Friday, August 14

Upcoming Scheduled Construction Closures


Loop 1604 – North Central San Antonio

  • Saturday, August 15 until Monday, August 17. Weekend overnight closure 2 a.m. until 5 a.m. Eastbound mainlane closure of the east- to southbound direct connector ramp to US 281 for striping. DETOUR: Take the US 281 north exit ramp and turn right on the southbound US 281 frontage road.
  • Saturday, August 15 until Monday, August 17. Weekend continuous closure 2 a.m. until 5 a.m. Left/center eastbound frontage road closure from the US 281 north exit ramp to the southbound US 281 frontage road for striping.
  • Monday, August 17 until Friday, August 21. Nightly 9 p.m. until 5 a.m. Eastbound mainlane closure of the east- to southbound direct connector ramp to US 281 for striping. DETOUR: Take the US 281 north exit ramp and turn right on the southbound US 281 frontage road.
  • Monday, August 17 until Friday, August 21. Nightly 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from the Stone Oak Parkway entrance ramp to the US 281 southbound frontage road.
  • Monday, August 17 until Friday, August 21. Nightly 9 p.m. until 5 a.m. Alternating westbound mainlane closure from the US 281 north exit ramp to the US 281 northbound frontage road.
  • Monday, August 17 until Friday, August 21. Nightly 9 p.m. to 5 a.m. Single eastbound mainlane closure from Redland Rd. to Bulverde Rd. for traffic rail construction.
  • Monday, August 17 until Friday, August 21. Daily 9 a.m. to 5 p.m. Single lane closure on eastbound frontage road from Redland Rd. to Bulverde Rd. for rip rap pouring.
  • Monday, August 17 until Friday, August 21. Nightly 9 p.m.to 5 a.m. Single lane closure on eastbound frontage road from Redland Rd. to Bulverde Rd. for barrier removal.

 

Loop 1604 – Northeast San Antonio

  • Friday, August 14 until Saturday, August 15. 8 p.m. to 12 p.m. I-35N collector ramp to southbound mainlanes of Loop 1604 closed for traffic switch.
  • Friday, August 14 until Saturday, August 15. 8 p.m. to 6 a.m. Left lane closure on southbound mainlanes from I-35 to Kitty Hawk Rd. for traffic switch.
  • Saturday, August 15 until Monday, August 17. Weekend closure 12 a.m. to 6 a.m. Right lane closure on southbound mainlanes from I-35 to Kitty Hawk Rd. for traffic switch.
  • Saturday, August 15 until Monday, August 17. Weekend closure 8 a.m. to 6 a.m. Single lane closure on southbound frontage road from Loop 1604 collector ramp to Kitty Hawk Rd. for traffic switch.
  • Sunday, August 16 until Friday, August 21. Single lane closures, in both directions, from Green Mountain Rd. to I-35 cloverleaf ramps for guardrail improvements.
  • Friday, August 21 until Monday, August 24. Weekend closure 8 p.m. to 5 a.m. Single southbound mainlane closure at the Pat Booker Road bridge for bridge demolition.

 

US 281 – North Central San Antonio/Bexar County

  • Friday, August 14 until Saturday, August 15. 9 p.m. to 5 a.m. Single southbound mainlane closure at Cibolo Creek for lane widening.
  • Saturday, August 15 until Monday, August 17. Weekend overnight closure 2 a.m. until 5 a.m. Northbound mainlane closure of the north- to eastbound direct connector ramp to Loop 1604 for striping. DETOUR: Take the frontage road exit ramp and turn right on the eastbound Loop 1604 frontage road. If heading north, use the turnaround at Gold Canyon Road, turn right at the northbound US 281 frontage road and use the Stone Oak Parkway exit ramp.
  • Saturday, August 15 until Monday, August 17. Weekend overnight closure 2 a.m. until 5 a.m. Northbound mainlane closure of the north- to westbound direct connector ramp to Loop 1604 for striping. DETOUR: Take the frontage road exit ramp, turn left at the westbound Loop 1604 frontage road and use the US 281 entrance ramp.
  • Saturday, August 15 until Monday, August 17. Weekend continuous closure 2 a.m. until 5 a.m. Northbound mainlane closure from the north- to southbound turnaround at Evans Road for concrete paving. DETOUR: Use the turnaround at Stone Oak/Tournament Players Club (TPC) Parkway. Closure will not happen concurrently with other turnaround closures in the same direction.
  • Saturday, August 15 until Monday, August 17. Weekend continuous closure 2 a.m. until 5 a.m. Northbound mainlane closure from the north- to southbound turnaround at Stone Oak/Tournament Players Club (TPC) Parkway for concrete paving. DETOUR: Use the turnaround north of Stone Oak/Tournament Players Club (TPC) Parkway. Closure will not happen concurrently with other turnaround closures in the same direction.
  • Saturday, August 15 until Monday, August 17. Weekend overnight closure 2 a.m. until 5 a.m. Left turn lane northbound mainlane closure at Evans Road both north- to westbound turn lanes for concrete paving. DETOUR: Use the turnaround at Stone Oak/Tournament Players Club (TPC) Parkway. Closure will not happen concurrently with the other turnaround closures in the same direction.
  • Saturday, August 15 until Monday, August 17. Weekend overnight closure 2 a.m. until 5 a.m. Left turn lane northbound mainlane closure at Stone Oak/Tournament Players Club (TPC) Parkway both north- to westbound turn lanes for concrete paving. DETOUR: Use the turnaround north of Stone Oak/Tournament Players Club (TPC) Parkway. Closure will not happen concurrently with the other turnaround closures in the same direction.
  • Saturday, August 15 until Monday, August 17. Weekend overnight closure 2 a.m. until 5 a.m. Left turn lane southbound mainlane closure at Stone Oak/Tournament Players Club (TPC) Parkway both south- to eastbound turn lanes for concrete paving. DETOUR: Use the turnaround at Evans Road. Closure will not happen concurrently with the other turnaround closures in the same direction.
  • Saturday, August 15 until Monday, August 17. Weekend continuous closure 2 a.m. until 5 a.m. Right/center southbound mainlane closure from the Redland Road exit ramp to Donella Drive for striping.
  • Saturday, August 15 until Monday, August 17. Weekend overnight closure 2 a.m. until 5 a.m. Left lane northbound mainlane closure from Loop 1604 to Sonterra Boulevard for concrete paving.
  • Saturday, August 15 until Monday, August 17. Weekend continuous closure 2 a.m. until 5 a.m. Alternating frontage road closure from Sonterra Boulevard to the Redland Road bypass ramp.
  • Saturday, August 15 until Monday, August 17. Weekend continuous closure 7 a.m. until 5 a.m. Left lane northbound frontage road closure from Encino Rio to Evans Road for concrete paving.
  • Saturday, August 15 until Monday, August 17. Weekend continuous closure 7 a.m. until 4 a.m. Alternating northbound frontage road closure from Loop 1604 to Sonterra Boulevard for lighting work.
  • Monday, August 17 until Friday, August 21. Nightly 9 p.m. until 5 a.m. Northbound mainlane closure of the north- to eastbound direct connector ramp to Loop 1604 for striping. DETOUR: Take the frontage road exit ramp and turn right on the eastbound Loop 1604 frontage road. If heading north, use the turnaround at Gold Canyon Road, turn right at the northbound US 281 frontage road and use the Stone Oak Parkway exit ramp.
  • Monday, August 17 until Friday, August 21. Nightly 9 p.m. until 5 a.m. Northbound mainlane closure of the north- to westbound direct connector ramp to Loop 1604 for striping. DETOUR: Take the frontage road exit ramp, turn left at the westbound Loop 1604 frontage road and use the US 281 entrance ramp.
  • Monday, August 17 until Friday, August 21. Nightly 9 p.m. until 5 a.m. Northbound mainlane closure of the exit ramp to the Sonterra Boulevard Access Road for concrete paving. DETOUR: Take the frontage road exit ramp and use the Sonterra Boulevard entrance ramp.
  • Monday, August 17 until Friday, August 21. Nightly 9 p.m. until 5 a.m. Right turn lane northbound mainlane closure from Sonterra Boulevard to Redland Road for concrete paving.
  • Monday, August 17 until Friday, August 21. Nightly 9 p.m. until 5 a.m. Right/center lane southbound frontage road closure from Evans Road to Encino Rio for soundwall work.
  • Monday, August 17 until Friday, August 21. Nightly 9 p.m. until 5 a.m. Left lane northbound mainlane closure from Loop 1604 to Sonterra Boulevard for concrete paving.
  • Monday, August 17 until Friday, August 21. Nightly 9 p.m. until 5 a.m. Left lane southbound mainlane closure from Sonterra Boulevard to Loop 1604 for concrete paving.
  • Monday, August 17 until Friday, August 21. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from the Donella Drive entrance ramp to the Sonterra Boulevard entrance ramp for bridge work.
  • Monday, August 17 until Friday, August 21. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from the Sonterra Boulevard entrance ramp to the Donella Drive exit ramp for bridge work.
  • Tuesday, August 18 until Thursday, August 20. 9 p.m. to 5 a.m. Alternating southbound lane closures at Marshall Road for barrier installation.
  • Saturday, August 22 until Monday, August 24. Weekend continuous closure 2 a.m. until 5 a.m. Right turn lane northbound frontage road closure at Redland Road for concrete paving.
  • Saturday, August 22 until Monday, August 24. Weekend continuous closure 2 a.m. until 5 a.m. Right lane southbound frontage road closure from Encino Rio to Sonterra Boulevard for striping.
  • Saturday, August 22 until Monday, August 24. Weekend continuous closure 2 a.m. until 5 a.m. Alternating northbound mainlane closure from Sonterra Boulevard to the Redland Road bypass ramp.

 

Redland Road – North Central San Antonio

  • Monday, August 17 until Friday, August 21. Nightly 9 p.m. until 5 a.m. Right turn lane westbound crossing closure at US 281 for concrete paving.
  • Saturday, August 22 until Monday, August 24. Weekend continuous closure 2 a.m. until 5 a.m. Right turn lane westbound crossing closure at US 281 for concrete paving.

 

I-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County

  • Current until Saturday, August 15. Nightly 8:00 p.m. to 6:00 a.m. Full closure of eastbound mainlanes from Old Fredericksburg Rd. to Ralph Fair Rd. (FM 3351) for asphalt work.
  • Current until Friday, August 28. Sunday through Thursday nights, 8:00 p.m. to 6:00 a.m. Alternating mainlane closures, in both directions, from Ralph Fair Rd. (FM 3351) to La Cantera Parkway for overlay and pavement markings.
  • Friday, August 14 until Saturday, August 15. 10 p.m. to 8 a.m. Full closure of eastbound mainlanes from Old Fredericksburg Road and Ralph Fair Road (FM 3351) for asphalt work.  
  • Sunday, August 16 until Monday, August 17. 8 p.m. to 6 a.m. Full closure of eastbound mainlanes from Old Fredericksburg Road to Ralph Fair Road (FM 3351) for asphalt work.
  • Sunday, August 16 until Friday, August 28. Nightly, 7 p.m. to 6 a.m. Alternating mainlane closures, in both directions, from Cibolo Creek to SH-46 for asphalt work.
  • Monday, August 17 until Tuesday, August 18. 8 p.m. to 6 a.m. Full closure of eastbound mainlanes from Ralph Fair Road (FM 3351) to Boerne Stage Road for asphalt work.
  • Monday, August 17 until Tuesday, August 18. 4 a.m. to 11 a.m. Single lane closure on eastbound frontage road at Boerne Stage Road for concrete rip rap installation.
  • Monday, August 17 until Friday, August 28. Daily, 7 a.m. to 7 p.m. Alternating mainlane closures, in both directions, from SH-16 to Kerr/Kendall County Line for asphalt work.
  • Tuesday, August 18 until Wednesday, August 19. 8 p.m. to 6 a.m. Full closure of eastbound mainlanes from Boerne Stage Road to Dominion Drive for asphalt work.
  • Wednesday, August 19 until Thursday, August 20. 8 p.m. to 6 a.m. Full closure of eastbound mainlanes from Dominion Drive to Camp Bullis Road for asphalt work.
  • Thursday, August 20 until Friday, August 21. 8 p.m. to 6 a.m. Full closure of eastbound mainlanes from Camp Bullis Road to La Cantera Parkway for asphalt work.

 

I-10 – Far East San Antonio/Bexar County/Seguin/Guadalupe County 

  • Friday, August 14 thru Saturday, August 15: Eastbound I-10 right lane closed between FM 1516 and Graytown Road from 7 p.m. to 7 p.m.  
  • Tuesday, August 18 until Wednesday, August 19. Daily 7 a.m. to 5 p.m. Westbound exit ramp at Foster Road will be closed for asphalt work.
  • Current until mid-September: Westbound I-10 entrance ramp from Ackerman Road closed. DETOURS:
    • Southbound Ackerman traffic can travel south under the I-10 overpass, use the eastbound frontage road to Foster Road, turn left on Foster, and take the westbound frontage road to the westbound entrance ramp just west of Foster.
    • Northbound Ackerman traffic can use the eastbound frontage road to Foster Road, turn left on Foster, and take the westbound frontage road to the westbound entrance ramp just west of Foster.
  • Current until further notice. Graytown Road bridge at I-10. DETOURS: Graytown Road traffic will use the frontage roads and the Pfeil Road underpass or Loop 1604 turnaround to cross I-10.
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Current until further notice. Eastbound entrance ramp from Foster Road. DETOUR: Take next entrance ramp east of Woodlake Parkway.

 

I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

  • Until further notice, the southbound entrance ramp at Schwab Rd. is closed.
  • Friday, August 14 until Saturday, August 15. 8 p.m. to 6 a.m. Double lane and ramp closure on southbound mainlanes from Watson Lane bridge to Conrad/Kohelenberg bridge for traffic switch.
  • Saturday, August 15 until Sunday, August 16. Weekend overnight closure 8 p.m. until 5 a.m. Right/center lane southbound mainlane closure from Watson Lane to Conrads Lane/Kohlenberg Road for striping.
  • Current until Saturday, August 15. Daily 9:00 a.m. to 5:30 p.m. Left lane northbound frontage road closure from Hubertus Rd. to Schwab Rd. for concrete and landscape work.
  • Current until Saturday August 15. Daily, 9:00 a.m. to 5:30 p.m. Left lane southbound frontage road closure from Schwab Rd. to Hubertus Rd. for concrete, landscape, and stripping work.
  • Current until Saturday, August 15. Daily 9:00 a.m. to 5:30 p.m. Right lane northbound frontage road closure from Hubertus Rd. to Schwab Rd. for sidewalk forming.
  • Friday, August 14 until Saturday, August 15. Nightly 8:00 p.m. to 5:00 a.m. Southbound mainlane closures from Watson Lane to Conrad/Kohelenberg Bridge for work zone striping and barrier installation.
  • Monday, August 17 until Saturday, August 22. Daily 9 a.m. to 5:30 p.m. Single lane closure on northbound frontage road from Hubertus Rd. to Schwab Rd. for landscape, ramp and sidewalk work.
  • Monday, August 17 until Saturday, August 22. Daily 9 a.m. to 5:30 p.m. Single lane closure on southbound frontage road from Schwab Rd. to Hubertus Rd. for stripping work.

 

I-37 – Central/Southeast San Antonio

  • Monday, August 17. 9 a.m. to 5 p.m. Single southbound mainlane closure at Loop 1604 for road improvements.
  • Tuesday, August 18 until Wednesday, August 19. Daily, 8:30 a.m. to 4:00 p.m. Southbound ramp closed to eastbound I-10 for mow strip installation.
  • Thursday, August 20. 8:30 a.m. to 4:00 p.m. Southbound ramp closed to westbound US-90 for mow strip installation.

 

I-410 – Central San Antonio

  • Tuesday, August 18 until Wednesday, August 19. Daily, 9 a.m. to 4 p.m. Single lane closure on westbound frontage road at Blanco Road (FM 2696) for utility work.

 

FM 2696 – Blanco Road

  • Monday, August 17 until Tuesday, August 18. Daily, 9 a.m. to 4 p.m. Single northbound lane closure at Lockhill Selma Road for utility work.

 

I-410 – West San Antonio

  • Current until Sunday, August 23. 9 a.m. to 3 p.m. Alternating frontage road closures, in both directions, from Marbach Rd. to Ingram Rd. for work to retaining wall and underground pipes.
  • Current until Monday, August 24. Nightly 8 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from Marbach Rd. to Culebra Rd. for barrier installation.
  • Current until Monday August 10. Daily 9:00 a.m. to 3:00 p.m. Full closure of southbound frontage road from N.W. Crossroads to Military Dr. for removal of concrete riprap.
  • Current until Monday August 24. Daily 9:00 a.m. to 3:00 p.m. Alternating lane closures, in both directions, from Marbach Rd. to Culebra Rd. for barrier installation. 
  • Current until Friday, August 24. Nightly 8:00 p.m. to 5:00 a.m. Alternating frontage road lane closures, in both directions, from Marbach Rd. to Ingram Rd. for retaining wall work.
  • Saturday, August 8 until Friday, August 21. Nightly 8 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from SH-151 to US-90 for painting operations.
  • Saturday, August 8 until Friday, August 21. Daily 9 a.m. to 3 p.m. Alternating mainlane closures, in both directions, from SH-151 to US-90 for concrete placement.
  • Monday, August 17 until Friday, August 21. 8:00 p.m. to 5:00 a.m. Full closure of northbound Loop 410 frontage road from Meadow Breeze Dr. to SH-151 for placement of concrete bridge beams. DETOUR: Use Loop 410 northbound mainlanes to exit Culebra Rd. and take the turnaround to Loop 410 southbound frontage road back to SH-151.

 

US 90 – West San Antonio

  • Current until Friday, August 21. Daily 9 a.m. to 3 p.m. Alternating lanes, in both directions, from Loop 410 to Hunt Lane for concrete placement.
  • Current until Friday, August 21. Nightly 8 p.m. to 5 a.m. Alternating lanes, in both directions from Loop 410 to Hunt Lane for painting operations.
  • Monday, August 17 until Friday, August 21. Daily 9 a.m. to 3 p.m. Eastbound exit ramp to Enrique M. Barrera Parkway closed for guardrail improvements.
  • Monday, August 17 until Friday, August 21. Daily 9 a.m. to 3 p.m. Single frontage road lane closures, in both directions, from W. Military Dr. to S.W. 36th St. for guardrail improvements.

 

SH 151 – West San Antonio

  • Current until Monday, August 24. Daily 9:00 a.m. to 3:00 p.m. Alternating frontage road lane closures, in both directions, from Loop 410 to Ingram Rd. for bent work.
  • Current until Monday, August 24. Daily 9:00 a.m. to 3:00 p.m. Alternating mainlane closures, in both directions, from Loop 410 to Ingram Rd. for bent work.
  • Current until Monday, August 24. Nightly 8:00 p.m. to 5:00 a.m. Full closure of eastbound frontage road from Loop 410 to Ingram Rd. for bridge rail demolition.
  • Current until Monday, August 24. Nightly 8:00 p.m. to 5:00 a.m. Alternating frontage road lane closures, in both directions, from Loop 410 to Ingram Rd. for bent work.

 

FM 1957 – Potranco Road

  • Current until Friday, August 28. Daily 9 a.m. to 4 p.m. Single eastbound lane closure from Stevens Parkway to 1,000 feet east of Stevens Parkway for curb and driveway construction.

 

PA 1502 – Wurzbach Parkway

  • City of San Antonio/PWD closure for Hardberger Park Land Bridge project. Monday, August 17 until Friday, August 21. 8 p.m. to 6 a.m. Full closure of mainlanes, in both directions, from NW Military Dr. (FM 1535) to Blanco Rd. (FM 2696) for bridge decking. DETOUR: Traffic should utilize West Ave. and Lockhill Selma Rd.
  • City of San Antonio/PWD closure for Hardberger Park Lane Bridge project. Monday, August 17 until Friday, August 21. 7 a.m. to 4 p.m. Single lane closure, in both directions, from 0.5 miles from N.W Military Dr. (FM 1535) to 0.25 miles from Blanco Rd. (FM 2696) to allow entry for construction trucks.
  • City of San Antonio/PWD closure for Hardberger Park Land Bridge project. Friday, August 21 until Sunday, August 23. 8 p.m. to 6 a.m. Full closure of mainlanes, in both directions, from NW Military Dr. (FM 1535) to Blanco Rd. (FM 2696) for bridge decking. DETOUR: Traffic should utilize West Ave. and Lockhill Selma Rd.
  • City of San Antonio/PWD closure for Hardberger Park Lane Bridge project. Saturday, August 22 until Sunday, August 23. 7 a.m. to 4 p.m. Single lane closure, in both directions, from 0.5 miles from N.W Military Dr. (FM 1535) to 0.25 miles from Blanco Rd. (FM 2696) to allow entry for construction trucks.

 

Loop 13 – S.W. Military Drive

  • Sunday, August 16 until Friday, August 21. Nightly 9 p.m. to 5 a.m. Single lane closures, in both directions, from Old Pearsall Road to Rockgate Drive for pavement work.

 

FM 1976 – Walzem Road/Gibbs Sprawl Road

  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes between Woodlake Parkway and Gibbs Sprawl Road for barrier/pavement work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
  • Current until further notice. Full-day closure. Southbound lane between Toepperwein Road and Walzem Road for barrier setting work and road rehab work.

 

FM 218 – Pat Booker Road

  • Friday, August 21 until Monday, August 24. Weekend closure 8 p.m. to 5 a.m. Full street closure, in both directions, at Loop 1604 turnarounds for bridge demolition.
  • Friday, August 21 until Monday, August 24. Weekend closure 8 a.m. to 5 a.m. Full closure of Pat Booker Rd. and Loop 1604 turnarounds for bridge demolition.

 

Other Roads – Bexar County

  • Borgfeld Rd. Monday, August 31 until Tuesday, September 1. 9 p.m. to 5 a.m. Full closure of Borgfeld Rd. from US-281 to Bulverde Rd. for restriping.

 

SH 46 – Boerne/Kendall County

  • Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).

RM/FM 1376 – Kendall County

  • Current until Saturday, August 22. Daily 7 a.m. to 7 p.m. Single lane closure, in both directions, from N. School St. to 0.5 miles past Wasp Creek Rd. for culvert work and roadway reconstruction.

 

FM 1863 – Comal

  • Monday, August 17 until Friday, August 21. Daily 8 a.m. to 7 p.m. Single mainlane closure, in both directions, from FM 46 to FM 3009 for asphalt work.

 

FM 479 – Kerr

  • Monday, August 17 until Thursday, August 20. Daily 7 a.m. to 7 p.m. Alternating lane and shoulder closures, in both directions, at I-10 for guardrail installation.