Friday, July 29

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North West San Antonio/Bexar County

  • Sunday, July 31 until Friday, August 12. Weeknights 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Bandera Road (SH 16) to IH-10 for barrier setting.
  • Sunday, July 31 until Friday, August 12. Weeknights 9 p.m. until 5 a.m. Alternating westbound mainlane closure from IH-10 to Bandera Road (SH 16) for barrier setting.
  • Sunday, July 31 until Friday, August 12. Weeknights 9 p.m. until 5 a.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for barrier setting.
  • Sunday, July 31 until Friday, August 12. Weeknights 9 p.m. until 5 a.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for barrier setting.
  • Sunday, July 31 until Friday, August 12. Weeknights 9 p.m. until 5 a.m. Westbound mainlane full closure from Chase Hill Boulevard/Brennan Avenue to Kyle Seale Parkway for bridge construction: caps, beams & rail demo.
  • Monday, August 1 until Monday, August 15. Weeknights 9 p.m. until 5 a.m. Westbound to eastbound turnaround closure at Loop 1604 and La Cantera Parkway/John Peace Boulevard for bridge construction. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Sunday, July 31 until Friday, August 12. Weeknights 10 p.m. until 12 p.m. Eastbound mainlane full closure from Babcock Road to La Cantera Parkway for bridge construction.
  • Sunday, July 31 until Friday, August 12. Weeknights 9 p.m. until 5 a.m. Full intersection closure at Loop 1604 and Bandera Road (SH 16), both directions, including turnarounds, for bridge construction.
  • Monday, August 1 until Friday, August 15. Weekdays 9 a.m. until 3 p.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for barrier setting.
  • Monday, August 1 until Friday, August 15. Weekdays 9 a.m. until 3 p.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for barrier setting.
  • Monday, August 1 until Friday, August 15. Weekdays 9 a.m. until 3 p.m. Eastbound frontage road right outside lane closure from Babcock Road to Chase Hill Boulevard/Brennan Avenue for gas utility work.
  • Monday, August 1 until Monday August 15. Weekdays 9 a.m. until 5 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Hausman Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, August 1 until Monday, August 15. Weekdays 9 a.m. until 5 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Hausman Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, August 1 until Monday, August 15. Weekdays 9 a.m. until 5 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Kyle Seale Parkway for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, August 1 until Monday, August 15. Weekdays 9 a.m. until 5 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Kyle Seale Parkway for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, August 1 until Monday, August 15. Weekdays 9 a.m. until 5 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, August 1 until Monday, August 15. Weekdays 9 a.m. until 5 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, August 1 until Monday, August 15. Weekdays 9 a.m. until 5 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, August 1 until Friday, August 15. Weekdays 9 a.m. until 5 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Friday, July 28 at 9 p.m. until Monday, August 1 at 5 a.m. Weekend Only. Eastbound mainlane entrance ramp full closure from La Cantera Parkway for storm drainage. Traffic will continue on the Loop 1604 eastbound frontage road to the IH-10 interchange. 

Loop 1604 – North Central San Antonio/Bexar County

  • Sunday, July 31 until Friday, August 5. Nightly 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Tradesman Road to US 281 exit ramp for barrier setting and striping.
  • Sunday, July 31 until Friday, August 5. Nightly 9 p.m. until 5 a.m. Alternating westbound mainlane closure from US 281 exit ramp to Tradesman Road for barrier setting and striping.
  • Sunday, July 31 until Friday, August 5. Nightly 9 p.m. until 5 a.m. Alternating eastbound frontage road closure from IH-10 to US 281 for barrier setting and striping.
  • Sunday, July 31 until Friday, August 5. Nightly 9 p.m. until 5 a.m. Alternating westbound frontage road closure from US 281 to IH-10 for barrier setting and striping.
  • Sunday, July 31 until Friday, August 5. Nightly 9 p.m. until 5 a.m. Westbound to eastbound turnaround full closure at Loop 1604 and NW Military Highway for drilling shafts.
  • Monday, August 1 until Friday, August 5. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround full closure at Loop 1604 and Lockhill Selma Road for concrete island demo and temporary traffic signal work.
  • Monday, August 1 until Friday, August 5. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround short term full closure at Loop 1604 and NW Military Highway for concrete placement and drill shafts.
  • Sunday, July 31 until Sunday, August 7. Weekdays/Weeknights 12 a.m. until 12 a.m. Eastbound to westbound turnaround full closure at Loop 1604 and NW Military Highway for bridge widening construction.
  • Saturday, July 30 only from 5:00 a.m. to 5:00 p.m. Eastbound to westbound turnaround full closure at Loop 1604 and Lockhill Selma Rd for traffic signal work. 

Loop 1604 – North East San Antonio/Bexar County

  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound Loop 1604 frontage road from Nacogdoches Road to Union Pacific Railroad for barrier work.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound Loop 1604 frontage road between Gateway Boulevard and Lookout Road for striping and barrier work.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Alternating lane closures on Loop 1604 frontage road eastbound to westbound turnaround between Nacogdoches Road and Union Pacific Railroad for striping and barrier work.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Alternating lane closures on Loop 1604 frontage road westbound to eastbound turnaround between Lookout Road and Union Pacific Railroad for striping and barrier work.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound Loop 1604 between Nacogdoches Road and I-35 for striping and barrier work.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound Loop 1604 between I-35 and Nacogdoches Road for striping and barrier work.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Left lane closure on eastbound Loop 1604 frontage road and entrance ramp to Loop 1604 between Nacogdoches Road and Union Pacific Railroad for striping and barrier work. Traffic must continue on eastbound frontage road bypass to access Loop 1604.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound Loop 1604 bypass between Union Pacific Railroad and Lookout Road for striping and barrier work.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Westbound Loop 1604 frontage road exit ramp closure from Gateway Boulevard to Lookout Road for striping and barrier work. Traffic must use Lookout Road Exit.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Westbound Loop 1604 entrance ramp closure from Union Pacific Railroad to Nacogdoches Road for striping and barrier work. Traffic must continue westbound on frontage road and use the next entrance ramp to access Loop 1604.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Lookout Road exit ramp closure on eastbound Loop 1604 and left lane frontage road closure between Nacogdoches Road and Union Pacific Railroad for striping work. Traffic must continue eastbound Loop 1604 and use the IKEA-RBFCU Parkway or Nacogdoches exit ramp to access Lookout Road.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Right lane closure on eastbound frontage road of Loop 1604 from Lookout Road to IKEA-RBFCU Parkway for utility inspection work.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Right lane closure on Loop 1604 frontage road eastbound to westbound turnaround from Nacogdoches Road to Union Pacific Railroad for geotechnical and drilling work.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Eastbound-to-westbound turnaround closure at Lookout Road for geotechnical and drilling work. Traffic will use the traffic signals at Lookout Road intersection to access westbound Loop 1604.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Right lane closure on Loop 1604 frontage road turnaround from Nacogdoches Road to Union Pacific Railroad for geotechnical and drilling work.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Left lane closure on Loop 1604 frontage road turnaround from Lookout Road to Union Pacific Railroad for geotechnical and drilling work.
  • Monday, August 1 until Friday, August 5. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound Loop 1604 frontage road from Nacogdoches Road to Union Pacific Railroad for barrier work. 

US 281 – North San Antonio/Bexar County

  • Monday, July 25 until Thursday, August 4. 9 p.m. to 5 a.m. Wilderness Oak and Overlook Parkway intersection closed for bridge work.
  • Sunday, July 31. 8 p.m. to 5 a.m. Single lane closure on the southbound frontage road from Mountain Lodge to Oakland Bend for concrete paving operations. 

I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

  • Sunday, July 31 until Friday, August 5. 9:00 p.m. to 5:00 a.m. Right lane closure on northbound I-35, Pat Booker Road exit ramp closure, and left lane closure on northbound frontage road of I-35 from Toepperwein Road to Shin Oak Road for geotechnical and drilling work. All traffic must exit Toepperwein Road (exit 170B) and follow the signs.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound frontage road of I-35 from Toepperwein Road and Judson Road for utility inspection work.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35 connector ramp from IKEA-RBFCU Parkway to McMorris Boulevard for geotechnical and drilling work.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Northbound-to-southbound turnaround closure at Thousand Oaks Drive for geotechnical and drilling work. Traffic will use the traffic signals at Thousand Oaks intersection to access southbound I-35 frontage road.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35 frontage road from Randolph Boulevard to Fratt road for geotechnical and drilling work.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. FM 1518 exit ramp (exit 174A) closure on northbound I-35 and left lane closure on northbound frontage road of I-35 from exit 174A to Pasatiempo for geotechnical and drilling work. Traffic must follow the detour signs.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Right lane closure on northbound I-35 mainlane from Olympia Parkway to Pasatiempo for geotechnical and drilling work.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35 and left lane closure on southbound frontage road of I-35 between Judson Road and O’Connor Road for barrier and sign work.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Multiple lane closures on southbound I-35 between Judson Road and O’Connor Road for striping and barrier work.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35, left lane closure on southbound frontage road and closure on southbound I-35 entrance ramp from Pat Booker Road to Ferrell Road for barrier work. Traffic must continue on southbound frontage road to access I-35.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Multiple lane closures on southbound I-35 between Pat Booker Road to Ferrell Road for striping and barrier work.
  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound frontage road of I-35 from Fratt Drive to Walzem Road for utility inspection work. 

I-10 – East San Antonio/Bexar County

  • Monday, August 1 until Thursday, August 4. 9 p.m. to 5 a.m. Full closure of the eastbound mainlanes at Loop 1604 for bridge work.
  • Continuing through Saturday, August 20. I-10 EB exit to Ackerman closed continuously for overpass work. Detour: Eastbound I-10 traffic can exit at Foster Road, turnaround at intersection, and use westbound frontage road back to Ackerman. Click here for detour map. 

I-410 – North San Antonio

  • Sunday, July 31 until Saturday, August 6. 9:00 p.m. to 5:00 a.m. Right lane closure on eastbound frontage road of I-410 from Starcrest Drive to Perrin Beitel Road for utility inspection work. 

I-410 – South San Antonio

  • Sunday, July 31. 7 a.m. to 4 p.m. Full closure of the mainlanes, in both directions, at Somerset Rd. for utility work. Traffic will be stopped intermittently throughout the day in 15 minute intervals. 

I-410 – East San Antonio

  • Continuing through Friday, August 12. NIGHTTIME northbound I-410 exit to eastbound I-10 closure from 9 p.m. to 5 a.m. for overpass work. Click here for detour map.
  • Continuing through Friday, August 12. DAYTIME southbound I-410 frontage road alternating lane closures between I-10 and East Houston Street from 8 a.m. to 5 p.m. for concrete work.
  • Friday, July 29 through Friday, August 12. DAYTIME northbound I-410 frontage road left lane closures between East Houston Street and Ackerman Road from 8 a.m. to 5 p.m. for wall work.    

I-410 – West San Antonio

  • Current until Monday, August 1. 9 a.m. to 3 p.m. Alternating lane closures of the frontage roads, in both directions, from Marbach Rd. to Ingram Rd. for road work.
  • Current until Monday, August 1. 8 p.m. to 5 a.m. Full closure of the northbound frontage road from Marbach Rd. to SH 151 for barrier work.
  • Current until Monday, August 1. 9 a.m. to 3 p.m. Alternating lane closures on the frontage roads, in both directions, from Marbach Rd. to Ingram Rd. for road work.
  • Current until Monday, August 1. 8 p.m. to 5 a.m. Alternating full southbound mainlane closures from Bandera Rd. to Marbach Rd. for mill and overlay work. 

SH 151 – Bexar County

  • Current until Monday, August 1. 8 p.m. to 5 a.m. Full closure of the westbound frontage road at Loop 410 for traffic switch. 

PA 1502 – Wurzbach Parkway

  • Monday, August 1 until Wednesday, August 31. 9 a.m. to 3 p.m. Various lane closures, in both directions, from Blanco Rd. to Wetmore Rd. for road work.
  • Monday, August 1 until Friday, August 12. 9 a.m. to 4 p.m. Right turn lane closure, in all directions, at the Lockhill Selma Rd. intersection for curb installation. 

Lockhill Selma Rd. – Bexar County

  • Monday, August 1 until Friday, August 12. 9 a.m. to 4 p.m. Right turn lane closure, in both directions, at the Wurzbach Parkway intersection for curb installation. 

FM 1535 – N.W. Military Highway

  • Monday, August 1 until Friday, August 12. 9 a.m. to 4 p.m. Right turn lane closures, in both directions, at Wurzbach Parkway intersection for curb installation. 

SH 181 – Bexar County

  • Monday, August 1 until Friday, August 5. 7 a.m. to 8 p.m. Single southbound lane closure from I-37 to Corpus Christi Rd. for seal coat work. 

FM 725 – Comal County

  • Current until Thursday, September 1. Full closure of the northbound to southbound turnaround at I-35 for operational improvements.

Friday, July 22

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North West San Antonio/Bexar County

  • Sunday, July 17 until Friday, July 29. Weeknights 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Bandera Road (SH 16) to IH-10 for barrier setting.
  • Sunday, July 17 until Friday, July 29. Weeknights 9 p.m. until 5 a.m. Alternating westbound mainlane closure from IH-10 to Bandera Road (SH 16) for barrier setting.
  • Sunday, July 17 until Friday, July 29. Weeknights 9 p.m. until 5 a.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for barrier setting.
  • Sunday, July 17 until Friday, July 29. Weeknights 9 p.m. until 5 a.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for barrier setting.
  • Sunday, July 17 until Friday, July 29. Weeknights 9 p.m. until 5 a.m. Westbound to eastbound turnaround closure left inside lane at the Loop 1604 intersection at Bandera Road (SH 16) for bridge widening construction. Traffic will utilize the existing signalized intersection.
  • Sunday, July 17 until Friday, July 29. Weeknights 9 p.m. until 5 a.m. Eastbound to westbound turnaround closure left inside lane at the Loop 1604 intersection at Bandera Road (SH 16) for bridge widening construction. Traffic will utilize the existing signalized intersection.
  • Sunday, July 17 until Friday, July 29. Weeknights 9 p.m. until 5 a.m. Westbound mainlane full closure from Chase Hill Boulevard/Brennan Avenue to Kyle Seale Parkway for bridge construction: caps, beams & rail demo.
  • Sunday, July 17 until Friday, July 29. Weeknights 9 p.m. until 5 a.m. Eastbound mainlane full closure from Kyle Seale Parkway to Chase Hill Boulevard for bridge construction.
  • Sunday, July 17 until Friday, July 29. Weeknights 9 p.m. until 5 a.m. Westbound to eastbound turnaround closure at Loop 1604 and La Cantera Parkway/John Peace Boulevard for bridge construction. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, July 18 until Friday, July 29. Weekdays 9 a.m. until 3 p.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for barrier setting.
  • Monday, July 18 until Friday, July 29. Weekdays 9 a.m. until 3 p.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for barrier setting.
  • Monday, July 18 until Friday, July 29. Weekdays 9 a.m. until 3 p.m. Eastbound frontage road right outside lane closure from Babcock Road to Chase Hill Boulevard/Brennan Avenue for gas utility work.
  • Monday, July 18 until Friday, July 29. Weekdays 9 a.m. until 5 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Hausman Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, July 18 until Friday, July 29. Weekdays 9 a.m. until 5 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Hausman Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, July 18 until Friday, July 29. Weekdays 9 a.m. until 5 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Kyle Seale Parkway for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, July 18 until Friday, July 29. Weekdays 9 a.m. until 5 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Kyle Seale Parkway for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, July 18 until Friday, July 29. Weekdays 9 a.m. until 5 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, July 18 until Friday, July 29. Weekdays 9 a.m. until 5 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, July 18 until Friday, July 29. Weekdays 9 a.m. until 5 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, July 18 until Friday, July 29. Weekdays 9 a.m. until 5 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Sunday, July 24 only. Nightly closure 9 p.m. until 5 a.m. Full closure of Bandera Road (SH 16) at the Loop 1604 intersection, both directions, including turnarounds for bridge construction.
  • Friday, July 22 at 9 p.m. until Monday, August 1 at 5 a.m. Weekends (Friday – Monday) Only. Eastbound mainlane entrance ramp full closure from La Cantera Parkway for storm drainage. Traffic will continue on the Loop 1604 eastbound frontage road to the IH-10 interchange. 

Loop 1604 – North Central San Antonio/Bexar County

  • Monday, July 25 until Friday, July 29. Nightly 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Tradesman Road to US 281 exit ramp for barrier setting and striping.
  • Monday, July 25 until Friday, July 29. Nightly 9 p.m. until 5 a.m. Alternating westbound mainlane closure from US 281 exit ramp to Tradesman Road for barrier setting and striping.
  • Monday, July 25 until Friday, July 29. Nightly 9 p.m. until 5 a.m. Alternating eastbound frontage road closure from IH-10 to US 281 for barrier setting and striping.
  • Monday, July 25 until Friday, July 29. Nightly 9 p.m. until 5 a.m. Alternating westbound frontage road closure from US 281 to IH-10 for barrier setting and striping.
  • Sunday, July 24 until Friday, July 29. Nightly 9 p.m. until 5 a.m. Westbound to eastbound turnaround full closure at Loop 1604 and NW Military Highway for drilling shafts.
  • Monday, July 25 until Friday, July 29. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround full closure at Loop 1604 and Lockhill Selma Road for concrete
  • island demo and temporary traffic signal work.
  • Monday, July 25 until Friday, July 29. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround short term full closure at Loop 1604 and NW Military Highway for concrete placement and drill shafts.
  • Thursday, July 21 until Sunday, July 31. Weekdays/Weeknights 12 a.m. until 12 a.m. eastbound to westbound turnaround full closure at Loop 1604 and NW Military Highway for bridge widening construction.
  • Sunday, July 24 until Monday, July 25 from 9:00 p.m. until 5:00 a.m. Eastbound mainlane full closure from IH-10 to Lockhill Selma Road for OSB removal. 

Loop 1604 – North East San Antonio/Bexar County

  • Sunday, July 24 until Friday, July 29. 9:00 p.m. to 5:00 a.m. Multiple lane closures on westbound Loop 1604 frontage road from Lookout Road to Nacogdoches Road for geotechnical and drilling work.
  • Sunday, July 24 until Friday, July 29. 9:00 p.m. to 5:00 a.m. Eastbound to westbound turnaround closure at Lookout Road for geotechnical and drilling work. Traffic will use the traffic signals at Lookout Road intersection to access westbound Loop 1604.
  • Sunday, July 24 until Friday, July 29. 9:00 p.m. to 5:00 a.m. Right lane closure of Loop 1604 frontage road eastbound to westbound turnaround from Nacogdoches Road to Union Pacific Railroad for geotechnical and drilling work.
  • Sunday, July 24 until Friday, July 29. 9:00 p.m. to 5:00 a.m. Left lane closure on Loop 1604 frontage road turnaround from Lookout Road to Union Pacific Railroad for geotechnical and drilling work.
  • Sunday, July 24 until Saturday, July 30. 9:00 p.m. to 5:00 a.m.  Alternating lane closures for westbound Loop 1604 entrance ramp and eastbound-to-westbound turnaround from Lookout Road to Union Pacific Railroad for striping and barrier work.
  • Sunday, July 24 until Saturday, July 30. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound Loop 1604 frontage road between Gateway Boulevard to Lookout Road for striping and barrier work.
  • Sunday, July 24 until Saturday, July 30. 9:00 p.m. to 5:00 a.m. Multiple lane closures on westbound Loop 1604 frontage road bypass between Union Pacific Railroad and Nacogdoches Road for striping and barrier work.
  • Sunday, July 24 until Saturday, July 30. 9:00 p.m. to 5:00 a.m. Alternating lane closures on Loop 1604 frontage road eastbound to westbound turnaround between Nacogdoches Road and Union Pacific Railroad for striping and barrier work.
  • Sunday, July 24 until Saturday, July 30. 9:00 p.m. to 5:00 a.m. Alternating lane closures on Loop 1604 frontage road westbound to eastbound turnaround between Lookout Road and Union Pacific Railroad for striping and barrier work.
  • Sunday, July 24 until Saturday, July 30. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound Loop 1604 between Nacogdoches Road and I-35 for striping and barrier work.
  • Sunday, July 24 until Saturday, July 30. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound Loop 1604 between I-35 and Nacogdoches Road for striping and barrier work.
  • Sunday, July 24 until Saturday, July 30. 9:00 p.m. to 5:00 a.m. Left lane closure on Loop 1604 frontage road and entrance ramp to Loop 1604 between Nacogdoches Road and Union Pacific Railroad for striping and barrier work. Traffic must continue on eastbound frontage road bypass to access Loop 1604.
  • Sunday, July 24 until Saturday, July 30. 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound Loop 1604 bypass frontage road ramp to Lookout Road for striping and barrier work.
  • Sunday, July 24 until Saturday, July 30. 9:00 p.m. to 5:00 a.m. Westbound Loop 1604 frontage road exit ramp closure from IKEA-RBFCU Parkway to Lookout Road for striping and barrier work. Traffic must use Lookout Road Exit.
  • Sunday, July 24 until Saturday, July 30. 9:00 p.m. to 5:00 a.m. Westbound Loop 1604 entrance ramp closure from Union Pacific Railroad to Nacogdoches Road  for striping and barrier work. Traffic must use the next entrance ramp and follow the detour signs.
  • Monday, July 25 until Sunday, July 31 9:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound Loop 1604 frontage road from Nacogdoches Road to Union Pacific Railroad for barrier work. 

US 281 – North San Antonio/Bexar County

  • Monday, July 25 until Thursday, August 4. 9 p.m. to 5 a.m. Wilderness Oak and Overlook Parkway intersection closed for bridge work. 

I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

  • Sunday, July 24 until Tuesday, July 26. 9 p.m. to 5 a.m. Alternating northbound mainlanes and ramps from Guadalupe River to FM 306 for paving work.
  • Sunday, July 24 until Thursday, July 28. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35 and left lane closure on southbound frontage road of I-35 from Judson Road to O’Connor Road for sign and barrier work.
  • Sunday, July 24 until Thursday, July 28. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35, left lane closure on southbound frontage road and closure of southbound I-35 entrance ramp from Pat Booker Road to Ferrell Road for barrier work.
  • Sunday, July 24 until Friday, July 29. 9:00 p.m. to 5:00 a.m. FM 1518 exit ramp (exit 174A) closure on northbound I-35 and left lane closure on northbound frontage road of I-35 from exit 174A to Pasatiempo for geotechnical and drilling work. Traffic must follow the detour signs.
  • Sunday, July 24 until Friday, July 29. 9:00 p.m. to 5:00 a.m. Right lane closure on northbound I-35 from Olympia Parkway to Pasatiempo for geotechnical and drilling work.
  • Sunday, July 24 until Friday, July 29. 9:00 p.m. to 5:00 a.m. Right lane closure on northbound I-35, Pat Booker Road exit ramp closure, and left lane closure on northbound frontage road of I-35 from Toepperwein Road to Shin Oak Road for geotechnical and drilling work. All traffic must exit Toepperwein Road (exit 170B) and follow the signs.
  • Sunday, July 24 until Friday, July 29. 9:00 p.m. to 5:00 a.m. Left lane closure on I-35 northbound frontage road from Pat Booker Road to Loop 1604 for geotechnical and drilling work.
  • Sunday, July 24 until Friday, July 29. 9:00 p.m. to 5:00 a.m. Right lane closure of southbound I-35 connector ramp from IKEA-RBFCU Parkway to McMorris Boulevard for geotechnical and drilling work.
  • Sunday, July 24 until Friday, July 29. 9:00 p.m. to 5:00 a.m. Northbound-to-southbound turnaround closure at Thousand Oaks Drive for geotechnical and drilling work. Traffic will use the traffic signals at Thousand Oaks intersection to access southbound I-35 frontage road.
  • Sunday, July 24 until Friday, July 29. 9:00 p.m. to 5:00 a.m. Right shoulder closure on northbound I-35 connector ramp from Loop 1604 to Forum Parkway for geotechnical and drilling work.
  • Sunday, July 24 until Friday, July 29. 9:00 p.m. to 5:00 a.m. Left lane closure on northbound frontage road of I-35 from Chelsea Place to Schertz Parkway for geotechnical and drilling work.
  • Sunday, July 24 until Friday, July 29. 9:00 p.m. to 5:00 a.m. Olympia Parkway exit ramp (exit 173) closure on northbound I-35 and left lane closure on northbound frontage road of I-35 from Forum Access to Olympia Parkway for geotechnical and drilling work. Traffic must use the Loop 1604 exit ramp (exit 172) and follow the detour signs.
  • Sunday, July 24 until Friday, July 29. 9:00 p.m. to 5:00 a.m. Left lane closure on northbound frontage road of I-35 from Olympia Parkway to Pasatiempo for geotechnical and drilling work.
  • Monday, July 25 until Thursday, July 28. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35 and left lane closure on southbound frontage road of I-35 between Judson Road and O’Connor Road for barrier and sign work.
  • Monday, July 25 until Thursday, July 28. 9:00 p.m. to 5:00 a.m. Multiple lane closures on southbound I-35 between Judson Road and O’Connor Road for striping and barrier work.  

I-10 – East San Antonio/Bexar County

  • Monday, July 25 until Tuesday, July 26. 8:30 p.m. to 5:30 a.m. Full eastbound mainlane closure at FM 1518 for bridge work.
  • Monday, July 25 until Thursday, July 28. 9 p.m. to 5 a.m. Full eastbound mainlane closure from FM 1516 to Weichold Rd. for bridge work.
  • Wednesday, July 20 to Saturday, August 20. I-10 EB exit to Ackerman closed continuously for overpass work. Detour: Eastbound I-10 traffic can exit at Foster Road, turnaround at intersection, and use westbound frontage road back to Ackerman. Click here for detour map.
  • Friday, July 22 through Wednesday, July 27. DAYTIME westbound I-10 frontage road left lane closure between FM 1516 and Loop 1604 from 6 a.m. to 4:30 p.m. for drainage work.   
  • Continuing through Saturday, August 20. I-10 EB exit to Ackerman closed continuously for overpass work. Detour: Eastbound I-10 traffic can exit at Foster Road, turnaround at intersection, and use westbound frontage road back to Ackerman. Click here for detour map.
  • Friday, July 22 through Wednesday, July 27. DAYTIME westbound I-10 frontage road left lane closure between FM 1516 and Loop 1604 from 6 a.m. to 4:30 p.m. for drainage work.
  • Monday, July 25 through Thursday, July 28 from 9 p.m. to 5 a.m.  NIGHTTIME full eastbound mainlane closure between FM 1516 and Weichold Road for overpass work. Detour: Eastbound I-10 traffic will take Loop 1604 exit, use the frontage road, and take next entrance ramp.   

I-410 – East San Antonio

  • Continuing through Monday, August 1. NIGHTTIME northbound I-410 exit to eastbound I-10 closure from 9 p.m. to 5 a.m. for overpass work. Click here for detour map.
  • Continuing through Monday, August 1. DAYTIME southbound I-410 frontage road alternating lane closures between I-10 and East Houston Street from 8 a.m. to 5 p.m. for concrete work.
  • Continuing through Monday, August 1. DAYTIME northbound I-410 frontage road alternating lane closures between East Houston Street and Ackerman Road from 8 a.m. to 5 p.m. for wall work.    

I-410 – West San Antonio

  • Current until Monday, July 25. 7 p.m. to 5 a.m. Full closure of the southbound mainlanes from Ingram Rd. to US 90 for mill and overlay work.
  • Current until Monday, August 1. 9 a.m. to 3 p.m. Alternating lane closures of the frontage roads, in both directions, from Marbach Rd. to Ingram Rd. for road work.
  • Current until Monday, August 1. 8 p.m. to 5 a.m. Full closure of the northbound frontage road from Marbach Rd. to SH 151 for barrier work.
  • Current until Monday, August 1. 9 a.m. to 3 p.m. Alternating lane closures on the frontage roads, in both directions, from Marbach Rd. to Ingram Rd. for road work.
  • Current until Monday, August 1. 8 p.m. to 5 a.m. Alternating full southbound mainlane closures from Bandera Rd. to Marbach Rd. for mill and overlay work. 

SH 151 – Bexar County

  • Current until Monday, August 1. 8 p.m. to 5 a.m. Full closure of the westbound frontage road at Loop 410 for traffic switch. 

PA 1502 – Wurzbach Parkway

  • Current until Friday, July 29. 9 a.m. to 3 p.m. Various lane closures, in both directions, at Wurzbach Parkway intersection for pothole and ITS work.
  • Monday, August 1 until Wednesday, August 31. 9 a.m. to 3 p.m. Various lane closures, in both directions, from Blanco Rd. to Wetmore Rd. for road work. 

Lockhill Selma Rd. – Bexar County

  • Current until Friday, July 29. 9 a.m. to 4 p.m. Right turn lane closures, in all directions, at the Wurzbach Parkway intersection. 

FM 1535 – N.W. Military Highway

  • Current until Friday, July 29. 9 a.m. to 4 p.m. Various lane closures, in both directions, at the Wurzbach Parkway intersection. 

US 90 – Bexar County

  • Monday, July 25. 5 a.m. to 4 p.m. Westbound mainlane closure from Loop 410 to Medina County Line for mill and inlay operations.
  • Tuesday, July 26 until Thursday, July 28. 9 p.m. to 5 a.m. Single lane closures on the frontage roads, in both directions, at Montgomery Rd. for pavement marking installations. 

FM 2252 – Nacogdoches Road

  • Sunday, July 24 until Tuesday, July 26. 6 p.m. to 6 a.m. Single lane closures, in both directions, at the Evans Rd. intersection for hot mix operations. 

FM 725 – Comal County

  • Current until Thursday, September 1. Full closure of the northbound to southbound turnaround at I-35 for operational improvements.

Friday, July 15

UPCOMING SCHEUDLED CONSTRUCTION CLOSURES

Loop 1604 – North West San Antonio/Bexar County

  • Sunday, July 17 until Friday, July 29. Weeknights 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Bandera Road (SH 16) to IH-10 for barrier setting.
  • Sunday, July 17 until Friday, July 29. Weeknights 9 p.m. until 5 a.m. Alternating westbound mainlane closure from IH-10 to Bandera Road (SH 16) for barrier setting.
  • Sunday, July 17 until Friday, July 29. Weeknights 9 p.m. until 5 a.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for barrier setting.
  • Sunday, July 17 until Friday, July 29. Weeknights 9 p.m. until 5 a.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for barrier setting.
  • Sunday, July 17 until Friday, July 29. Weeknights 9 p.m. until 5 a.m. Westbound to eastbound turnaround closure left inside lane at the Loop 1604 intersection at Bandera Road (SH 16) for bridge widening construction. Traffic will utilize the existing signalized intersection.
  • Sunday, July 17 until Friday, July 29. Weeknights 9 p.m. until 5 a.m. Eastbound to westbound turnaround closure left inside lane at the Loop 1604 intersection at Bandera Road (SH 16) for bridge widening construction. Traffic will utilize the existing signalized intersection.
  • Sunday, July 17 until Friday, July 29. Weeknights 9 p.m. until 5 a.m. Westbound mainlane full closure from Chase Hill Boulevard/Brennan Avenue to Kyle Seale Parkway for bridge construction: caps, beams & rail demo.
  • Sunday, July 17 until Friday, July 29. Weeknights 9 p.m. until 5 a.m. Eastbound mainlane full closure from Kyle Seale Parkway to Chase Hill Boulevard for bridge construction.
  • Sunday, July 17 until Friday, July 29. Weeknights 9 p.m. until 5 a.m. Westbound to eastbound turnaround closure at Loop 1604 and La Cantera Parkway/John Peace Boulevard for bridge construction. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, July 18 until Friday, July 29. Weekdays 9 a.m. until 3 p.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for barrier setting.
  • Monday, July 18 until Friday, July 29. Weekdays 9 a.m. until 3 p.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for barrier setting.
  • Monday, July 18 until Friday, July 29. Weekdays 9 a.m. until 3 p.m. Eastbound frontage road right outside lane closure from Babcock Road to Chase Hill Boulevard/Brennan Avenue for gas utility work.
  • Monday, July 18 until Friday, July 29. Weekdays 9 a.m. until 5 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Hausman Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, July 18 until Friday, July 29. Weekdays 9 a.m. until 5 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Hausman Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, July 18 until Friday, July 29. Weekdays 9 a.m. until 5 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Kyle Seale Parkway for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, July 18 until Friday, July 29. Weekdays 9 a.m. until 5 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Kyle Seale Parkway for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, July 18 until Friday, July 29. Weekdays 9 a.m. until 5 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, July 18 until Friday, July 29. Weekdays 9 a.m. until 5 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, July 18 until Friday, July 29. Weekdays 9 a.m. until 5 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time.
  • Monday, July 18 until Friday, July 29. Weekdays 9 a.m. until 5 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Full alternating turnaround closures. Only one direction turnaround to be closed at a time. 

Loop 1604 – North Central San Antonio/Bexar County

  • Sunday, July 17 until Friday, July 22. Nightly 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Tradesman Road to US 281 exit ramp for barrier setting and striping.
  • Sunday, July 17 until Friday, July 22. Nightly 9 p.m. until 5 a.m. Alternating westbound mainlane closure from US 281 exit ramp to Tradesman Road for barrier setting and striping.
  • Sunday, July 17 until Friday, July 22. Nightly 9 p.m. until 5 a.m. Alternating eastbound frontage road closure from IH-10 to US 281 for barrier setting and striping.
  • Sunday, July 17 until Friday, July 22. Nightly 9 p.m. until 5 a.m. Alternating westbound frontage road closure from US 281 to IH-10 for barrier setting and striping.
  • Sunday, July 17 until Friday, July 22. Nightly 9 p.m. until 5 a.m. Westbound to eastbound frontage road full closure at Loop 1604 and NW Military Highway for drilling shafts.
  • Monday, July 18 until Friday, July 22. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Lockhill Selma Road for concrete island demo and temporary traffic signal work.
  • Monday, July 18 until Friday, July 22. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Lockhill Selma Road for concrete island demo and temporary traffic signal work.
  • Monday, July 18 until Friday, July 22. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround short term full closure at Loop 1604 and NW Military Highway for concrete placement and drill shafts.
  • Monday, July 18 until Friday, July 22. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and NW Military Highway for concrete island demo and traffic signal work.
  • Thursday, July 21 until Sunday, July 31. Weekdays/Weeknights 12 a.m. until 12 a.m. eastbound to westbound turnaround full closure at Loop 1604 and NW Military Highway for bridge widening construction. 

Loop 1604 – North East San Antonio/Bexar County

  • Sunday July 17 until Friday July 22. 9:00 p.m. to 5:00 a.m. Left lane closure on westbound Loop 1604 from Pat Booker Road to Gateway Boulevard for geotechnical drilling work.
  • Sunday July 17 until Friday July 22. 9:00 p.m. to 5:00 a.m. Various lane closures on westbound frontage road of Loop 1604 from Lookout Road to Nacogdoches Road for geotechnical drilling work.
  • Sunday July 17 until Friday July 22. 9:00 p.m. to 5:00 a.m. Eastbound to westbound turnaround closure at Lookout Road for geotechnical and drilling work. Traffic will use the traffic signals at Lookout Road intersection to access westbound Loop 1604.
  • Sunday July 17 until Friday July 22. 9:00 p.m. to 5:00 a.m. Right lane closure on frontage road of Loop 1604 turnaround from Nacogdoches Road to Union Pacific Railroad for geotechnical drilling work.
  • Sunday July 17 until Friday July 22. 9:00 p.m. to 5:00 a.m. Left lane closure on frontage road of Loop 1604 turnaround from Lookout Road to Union Pacific Railroad for geotechnical drilling work.
  • Sunday July 17 until Friday July 22. 9:00 p.m. to 5:00 a.m. Closure on westbound Loop 1604 connector ramp from Pat Booker Road to Gateway Boulevard for geotechnical and drilling work. All traffic must continue on northbound I-35 frontage road and make a U-turn at Forum Parkway to continue on southbound I-35 frontage road to access westbound 1604.
  • Sunday July 17 until Friday July 22. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound Loop 1604 connector ramp from I-35 to Pat Booker Road for survey work.
  • Sunday July 17 until Saturday July 23. 9:00 p.m. to 5:00 a.m. Left lane closure on Loop 1604 frontage road and entrance ramp to Loop 1604 between Nacogdoches Road./FM 2252 and Union Pacific Railroad for striping work.
  • Sunday July 17 until Saturday July 23. 9:00 p.m. to 5:00 a.m. Various lane closures on eastbound Loop 1604 bypass frontage road ramp to Lookout Road. for striping work.
  • Sunday July 17 until Saturday July 23. 9:00 p.m. to 5:00 a.m. Right lane closure on eastbound frontage road to Loop 1604 between Nacogdoches Road/FM 2252 and Union Pacific Railroad for striping work.
  • Sunday July 17 until Saturday July 23. 09:00 p.m. to 5:00 a.m. Lookout Road exit ramp closure on eastbound Loop 1604 for striping work. Traffic must continue eastbound Loop 1604 and use the IKEA-RBFCU Pkwy exit ramp to access Lookout Road.
  • Monday July 18 until Friday July 22. 9:00 p.m. to 5:00 a.m. Various lane closures on eastbound Loop 1604 from Nacogdoches Road to Union Pacific Railroad for barrier work.
  • Monday July 18 until Monday July 25. 9:00 p.m. to 5:00 a.m. Various lane closures on eastbound Loop 1604 frontage road from Nacogdoches Road to Union Pacific Railroad for barrier work.
  • Tuesday July 19 until Saturday July 23. 9:00 p.m. to 5:00 a.m. Eastbound entrance ramp closure to Loop 1604 between Nacogdoches Road/FM 2252 and Union Pacific Railroad for striping work.
  • Tuesday July 19 until Saturday July 23. 9:00 p.m. to 5:00 a.m. Various lane closures on eastbound Loop 1604 bypass frontage road ramp to Lookout Road for striping work.
  • Tuesday July 19 until Saturday July 23. 9:00 p.m. to 5:00 a.m. Westbound Loop 1604 frontage road exit ramp closure from RBFCU-IKEA Parkway to Lookout Road for barrier and striping work. Traffic must continue on westbound Loop 1604 and use the Lookout Road exit ramp.
  • Tuesday July 19 until Saturday July 23. 9:00 p.m. to 5:00 a.m. Westbound Lookout Road exit ramp closure between between RBFCU-IKEA Parkway to Lookout Road for barrier and striping work. Traffic must continue on westbound Loop 1604 and use the Nacogdoches Road exit ramp and make U-turn to access Lookout Road.
  • Tuesday July 19 until Saturday July 23. 9:00 p.m. to 5:00 a.m. Various lane closures on westbound Loop 1604 entrance ramp from Lookout Road to Union Pacific Railroad for barrier and striping work.
  • Tuesday July 19 until Saturday July 23. 9:00 p.m. to 5:00 a.m. Westbound Nacogdoches exit ramp closure from Union Pacific Railroad to Nacogdoches Road for barrier and striping work. Traffic must continue on westbound Loop 1604 and use the Green Mountain exit ramp and make U-turn to access Nacogdoches Road.
  • Tuesday July 19 until Saturday July 23. 9:00 p.m. to 5:00 a.m. Westbound Loop 1604 entrance ramp closure from Union Pacific Railroad to Nacogdoches Road for barrier and striping work. Traffic must continue on westbound Loop 1604 frontage road and use the Lookout Road exit ramp.
  • Tuesday July 19 until Saturday July 23. 9:00 p.m. to 5:00 a.m. Various lane closures on westbound Loop 1604 frontage road between RBFCU-IKEA Parkway to Lookout Road for barrier and striping work.
  • Tuesday July 19 until Saturday July 23. 9:00 p.m. to 5:00 a.m. Various lane closures of westbound Loop 1604 frontage road bypass from Lookout Road to Union Pacific Railroad for barrier and striping work.
  • Tuesday July 19 until Saturday July 23. 9:00 p.m. to 5:00 a.m. Various lane closures on westbound Loop 1604 frontage road bypass between Union Pacific Railroad and Nacogdoches Road for barrier and striping work.
  • Tuesday July 19 until Saturday July 23. 9:00 p.m. to 5:00 a.m. Various lane closures on Loop 1604 frontage road eastbound to westbound turnaround between Nacogdoches Road and Union Pacific Railroad for barrier and striping work.
  • Tuesday July 19 until Saturday July 23. 9:00 p.m. to 5:00 a.m. Various lane closures on Loop 1604 frontage road westbound to eastbound turnaround between Lookout Road and Union Pacific Railroad for barrier and striping work.
  • Tuesday July 19 until Saturday July 23. 9:00 p.m. to 5:00 a.m. Various lane closures on eastbound Loop 1604 between Nacogdoches Road and I-35 for barrier and striping work.
  • Tuesday July 19 until Saturday July 23. 9:00 p.m. to 5:00 a.m. Various lane closures on westbound Loop 1604 between I-35 and Nacogdoches Road for barrier and striping work. 

US 281 – North San Antonio/Bexar County

  • Monday, July 18. 8 p.m. to 6 a.m. Full closure of the Overlook Parkway intersection for bridge work. 

I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

  • Sunday, July 17 until Friday, July 22. 9 p.m. to 5 a.m. Alternating southbound mainlanes and ramps from Guadalupe River to FM 306 for paving work.
  • Sunday, July 17 until Friday, July 22. 9:00 p.m. to 5:00 a.m. Right lane closure on northbound frontage road of I-35 from Pat Booker Road to Loop 1604 for geotechnical and drilling work.
  • Sunday, July 17 until Friday, July 22. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35 from Forum Parkway to Pat Booker Road for geotechnical and drilling work.
  • Sunday, July 17 until Friday, July 22. 9:00 p.m. to 5:00 a.m. Left lane closure on northbound I-35 from Pat Booker Road to Forum Parkway for geotechnical and drilling work.
  • Sunday, July 17 until Friday, July 22. 9:00 p.m. to 5:00 a.m. Left lane closure on northbound frontage road of I-35 from Pat Booker Road to Forum Parkway for geotechnical drilling work.
  • Sunday, July 17 until Friday, July 22. 9:00 p.m. to 5:00 a.m. Olympia Parkway exit ramp (exit 173) closure on northbound I-35 and left lane closure on northbound frontage road of I-35 from Forum Access to Olympia Parkway for geotechnical drilling work. All traffic must exit at Loop 1604 exit 172.
  • Sunday, July 17 until Friday, July 22. 9:00 p.m. to 5:00 a.m. Left lane closure on northbound frontage road of I-35 from Olympia Parkway to Pasatiempo for geotechnical drilling work.
  • Sunday, July 17 until Friday, July 22. 9:00 p.m. to 5:00 a.m. FM 1518 exit ramp (exit 174A) closure on northbound I-35 and left lane closure on northbound frontage road of I-35 from FM 1518 exit ramp (exit 174A) to Pasatiempo for geotechnical drilling work. All traffic must exit at Olympia Pkwy.
  • Sunday, July 17 until Friday, July 22. 9:00 p.m. to 5:00 a.m. Right lane closure on northbound I-35 frontage road between Olympia Pkwy and Pasatiempo for geotechnical drilling work.
  • Sunday, July 17 until Friday, July 22. 9:00 p.m. to 5:00 a.m. Right exit lane closure on northbound I-35, Pat Booker Road exit ramp closure and left lane closure on northbound frontage road of I-35 from Toepperwein Road to Shin Oak Road for geotechnical drilling. All traffic must exit at Toepperwein Road.
  • Sunday, July 17 until Friday, July 22. 9:00 p.m. to 5:00 a.m. Right lane closure of I-35 connector ramp from IKEA-RBFCU Parkway to McMorris Boulevard for survey work.
  • Sunday, July 17 until Friday, July 22. 9:00 p.m. to 5:00 a.m. Northbound-to-southbound turnaround closure at Thousand Oaks Drive for geotechnical and drilling work. Traffic will use the traffic signals at Thousand Oaks intersection to access southbound I-35 frontage road.
  • Sunday, July 17 until Saturday, July 23. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35 and left lane closure on southbound frontage road of I-35 between Judson Road and O’Connor Road for barrier and sign work.
  • Sunday, July 17 until Saturday, July 23. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35 and left lane closure on southbound frontage road of I-35 between Judson Road and O’Connor Road for barrier and sign work.
  • Monday, July 18 until Wednesday, July 20. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound frontage road of I-35 from IKEA-RBFCU Parkway to Pat Booker Road for barrier work.
  • Monday, July 18 until Wednesday, July 20. 9:00 p.m. to 5:00 a.m. Left lane closure on northbound frontage road of I-35 from Chelsea Place to Schertz Parkway for geotechnical and drilling work.
  • Monday, July 18 until Wednesday, July 20. 9:00 p.m. to 5:00 a.m. Right shoulder closure on northbound I-35 connector ramp from Loop 1604 to Forum Parkway for geotechnical drilling work.
  • Monday, July 18 until Saturday, July 23. 9:00 p.m. to 5:00 a.m. Southbound I-35 entrance ramp closure and right lane closure from Pat Booker Road to Ferrell Road for barrier work. All traffic must continue on southbound I-35 frontage road to access southbound I-35 mainlane.
  • Monday, July 18 until Saturday, July 23. 9:00 p.m. to 5:00 a.m. Pat Booker Road exit ramp closure on southbound I-35 connector ramp from McMorris Boulevard to Pat Booker Road for barrier work. All traffic must continue southbound on I-35 mainlane and U-turn at Judson Road to access Pat Booker Road.
  • Tuesday, July 19 until Saturday July 23. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35 frontage road from IKEA-RBFCU Parkway to Pat Booker Road for barrier work.
  • Tuesday, July 19 until Saturday, July 23. 9:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35 frontage road from IKEA-RBFCU Parkway to Pat Booker Road for barrier work.
  • Tuesday, July 19 until Saturday, July 23. 9:00 p.m. to 5:00 a.m. Alternating lane closures on westbound and eastbound Pat Booker Road from southbound I-35 frontage road to northbound I-35 frontage road for barrier work. 

I-10 – North West San Antonio/Bexar County

  • Monday, July 18. 9 a.m. to 1 p.m. Single westbound mainlane closure from Bexar County Line to Fair Oaks Parkway for illumination work. 

I-10 – East San Antonio/Bexar County

  • Current until Friday, July 22. 6 a.m. to 4:30 p.m. Single lane closure on the westbound frontage road from Loop 1604 to FM 1516 for storm drain improvements.
  • Monday, July 18 until Thursday, July 21. 8:30 p.m. to 5:30 a.m. Full westbound mainlane closure from Zuehl Rd. to FM 2538 for bridge work.
  • Tuesday, July 19 until Thursday, July 21. 6 p.m. to 10 a.m. Single eastbound mainlane closure from FM 2538 to Zuehl Rd. for bridge work.
  • Monday, July 25 until Tuesday, July 26. 8:30 p.m. to 5:30 a.m. Full eastbound mainlane closure at FM 1518 for bridge work.
  • Wednesday, July 20 to Saturday, August 20. I-10 EB exit to Ackerman closed continuously for overpass work. Detour: Eastbound I-10 traffic can exit at Foster Road, turnaround at intersection, and use westbound frontage road back to Ackerman. Click here for detour map.
  • Friday, July 22 through Wednesday, July 27. DAYTIME westbound I-10 frontage road left lane closure between FM 1516 and Loop 1604 from 6 a.m. to 4:30 p.m. for drainage work.    

I-410 – East San Antonio

  • Continuing through Monday, August 1. NIGHTTIME northbound I-410 exit to eastbound I-10 closure from 9 p.m. to 5 a.m. for overpass work. Click here for detour map.
  • Continuing through Monday, August 1. DAYTIME southbound I-410 frontage road alternating lane closures between I-10 and East Houston Street from 8 a.m. to 5 p.m. for concrete work.
  • Continuing through Monday, August 1. DAYTIME northbound I-410 frontage road alternating lane closures between East Houston Street and Ackerman Road from 8 a.m. to 5 p.m. for wall work.    

I-410 – West San Antonio

  • Current until Monday, July 25. 7 p.m. to 5 a.m. Full closure of the southbound mainlanes from Ingram Rd. to US 90 for mill and overlay work.
  • Monday, July 18 until Friday, July 22. 9 p.m. to 5 a.m. Single northbound  mainlane closure from Old Pearsall Rd. to Medina Base Rd. for barrier work.
  • Monday, July 18 until Monday, August 1. 9 a.m. to 3 p.m. Alternating lane closures of the frontage roads, in both directions, from Marbach Rd. to Ingram Rd. for road work.
  • Saturday, July 16 until Saturday, July 23. 8 p.m. to 5 a.m. Full closure of northbound entrance ramp from Marbach Rd. for barrier work.
  • Sunday, July 17 until Monday, August 1. 8 p.m. to 5 a.m. Full closure of the northbound frontage road from Marbach Rd. to SH 151 for barrier work.
  • Monday, July 18 until Monday, August 1. 9 a.m. to 3 p.m. Alternating lane closures on the frontage roads, in both directions, from Marbach Rd. to Ingram Rd. for road work.
  • Sunday, July 17 until Monday, August 1. 8 p.m. to 5 a.m. Alternating full southbound mainlane closures from Bandera Rd. to Marbach Rd. for mill and overlay work. 

SH 151 – Bexar County

  • Sunday, July 17 until Monday, August 1. 8 p.m. to 5 a.m. Full closure of the westbound frontage road at Loop 410 for traffic switch. 

PA 1502 – Wurzbach Parkway

  • Current until Friday, July 29. 9 a.m. to 3 p.m. Various lane closures, in both directions, at Wurzbach Parkway intersection for pothole and ITS work. 

Lockhill Selma Rd. – Bexar County

  • Monday, July 18 until Friday, July 29. 9 a.m. to 4 p.m. Right turn lane closures, in all directions, at the Wurzbach Parkway intersection. 

FM 1535 – N.W. Military Highway

  • Monday, July 18 until Friday, July 29. 9 a.m. to 4 p.m. Various lane closures, in both directions, at the Wurzbach Parkway intersection. 
  • Monday, July 18 until Friday, July 22. 9 a.m. to 5 p.m. Alternating lane closures, in both directions, from Loop 1604 to Huebner Rd. for utility work.

US 90 – Bexar County

  • Current until Friday, July 22. 6:30 a.m. to 7 p.m. Alternating mainlane closures, in both directions, from Loop 410 to Medina County Line for mill and overlay work.
  • Monday, July 18 until Friday, July 22. 9 a.m. to 5 p.m. Single mainlane and exit ramp closures, in both directions, at Montgomery Rd. for barrier work. 

FM 725 – Comal County

  • Current until Thursday, September 1. Full closure of the northbound to southbound turnaround at I-35 for operational improvements.