m. Saturday, September 7. Alternating southbound mainlanes between south of FM 1957 (Potranco Road) to just south of US 90 for closeout item, sidewalk, curb, mow strip and rip rap work.
- Current until 5 p.m. Saturday, September 7. The northbound Wiseman Boulevard exit ramp for beam curb work.
- Current until 7 p.m. Saturday, September 7. Alternating northbound frontage road lanes between south of FM 1957 (Potranco Road) to SH 151 for driveway and sign work.
- Current until 7 p.m. Saturday, September 7. Alternating southbound frontage road lanes between SH 151 to south of FM 1957 (Potranco Road) for driveway and sign work.
- Current until 5 a.m. Saturday, September 7. Alternating northbound frontage road lanes between SH 151 to south of FM 1957 (Potranco Road) for milling and paving work.
- Current until 5 a.m. Saturday, September 7. Alternating lanes in both directions at FM 1957 (Potranco Road), Military Drive and Wiseman Boulevard for milling and final pavement work.
- Monday, September 9 until Friday, September 13. Daily 9 a.m. to 5 p.m. Alternating lanes in both directions at FM 1957 (Potranco Road), Military Drive, and Wiseman Boulevard for sign work.
- Monday, September 9 until Friday, September 13. Daily 9 a.m. to 7 p.m. Alternating northbound frontage road lanes between south of FM 1957 (Potranco Road) to SH 151 for driveway and sign work.
- Monday, September 9 until Friday, September 13. Daily 9 a.m. to 7 p.m. Alternating southbound frontage road lanes between SH 151 to south of FM 1957 (Potranco Road) for driveway and sign work.
- Saturday, September 7 until Sunday, September 8. Weekend closure 2 a.m. until 5 a.m. Full northbound mainlane closure from the frontage road exit ramp to the Sonterra Boulevard entrance ramp for beam setting work. DETOUR: Take the frontage road exit ramp, continue on the US 281 northbound frontage road through the Loop 1604 intersection and use the Sonterra Boulevard entrance ramp.
- Saturday, September 7 until Sunday, September 8. Weekend closure 2 a.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for beam setting work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound frontage road through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
- Saturday, September 7 until Sunday, September 8. Weekend closure 2 a.m. until 5 a.m. Full northbound frontage road closure from the Loop 1604 westbound frontage road to Sonterra Boulevard for beam work. DETOUR: On the Loop 1604 westbound frontage road, turn left on the US 281 southbound frontage road, take the turnaround at Donella Drive and use the US 281 Donella Drive entrance ramp.
- Monday, September 9 until Friday, September 13. Nightly 9 p.m. until 5 a.m. Full northbound mainlane closure from the frontage road exit ramp to the Sonterra Boulevard entrance ramp for direct connector work. DETOUR: Take the frontage Road exit ramp, continue on the US 281 northbound frontage road through the Loop 1604 intersection and use the Sonterra Boulevard entrance ramp.
- Monday, September 9 until Friday, September 13. Nightly 9 p.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound frontage road through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
- Monday, September 9 until Friday, September 13. Nightly 9 p.m. until 5 a.m. Full northbound frontage road closure from the Loop 1604 westbound frontage road to Sonterra Boulevard for direct connector work. DETOUR: On the Loop 1604 westbound frontage road, turn left on the US 281 southbound frontage road, take the turnaround at Donella Drive and use the US 281 Donella Drive entrance ramp.
- Monday, September 9 until Friday, September 13. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Marshall Road for bridge work and safety enhancements.
- Monday, September 9 until Friday, September 13. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for bridge and soundwall work and safety enhancements.
- Monday, September 9 until Friday, September 13. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure of one of two left turn lanes at Evans Road for utility work.
- Monday, September 9 until Friday, September 13. Nightly 9 p.m. until 5 a.m. Alternating southbound frontage road closure from Sonterra Boulevard to the US 281 westbound frontage road for drainage work.
- Saturday, September 14 until Monday, September 16. Full weekend closure 3 a.m. until 5 a.m. Full northbound mainlane closure from the frontage road exit ramp to the Sonterra Boulevard entrance ramp for beam setting work. DETOUR: Take the frontage road exit ramp, continue on the US 281 northbound frontage road through the Loop 1604 intersection and use the Sonterra Boulevard entrance ramp.
- Saturday, September 14 until Monday, September 16. Full weekend closure 3 a.m. until 5 a.m. Full northbound frontage road closure from the Loop 1604 westbound frontage road to Sonterra Boulevard for beam work. DETOUR: On the Loop 1604 westbound frontage road, turn left on the US 281 southbound frontage road, take the turnaround at Donella Drive and use the US 281 Donella Drive entrance ramp.
- Current until Friday, September 13. Daily 9 a.m. until 3 p.m. Westbound frontage road turnaround at Boerne Stage Road for bridge widening work.
- Sunday, September 8 until Friday, September 20. Nightly 9 p.m. until 5 a.m. Alternating mainlanes in both directions between Fair Oaks Parkway and Old Fredericksburg Road (including the Fair Oaks Parkway ramp temporarily) for milling and paving work.
- Sunday, September 8 until Friday, September 13. Nightly 9 p.m. until 5 a.m. Alternating westbound mainlanes between Scenic Loop Road and SH 46 for moving barrier work.
- Sunday, September 15 until Thursday, September 19. Nightly 9 p.m. until 5 a.m. Alternating mainlanes in both directions between Camp Bullis Road and La Cantera Parkway for moving barrier work.
- Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
- Current until further notice. Eastbound Ackerman Road exit ramp will be closed through the fall. DETOUR: Eastbound I-10 and southbound I-410 traffic needing to access Ackerman Road must take southbound I-410, exit at FM 1346/E. Houston St., turn around, and take the northbound frontage road to Ackerman Road.
- Sunday, September 8 until Monday, September 9. 7 p.m. to 5 a.m. Nnorthbound and southbound I-410 connecting ramps to eastbound I-10 for asphalt repairs. NORTHBOUND I-410 RAMP DETOUR: Northbound I-410 traffic needing to access eastbound I-10 will take the cloverleaf exit ramp to westbound I-10, stay in the right lane and take the next cloverleaf ramp to southbound I-410, then take a third and final cloverleaf ramp from southbound I-410 to eastbound I-10. SOUTHBOUND I-410 RAMP DETOUR: Southbound I-410 traffic needing to access eastbound I-10 will stay on I-410, exit at FM 1346/E. Houston St., turn around, enter the northbound I-410 mainlanes, and take the connecting ramp to eastbound I-10.
- Sunday, September 9 until Monday, September 10. 9 a.m. until 3 p.m. Westbound right frontage road lane from Graytown Road to Scenic Lake Drive for paving work.
- Sunday, September 8 until Friday, September 13. Nightly 9 p.m. to 5 a.m. The left eastbound mainlane from the Rosillo Creek bridge to Woodlake Parkway for concrete truck access.
- Monday, September 9 until Wednesday, September 11. Nightly 9 p.m. to 5 a.m. Ackerman Road in both directions under I-10 for concrete beam placement. DETOURS: Northbound Ackerman Road traffic will take the I-10 eastbound frontage road to Foster Road, turn around, and take the I-10 westbound frontage road back to Ackerman Road. Southbound Ackerman Road traffic will take the I-10 westbound entrance ramp just west of Ackerman, stay in the right lane, take the I-410 South connecting ramp, travel southbound on I-410, exit to FM 1346/E. Houston St., turn around, and take the northbound I-410/eastbound I-10 frontage road back to Ackerman Road.
- Wednesday, September 11 until Thursday, September 12. 9 p.m. to 5 a.m. A two -phased closure is required to restripe the westbound I-10 mainlanes at I-410. Phase 1: All I-10 westbound mainlanes will be closed between the exit ramp to I-410 and the I-10 westbound entrance ramp located just west of the I-410 interchange as crews restripe the left lane. DETOUR: All westbound I-10 traffic will be directed to the I-410 exit ramp, stay left on the parallel collector-distributor road that travels under I-410, and re-enter westbound I-10 just west of I-410. Phase 2: Once the left westbound mainlane of I-10 has been restriped, that single lane will be re-opened to traffic and the westbound parallel collector-distributor road that travels under I-410 will be closed at the I-410 interchange. The ramps connecting I-410 to westbound I-10 will also be closed. DETOUR: All I-10 westbound through-traffic will be directed to the left (inside) mainlane. SOUTHBOUND I-410 RAMP DETOUR: All southbound I-410 traffic needing to access I-10 westbound will stay on I-410, exit at FM 1346/E. Houston St., turn around, enter the northbound I-410 mainlanes, take the connecting ramp to eastbound I-10, exit to Foster Road, turn around, and enter the I-10 westbound mainlanes just west of Foster. NORTHBOUND I-410 RAMP DETOUR: All northbound I-410 traffic needing to access westbound I-10 should take the connecting ramp to eastbound I-10, exit to Foster Road, turn around, and enter the I-10 westbound mainlanes just west of Foster.
- Sunday, September 8 until Tuesday, September 10. Nightly 8:30 p.m. until 5 a.m. Eastoubnd left mainlane at I-37 (including I-37 northbound exit ramp) for guard fence installation work.
- Tuesday, September 10 until Thursday, September 12. Nightly 8:30 until 5 a.m. Westbound right mainlane at I-37 (including I-37 northbound exit ramp) for guard fence installation work.
- Current until 3 p.m. Saturday, September 7. Right frontage road lane in both directions between Austin Street and New Braunfels Avenue for sidewalk and driveway work.
- Sunday, September 8 until Tuesday, September 10. 9 p.m. until 5 a.m. Alternating southbound frontage road lanes between Schwab Road and FM 1103 for barrier installation work.
- Sunday, September 8 until Friday, September 13. Nightly 9 p.m. to 5 a.m. Alternating frontage road lanes in both directions between Walters Street to just north of FM 1103 for pavement bore work.
- Sunday, September 8 until Friday, September 13. Nightly 9 p.m. to 5 a.m. The left mainlane shoulder in both directions between Walters Street to just north of FM 1103 for pavement bore work.
- Sunday, September 8 until Friday, September 13. Nightly 9 p.m. to 5 a.m. Left mainlane in both directions between Walters Street to just north of FM 1103 for pavement bore work.
- Tuesday, September 10 until Wednesday, September 11. Nightly 9 p.m. until 5 a.m. Alternating northbound frontage road lanes between FM 1103 and Schwab Road for material hauling work.
- Wednesday, September 11 until Saturday, September 14. Nightly 9 p.m. until 5 a.m. Alternating southbound frontage road lanes between FM 1103 and Schwab Road for excavation work.
- Friday, September 6 until Monday, September 9. Weekend 8 p.m. until 5 p.m. The left lane in both directions on the frontage road for demolishing the old Marbach Road bridge.
- Monday, September 9 and Thursday, September 12. Daily 10 a.m. to 3 p.m. Two right southbound mainlanes between the US 90 ramp to the US 90 bridge for staging equipment and trucks for rail work.
- Monday, September 9 until Friday, September 13. Daily 9 a.m. to 3 p.m. The right northbound frontage road lane between Meadow Bend Drive to Timbercreek Drive for sidewalk work.
- Sunday, September 8 until Friday, September 13. Nightly 8 p.m. to 5 p.m. All northbound mainlanes between the Marbach Road exit ramp to the SH 151 entrance ramp for single slope concrete barrier work. DETOUR: Traffic will use the frontage road to access the next entrance ramp.
- Sunday, September 8 until Friday, September 13. Nightly 9 p.m. to 5 a.m. The left frontage road lane in both directions between Wehman Drive to Nacogdoches Road for pavement bore work.
- Sunday, September 8 until Friday, September 13. Nightly 9 p.m. to 5 a.m. The right mainlane in both directions between Wehman Drive to Nacogdoches Road for pavement bore work.
- Current until 7 p.m. Saturday, September 7. The left westbound mainlane between just east of Loop 1604 to just west of US 90 for mow strip work.
- Current until 3 p.m. Saturday, September 7. Alternating eastbound frontage road between west of Loop 1604 to east of Loop 1604 island ramp work.
- Current until 3 p.m. Saturday, September 7. Eastbound right frontage road lane from Springvale Drive to West Military Road for sidewalk and driveway work.
- Sunday, September 8 until Friday, September 13. Nightly 8 p.m. to 5 a.m. All westbound mainlanes between I-410 to Hunt Lane for rail and single slope concrete barrier work. DETOUR: Traffic will continue on the frontage road to access the next entrance ramp.
- Monday, September 9 until Saturday, September 14. Daily 9 a.m. to 3 p.m. The right eastbound access road lane between Springvale Drive to Pvt Drive for sidewalk and driveway work.
- Monday, September 9 until Saturday, September 14. Daily 9 a.m. to 3 p.m. The right westbound access road lane between W. Military Drive to Colt Drive for sidewalk and driveway work.
- City of San Antonio closure for Hardberger Park Landbridge project. Monday, September 9 until Friday, September 13. Daily 9 a.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
- City of San Antonio closure for Hardberger Park Landbridge project. Saturday, September 14. 7 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
- Monday, September 9 until Friday, September 13. Daily 7 a.m. to 3 p.m. The northbound left lane between Billy Mitchell Boulevard and Cupples Road for removing existing guardrail and installing concrete barrier.
- Monday, September 9 until Friday, September 13. Daily 9 a.m. to 5 p.m. The southbound left lane between Billy Mitchell Boulevard and Cupples Road for removing existing guardrail and installing concrete barrier.
- Current until 4 p.m. Saturday, September 7.. Northbound right lane from Emil Road to Springfield Road for sidewalk and driveway work.
- Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes from Woodlake Parkway until Gibbs Sprawl Road for barrier work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
- Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
- Thursday, September 12 until Friday, September 13. Nightly 8:30 p.m. until 5 a.m. Alternating southbound mainlanes (including I-10 eastbound exit ramp) for guard fence installation work.
- Monday, September 9 until Friday, September 13. Alternating southbound lanes from Tilden to FM 624 (mile markers 686-696) for barrier and excavation work.
- Monday, September 9 until Thursday, September 12. Daily 8 a.m. until 4 p.m. Alternating lanes in both directions at Indian Creek for rail foundation, parapet wall and curb work.
- Monday, September 9 until Friday, September 14. Nightly 9 p.m. until 5 a.m. All lanes in both directions of Summer Glen/Wilderness Parkway at US 281 for restriping work.
- Monday, September 9 until Friday, September 13. Nightly 9 p.m. until 5 a.m. Alternating eastbound lanes of Evans Road east of US 281 for traffic phasing.
- Monday, September 9 until Friday, September 13. Nightly 9 p.m. until 5 a.m. Alternating westbound lanes of Evans Road east of US 281 for traffic phasing.
- Monday, September 9, until Friday, September 27. Full-time extended closure 7 a.m. until 5 p.m. All lanes of Woodlake Parkway at the I-10 westbound frontage road. DETOUR: Traffic wishing to access the Horizon Pointe subdivision will continue traveling on the westbound frontage road, turn right on Foster Road, and take another right on Sierra Sunset to return to Woodlake Parkway.