- Saturday, April 25 until Monday, April 27. Weekend closure 2 a.m. until 5 a.m. Eastbound mainlane closure of the east- to southbound direct connector ramp for safety enhancements. DETOUR: Take the US 281 north exit ramp and turn right at the US 281 southbound frontage road.
- Saturday, April 25 until Monday, April 27. Weekend closure 2 a.m. until 5 a.m. Right/center lane eastbound mainlane closure from the Blanco Road exit ramp to the east- to southbound direct connector ramp for safety enhancements. DETOUR: Take the Blanco Road exit ramp.
- Saturday, April 25 until Monday, April 27. Weekend closure 2 a.m. until 5 a.m. Alternating eastbound mainlane closure from US 281 to the Gold Canyon Road exit ramp for bridge work.
- Sunday, April 26 until Friday, May 1. Nightly 9 p.m. until 5 a.m. Left lane westbound frontage road closure from the US 281 north exit ramp to the northbound US 281 frontage road.
- Saturday, May 2 until Monday, May 4. Full weekend closure 3 a.m. until 5 a.m. Full eastbound mainlane closure of the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
- Saturday, May 2 until Monday, May 4. Full weekend closure 3 a.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
- Saturday, May 2 until Monday, May 4. Full Weekend closure 3 a.m. until 5 a.m. Full eastbound frontage road closure of the east- to westbound turnaround at US 281 for direct connector work.
- Sunday, April 26 until Thursday, April 30. Nightly 6 p.m. until 6 a.m. Full mainlane closure in both directions between Redland Road and Green Mountain Road for milling and overlay work. DETOUR: Traffic will be diverted to the frontage road.
- Sunday, April 26 until Friday, May 1. Nightly 8 p.m. until 5 a.m. One mainlane in both directions between Green Mountain Road and I-35 for mill/paving, guardrail and mow strip work.
- Monday, April 27 until Friday, May 1. Daily 9:30 a.m. to 3:30 p.m. One mainlane in each direction between Bulverde Road and Green Mountain for striping work.
- Thursday, April 30 until Friday, May 1. Daily 8 a.m. to 4 p.m. The right southbound mainlane between I-35 to the SH 218 (Pat Booker Road) exit ramp for mill and pavement work.
- Sunday, May 3 until Thursday, May 7. Nightly 6 p.m. until 6 a.m. Full mainlane closure in both directions between Redland Road and Green Mountain Road for milling and overlay work. DETOUR: Traffic will be diverted to the frontage road.
- None scheduled.
- None scheduled.
- None scheduled.
- None scheduled.
- Saturday, April 25 until Sunday, April 26. 3 a.m. until 12 midnight. One northbound lane between Summer Glen and 1400ft north of Overlook Parkway for completing the traffic switch to the new frontage road.
- Saturday, April 25 until Monday, April 27. Full weekend closure 2 a.m. until 5 a.m. Full southbound frontage road closure from the Sonterra Boulevard exit ramp to the Loop 1604 westbound frontage road for bridge work. DETOUR: Take the Donella Drive exit ramp, take the turnaround at Donella Drive and turn left on the westbound frontage road.
- Saturday, April 25 until Monday, April 27. Weekend closure 2 a.m. until 5 a.m. Right lane southbound mainlane closure from the Sonterra Boulevard entrance ramp to Loop 1604 for bridge work.
- Saturday, April 25 until Monday, April 27. Weekend closure 2 a.m. until 5 a.m. Right lane southbound mainlane closure of the south- to northbound turnaround at Redland Road for barrier work.
- Sunday, April 26 until Friday, May 1. Nightly 9 p.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound frontage road through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
- Sunday, April 26 until Friday, May 1. Nightly 9 p.m. until 5 a.m. Full northbound mainlane ramp closure of the north- to westbound Loop 1604 direct connector ramp for bridge work. DETOUR: Use the frontage road exit ramp, turn left on the Loop 1604 westbound frontage road, and take the US 281 entrance ramp.
- Sunday, April 26 until Friday, May 1. Nightly 9 p.m. until 5 a.m. Full northbound frontage road closure from Loop 1604 to Sonterra Boulevard for bridge work. DETOUR: Turn left on the southbound US 281 frontage road, take the turnaround at Donella Drive and use the Donella Drive entrance ramp.
- Sunday, April 26 until Friday, May 1. Nightly 9 p.m. until 5 a.m. Northbound mainlane closure from the north- to southbound turnaround at Evans Road for bridge work. DETOUR: Use the next turnaround at Stone Oak/Tournament Players Club (TPC) Parkway.
- Sunday, April 26 until Friday, May 1. Nightly 9 p.m. until 5 a.m. Southbound mainlane closure from the south- to northbound turnaround at Evans Road for bridge work. DETOUR: Use the next turnaround at Encino Rio.
- Sunday, April 26 until Friday, May 1. Nightly 9 p.m. until 5 a.m. Left turn lane northbound mainlane closure at Encino Rio both north- to westbound turn lanes for bridge work. DETOUR: Use the turnaround north of Evans Road.
- Sunday, April 26 until Friday, May 1. Nightly 9 p.m. until 5 a.m. Left turn lane southbound mainlane closure at Encino Rio both south- to eastbound turn lanes for bridge work. DETOUR: Use the turnaround south of Encino Rio.
- Sunday, April 26 until Friday, May 1. Nightly 9 p.m. until 5 a.m. Left turn lane northbound mainlane closure at Evans Road both north- to westbound turn lanes for bridge work. DETOUR: Use the next turnaround at Stone Oak/Tournament Players Club (TPC) Parkway.
- Sunday, April 26 until Friday, May 1. Nightly 9 p.m. until 5 a.m. Left turn lane southbound mainlane closure at Evans Road both south- to eastbound turn lanes for bridge work. DETOUR: Use the next turnaround at Encino Rio.
- Sunday, April 26 until Friday, May 1. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Marshall Road for bridge work and safety enhancements.
- Sunday, April 26 until Friday, May 1. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for bridge work and safety enhancements.
- Monday, April 27. Daily 8 a.m. to 4 p.m. The north to southbound Cibolo Creek turnaround for overhead sign work.
- Monday, April 27 until Friday, May 1. Daily 9 a.m. to 4 p.m. The northbound left lane between Summer Glen to 1400ft north of Overlook Parkway for detour ramp work.
- Wednesday, April 29 until Friday, May 1. Daily 9 a.m. to 5 p.m. One southbound mainlane between 1600ft north of Overlook Parkway to Summer Glen for mill work.
- Saturday, May 2 until Monday, May 4. Full weekend closure 3 a.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, proceed on the southbound frontage road, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
- Saturday, May 2 until Monday, May 4. Full weekend closure 3 a.m. until 5 a.m. Full northbound mainlane closure from the frontage road exit ramp to the Sonterra Boulevard entrance ramp. DETOUR: Use the frontage road exit ramp, turn right on the Loop 1604 eastbound frontage road, if heading north, take the turnaround at Gold Canyon Road, turn right on the northbound frontage road and use the Stone Oak Parkway exit ramp.
- Saturday, May 2 until Monday, May 4. Full weekend closure 3 a.m. until 5 a.m. Full southbound frontage road closure at Loop 1604 for direct connector work. DETOUR: Turn right on the westbound frontage road, take the turnaround at Stone Oak Parkway and turn right on the southbound frontage road.
- Saturday, May 2 until Monday, May 4. Weekend closure 3 a.m. until 5 a.m. Northbound Redland Road bypass ramp mainlane closure from Sonterra Boulevard to Encino Rio for ramp work.
- Saturday, May 2 until Monday, May 4. Weekend closure 3 a.m. until 5 a.m. Left turn lane northbound mainlane closure at Evans Road both north- to westbound turn lanes for bridge work. DETOUR: Use the turnaround north of Evans Road.
- Saturday, May 2 until Monday, May 4. Weekend closure 3 a.m. until 5 a.m. Left turn lane southbound mainlane closure at Evans Road both south- to eastbound turn lanes for bridge work. DETOUR: Use the turnaround south of Evans Road.
- None scheduled.
- Sunday, April 26 until Friday, May 1. Nightly 9 p.m. to 5 a.m. Alternating mainlanes in both directions between SH 46 and Scenic Loop for moving concrete traffic barrier and pavement marking work.
- Monday, April 27. Daily 9 a.m. to 4 p.m. One westbound frontage road lane between Cascade Caverns and Scenic Loop for barricade and pavement marking to convert the frontage road to one-way.
- Current until Saturday, May 30. Daily 7 a.m. until 7 p.m. Alternating mainlanes in both directions between Kerr/Gillespie county line and Kerr/Kimble county line for paving work.
- Friday, April 24 from 9 p.m. until 5 a.m. Monday, April 27. Full weekend closure of all east and westbound mainlanes between Graytown Road and Pfeil Road for Graytown bridge demolition. DETOURS: Eastbound mainlane traffic will take the Graytown Road exit and re-enter the mainlanes on the newly constructed temporary entrance ramp located east of Graytown Road. Westbound mainlane traffic will take the newly constructed temporary Graytown Road exit ramp and re-enter the mainlanes at the next entrance ramp.
- Friday, April 24 until Friday, May 1. Daily 9 a.m. to 4 p.m. and nightly 9 p.m. to 5 a.m. Alternating east and westbound mainlanes from Foster Road to Martinez Creek to remove barrier and complete striping.
- Monday, April 27 until Thursday, April 30. Daily 6 a.m. to 4 p.m. Eastbound and westbound right lane from Graytown Road to Pfeil Road to move portable barrier and mill and overlay shoulder.
- Current until further notice. Graytown Road bridge at I-10. DETOURS: Graytown Road traffic will use the frontage roads and the Pfeil Road underpass or Loop 1604 turnaround to cross I-10.
- Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
- Current until further notice. Eastbound entrance ramp from Foster Road. DETOUR: Take next entrance ramp east of Woodlake Parkway.
- Thursday, April 30. Daily 8 a.m. to 5 p.m. Daily 8 a.m. to 5 p.m. The eastbound entrance ramp from Probandt Street for installing high mast pole work.
- Sunday, April 26 until Monday, April 27. Nightly 9 p.m. to 5 a.m. Two northbound mainlanes between Business 35 Bridge to north of FM 306 Bridge including the exit and entrance ramps for barrier work and on the left northbound frontage road lanes between Emerald Drive and the entrance ramp at Bucee’s for paving and sidewalk work.
- Monday, April 27 until Tuesday, April 28. Nightly 9 p.m. until 5 a.m. Alternating northbound frontage road lanes between Emerald Drive to FM 306 for setting barrier for turnaround pavement work. The north to southbound turnaround at FM 306 and entrance ramp from FM 306 will also be closed.
- Monday, April 27 until Wednesday, April 29. Nightly 8 p.m. to 6 a.m. One northbound mainlanes between FM 1106 to Conrads Lane/Kohlenberg Road for barrier work.
- Thursday, April 30. Daily 8 a.m. to 5 p.m. Daily 8 a.m. to 5 p.m. The southbound exit ramp to I-10 east and westbound for installing high mast pole work.
- Tuesday, April 28 until Wednesday, April 29. Daily 8 a.m. to 5 p.m. The northbound exit ramp at I-10 east and westbound for guardrail work.
- Monday, April 27 until Thursday, April 30. Nightly 8 p.m. to 5 a.m. All southbound mainlanes between W. Military Drive and Marbach Road for placing concrete traffic barrier. DETOUR: All traffic will exit at W. Military Drive to the frontage road and re-enter the highway after SH 151.
- Monday, April 27 until Monday, May 4. Daily 9 a.m. to 3 p.m. The left mainlane in both directions between Marbach Road and W. Military Drive for column work.
- Monday, April 27 until Monday, May 4. Daily 9 a.m. to 3 p.m. Alternating frontage road lanes in both directions between Marbach Road and Ingram Road for underground pipe work.
- Monday, April 27 until Monday, May 4. Nightly 8 p.m. to 5 a.m. The left lane in both directions between Marbach Road and W. Military Drive for column work.
- Current until Friday, May 18. Nightly 8 p.m. to 5 a.m./Weekend 7 p.m. to 6 a.m. Alternating full closure in both directions between US 90 to Valley Hi Drive for mill and inlay operations. NORTHBOUND DETOUR: Traffic will be detoured to take the exit to US 90, continue on the northbound frontage road through the Marbach Road intersection, and utilize the entrance ramp past Marbach Road to access the mainlanes. SOUTHBOUND DETOUR: Traffic traveling south will be detoured to take the exit ramp to Marbach Road, continue on the southbound frontage road through the Marbach Road intersection, and use the entrance ramp before Valley Hi Drive to access the mainlanes. Several ramps within the limits will also be closed.
- Current until Friday, May 1. Nightly 8 p.m. to 5 a.m. Alternating mainlanes in both directions between US 90 to Valley Hi Drive for mill and inlay operations.
- Current until Friday, May 1. Daily 9 a.m. to 3 p.m. Alternating frontage road lanes in both direction between SH 151 to US 90 for staging equipment and trucks.
- Sunday, April 27 until Friday, May 1. Nightly 8 p.m. until 5 a.m. All mainlanes in both directions between the exit to Ray Ellison Drive to the on-ramp past US 90 bridge (eastbound) and the exit to Hunt Lane to the Hunt Lane bridge (westbound) for mill and inlay work. EASTBOUND DETOUR: Traffic will exit at Ray Ellison Drive and use the next available entrance ramp. WESTBOUND DETOUR: Traffic will exit at Hunt Lane and use the next available entrance ramp.
- Current until Friday, May 1. Daily 9 a.m. to 3 p.m. Alternating frontage road lanes in both direction between Hunt Lane bridge to US 90 bridge for staging equipment, trucks and ground rock.
- None scheduled.
- None scheduled.
- City of San Antonio/PWD closure for Hardberger Park Land Bridge project. Friday, April 24 until Monday, April 27. 9 p.m. until 5 a.m. All lanes in both directions from FM 1535 (NW Military Hwy) to FM 2696 (Blanco Road) for bridge work. DETOUR: Traffic will need to use West Avenue and Lockhill Selma Road.
- City of San Antonio/PWD closure for Hardberger Park Land Bridge project. Monday, April 27 until Friday, May 1. 9 a.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy) to FM 2696 (Blanco Road) for construction truck and equipment access.
- City of San Antonio/PWD closure for Hardberger Park Land Bridge project. Monday, April 27 until Friday, May 1. 9 p.m. until 5 a.m. All lanes in both directions from FM 1535 (NW Military Hwy) to FM 2696 (Blanco Road) for bridge work. DETOUR: Traffic will need to use West Avenue and Lockhill Selma Road.
- City of San Antonio/PWD closure for Hardberger Park Land Bridge project. Friday, May 1 until Monday, May 4. 9 p.m. until 5 a.m. All lanes in both directions from FM 1535 (NW Military Hwy) to FM 2696 (Blanco Road) for bridge work. DETOUR: Traffic will need to use West Avenue and Lockhill Selma Road.
- City of San Antonio/PWD closure for Hardberger Park Land Bridge project. Monday, May 4 until Friday, May 8. 9 p.m. until 5 a.m. All lanes in both directions from FM 1535 (NW Military Hwy) to FM 2696 (Blanco Road) for bridge work. DETOUR: Traffic will need to use West Avenue and Lockhill Selma Road.
- City of San Antonio/PWD closure for Hardberger Park Land Bridge project. Friday, May 8 until Monday, May 11. 9 p.m. until 5 a.m. All lanes in both directions from FM 1535 (NW Military Hwy) to FM 2696 (Blanco Road) for bridge work. DETOUR: Traffic will need to use West Avenue and Lockhill Selma Road.
- City of San Antonio/PWD closure for Hardberger Park Land Bridge project. Friday, May 15 until Monday, May 18. 9 p.m. until 5 a.m. All lanes in both directions from FM 1535 (NW Military Hwy) to FM 2696 (Blanco Road) for bridge work. DETOUR: Traffic will need to use West Avenue and Lockhill Selma Road.
- City of San Antonio/PWD closure for Hardberger Park Land Bridge project. Friday, May 29 until Monday, June 1. 9 p.m. until 5 a.m. All lanes in both directions from FM 1535 (NW Military Hwy) to FM 2696 (Blanco Road) for bridge work. DETOUR: Traffic will need to use West Avenue and Lockhill Selma Road.
- Saturday, April 25 and Monday, April 27 until Friday, May 1. Daily 9 a. m. to 5 p.m. One lane in both directions between FM 2536 (Old Pearsall Road) to Rockgate Drive for mow strip, sidewalk and signal improvements.
- Monday, April 27 until Friday, May 1. Nightly 7 p. m. to 5 a.m. One lane in both directions between FM 2536 (Old Pearsall Road) to Rockgate Drive for milling and paving work.
- None scheduled.
- Exit ramp from Loop 1604 eastbound closed for approximately two months starting Monday, March 16.
- None scheduled.
- None scheduled.
- Wednesday, April 29 until Friday, May 1. Nightly 7 p.m. until 6 a.m. The right southbound lane between Super 8 Motel to Aurelia Street for mill and asphalt pavement work.
- None scheduled.
- Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes between Woodlake Parkway and Gibbs Sprawl Road for barrier/pavement work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
- Current until further notice. Full-day closure. Southbound lane between Toepperwein Road and Walzem Road for barrier setting work and road rehab work.
- None scheduled.
- Sunday, April 26 until Friday, May 1. Nightly 9 p.m. until 5 a.m. Full westbound crossing closure of Encino Rio at US 281 for bridge work. DETOUR: Turn right onto northbound US 281 and take the next turnaround.
- Current until Friday, May 8. Daily 7 a.m. until 5:30 p.m. Full closure of Borgfeld Drive in both directions at US 281 for intersection roadway work.
- Tuesday, April 28 until Wednesday, April 29. Nightly 9 p.m. to 5 a.m. One lane in each direction between east of I-35 to Town Center Drive for setting barrier in the median for pavement work.
- Wednesday, April 29 until Thursday, April 30. Nightly 9 p.m. to 5 a.m. One lane in each direction under I-35 bridge for setting barrier.
- None scheduled.
- Current until Friday, May 1. Daily 7 a.m. to 5 p.m. Alternating lanes in each direction for signal and lighting work.
- None scheduled.
- None scheduled.
- None scheduled.
- None scheduled.
- None scheduled.
- None scheduled.
- None scheduled.
- None scheduled.
- None scheduled.
- None scheduled.
- None scheduled.
- None scheduled.
- None scheduled.
- Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
- Current until Friday, May 1. Daily 7 a.m. to 5 p.m. Alternating lanes in each direction at FM 3351 (Ralph Fair Road) for signal and lighting work.
- Monday, April 27 until Saturday, May 1. Daily 7 a.m. until 7 p.m. Various locations in both directions between North School Street and ½-mile north of Wasp Creek Road for culvert work.
- Current until Friday, May 1. Full closure (all day) in both directions at Atascosa River (between FM 476 and SH 173) for culvert removal and replacement work.
- None scheduled.
- None scheduled.